VALORIZACIÓN 06

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 01/07/2019 AL 15/07/2019

ANTERIOR VALORIZACION 7

PRECIO
DIAMETR CANT.
ITEM PESO TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO
O VARILLAS (S/.)
ø CANT KG. s/ s/ s/ CANT KG. s/ CANT KG.
1 ø 5/8 1850 13.97 25844.50 0.80508 20807.01 1640.00 22910.80 18445.14 230.00 3213.10
2 ø 1/2 3075 8.95 27521.25 0.80508 22156.94 2403.00 21506.85 17314.84 571.00 5110.45
3 ø 3/8 4144 5.04 20885.76 0.80508 16814.81 3550.00 17892.00 14404.58 634.00 3195.36
4 ø 1/4 2950 2.25 6637.50 0.80508 5343.75 2150.00 4837.50 3894.60 510.00 1147.50
5 #16 2000 1.00 2000.00 0.80508 1610.17 500.00 500.00 402.54 - 0.00
SUB TOTAL S/66,732.68 SUB TOTAL 54461.69 SUB TOTAL
IGV (18%) S/12,011.88 IGV (18%) 9803.10 IGV (18%)
TOTAL S/78,744.56 TOTAL 64264.79 TOTAL

ADENDA 01

ANTERIOR VALORIZACION 02

PRECIO
TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO
ITEM DESCRIPCION (S/.)
CANT KG. s/ CANT KG.
1 SOBRECIMIENTO ARMADO 213.87 0.211864 S/. 45.31 - 106.94 22.66 106.94
2 COLUMNETAS Y VIGUETAS 10825.94 0.211864 S/. 2,293.63 5412.97 1146.82 5412.97
SUB TOTAL S/. 1,169.47 SUB TOTAL
IGV (18%) S/. 210.50 IGV (18%)
TOTAL S/. 1,379.98 TOTAL
DEPARTAMENTO DE TACNA

ALORIZACION 7 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/ CANT KG s/ CANT KG s/
2586.82 1870.00 26123.90 21031.95 -20.00 -279.40 -224.94
4114.35 2974.00 26617.30 21429.18 101.00 903.95 727.76
2572.54 4184.00 21087.36 16977.11 -40.00 -201.60 -162.31
923.83 2660.00 5985.00 4818.43 290.00 652.50 525.32
0.00 500.00 500.00 402.54 1500.00 1500.00 1207.63
S/. 10,197.53 SUB TOTAL S/. 64,659.22 SUB TOTAL S/. 2,073.46
S/. 1,835.56 IGV (18%) S/. 11,638.66 IGV (18%) S/. 373.22
S/. 12,033.09 TOTAL S/. 76,297.88 TOTAL S/. 2,446.68

ALORIZACION 02 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/ CANT KG s/ CANT KG s/
S/. 22.66 - 213.87 S/. 45.31 - 0.00 0.00
S/. 1,146.82 0.00 10825.94 S/. 2,293.63 0.00 0.00 0.00
S/. 1,169.47 SUB TOTAL S/. 2,338.94 SUB TOTAL S/. 0.00
S/. 210.50 IGV (18%) S/. 421.01 IGV (18%) S/. 0.00
S/. 1,379.98 TOTAL S/. 2,759.95 TOTAL S/. 0.00
OBRA: CREACION DEL CENTRO DE ATENCION I
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 16/05/2019 AL 31/05/2019

CANT.
ITEM DIAMETRO VARILLAS

UND
1 ø 5/8 1850
2 ø 1/2 2600
3 ø 3/8 4100
4 ø 1/4 2650
5 #16 2000
VALORIZACIÓN 03

REACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
CERO GRADO 60
MOISES ANCCO NINA
EL 16/05/2019 AL 31/05/2019
ANTERIOR VALORIZACIÓN 04 ACUMULADO
PRECIO TOTAL EN
PESO TOTAL KG. UNITARIO METRADO MONTO METRADO MONTO METRADO
SOLES
(S/.)
KG KG s/ s/ CANT KG. s/ CANT KG. s/ KG.
13.97 25844.5 0.80508 20807.01 0.00 0.00 0.00 201.00 2807.97 S/ 2,260.65 2807.97
8.95 23270 0.80508 18734.32 0.00 0.00 0.00 480.00 4296.00 S/ 3,458.64 4296.00
5.04 20664 0.80508 16636.27 0.00 0.00 0.00 450.00 2268.00 S/ 1,825.93 2268.00
2.25 5962.5 0.80508 4800.32 0.00 0.00 0.00 420.00 945.00 S/ 760.81 945.00
1.00 2000 0.80508 1610.17 0.00 0.00 0.00 500.00 500.00 S/ 402.54 500.00
SUB TOTAL S/62,588.09 SUB TOTAL 0.00 SUB TOTAL S/ 8,708.58 SUB TOTAL
IGV (18%) S/11,265.86 IGV (18%) 0.00 IGV (18%) S/ 1,567.54 IGV (18%)
TOTAL S/73,853.95 TOTAL 0.00 TOTAL S/10,276.12 TOTAL
ACUMULADO SALDO

MONTO METRADO MONTO

s/ KG s/
S/ 2,260.65 23036.53 S/ 18,546.36
S/ 3,458.64 18974.00 S/ 15,275.68
S/ 1,825.93 18396.00 S/ 14,810.34
S/ 760.81 5017.50 S/ 4,039.51
S/ 402.54 1500.00 S/ 1,207.63
S/ 8,708.58 SUB TOTAL S/ 53,879.52
S/ 1,567.54 IGV (18%) S/ 9,698.31
S/10,276.12 TOTAL S/63,577.83
VALORIZACIÓN 09

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 19/08/2019 AL 31/08/2019

ANTERIOR VALORIZACION 9

PRECIO
DIAMETR CANT.
ITEM PESO TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO
O VARILLAS (S/.)
ø CANT KG. s/ s/ s/ CANT KG. s/ CANT KG.
1 ø 5/8 1850 13.97 25844.50 0.80508 20807.01 1799.00 25132.03 20109.70 0.00 0.00
2 ø 1/2 3175 8.95 28416.25 0.80508 22877.49 3135.00 28058.25 21436.39 34.00 304.30
3 ø 3/8 4310 5.04 21722.40 0.80508 17488.37 4280.00 21571.20 16356.29 6.00 30.24
4 ø 1/4 2950 2.25 6637.50 0.80508 5343.75 2891.00 6504.75 4773.15 35.00 78.75
5 #16 2000 1.00 2000.00 0.80508 1610.17 1000.00 1000.00 402.54 - 0.00
SUB TOTAL S/68,126.79 SUB TOTAL 63078.07 SUB TOTAL
IGV (18%) S/12,262.82 IGV (18%) 11354.05 IGV (18%)
TOTAL S/80,389.62 TOTAL 74432.12 TOTAL
DEPARTAMENTO DE TACNA

ALORIZACION 9 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/ CANT KG s/ CANT KG s/
0.00 1799.00 25132.03 20109.70 51.00 712.47 697.32
244.99 3169.00 28362.55 21681.38 6.00 53.70 1196.11
24.35 4286.00 21601.44 16380.64 24.00 120.96 1107.73
63.40 2926.00 6583.50 4836.55 24.00 54.00 507.20
0.00 1000.00 1000.00 402.54 1000.00 1000.00 1207.63
332.73 SUB TOTAL S/. 63,410.80 SUB TOTAL S/. 4,715.99
S/. 59.89 IGV (18%) S/. 11,413.94 IGV (18%) S/. 848.88
S/. 392.63 TOTAL S/. 74,824.75 TOTAL S/. 5,564.87
VALORIZACIÓN 07

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 01/07/2019 AL 15/07/2019

ANTERIOR VALORIZACION 7

PRECIO
DIAMETR CANT.
ITEM PESO TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO
O VARILLAS (S/.)
ø CANT KG. s/ s/ s/ CANT KG. s/ CANT KG.
1 ø 5/8 1850 13.97 25844.50 0.80508 20807.01 1640.00 22910.80 18445.14 148.00 2067.56
2 ø 1/2 3175 8.95 28416.25 0.80508 22877.49 2403.00 21506.85 17314.84 572.00 5119.40
3 ø 3/8 4244 5.04 21389.76 0.80508 17220.57 3550.00 17892.00 14404.58 481.00 2424.24
4 ø 1/4 2950 2.25 6637.50 0.80508 5343.75 2150.00 4837.50 3894.60 485.00 1091.25
5 #16 2000 1.00 2000.00 0.80508 1610.17 500.00 500.00 402.54 - 0.00
SUB TOTAL S/67,858.99 SUB TOTAL 54461.69 SUB TOTAL
IGV (18%) S/12,214.62 IGV (18%) 9803.10 IGV (18%)
TOTAL S/80,073.61 TOTAL 64264.79 TOTAL

ADENDA 01

ANTERIOR VALORIZACION 02

PRECIO
TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO
ITEM DESCRIPCION (S/.)
CANT KG. s/ CANT KG.
1 SOBRECIMIENTO ARMADO 213.87 0.211864 S/. 45.31 106.94 106.94 22.66 106.94
2 COLUMNETAS Y VIGUETAS 10825.94 0.211864 S/. 2,293.63 5412.97 5412.97 1146.82 5412.97
SUB TOTAL S/. 1,169.47 SUB TOTAL
IGV (18%) S/. 210.50 IGV (18%)
TOTAL S/. 1,379.98 TOTAL
DEPARTAMENTO DE TACNA

