Documentos de Académico
Documentos de Profesional
Documentos de Cultura
2006
The upward or downward movement of a concrete Slabs curl due to moisture or temperature
slab’s corners or edges due to moisture and/or gradients between their top and bottom surfaces.
temperature differentials within the concrete is The slab edges curl upwards when the top surface
known as ‘curling’ or ‘warping’. It may be evident in is either drier (shrinks more) or cooler (contracts
concrete elements other than slabs, eg wall panels. more) than the bottom of the slab.
This Data Sheet is concerned only with curling in When greater moisture loss and shrinkage
slabs, and particularly slabs on ground. occur near the top and exposed concrete surface
Curling typically occurs some months after than the bottom of the slab the shrinkage gradient
concrete placement but can occur much earlier. The applies a curling moment to the slab. If the curling
extent of movement is usually minimal (up to only moment is greater than can be resisted by the
a few millimeters) but may in severe cases be as weight of the slab plus any applied loads, the slab
much as 20–25 mm. In the worst cases, slab edges will deflect upwards or curl. Figure 1.
and corners may lift off the ground and stepping
between adjacent panels may occur. The areas
>
The long-term magnitude of curling will reduce reinstate adequate support for the slab is to
as moisture and temperature gradients stabilise cut extra joints across the corners of the slab
and concrete creep occurs. Curling may reduce to a as shown in Figure 4. For residential floors
tolerable level over time, possibly avoiding the need or floors with no heavy loading saw cuts may
for repairs. If the construction schedule permits, be full depth to ensure settlement of the
this could be an available option and should be slab. For light forklift traffic and loading,
considered. saw cuts are made to only one-third of the
slab thickness to allow aggregate interlock
5 RECTIFICATION OF CURLING and thus load transfer across the joint.
It is important to establish whether or not the slab > Grouting of void The void beneath the slab
is still curling prior to carrying out repairs, as is filled with either cement-, urethane- or
curling can continue for some months. Carrying out epoxy-based grout, depending on the size of
repairs while the slab is still curling may compound the gap. Figure 5.
the problem. Also, the repair method may vary
depending on whether the slab is dry, still drying, n Reducing stepping The three methods are:
or has the potential for long-term cycles of wetting > Raise the lower slab by injecting grout
and drying. beneath it.
While a number of options to repair the effects > Grind the higher slab edge (150 to 200-mm-
areas that require a flatter profile should n Use a mix with low-shrinkage characteristics.
be ground, and that grinding may not be an n Use largest practical aggregate size
option for slabs with decorative finishes. n Where possible, place concrete on lightly
While minor grinding should not affect moistened, pervious subbase/subgrade that
the performance of the slab, if more than a absorbs moisture from the bottom of the
few millimeters are required to be removed, slab during initial set.
the minimum required slab thickness and n Use a thicker slab (minimum 100 mm is
epoxy mortar topping provided to reinstate n Minimise the rate of evaporation by using
the slab surface. Note that any joints evaporative retarders particularly in hot,
must be reinstated in the topping, and windy or low humidity conditions.
the reduced slab thickness checked for n For industrial floor slabs, ensure the roof,
placing a topping beneath flat finishes such water to retemper the mix.
as vinyl sheeting or carpet may be an option. n Take precautions when placing in hot
is typically required only in high traffic areas apply membrane-forming curing compounds
where differential movement is a problem, and as soon as the finishing operation is
where the slab thickness is at least 150 mm. completed.
Bars are installed by saw cutting a groove across n Avoid rapid drying of surface after curing.
the joint, installing the dowel/bar into the cut Consider application of surface coating or
and using epoxy to bond the bar to the concrete. sealer to provide more-uniform moisture
Details such as bar type, size and spacing, saw conditions within the slab by reducing
cut depth, etc will need to be determined for each evaporation from the surface.
specific case. Note that to reduce the saw cut n Ensure adequate preparation for bonded
curling moment.
n Slab replacement This should be considered as
the last option to rectify curled slabs, particularly
if decorative finishes have been provided. This is
due to the difficulty of exactly matching the colour
and/or finish of a new section of pavement with
that of adjacent existing areas. Note that the
causes of the curling should be identified prior to
replacement to avoid a recurrence of the situation.
TASMANIAN OFFICE:
EXTRACTIVE INDUSTRIES OFFICE
PO Box 246
Sheffield TAS 7306
TELEPHONE: (61 3) 6491 2529
FACSIMILE: (61 3) 6491 2529
WEBSITE: www.concrete.net.au
EMAIL: info@ccaa.com.au