Está en la página 1de 2

RINCIAN

PENAWARAN BIAYA PEKERJAAN (RAB)


PEKERJAAN : REHABILITASI RUMAH DINAS DAN PEMBUATAN DRAINASE
LOKASI : JL. MARSMA R. ISWAHYUDI SEBERANG BANDAR UDARA SEPINGGAN BALIKPAPAN
SUMBER DANA : DIPA APBN KANTOR OTORITAS BANDAR UDARA WILAYAH VII BALIKPAPAN
TAHUN ANGGARAN : 2019

Harga Satuan
No Uraian Pekerjaan Volume Sat. Jumlah Harga (Rp)
(Rp)
1 2 3 4 5 6

A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 Ls 3,870,000.00 3,870,000.00

TOTAL PEKERJAAN PERSIAPAN 3,870,000.00

B PEKERJAAN REHAB BANGUNAN


Rehab bangunan type 120 dan type 70
1 Pek. Pembongkaran plafond 505.32 m2 120,830.00 61,057,815.60
2 Pek. Pembongkaran lantai keramik kamar mandi 777.67 m2 133,816.00 104,064,688.72
3 Pek. Pergantian plafond 1377.12 m2 94,600.00 130,275,552.00
4 Pek. Pergantian lantai keramik WC unpolished 60 x 60 857.60 m2 227,900.00 195,447,040.00
5 Pek. Shower K. Mandi 1.00 set 240,800.00 240,800.00
6 Pek. Closet duduk K. Mandi 27.00 bh 1,892,000.00 51,084,000.00
7 Pek. Wastafel K. Mandi 5.00 bh 688,000.00 3,440,000.00
8 Pek. Kran wastafel 5.00 bh 210,700.00 1,053,500.00
9 Pek. Kran air dinding 27.00 bh 151,016.00 4,077,432.00
10 Pemasangan Jet Shower 27.00 bh 227,900.00 6,153,300.00
11 Pemasangan floor drain 36.00 bh 136,396.00 4,910,256.00
12 Pek. Pergantian lampu teras 22.00 titik 150,500.00 3,311,000.00
13 Pek. Bak K. Mandi 31.00 unit 645,000.00 19,995,000.00
14 Water haeter 2.00 unit 202,788.00 405,576.00
15 Pek. Pergantian pintu 166.60 m2 860,000.00 143,276,000.00
16 Handle pintu 119.00 bh 245,100.00 29,166,900.00
17 Engsel 119.00 bh 79,636.00 9,476,684.00
18 Pek. Pengecatan interior 2237.48 m2 79,120.00 177,029,417.60
19 Pek. Pengecatan exterior 3198.90 m2 75,396.20 241,184,904.18

JUMLAH TOTAL PEKERJAAN REHAB BANGUNAN 1,185,649,866.10

C PEKERJAAN DRAINASE
Drainase (150 x 160) Box Culvert
1 Galian tanah biasa sedalam 2 m 16.00 m3 133,816.00 2,141,056.00
2 Urugan kembali bekas galian 1.60 m3 77,400.00 123,840.00
3 Plastik cor 15.00 m2 34,400.00 516,000.00
4 Cor beton mutu K-300 6.23 m3 1,599,600.00 9,965,508.00
5 Besi polos U-24 682.51 kg 13,760.00 9,391,337.60
6 Begesting dinding 35.00 m2 210,700.00 7,374,500.00
7 begesting lantai 9.00 m2 193,500.00 1,741,500.00
8 pancang ulin 8/8-400 1.43 titik 296,700.00 424,281.00

JUMLAH TOTAL PEKERJAAN DRAINASE 31,678,022.60


D PERLENGKAPAN APD K3
1 Helmet safety 10.00 bh 120,400.00 1,204,000.00
2 Sepatu boot 10.00 psg 159,100.00 1,591,000.00
3 Sarung tangan safety 10.00 psg 38,700.00 387,000.00
4 Rompi kerja 10.00 psg 129,000.00 1,290,000.00
Harga Satuan
No Uraian Pekerjaan Volume Sat. Jumlah Harga (Rp)
(Rp)
1 2 3 4 5 6
5 Kotak P3k 1.00 box 473,000.00 473,000.00
6 Papan nama kerjaan 1.00 ls 387,000.00 387,000.00

JUMLAH TOTAL PERLENGKAPAN APD K3 5,332,000.00