ALORIZACION 7 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/ CANT KG s/ CANT KG s/
1664.56 1788.00 24978.36 20109.70 62.00 866.14 697.32
4121.55 2975.00 26626.25 21436.39 200.00 1790.00 1441.10
1951.72 4031.00 20316.24 16356.29 213.00 1073.52 864.27
878.55 2635.00 5928.75 4773.15 315.00 708.75 570.60
0.00 500.00 500.00 402.54 1500.00 1500.00 1207.63
8616.38 SUB TOTAL S/. 63,078.07 SUB TOTAL S/. 4,780.92
S/. 1,550.95 IGV (18%) S/. 11,354.05 IGV (18%) S/. 860.57
S/. 10,167.33 TOTAL S/. 74,432.12 TOTAL S/. 5,641.49

ALORIZACION 02 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/ CANT KG s/ CANT KG s/
S/. 22.66 - 213.87 S/. 45.31 - 0.00 0.00
S/. 1,146.82 0.00 10825.94 S/. 2,293.63 0.00 0.00 0.00
S/. 1,169.47 SUB TOTAL S/. 2,338.94 SUB TOTAL S/. 0.00
S/. 210.50 IGV (18%) S/. 421.01 IGV (18%) S/. 0.00
S/. 1,379.98 TOTAL S/. 2,759.95 TOTAL S/. 0.00
OBRA: CREACION DEL CENTRO DE ATENCION I
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 16/05/2019 AL 31/05/2019

CANT.
ITEM DIAMETRO VARILLAS

UND
1 ø 5/8 1850
2 ø 1/2 2600
3 ø 3/8 4100
4 ø 1/4 2650
5 #16 2000
VALORIZACIÓN 03

REACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
CERO GRADO 60
MOISES ANCCO NINA
EL 16/05/2019 AL 31/05/2019
ANTERIOR VALORIZACIÓN 04 ACUMULADO
PRECIO TOTAL EN
PESO TOTAL KG. UNITARIO METRADO MONTO METRADO MONTO METRADO
SOLES
(S/.)
KG KG s/ s/ CANT KG. s/ CANT KG. s/ KG.
13.97 25844.5 0.80508 20807.01 0.00 0.00 0.00 201.00 2807.97 S/ 2,260.65 2807.97
8.95 23270 0.80508 18734.32 0.00 0.00 0.00 480.00 4296.00 S/ 3,458.64 4296.00
5.04 20664 0.80508 16636.27 0.00 0.00 0.00 450.00 2268.00 S/ 1,825.93 2268.00
2.25 5962.5 0.80508 4800.32 0.00 0.00 0.00 420.00 945.00 S/ 760.81 945.00
1.00 2000 0.80508 1610.17 0.00 0.00 0.00 500.00 500.00 S/ 402.54 500.00
SUB TOTAL S/62,588.09 SUB TOTAL 0.00 SUB TOTAL S/ 8,708.58 SUB TOTAL
IGV (18%) S/11,265.86 IGV (18%) 0.00 IGV (18%) S/ 1,567.54 IGV (18%)
TOTAL S/73,853.95 TOTAL 0.00 TOTAL S/10,276.12 TOTAL
ACUMULADO SALDO

MONTO METRADO MONTO

s/ KG s/
S/ 2,260.65 23036.53 S/ 18,546.36
S/ 3,458.64 18974.00 S/ 15,275.68
S/ 1,825.93 18396.00 S/ 14,810.34
S/ 760.81 5017.50 S/ 4,039.51
S/ 402.54 1500.00 S/ 1,207.63
S/ 8,708.58 SUB TOTAL S/ 53,879.52
S/ 1,567.54 IGV (18%) S/ 9,698.31
S/10,276.12 TOTAL S/63,577.83
ADENDA

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: COLUMNETAS Y VIGUETAS
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 01/07/2019 AL 17/07/2019

VALORIZACIÓN 01 VALORIZACION 02 VALORIZACION 03

PRECIO
ITEM DESCRIPCION TOTAL KG. UNITARIO PARCIAL METRADO MONTO METRADO MONTO METRADO
(S/.)
CANT KG s/ s/ CANT KG. s/ CANT KG. s/ CANT
1 SOBRECIMIENTO ARMADO 213.87 0.21186 45.31 - 0.00 0.00
2 COLUMNETAS Y VIGUETAS 10825.94 0.21186 2293.63 - 0.00 0.00
SUB TOTAL S/2,338.94 SUB TOTAL 0.00 SUB TOTAL 0.00
IGV (18%) S/421.01 IGV (18%) 0.00 IGV (18%) 0.00
TOTAL S/2,759.95 TOTAL 0.00 TOTAL 0.00
ADENDA 01

TO DE TACNA

VALORIZACION 03 VALORIZACION 04 ANTERIOR VALORIZACION 02 ACUMULADO SALDO

METRADO MONTO METRADO MONTO METRADO MONTO METRADO monto METRADO MONTO METRADO

KG. s/ CANT KG. s/ CANT KG. s/ CANT KG. s/ CANT KG s/ CANT


0.00 0.00 - 106.94 22.66 - 106.94 S/. 22.66 - 213.87 45.31 -
0.00 0.00 - 5412.97 1146.82 - 5412.97 S/. 1,146.82 - 10825.94 2293.63 -
SUB TOTAL 0.00 SUB TOTAL 0.00 SUB TOTAL 1169.47 SUB TOTAL S/. 1,169.47 SUB TOTAL 2338.94
IGV (18%) 0.00 IGV (18%) 0.00 IGV (18%) 210.50 IGV (18%) S/. 210.50 IGV (18%) 421.01
TOTAL 0.00 TOTAL 0.00 TOTAL 1379.98 TOTAL S/. 1,379.98 TOTAL 2759.95
SALDO

METRADO MONTO

KG s/
0.00 0.00
0.00 0.00
SUB TOTAL 0.00
IGV (18%) 0.00
TOTAL 0.00

0.00
VALORIZACIÓN 03
OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENT
PARTIDA: ACERO GRADO 60
EJECUTA: MOISES ANCCO NINA
PERIODO: DEL 16/05/2019 AL 31/05/2019
ANTERIOR
PRECIO
CANT. TOTAL EN
ITEM DIAMETRO PESO TOTAL KG. UNITARIO METRADO MONTO
VARILLAS SOLES
(S/.)
UND KG KG s/ s/ CANT KG. s/
1 ø 5/8 1850 13.97 25844.5 0.80508 20807.01 0.00 0.00 0.00
2 ø 1/2 2600 8.95 23270 0.80508 18734.32 0.00 0.00 0.00
3 ø 3/8 4100 5.04 20664 0.80508 16636.27 0.00 0.00 0.00
4 ø 1/4 2650 2.25 5962.5 0.80508 4800.32 0.00 0.00 0.00
5 #16 2000 1.00 2000 0.80508 1610.17 0.00 0.00 0.00
SUB TOTAL S/62,588.09 SUB TOTAL 0.00
IGV (18%) S/11,265.86 IGV (18%) 0.00
TOTAL S/73,853.95 TOTAL 0.00
03
ENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA

VALORIZACIÓN 04 ACUMULADO SALDO

METRADO MONTO METRADO MONTO METRADO MONTO

CANT KG. s/ KG. s/ KG s/


201.00 2807.97 S/ 2,260.65 2807.97 S/ 2,260.65 23036.53 S/ 18,546.36
480.00 4296.00 S/ 3,458.64 4296.00 S/ 3,458.64 18974.00 S/ 15,275.68
450.00 2268.00 S/ 1,825.93 2268.00 S/ 1,825.93 18396.00 S/ 14,810.34
420.00 945.00 S/ 760.81 945.00 S/ 760.81 5017.50 S/ 4,039.51
500.00 500.00 S/ 402.54 500.00 S/ 402.54 1500.00 S/ 1,207.63
SUB TOTAL S/ 8,708.58 SUB TOTAL S/ 8,708.58 SUB TOTAL S/ 53,879.52
IGV (18%) S/ 1,567.54 IGV (18%) S/ 1,567.54 IGV (18%) S/ 9,698.31
TOTAL S/10,276.12 TOTAL S/10,276.12 TOTAL S/63,577.83
CONSORCIO HATUN WASI

SR MOISES ANCCO NINA


PARTIDA ACERO GRADO 60
PERIODO DEL 19 AL 31 DE AGOSTO

DESCRIPCION

VALORIZACION N° 9 DE LA SEGUNDA QUINCENA DE AGOSTO

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
AMORTIZACION DE ADELANTO B

MONTO TOTAL A PAGAR A-B

SUB TOTAL
IGV 18%
TOTAL

SON: TRESCIENTOS NOVENTA Y DOS CON 63/100 SOLES


IMPORTE

S/. 332.73
S/. 0.00

S/. 332.73

S/. 332.73
S/. 59.89
S/. 392.63
OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: ENCOFRADO Y DESENCOFRADO
EJECUTA: CONSTRUCTORA VILCA S.A.C.
PERIODO: DEL 21/07/2019 AL 31/07/2019

VALORIZACIÓN 01 VALORIZACIÓN 02

ITEM DESCRIPCION METRADO PARCIAL TOTAL METRADO MONTO METRADO

METRADO S/ s/. METRADO % s/. METRADO %


1 ZAPATA ENCO. Y DESENC. 189.24 16.94915 3207.46 62.37 32.96% S/. 1,057.12 126.87 67.04%
2 COLUMNA ENCOF. Y DESEN. CARAVISTA 1336.1 38.13559 50952.97 83.19 6.23% S/. 3,172.50 277.90 20.80%
3 VIGAS ENCOF. Y DESENCOFRADO CARAVISTA 1061.46 38.13559 40479.41 0.00 0.00% S/. - 0.00 0.00%
4 CIMIENTO ENCO. Y DESENC.NORMAL 514.82 29.66102 15270.08 0.00 0.00% S/. - 50.44 9.80%
5 SOBRECIMIENTO ENCOF Y DESENC. NORMAL 376.85 29.66102 11177.75 0.00 0.00% S/. - 0.00 0.00%
6 VIGUETAS ENCOF. Y DESENC. NORMAL
1254.72 29.66102 37216.27 0.00 0.00% S/. - 118.82 9.47%
7 COLUMNETAS ENCOF. Y DESENC. NORMAL
8 LOSA ALIGERADA ENCO. Y DESENCO. NORMAL 1496.67 29.66102 44392.75 0.00 0.00% S/. - 0.00 0.00%
9 TANQUE CISTERNA 97.36 38.13559 3712.88 97.36 100.00% S/. 3,712.88 0.00 0.00%
10 ESCALERA 200 29.66102 5932.20 0.00 0.00% S/. - 0.00 0.00%
SUB TOTAL S/212,341.78 SUB TOTAL S/. 7,942.50 SUB TOTAL
IGV (18%) S/38,221.52 IGV (18%) S/. 1,429.65 IGV (18%)
TOTAL S/250,563.30 TOTAL S/. 9,372.15 TOTAL

