Rab Terminal
Rab Terminal
Harga Satuan
No Uraian Pekerjaan Volume Sat. Jumlah Harga (Rp)
(Rp)
1 2 3 4 5 6
A PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi 1.00 Ls 3,870,000.00 3,870,000.00
C PEKERJAAN DRAINASE
Drainase (150 x 160) Box Culvert
1 Galian tanah biasa sedalam 2 m 16.00 m3 133,816.00 2,141,056.00
2 Urugan kembali bekas galian 1.60 m3 77,400.00 123,840.00
3 Plastik cor 15.00 m2 34,400.00 516,000.00
4 Cor beton mutu K-300 6.23 m3 1,599,600.00 9,965,508.00
5 Besi polos U-24 682.51 kg 13,760.00 9,391,337.60
6 Begesting dinding 35.00 m2 210,700.00 7,374,500.00
7 begesting lantai 9.00 m2 193,500.00 1,741,500.00
8 pancang ulin 8/8-400 1.43 titik 296,700.00 424,281.00