S10 INGº NOE ESTEBAN RODRIGUEZ ROJAS Página :

Precios y cantidades de insumos requeridos


Obra 0492002 CONSTRUCCION DEL PUENTE CARAHUANGA SOBRE EL RIO CHONTA
Fórmula 01 PRESUPUESTO PUENTE CARAHUANGA
Fecha 20/06/2006

Código Descripción insumo Unidad Precio Cant. Requerida Parcial Presupuestado


MANO DE OBRA
470032 TOPOGRAFO HH 9.09 4.87 44.27 43.78
470102 OPERARIO HH 9.09 1,944.83 17,678.50 17,611.46
470103 OFICIAL HH 8.17 1,865.03 15,237.30 15,301.45
470104 PEON HH 7.31 5,398.90 39,465.96 39,465.26
72,426.03 72,421.95
MATERIALES
020105 CLAVOS PARA MADERA C/C 3" KG 3.36 155.67 523.05 522.50
020107 CLAVOS PARA MADERA C/C 4" KG 3.36 48.00 161.28 161.28
020409 ALAMBRE NEGRO N°16 KG 3.36 1,098.45 3,690.79 3,661.52
020410 ALAMBRE NEGRO N°8 KG 3.36 105.07 353.04 351.25
025199 PERNOS 3/4" PZA 1.50 8.00 12.00 12.00
030032 FIERRO CORRUGADO PROMEDIO KG 2.33 19,595.60 45,657.75 45,601.00
040000 ARENA FINA M3 58.83 0.52 30.59 30.41
040401 PLACA RECORDATORIA DE CANTERIA UND 150.06 1.00 150.06 150.06
050004 PIEDRA CHANCADA DE 3/4" M3 54.62 143.92 7,860.91 7,861.67
050009 PIEDRA GRANDE DE 8" M3 46.22 171.86 7,943.37 7,941.65
050104 ARENA GRUESA M3 54.62 140.68 7,683.94 7,683.47
050220 PIEDRA MEDIANA M3 46.22 34.11 1,576.56 1,577.02
053040 MATERIAL AFIRMADO M3 42.02 224.00 9,412.48 9,412.48
210000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 16.39 4,343.17 71,184.56 71,183.49
291261 NEOPRENE M2 125.00 0.25 31.25 31.50
292010 THINNER CORRIENTE GLN 16.00 0.96 15.36 15.36
295504 SOLDADURA CELLOCORD PUNTO AZUL 3/16 KG 6.73 4.10 27.59 27.50
300201 YESO DE 28 Kg BOL 4.21 1.82 7.66 7.30
320026 FLETE TERRESTRE GLB 4,000.00 1.00 4,000.00 4,000.00
380000 HORMIGON M3 46.22 396.75 18,337.79 18,337.45
390501 AGUA GLB 1,500.00 1.00 1,500.00 1,500.00
431652 REGLA DE MADERA P2 1.52 4.64 7.05 7.74
435162 ESTACA DE MADERA UND 0.50 45.60 22.80 23.71
435805 LISTONES DE MADERA P2 1.80 1,444.00 2,599.20 2,599.20
437201 MADERA EUCALIPTO ROLLIZO P2 1.50 1,920.00 2,880.00 2,880.00
440119 MADERA EUCALIPTO PARA ENCOFRAR P2 1.60 4,233.10 6,772.96 6,772.96
450107 TRIPLAY 4 X 8 X 6 MM. PLN 17.00 3.00 51.00 51.00
541190 PINTURA ESMALTE GLN 29.42 0.98 28.83 29.15
542101 PINTURA ANTICORROSIVA GLN 29.42 0.80 23.54 23.68
562207 PLANCHA METALICA A-25 M2 126.05 0.50 63.03 63.52
600002 TEKNOPOR DE 1" x 4' x 8' PLN 12.00 16.29 195.48 195.48
650049 TUBO Fo.GALV. DE 3" x 6.40m UND 231.09 10.56 2,440.31 2,440.32
720001 TUB. PVC SAP PRESION P/AGUA C-5 EC 3"x5m UND 15.50 14.00 217.00 217.00
720636 GIGANTOGRAFIA DIGITAL BANNER UND 350.00 1.00 350.00 350.00
195,811.23 195,722.67
EQUIPOS
480108 MEZCLADORA CONCRETO TAMBOR 11 P3-18 HP HM 10.92 279.45 3,051.59 3,052.75
480423 CAMION VOLQUETE 4x2 140-210 HP 6 M3. HM 50.00 8.00 400.00 400.00
480811 MOTOBOMBA 5 HP 3" HM 12.61 40.00 504.40 504.50
490307 RODILLO LISO VIBR AUTOP 101-135HP 10-12T HM 121.85 2.20 268.07 270.00
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 9.24 108.85 1,005.77 1,006.85
490750 MOTOSOLDADORA DE 250 AMP. HM 42.02 4.00 168.08 168.00
490900 MOTONIVELADORA DE 125 HP HM 147.05 2.20 323.51 325.00
491021 PLANCHA COMPACTADORA HM 10.09 115.39 1,164.29 1,164.29
491901 TEODOLITO HM 10.09 4.87 49.14 49.25
491903 NIVEL HE 8.41 4.87 40.96 40.13
6,975.81 6,980.77
SUB-TOTAL 275,213.06 275,125.39
INSUMOS COMODIN
EQUIPOS
370101 HERRAMIENTAS MANUALES %MO 2,100.99
0.00 2,100.99
SUB-TOTAL 0.00 2,100.99
TOTAL 275,213.06 277,226.38
MONTO PARTIDAS ESTIMADAS 0.00

277,226.38
La columna parcial es el producto del precio por la cantidad requerida; y en la última columna se muestra el Monto Real que se está
utilizando