VALORIZACIÓN 01 VALORIZACIÓN 02
ITEM DESCRIPCION METRADO PARCIAL TOTAL METRADO MONTO METRADO

METRADO S/ s/. METRADO % s/. METRADO %

CERCO PERIMETRICO
SOBRECIMIENTOS,NORMAL 42.98 29.66102 1274.83 0.00% S/. - 0.00%
COLUMENTAS Y VIGUETAS 30.15 29.66102 894.28 0.00% S/. - 0.00%
AREA DE CIRCULACION
SARDINELES 29.5 16.94915 500.00 0.00% S/. - 0.00%
RAMPA ENCOFRADO CARAVISTA 3.58 38.13559 136.53 0.00% S/. - 0.00%
GRADAS, ENCOFRADO Y DES NORMAL 2.02 29.66102 59.92 0.00% S/. - 0.00%
INSTALACION DE AREAS VERDES
SARDINEL PERALTADO, CARAVISTA 39.96 38.13559 1523.90 0.00% S/. - 0.00%
PLAZOLETA CENTRAL
PISOS, ENCOFRADO NORMAL 5.8 29.66102 172.03 0.00% S/. - 0.00%
SARDINEL PERALTADO, CARAVISTA 5.28 38.13559 201.36 0.00% S/. - 0.00%
BANCA, ENFORADO CARAVISTA 4.17 38.13559 159.03 0.00% S/. - 0.00%
MURO DE CONTENCION FRENTE A B1

SOBRECIMIENTOS ENCOFRADO CARAVISTA 14.82 29.66102 439.58 0.00% S/. - 0.00%


COLUMNAS, CARAVISTA 13.39 38.13559 510.64 0.00% S/. - 0.00%
VIGAS, CARAVISTA 15.61 38.13559 595.30 0.00% S/. - 0.00%
LOSA ALIGERADA, NORMAL 17.26 29.66102 511.95 0.00% S/. - 0.00%
COLUMNETAS Y VIGUETAS 10.75 29.66102 318.86 0.00% S/. - 0.00%
SUB TOTAL S/7,298.18
IGV (18%) S/1,313.67
TOTAL S/8,611.85

VALORIZACIÓN 03

1 OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
2 PARTIDA: ENCOFRADO Y DESENCOFRADO
3 EJECUTA: EDGAR VILCA
4 PERIODO: :DEL 16/05/2019 AL 31/05/2019
ANTERIOR VALORIZACIÓN 03
ITEM DESCRIPCION METRADO PARCIAL TOTAL EN SOLES METRADO MONTO METRADO

M2 s/ s/ METRADO % s/ METRADO %
1 ZAPATA ENCO. Y DESENC. 189.24 16.94915 3207.46 189.24 1.00 S/ 3,207.46 0.00 0%
2 COLUMNA ENCOF. Y DESEN. NORMAL 126.28 29.66102 3745.59 118.82 0.00 7.46 6%
3 COLUMNA ENCOF. Y DESEN. CARAVISTA 1336.1 38.13559 50952.97 361.09 0.27 S/ 13,770.38 139.38 10%
4 VIGAS ENCOF. Y DESENCOFRADO CARAVISTA 1061.46 38.13559 40479.41 0.00 0.00 S/ - 226.05 21%
5 CIMIENTO ENCO. Y DESENC.NORMAL 514.82 29.66102 15270.08 50.44 0.10 S/ 1,496.10 250.85 49%
6 SOBRECIMIENTO ENCOF Y DESENC. NORMAL 376.85 29.66102 11177.75 0.00 0.00 S/ - 89.65 24%
7 VIGUETAS ENCOF. Y DESENC. NORMAL
1128.44 29.66102 33470.68 0.00 0.00 S/ - 0.00 0.00
8 COLUMNETAS ENCOF. Y DESENC. NORMAL
9 LOSA ALIGERADA ENCO. Y DESENCO. NORMAL 1496.67 29.66102 44392.75 0.00 0% S/ - 331.80 22%
10 TANQUE CISTERNA 97.36 38.13559 3712.88 97.36 100% S/ 3,712.88 0.00 0%
SUB TOTAL S/206,409.58 SUB TOTAL 22186.82 SUB TOTAL
IGV (18%) S/37,153.72 IGV (18%) 3993.63 IGV (18%)
TOTAL S/243,563.30 TOTAL 26180.45 TOTAL

B1 B2 B3 B4 B5 O. COMPLE. TOTAL
ZAPATAS
COLUMNA CARAVISTA 347.82 139.86 240.72 165.3 193.83 13.39 1100.92
VIGA CARAVISTA 306.14 139.86 240.72 165.3 193.83 15.61 1061.46
CIMIENTO NORMAL 100 100 100 100 100 14.82 514.82
SOBRCIMIENTO NORMAL 117.65 48.18 57.57 63.16 47.31 42.98 376.85
VIGUETA NORMAL
COLUMNETA NORMAL 325.07 149.96 136.27 327.71 148.53 40.9
LOSA ALIGERADA 440.68 211.21 305.28 291.57 230.57 17.26
TANQUE CISTERNA 97.36
ESCALERA
MESON DE CONCRETO
RAMPA
PISO Y VEREDA CARAVISTA
ADOQUINES CARAVISTA
GRADA
SARDINELES CARAVISTA
BANCAS CARAVISTAS
VALORIZACIÓN 07

RTAMENTO DE TACNA

VALORIZACIÓN 02 VALORIZACIÓN 03 VALORIZACIÓN 04 VALORIZACIÓN 05 VALORIZACIÓN 06

MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO

s/. METRADO % s/. METRADO % s/. METRADO % s/. METRADO %


S/. 2,150.34 0.00 0.00% S/. - 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00
S/. 10,597.88 139.38 10.43% S/. 5,315.34 145.72 0.11 5557.12 293.07 21.93% 11176.40 113.29 0.08
S/. - 226.05 21.30% S/. 8,620.55 201.58 0.19 7687.37 185.21 17.45% 7063.09 235.12 0.22
S/. 1,496.10 250.85 48.73% S/. 7,440.47 47.79 0.09 1417.50 0.00 0.00% 0.00 9.47 0.02
S/. - 89.65 23.79% S/. 2,659.11 136.80 0.36 4057.63 31.66 8.40% 939.07 56.50 0.15

S/. 3,524.32 7.46 0.59% S/. 221.27 121.78 9.71% 3612.12 95.91 7.64% 2844.79 42.63 0.00

S/. - 331.80 22.17% S/. 9,841.53 291.42 0.19 8643.81 238.12 15.91% 7062.88 319.04 0.21
S/. - 0.00 0.00% S/. - 0.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00
S/. - 0.00 0.00% S/. - 0.00 0.00 0.00 99.21 49.61% 2942.67 0.00 0.00
S/. 17,768.64 SUB TOTAL S/. 34,098.26 SUB TOTAL S/30,975.55 SUB TOTAL S/32,028.90 SUB TOTAL
S/. 3,198.36 IGV (18%) S/. 6,137.69 IGV (18%) S/5,575.60 IGV (18%) S/5,765.20 IGV (18%)
S/. 20,967.00 TOTAL S/. 40,235.95 TOTAL S/36,551.15 TOTAL S/37,794.10 TOTAL

VALORIZACIÓN 02 VALORIZACIÓN 03 VALORIZACIÓN 04 VALORIZACIÓN 05 VALORIZACIÓN 06


MONTO METRADO MONTO METRADO MONTO METRADO MONTO METRADO

s/. METRADO % s/. METRADO % s/. METRADO % s/. METRADO %

S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00


S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00

S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00


S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00
S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00

S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00

S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00


S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00
S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00

S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00


S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00
S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00
S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00
S/. - 0.00% S/. - 0.00 0.00 0.00% 0.00 0.00

RTAMENTO DE TACNA

VALORIZACIÓN 03 ACUMULADO SALDO


MONTO METRADO MONTO METRADO MONTO

s/ M2 s/ M2 s/
S/ - 189.24 S/ 3,207.46 0.00 S/ -
S/ 221.27 126.28 S/ 221.27 0.00 S/ 3,524.32
S/ 5,315.34 500.47 S/ 19,085.72 835.63 S/ 31,867.25
S/ 8,620.55 226.05 S/ 8,620.55 835.41 S/ 31,858.86
S/ 7,440.47 301.29 S/ 8,936.57 213.53 S/ 6,333.52
S/ 2,659.11 89.65 S/ 2,659.11 287.20 S/ 8,518.64

S/ - 0.00 S/ - 1128.44 S/ 33,470.68

S/ 9,841.53 -331.80 S/ 9,841.53 1828.47 S/ 34,551.23


S/ - 97.36 S/ 3,712.88 0.00 S/ -
S/ 34,098.26 SUB TOTAL S/ 56,285.08 SUB TOTAL S/ 150,124.49
S/ 6,137.69 IGV (18%) S/ 10,131.32 IGV (18%) S/ 27,022.41
S/ 40,235.95 TOTAL S/ 66,416.40 S/ 177,146.90
ALORIZACIÓN 06 VALORIZACIÓN 07 ANTERIOR VALORIZACIÓN 07 ACUMULADO

MONTO METRADO MONTO METRADO MONTO METRADO monto METRADO

s/. METRADO % s/. METRADO % s/. METRADO % s/. METRADO %


0.00 0.00 0.00 0.00 189.24 100.00% 3207.46 0.00 0.00% 0.00 189.24 100.00%
4320.38 16.98 0.00 647.54 1069.53 78.78% 40787.16 107.31 8.03% 4092.33 1176.84 86.81%
8966.44 50.21 0.00 1914.79 898.17 79.89% 34252.25 133.43 12.57% 5088.43 1031.60 92.46%
280.89 0.00 0.00 0.00 358.55 69.65% 10634.96 0.00 0.00% 0.00 358.55 69.65%
1675.85 3.19 0.00 94.62 317.80 83.48% 9426.27 50.74 13.46% 1505.00 368.54 96.95%
9,152.50
1264.45 308.57 0.00 695.17 7.64% 20619.45 453.45 36.14% 13449.79 1148.62 43.78%

9463.05 85.88 0.00 2547.29 1266.26 78.87% 37558.56 198.54 13.27% 5888.90 1464.80 92.13%
0.00 0.00 0.00 0.00 97.36 100.00% 3712.88 0.00 0.00% 0.00 97.36 100.00%
0.00 26.43 0.00 783.94 125.64 49.61% 3726.61 26.43 13.22% 783.94 152.07 62.82%
S/25,971.06 SUB TOTAL S/15,140.68 SUB TOTAL S/. 163,925.59 SUB TOTAL S/. 30,808.39 SUB TOTAL
S/4,674.79 IGV (18%) S/2,725.32 IGV (18%) S/. 29,506.61 IGV (18%) S/. 5,545.51 IGV (18%)
S/30,645.85 TOTAL S/17,866.00 TOTAL S/. 193,432.20 TOTAL S/. 36,353.90 TOTAL

ALORIZACIÓN 06 VALORIZACIÓN 07 ANTERIOR VALORIZACIÓN 07 ACUMULADO


MONTO METRADO MONTO METRADO MONTO METRADO monto METRADO

s/. METRADO % s/. METRADO % s/. METRADO % s/. METRADO %

0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%

0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%

0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%

0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%

0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
0.00 0.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00%
ACUMULADO SALDO

MONTO METRADO MONTO

s/. METRADO s/. 0 0 30975.55 5575.60 36551.15


3207.46 0.00 0.00 20 0 4413.69 794.46 5208.15
44879.49 159.26 6073.47 45 4828.95 #REF! #REF! #REF!
39340.68 29.86 1138.73 45 6004.35 #REF! #REF! #REF! -
10634.96 156.27 4635.13 35 0 #REF! #REF! #REF!
10931.27 8.31 246.48 35 1775.9 #REF! #REF! #REF!
34069.24 106.10 3147.03
35 15870.75
43447.46 31.87 945.30 35 6948.9
3712.88 0.00 0.00 45 0
4510.55 47.93 1421.65 35 925.05
S/ 194,733.98 SUB TOTAL S/ 17,607.80 36353.9 30808.3898
S/ 35,052.12 IGV (18%) S/ 3,169.40
S/ 229,786.10 TOTAL S/ 20,777.20

ACUMULADO SALDO
MONTO METRADO MONTO

s/. METRADO s/.

0.00 42.98 100.00% 1274.83


0.00 30.15 100.00% 894.28

0.00 29.50 100.00% 500.00


0.00 3.58 100.00% 136.53
0.00 2.02 100.00% 59.92

0.00 39.96 100.00% 1523.90

0.00 5.80 100.00% 172.03


0.00 5.28 100.00% 201.36
0.00 4.17 100.00% 159.03

0.00 14.82 100.00% 439.58


0.00 13.39 100.00% 510.64
0.00 15.61 100.00% 595.30
0.00 17.26 100.00% 511.95
0.00 10.75 100.00% 318.86
ANTERIOR VALORIZACIÓN 10
ITEM DESCRIPCION METRADO PARCIAL TOTAL METRADO MONTO METRADO

METRADO S/ s/. METRADO % s/. METRADO

CERCO PERIMETRICO
SOBRECIMIENTOS,NORMAL 42.98 29.66102 1274.83 0.00 0.00% 0.00 42.98
COLUMENTAS Y VIGUETAS 30.15 29.66102 894.28 0.00 0.00% 0.00 30.15
AREA DE CIRCULACION
SARDINELES 29.5 16.94915 500.00 0.00 0.00% 0.00 29.50
RAMPA ENCOFRADO CARAVISTA 3.58 38.13559 136.53 0.00 0.00% 0.00 3.58
GRADAS, ENCOFRADO Y DES NORMAL 2.02 29.66102 59.92 0.00 0.00% 0.00 2.02
INSTALACION DE AREAS VERDES
SARDINEL PERALTADO, CARAVISTA 39.96 38.13559 1523.90 0.00 0.00% 0.00 39.25
PLAZOLETA CENTRAL
PISOS, ENCOFRADO NORMAL 5.8 29.66102 172.03 0.00 0.00% 0.00
SARDINEL PERALTADO, CARAVISTA 5.28 38.13559 201.36 0.00 0.00% 0.00 5.28
BANCA, ENFORADO CARAVISTA 4.17 38.13559 159.03 0.00 0.00% 0.00
MURO DE CONTENCION FRENTE A B1

SOBRECIMIENTOS ENCOFRADO CARAVISTA 14.82 29.66102 439.58 0.00 0.00% 0.00 14.82
COLUMNAS, CARAVISTA 13.39 38.13559 510.64 0.00 0.00% 0.00 13.39
VIGAS, CARAVISTA 15.61 38.13559 595.30 0.00 0.00% 0.00 15.61
LOSA ALIGERADA, NORMAL 17.26 29.66102 511.95 0.00 0.00% 0.00 17.26
COLUMNETAS Y VIGUETAS 10.75 29.66102 318.86 0.00 0.00% 0.00 10.75
SUB TOTAL S/7,298.18 SUB TOTAL S/0.00
IGV (18%) S/1,313.67 IGV (18%) S/0.00
TOTAL S/8,611.85 TOTAL S/0.00
VALORIZACIÓN 10 ACUMULADO SALDO
METRADO monto METRADO MONTO METRADO MONTO

% s/. METRADO % s/. METRADO s/.

100.00% 1274.83 42.98 100.00% 1274.83 0.00 0.00% 0.00


100.00% 894.28 30.15 100.00% 894.28 0.00 0.00% 0.00

100.00% 500.00 29.50 100.00% 500.00 0.00 0.00% 0.00


100.00% 136.53 3.58 100.00% 136.53 0.00 0.00% 0.00
100.00% 59.92 2.02 100.00% 59.92 0.00 0.00% 0.00

98.22% 1496.82 39.25 98.22% 1496.82 0.71 1.78% 27.08

0.00% 0.00 0.00 0.00% 0.00 5.80 100.00% 172.03


100.00% 201.36 5.28 100.00% 201.36 0.00 0.00% 0.00
0.00% 0.00 0.00 0.00% 0.00 4.17 100.00% 159.03

100.00% 439.58 14.82 100.00% 439.58 0.00 0.00% 0.00


100.00% 510.64 13.39 100.00% 510.64 0.00 0.00% 0.00
100.00% 595.30 15.61 100.00% 595.30 0.00 0.00% 0.00
100.00% 511.95 17.26 100.00% 511.95 0.00 0.00% 0.00
100.00% 318.86 10.75 100.00% 318.86 0.00 0.00% 0.00
SUB TOTAL S/6,940.04 SUB TOTAL S/6,940.04 SUB TOTAL S/358.14
IGV (18%) S/1,249.21 IGV (18%) S/1,249.21 IGV (18%) S/64.46
TOTAL S/8,189.25 TOTAL S/8,189.25 TOTAL S/422.60
9404.4
4472.2
9319.2
5032.3
3845.8
9769.5
5516.5
6588
6390.5
10856.5
2290
73484.9
VALORIZACIÓN 05

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: ENCOFRADO Y DESENCOFRADO
EJECUTA: CONSTRUCTORA VILCA S.A.C.
PERIODO: DEL 01/07/2019 AL 15/07/2019

ANTERIOR VALORIZACIÓN 06

ITEM DESCRIPCION METRADO PARCIAL TOTAL METRADO MONTO METRADO

METRADO S/ s/. METRADO % s/. METRADO %


1 ZAPATA ENCO. Y DESENC. 189.24 16.94915 3207.46 189.24 100.00% 3207.46 0.00 0.00%
2 COLUMNA ENCOF. Y DESEN. CARAVISTA 1336.1 38.13559 50952.97 939.26 70.30% 35819.24 113.29 8.48%
3 VIGAS ENCOF. Y DESENCOFRADO CARAVISTA 1061.46 38.13559 40479.41 612.84 57.74% 23371.02 235.12 22.15%
4 CIMIENTO ENCO. Y DESENC.NORMAL 514.82 29.66102 15270.08 349.08 67.81% 10354.07 9.47 1.84%
5 SOBRECIMIENTO ENCOF Y DESENC. NORMAL 376.85 29.66102 11177.75 258.11 68.49% 7655.81 56.50 14.99%
6 VIGUETAS ENCOF. Y DESENC. NORMAL
1254.72 29.66102 37216.27 343.97 0.08 10202.50 42.63 3.40%
7 COLUMNETAS ENCOF. Y DESENC. NORMAL
8 LOSA ALIGERADA ENCO. Y DESENCO. NORMAL 1496.67 29.66102 44392.75 861.34 57.55% 25548.22 319.04 21.32%
9 TANQUE CISTERNA 97.36 38.13559 3712.88 97.36 100.00% 3712.88 0.00 0.00%
10 ESCALERA 200 29.66102 5932.20 99.21 49.61% 2942.67 0.00 0.00%
SUB TOTAL S/212,341.78 SUB TOTAL S/. 122,813.86 SUB TOTAL
IGV (18%) S/38,221.52 IGV (18%) S/. 22,106.49 IGV (18%)
TOTAL S/250,563.30 TOTAL S/. 144,920.35 TOTAL

MONTO VALORIZADO ( A ) A
AMORTIZACION DE ADELANTO ( B ) B
SALDO VALORIZADO ( C ) (A-B) C (A-B)
MONTO RETENIDO 4% (4% DE C) 4% C
MONTO TOTAL A PAGAR TOTAL
VALORIZACIÓN 03

1 OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERAB


2 PARTIDA: ENCOFRADO Y DESENCOFRADO
3 EJECUTA: EDGAR VILCA
4 PERIODO: :DEL 16/05/2019 AL 31/05/2019

ITEM DESCRIPCION METRADO PARCIAL TOTAL EN SOLES

M2 s/ s/
1 ZAPATA ENCO. Y DESENC. 189.24 16.94915 3207.46
2 COLUMNA ENCOF. Y DESEN. NORMAL 126.28 29.66102 3745.59
3 COLUMNA ENCOF. Y DESEN. CARAVISTA 1336.1 38.13559 50952.97
4 VIGAS ENCOF. Y DESENCOFRADO CARAVISTA 1061.46 38.13559 40479.41
5 CIMIENTO ENCO. Y DESENC.NORMAL 514.82 29.66102 15270.08
6 SOBRECIMIENTO ENCOF Y DESENC. NORMAL 376.85 29.66102 11177.75
7 VIGUETAS ENCOF. Y DESENC. NORMAL
1128.44 29.66102 33470.68
8 COLUMNETAS ENCOF. Y DESENC. NORMAL
9 LOSA ALIGERADA ENCO. Y DESENCO. NORMAL 1496.67 29.66102 44392.75
10 TANQUE CISTERNA 97.36 38.13559 3712.88
SUB TOTAL S/206,409.58
IGV (18%) S/37,153.72
TOTAL S/243,563.30

B1 B2 B3 B4
ZAPATAS
COLUMNA CARAVISTA 347.82 139.86 240.72 165.3
VIGA CARAVISTA 306.14 139.86 240.72 165.3
CIMIENTO NORMAL 100 100 100 100
SOBRCIMIENTO NORMAL 117.65 48.18 57.57 63.16
VIGUETA NORMAL
COLUMNETA NORMAL 325.07 149.96 136.27 327.71
LOSA ALIGERADA 440.68 211.21 305.28 291.57
TANQUE CISTERNA
ESCALERA
MESON DE CONCRETO
RAMPA
PISO Y VEREDA CARAVISTA
ADOQUINES CARAVISTA
GRADA
SARDINELES CARAVISTA
BANCAS CARAVISTAS
NTO DE TACNA

LORIZACIÓN 06 ACUMULADO SALDO

monto METRADO MONTO METRADO MONTO

s/. METRADO % s/. METRADO s/. 0 0 30975.55 5575.60


0.00 189.24 100.00% 3207.46 0.00 0.00 20 0 4413.69 794.46
4320.38 1052.55 78.78% 40139.62 283.55 10813.35 45 5098.05 #REF! #REF!
8966.44 847.96 79.89% 32337.46 213.50 8141.95 45 10580.4 #REF! #REF!
280.89 358.55 69.65% 10634.96 156.27 4635.13 35 331.45 #REF! #REF!
1675.85 314.61 83.48% 9331.65 62.24 1846.10 35 1977.5 #REF! #REF!
1264.45 386.60 11.04% 11466.95 868.12 25749.32
35 1492.05
9463.05 1180.38 78.87% 35011.27 316.29 9381.48 35 11166.4
0.00 97.36 100.00% 3712.88 0.00 0.00 45 0
0.00 99.21 49.61% 2942.67 100.79 2989.53 35 0
S/. 25,971.06 SUB TOTAL S/ 148,784.92 SUB TOTAL S/ 63,556.86 30645.85 25971.0593
S/. 4,674.79 IGV (18%) S/ 26,781.28 IGV (18%) S/ 11,440.24
S/. 30,645.85 TOTAL S/ 175,566.20 TOTAL S/ 74,997.10

S/30,645.85
S/. 5,208.15
S/. 25,437.70
S/. 1,018.00
S/. 24,419.70
36551.15
5208.15
#REF!
#REF! -
#REF!
#REF!
CONSORCIO HATUN WASI

SR CONSTRUCTORA VILCA S.A.C.


PARTIDA ENCOFRADO Y DESENCOFRADO DE ELEMENTOS ESTRUCTURALES
PERIODO DEL 19 AL 31 DE AGOSTO

DESCRIPCION

VALORIZACION N° 10 DE LA SEGUNDA QUINCENA DE AGOSTO

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
AMORTIZACION DE ADELANTO B

MONTO TOTAL A PAGAR A-B

SUB TOTAL
IGV 18%
TOTAL

SON: DOS MIL NOVECIENTOS NOVENTA Y SIETE CON 42/100 SOLES


IMPORTE

S/. 6,940.04
S/. 4,399.86

S/. 2,540.18

S/. 2,540.18
S/. 457.23
S/. 2,997.42
VIGUETA Y
COLUMNET
SOBRECIMIENTO A COLUMNAS VIGAS LOSA ESCALERA MESON
92.86 11.4 223.2 155.42 236.43 18.07 15.8
24.79 5.48 124.62 150.72 204.25
11.4
B1
1.83
141.47
145.89
7.5
117.65 324.97 347.82 306.14 440.68 18.07 15.8
28.34 91.91 148.48 77.54 117.68 7.17
19.84 46.68 54.18 62.32 93.53
B2 8.05 2.75
0.57
56.8 141.34 202.66 139.86 211.21 0 7.17
57.57 16.9 118.67 81.2 97.25 36.24 4.74
7.75 60.32 79.76 98.66
7.75 60.32 79.76 109.37
19.29
9.28
B3 9.48
30.03
14.79
15.75
5.25
57.57 136.27 239.31 240.72 305.28 36.24 4.74
63.16 15.18 109.62 50.21 85.88 32.31 6.48
12.4 50.46 48.88 85.88
12.4 50.46 50.91 85.88
153.39 29.58 15.3 34.03
37.32
36.96
B4
17.01
18.64
8.7
8.7
7.01
63.16 327.71 240.12 165.3 291.67 32.31 6.48
40.71 55.27 181.44 86.19 120.59 23.83
6.6 61.21 55.68 53.82 54.99
B5 29.65 55.68 53.82 54.99
2.4
47.31 148.53 292.8 193.83 230.57 0 23.83
342.49 1078.82 1322.71 1045.85 1479.41 86.62 58.02
VALORIZACIÓN 07

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: INSTALACCIONES ELECTRICAS
EJECUTA: IDEL CARPIO LOPEZ
PERIODO: DEL 19/08/2019 AL 31/08/2019

VALORIZACION 6 ANTERIOR
ITEM DESCRIPCION UND CANTIDAD PRECIO COSTO
MONTOMETRADO %
1 TABLERO GENERAL UND 1 S/. 300.00 S/. 300.00### 0.67 67%
2 TABLERO DE DISTRIBUCION UND 12 S/. 200.00 S/. 2,400.00### 5.00 42%
3 SUBTABLERO DE DISTRIBUCION UND 6 S/. 200.00 S/. 1,200.00### 6.00 100%
4 SALIDA PARA CENTRO DE LUZ UND 348 S/. 27.00 S/. 9,396.00### 182.11 52%
SALIDAS PARA INTERRUPTORES SIMPLES, DOBLES Y DE
5 UND 149 S/. 27.00 S/. 4,023.00### 85.11 57%
CONMUTACION
6 SALIDA PARA TOMACORRIENTES UND 319 S/. 27.00 S/. 8,613.00### 144.22 45%
7 SALIDA P/TOMACORRIENTES ESTABILIZADOS UND 54 S/. 27.00 S/. 1,458.00### 39.00 72%
8 SALIDA PARA LUZ DE EMERGENCIA UND 51 S/. 27.00 S/. 1,377.00### 30.70 60%
SALIDA PARA SISTEMA DE ALARMAS Y SENSOR
9 UND 58 S/. 20.00 S/. 1,160.00### 44.00 76%
DETECTOR DE HUMO
10 SALIDA PARA TV CABLE Y AUDIO UND 63 S/. 20.00 S/. 1,260.00### 28.00 44%
11 CAJAS DE PASE UND 89 S/. 15.00 S/. 1,335.00### 26.67 30%
12 ALIMENTACION DE SUBESTACION A TABLERO GENERAL ML 8 S/. 10.00 S/. 80.00### 0.00 0%
ALIMENTADORES DE TABLERO GENERAL A TABLEROS
13 ML 375 S/. 8.00 S/. 3,000.00### 68.00 18%
DE DISTRIBUCION Y SUB TABLEROS DE DISTR.
14 ALIMENTADORES DE TG A T.D.T. Y T.E. ML 60 S/. 10.00 S/. 600.00### 40.00 67%
15 CIRCUITO PARA TERMA ELECTRICA UND 1 S/. 300.00 S/. 300.00### 0.33 33%
16 SALIDA PARA DATA, WIFI Y CAMARAS DE VIGILANCIA UND 60 S/. 20.00 S/. 1,200.00### 59.00 98%
17 ELECTROBOMBA EN RADARES UND 1 S/. 600.00 S/. 600.00### 0.17 17%
18 POZO Y SISTEMA DE PUESTA A TIERRA UND 7 S/. 550.00 S/. 3,850.00### 7.00 100%
19 SALIDA PARA INTERCOMUNICADORES Y TELEFONOS UND 10 S/. 20.00 S/. 200.00### 9.50 95%
20 BUZON DE PASE DE 70 X 60 X 65 X 47 UND 4 S/. 150.00 S/. 600.00### 1.00 25%
21 SALIDA PARA TERMA DE 6K=22v UND 1 S/. 250.00 S/. 250.00### 0.00 0%
22 SISTEMA ELECTRICO PARA ELEVADOR UND 1 S/. 350.00 S/. 350.00### 0.57 57%

COLOCACION DE ARTEFACTOS DE ILUMINACION Y


23 UND 377 S/. 20.00 S/. 7,540.00### 5.00 1%
EQUIPOS DE LUZ DE EMERGENCIA

SUBTOTAL S/. 51,092.00### SUBTOTAL


IGV(18%) S/. 9,196.56### IGV(18%)
TOTAL S/. 60,288.56### TOTAL
ZACIÓN 07

EL DEPARTAMENTO DE TACNA

ANTERIOR VALORIZACION 07 ACUMULADO SALDO


MONTO METRADO % MONTO METRADO % MONTO METRADO MONTO
S/. 200.00 0.00 0% S/. - 0.67 67% S/. 200.00 0.33 S/. 100.00
S/. 1,000.00 0.00 0% S/. - 5.00 42% S/. 1,000.00 7.00 S/. 1,400.00
S/. 1,200.00 0.00 0% S/. - 6.00 100% S/. 1,200.00 0.00 S/. -
S/. 4,917.00 58.00 17% S/. 1,566.00 240.11 69% S/. 6,483.00 107.89 S/. 2,913.00

S/. 2,298.00 25.00 17% S/. 675.00 110.11 74% S/. 2,973.00 38.89 S/. 1,050.00

S/. 3,894.00 61.00 19% S/. 1,647.00 205.22 64% S/. 5,541.00 113.78 S/. 3,072.00
S/. 1,053.00 0.00 0% S/. - 39.00 72% S/. 1,053.00 15.00 S/. 405.00
S/. 829.00 10.00 20% S/. 270.00 40.70 80% S/. 1,099.00 10.30 S/. 278.00

S/. 880.00 0.00 0% S/. - 44.00 76% S/. 880.00 14.00 S/. 280.00

S/. 560.00 0.00 0% S/. - 28.00 44% S/. 560.00 35.00 S/. 700.00
S/. 400.00 0.00 0% S/. - 26.67 30% S/. 400.00 62.33 S/. 935.00
S/. - 0.00 0% S/. - 0.00 0% S/. - 8.00 S/. 80.00

S/. 544.00 0.00 0% S/. - 68.00 18% S/. 544.00 307.00 S/. 2,456.00

S/. 400.00 16.00 27% S/. 160.00 56.00 93% S/. 560.00 4.00 S/. 40.00
S/. 100.00 0.00 0% S/. - 0.33 33% S/. 100.00 0.67 S/. 200.00
S/. 1,180.00 0.00 0% S/. - 59.00 98% S/. 1,180.00 1.00 S/. 20.00
S/. 100.00 0.00 0% S/. - 0.17 17% S/. 100.00 0.83 S/. 500.00
S/. 3,850.00 0.00 0% S/. - 7.00 100% S/. 3,850.00 0.00 S/. -
S/. 190.00 0.00 0% S/. - 9.50 95% S/. 190.00 0.50 S/. 10.00
S/. 150.00 0.00 0% S/. - 1.00 25% S/. 150.00 3.00 S/. 450.00
S/. - 0.00 0% S/. - 0.00 0% S/. - 1.00 S/. 250.00
S/. 200.00 0.00 0% S/. - 0.57 57% S/. 200.00 0.43 S/. 150.00

S/. 100.00 0.00 0% S/. - 5.00 1% S/. 100.00 372.00 S/. 7,440.00

S/. 24,045.00 SUBTOTAL S/. 4,318.00 SUBTOTAL S/. 28,363.00 SUBTOTAL S/. 22,729.00
S/. 4,328.10 IGV(18%) S/. 777.24 IGV(18%) S/. 5,105.34 IGV(18%) S/. 4,091.22
S/. 28,373.10 TOTAL S/. 5,095.24 TOTAL S/. 33,468.34 TOTAL S/. 26,820.22
CONSORCIO HATUN WASI

SR IDEL CARPIO LOPEZ


PARTIDA INSTALACIONES ELECTRICAS
PERIODO DEL 19 AL 31 DE AGOSTO

DESCRIPCION

VALORIZACION N° 6 DE LA PRIMERA QUINCENA DE AGOSTO DEL 2019 DE :

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
AMORTIZACION DE ADELANTO B

MONTO TOTAL A PAGAR A-B

SUB TOTAL
IGV 18%
TOTAL

SON: CUATRO MIL QUINIENTOS NOVENTA Y CINCO CON 24/100 SOLES


IMPORTE

S/. 4,318.00
S/. 423.73

S/. 3,894.27

S/. 3,894.27
S/. 700.97
S/. 4,595.24
VALORIZACIÓN 07

OBRA: CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA: INSTALACIONES SANITARIAS
EJECUTA: IDEL CARPIO LOPEZ
PERIODO: DEL 19/08/2019 AL 31/08/2019

ANTERIOR
ITEM DESCRIPCION UND CANTIDAD PRECIO COSTO
METRADO %
1 SALIDADE DESAGUE PTO 209 S/. 35.00 S/. 7,315.00 194 93%
EXCAVACION DE ZANJA
2 TUBERIA DE Ø 6" m 26 S/. 5.00 S/. 130.00 26 100%
3 TUBERIA DE Ø 4" m 113 S/. 5.00 S/. 565.00 95 84%

5 COSTRUCCION DE CAJA DE REGISTRO DE 0.3X0.6 SIN TAPA UND 18 S/. 60.00 S/. 1,080.00 14 78%

6 INSTALACION DE VENTILACION DE Ø 2" UND 68 S/. 35.00 S/. 2,380.00 68 100%


7 AMARRES DE VENTILACION DE Ø 2" UND 45 S/. 30.00 S/. 1,350.00 45 100%
8 INSTALACION DE MONTANTES DE DESAGUE Ø 4" UND 20 S/. 45.00 S/. 900.00 11 55%
AGUA POTABLE

9 SALIDA DE AGUA FRIA, CALIENTE PARA SANITARIOS Y DUCHAS PTO 140 S/. 35.00 S/. 4,900.00 103 74%

10 INSTALACIONES DE LLAVES DE PASO DE Ø 1", Ø 3/4" UND 38 S/. 35.00 S/. 1,330.00 2 5%
11 INSTALACION DE LLAVES DE MEZCLADORAS DE DUCHA UND 21 S/. 80.00 S/. 1,680.00 0 0%
INTALACIONES DE APARATOS SANITARIOS CON SUS
12 UND 84 S/. 60.00 S/. 5,040.00 0 0%
RESPECTIVOS WC, OVALINES Y URINARIOS
INSTALACIONES DE LAVADEROS Y LAVAPLATOS CON
13 UND 12 S/. 60.00 S/. 720.00 0 0%
ACCESORIOS

TENDIDO DE TUBERIAS DE ALIMENTACION DE AGUA FRIA Y CALIENTE EN TECHOS Y PRIMER

14 1ER NIVEL TUBERIA Ø 1" m 40 S/. 10.00 S/. 400.00 2 5%


15 3ER NIVEL TUBERIA Ø 1", Ø 1/4", Ø 1/2" m 60 S/. 10.00 S/. 600.00 0 0%
16 4TO NIVEL TUBERIA DE Ø 2", Ø 1 1/2", Ø 1 1/4" Y Ø 1" m 108 S/. 10.00 S/. 1,080.00 0 0%
17 AZOTEA TUBERIA DE Ø 2 1/2", Ø2" Y Ø 1 1/2" m 38 S/. 10.00 S/. 380.00 0 0%
INTALACION DE TUBERIAS DE ALIMENTACION DE AGUA FRIA Y
18 CALIENTE EN DUCTOS: TUBERIA DE Ø 2",1 1/2 Y 1" m 95 S/. 10.00 S/. 950.00 0 0%

19 INSTALACION DE GRIFO RIEGO PTO 2 S/. 45.00 S/. 90.00 0 0%


20 INSTALACION DE SUMIDERO Y REGISTROS ROSCADOS DE 4" Y 2" UND 114 S/. 15.00 S/. 1,710.00 0 0%
INSTALACION DE DOS TANQUES ELEVADOS DE AGUA DE 2500 LITROS
21 CADA UNO, CON SUS ACCESORIOS GLB 1 S/. 1,000.00 S/. 1,000.00 0 0%

INSTALACION DE DOS ELECTROBOMBAS CON SUS ACCESORIOS,


22 VALVULAS DE PASO, VALVULA CHECK, LINEA DE SUCCION E GLB 1 S/. 1,000.00 S/. 1,000.00 0 0%
IMPULSION
23 INSTALACION DE DRENAJE PLUVIAL 1ER NIVEL UND 8 S/. 35.00 S/. 280.00 0 0%
24 TENDIDO DE TUBERIAS DE DRENAJE PLUVIAL 1ER NIVEL m 26 S/. 5.00 S/. 130.00 0 0%
BAJADA DE DRENAJE PLUVIAL
25 2DO NIVEL UND 8 S/. 45.00 S/. 360.00 0 0%
26 3ER NIVEL UND 4 S/. 45.00 S/. 180.00 0 0%
27 4TO NIVEL UND 4 S/. 45.00 S/. 180.00 0 0%
28 5TO NIVEL UND 1 S/. 45.00 S/. 45.00 0 0%
SUBTOTAL ### SUBTOTAL
IGV(18%) S/. 6,439.50 IGV(18%)
TOTAL ### TOTAL
N 07

DEPARTAMENTO DE TACNA

ANTERIOR VALORIZACION 7 ACUMULADO SALDO


MONTO METRADO % MONTO METRADO MONTO METRADO MONTO
S/. 6,790.00 15 7% S/. 525.00 209 S/. 7,315.00 0 S/. -
ANJA
S/. 130.00 0 0% S/. - 26 S/. 130.00 0 S/. -
S/. 475.00 0 0% S/. - 95 S/. 475.00 18 S/. 90.00

S/. 840.00 0 0% S/. - 14 S/. 840.00 4 S/. 240.00

S/. 2,380.00 0 0% S/. - 68 S/. 2,380.00 0 S/. -


S/. 1,350.00 0 0% S/. - 45 S/. 1,350.00 0 S/. -
S/. 495.00 9 45% S/. 405.00 20 S/. 900.00 0 S/. -
LE

S/. 3,605.00 45 32% S/. 1,575.00 148 S/. 5,180.00 -8 S/. -280.00

S/. 70.00 20 53% S/. 700.00 22 S/. 770.00 16 S/. 560.00


S/. - 0 0% S/. - 0 S/. - 21 S/. 1,680.00

S/. - 0 0% S/. - 0 S/. - 84 S/. 5,040.00

S/. - 0 0% S/. - 0 S/. - 12 S/. 720.00

IA Y CALIENTE EN TECHOS Y PRIMER NIVEL

S/. 20.00 0 0% S/. - 2 S/. 20.00 38 S/. 380.00


S/. - 0 0% S/. - 0 S/. - 60 S/. 600.00
S/. - 0 0% S/. - 0 S/. - 108 S/. 1,080.00
S/. - 0 0% S/. - 0 S/. - 38 S/. 380.00

S/. - 40 42% S/. 400.00 40 S/. 400.00 55 S/. 550.00

S/. - 0 0% S/. - 0 S/. - 2 S/. 90.00


S/. - 0 0% S/. - 0 S/. - 114 S/. 1,710.00

S/. - 0 0% S/. - 0 S/. - 1 S/. 1,000.00

S/. - 0 0% S/. - 0 S/. - 1 S/. 1,000.00

S/. - 0 0% S/. - 0 S/. - 8 S/. 280.00


S/. - 0 0% S/. - 0 S/. - 26 S/. 130.00
PLUVIAL
S/. - 0 0% S/. - 0 S/. - 8 S/. 360.00
S/. - 0 0% S/. - 0 S/. - 4 S/. 180.00
S/. - 0 0% S/. - 0 S/. - 4 S/. 180.00
S/. - 0 0% S/. - 0 S/. - 1 S/. 45.00
S/. 16,155.00 SUBTOTAL S/. 3,605.00 SUBTOTAL S/. 19,760.00 SUBTOTAL S/. 16,015.00
S/. 2,907.90 IGV(18%) S/. 648.90 IGV(18%) S/. 3,556.80 IGV(18%) S/. 2,882.70
S/. 19,062.90 TOTAL S/. 4,253.90 TOTAL S/. 23,316.80 TOTAL S/. 18,897.70
CONSORCIO HATUN WASI

SR IDEL CARPIO LOPEZ


PARTIDA INSTALACIONES SANITARIAS
PERIODO DEL 19 AL 31 DE AGOSTO

DESCRIPCION

VALORIZACION N° 7 DE LA SEGUNDA QUINCENA DE AGOSTO

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
AMORTIZACION DE ADELANTO B

MONTO TOTAL A PAGAR A-B

SUB TOTAL
IGV 18%
TOTAL

SON: TRES MIL SETECIENTOS CINCUENA Y TRES CON 90/100 SOLES


IMPORTE

S/. 3,605.00
S/. 423.73

S/. 3,181.27

S/. 3,181.27
S/. 572.63
S/. 3,753.90
VALORIZACION N°06

OBRA :CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA : ALBAÑILERIA
V
SUBCONTRATIST:COLLAF CONTRATISTAS GENERALES S.A.C. A
EJECUTA :CONSORCIO HATUN WASI L
O
PERIODO : DEL 19/08/2019 AL 31/08/2019 R
BLOQUE 1,2 Y 4 I
M
Z
EC ANTERIOR
TI
ITEM ESPECIFICACIONES UND METRADO PRECIO PARCIAL PRECIO TOTAL R O METRADO MONTO
A
N
1 MUROS DE ARCILLA DE CABEZA M2 460.69 S/. 28.00 S/. 12,899.32### D 66.58 S/. 1,864.24
2 MUROS DE ARCILLA DE SOGA M2 1480.37 S/. 15.00 S/. 22,205.55### O
1 541.07 S/. 8,116.05
3 TARRAJEO EN MUROS M2 3113.52 S/. 15.00 S/. 46,702.80### 1734.85 S/. 26,022.75
MURO INTERIOR M2 2003.38
MURO EXTERIOR M2 663.42
PRIMARIO Y RAYADO M2 446.72
4 FONDO DE ESCALERA M2 55.93 S/. 15.00 S/. 838.95 ### 4.56 S/. 68.40
5 TARRAJEO DE CIELO RASO M2 807.55 S/. 15.00 S/. 12,113.25### 693.64 S/. 10,404.65
6 DERRAMES ML 715.20 S/. 9.00 S/. 6,436.80 ### 0.00 S/. 0.00
TOTAL S/. 101,196.67
SUBTOTALTOTAL S/. 46,476.09

47169.21
MENTO DE TACNA

VALORIZACIÓN 6 ACUMULADO SALDO


METRADO MONTO METRADO MONTO METRADO MONTO
0.00 S/. 0.00 66.58 S/. 1,864.24 394.11 S/. 11,035.08
0.00 S/. 0.00 541.07 S/. 8,116.05 939.30 S/. 14,089.50
601.34 S/. 9,020.11 2336.19 S/. 35,042.86 777.33 S/. 11,659.94

18.63 S/. 279.42 23.19 S/. 347.82 32.74 S/. 491.13


114.78 S/. 1,721.70 808.42 S/. 12,126.35 -0.87 -S/. 13.10
0.00 S/. 0.00 0.00 S/. 0.00 715.20 S/. 6,436.80
TOTAL S/. 11,021.23 TOTAL S/. 57,497.32 TOTAL S/. 43,699.35
CONSORCIO HATUN WASI

SR COLLAF CONTRATISTAS GENERALES S.A.C.


PARTIDA ALBAÑILERIA EN OBRA
PERIODO DEL 19 AL 31 DE AGOSTO DE 2019

DESCRIPCION

VALORIZACION N° 6 DE LA SEGUNDA QUINCENA DE AGOSTO

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
RETENCION (5%) B

MONTO TOTAL A PAGAR A-B

SUB TOTAL

SON: DIEZ MIL QUINIENTOS TREINTA Y TRES CON 19/100 SOLES


IMPORTE

S/. 11,021.23
S/. 551.06

S/. 10,470.17

S/. 10,470.17
cielo raso tarrajeo de muro
bloque 1 253.82
bloque 4
1er nivel 55.78 eje 4-5
volado frontal 10.41 eje 4b
sh damas 4
cocienta
9.1
guardiania eje 4-6
pasadizo 22.42
volado posterior 13.85 eje 4-6
eje 4-7
sh varones 4
EJE 4B

2do nivel 198.04


volado frontal 19.25
taller zapateria 41.87 bloque 1
taller de textileria 30.79 1er nivel
taller reposteria 30.79 GUARDIANIA
techo sobre escalera 10.78
pasillo 3 5
ta. Comp. Diseño 20.17
ta comput. Ensable 21.01 BORDE DE ESCALERA
pasillo 2 18.38

eje 1-4

eje 1-2

EJE 1-A
ESCALERA

EJE ENTRE 1-A Y 1-B

2DO NIVEL}
tarrajeo de muro 326.65

3.5 4.1 14.35 33.37


3.5 3.15 11.025

1.95 4.1 7.995

3.5 4.1 14.35 39.2


3.5 4.1 14.35
3.5 3 10.5

TOTAL B4 72.57

altura ANCHO
SE RESTAN VENTANAS Y PEUSRTA
guardiania int 3.6 2.93 10.55 10.55
3.2 4.25 13.6 9.475
guardiania ext 3.6 6.5 23.4 19.73
Y COCINETA 39.75
RDE DE ESCALERA 3.5 4.3 15.05
3.5 4.3 15.05
30.1

de 1D a 1E 2 3.3 3.2 20.02


EVNTANA 1.105
23.67
1B A 1C 5.05
1C A 1D 6.09
1D A 1E 6.11
1E A 1F 6.43

2.85 4 11.4 11.4


AREA LATERAL DE ESCALERA

ENTRE 1-A Y 1-B 3.15 4.3 13.545 13.55


AREA LATERAL DE ESCALERA

TALLER DE TEXTILERIA 26.06


EJE 1-D 11.87
EJE 1-C 14.19

TALLER DE REPOSTERIA 29.70


1D 14.19
1F 15.51

TALL. DE COMPUTO ENSAMBL 12.54


EJE 1-E 12.54

BORDE DE ESCALERA 47.32


EJE 1-A 14.05
EJE ENTRE
1-A Y1-B 28.38
(X2)
ENTREN 1-3 Y 1-4 4.88
TOTAL B1 254.08

TOTAL TARRAJEO MUROS 326.65


ASENTADO DE MUROS H=0.74 M QUITAR AREA DE VENTAN
BLOQUE 4 4.76
ALTURA ANCHO
EJE 4-2 0.74 1.12 3.32 3.91
DESDE 4-A A VOLADO X4

EJE 4-A´(VOLADO) 0.74 15.32 11.34


DESDE 4-2 A 4-7
RESUMEN
TARRAJEO CIELO RASO
TARRAJEO MURO
TOTAL ASENTADO DE MURO SOGA 14.65 ASENTADO MURO SOGA
QUITAR MURO NO EXISTENTE BLOQUE
QUITAR AREA DE VENTANA 1 EJE 1B DE 11 A 12
10.88

VAL 4 DESCUENTO TOTAL VAL 4


253.82 0 253.82
326.65 19.55 307.10
14.65 0 14.65
2DO NIVEL CIELO RASO
BLOQUE 02 ancho altura AREA PARCIAL BLOQUE 1 AREA
EJE 2-2 0.31 1-1 a 1-3 // 1-A a 1-B 45.40
De 2-A¨a 2-A 0.57 0.54 0.31 1-2 a 1-3 // 1-B a 1-C 15.04
de 2 - A a columneta 2.53 0 0.00 1-2 a 1-3 // 1-C a 1-D 15.75
de columneta a columneta 1.99 0 0.00 1-2 a 1-3 // 1-D a 1-E 14.34
1-2 a 1-3 // 1-E a 1-F 16.45
EJE 2-4 0.00 1-3 a 1-4 // 1-A´ a 1-B 15.08
de 2-b a columneta 0.98 0 0.00 1-B a 1-C // EJE ENTRE 1-3 Y 1-4 a 1-4 12.00
1-C a 1-D // EJE ENTRE 1-3 Y 1-4 a 1-4 12.56
EJE 2-5 4.59 1-D a 1-E // EJE ENTRE 1-3 Y 1-4 a 1-4 11.44
De 2-A¨a 2-A 0.57 0.96 0.55 TOTAL B1 1ER NIVEL 158.06
de 2 - A a columneta
4.04 0 4.04
de columneta a 2 -B BLOQUE 2
de 2B a 2C 2.15 0 0.00 1er paño 0 4.89 0.00
2do paño 0 3.35 0.00
EJE 2-B 0.00 3er paño PAÑO RESTANTE 22.88
de 2-4 a 2-5 3.52 2.74 0.00 TOTAL B2 2DO NIVEL 22.88

1ER NVEL BLOQUE 5


BLOQUE 02 paño entre 5-1 a 5-2 12.25
EJE 2-1 0.43 paño entre 5-2 a 5-3 11.62
de 2-A a 2-B 0.88 0 0.00 paño entre 5-3 a 5-4 13.30
0.23 0.63 0.14 paño entre 5-4 a 5-5 18.94
0.45 0.63 0.28 AREA TOTAL BLOQUE 5 2DO NIVEL 56.11
0.43 AREA 1 VALORIZACION 43.28
EJE 2-2 TOTAL B5 2DO NIVEL (2VAL) 12.83
de 2-A a 2-B 3.8 0.75 2.85 2.85
TOTAL CIELO RASO
EJE 2-5 4.08
de 2-A a columneta 2.6 0.75 1.95
de columneta a 2-B 2.84 0.75 2.13 VOLADO B1
4.08 AREA= 8.84

EJE 2- A 6.06
de 2-1 a 2-2 2.47 1.9 4.69
de 2-2 a 2-3 2.74 0 0.00
de 2-3 a 2-4 2.1 0 0.00
de 2-4 a 2-5 1.44 0.95 1.37
6.06
EJE 2-C 21.72 TOTAL
de 2-2 a columnete despues
de 2-3 4.78 0.95 4.54
de 2-4 a 2-5 2.52 0.95 2.39
(2-A/2-B)//(2-1/2-B) 14.79 14.79

AREA TOTAL MURO SOGA B2 40.04 ADICIONALES


AREA TOTAL MURO CABEZA B2 0 TARRAJEO PRIMARIO
bloque 4
ancho altura area PARCIAL
EJE 4-1 10.55
desde 4-A´ a 4-A 1.4 2.9 4.06
desde 4-A a columneta 1.93 2.9 5.60
desde columneta a 4-B 0.65 1.38 0.90
0.00
10.55
EJE 4-2 ancho altura area 8.26
desde 4-A´ a 4-A 0 0 0.00
desde 4-A a columneta 1.93 2.9 5.60
desde columneta a 4-B 1.93 1.38 2.66
8.26
EJE 4-4 ancho altura area
desde 4-A´ a 4-A 0 0 0.00 11.19
desde 4-A a columneta 1.93 2.9 5.60
desde columneta a 4-B 1.93 2.9 5.60
11.19
EJE 4-5 ancho altura area 10.62
desde 4-A´ a 4-A 0 0 0.00
desde 4-A a columneta 1.93 2.75 5.31
desde columneta a 4-B 1.93 2.75 5.31
10.62
EJE 4-6 ancho altura area 10.62
desde 4-A´ a 4-A 0 0 0.00
desde 4-A a columneta 1.93 2.75 5.31
desde columneta a 4-B 1.93 2.75 5.31
10.62
EJE 4-7 ancho altura area 14.47
desde 4-A´ a 4-A 1.4 2.75 3.85
desde 4-A a columneta 1.93 2.75 5.31
desde columneta a 4-B 1.93 2.75 5.31
14.47
EJE 4-A' ancho altura area 10.49
desde 4-1 a 4-2 1.05 1.02 1.07
desde 4-3 A 4-4 2.94 1.02 3.00
desde 4-4 A 4-5 2.94 1.02 3.00
desde 4-5 A 4-6 1.65 1.02 1.68
desde 4-6 A 4-7 1.7 1.02 1.73
10.49

EJE 4-A ancho altura area 9.53


desde 4-3 A 4-4 1.47 1.02 1.50
desde 4-4 A 4-5 1.52 1.02 1.55
desde 4-5 A 4-6 1.72 1.97 3.39
desde 4-6 A 4-7 1.57 1.97 3.09
9.53

EJE 4-B ancho altura area


4-1 A 4-2 2.4 2.9 6.96 6.96
4-2 A 4-7 15 2.9 43.5 43.5

AREA TOTAL MURO SOGA B4 110.41


AREA TOTAL MURO CABEZA B2 25.77
bloque 5
BLOQUE 5

eje 5-A ancho altura area


desde 5-1 a 5-2 2.19 0.98 2.15
desde 5-2 a 5-3 2.04 0.98 2.00
4.15

eje 5-B ancho altura area


desde 5-1 a 5-2 1.32 2.42 3.19
DESE 5-2 a 5-3 1.17 2.42 2.83
desde 5-3 a 5-4 1.17 1.05 1.23
7.25

eje 5-C ancho altura area


7.76 0.98 7.60

eje 5-5 ancho altura area


desde 5-a a 5-b 1.22 2.42 2.95

eje 5-4 ancho altura area


1.74 2.42 4.21
eje 5-2 ancho altura area
1.74 2.42 4.21

AREA TOTAL BLOQUE 5 2DO NIVEL 41.70


AREA 1 VALORIZACION 30.38
AREA TOTAL MURO SOGA B5 2DO NIVEL (2DA VAL) 11.32

TOTAL MURO DE SOGA 161.76


TOTAL MURO DE CABEZA 25.77
TARRAJEO DE MUROS
BLOQUE 2
base altura
VOLADO
EJE 2-A DE 2-1/2-2 3.03 1.50 4.55
EJE 2-1 DE 2-A/2-B 4.67 1.50 7.01
EJE 2-B DE 2-1/2-1´ 1.1 1.50 1.65
EJE 2-1´ DE 2-B/2-C 3.03 0.90 2.73
EJE 2-C DE 2-1´/2-2 1.94 0.90 1.75
17.67

base altura
EJE 2-C
desde 2-2 a 2-3 4.5 2.75 12.38

EJE 2-4 base altura


de 2-B a columneta(exte) 1.38 2.55 3.52
de 2-B a columneta(inte) 1.23 2.55 3.14
6.66

EJE 2-B base altura


desde 2-4 a 2-5 (exterior) 3.88 2.99 11.60
desde 2-4 a 2-5 (intterior) 3.73 2.95 11.00
22.60

EJE 2-5 base altura


desde 2B a 2C 2.40 2.55 6.12
AREA TOTAL TARRAJEO B2 2DO NIVEL 59.31
193.77
BLOQUE 1
EJE 1-A base altura
de 1-1 a ascensor (right) 6.42 3.2 20.54
20.54
EJE 1-B
de 1-1 a 1-3(left) 7.70 3.2 24.64
de 1-2 a 1-3(right) 4.3 3.2 13.76
38.40
EJE 1-C
de 1-2 a 1-3(left) 4.3 3.2 13.76
de 1-2 a 1-3(right) 4.3 3.2 13.76
202.61 27.52
EJE 1-D
de 1-2 a 1-3(left) 4.3 3.2 13.76
de 1-2 a 1-3(right) 4.3 3.2 13.76
27.52
EJE 1-E
de 1-2 a 1-3(left) 4.3 3.2 13.76
de 1-2 a 1-3(right) 4.3 3.2 13.76
27.52
EJE 1-A´ base altura
de 1-3´ a 1-4 right 4.12 3.2 13.18
13.18
EJE 1-B
de 1-3´ a 1-4 (left) 3.80 3.2 12.16
de 1-3´ a 1-4 (right) 3.8 3.2 12.16
24.32
EJE 1-C
de 1-2 a 1-3(left) 3.8 3.2 12.16
de 1-2 a 1-3(right) 3.8 3.2 12.16
24.32
EJE 1-D
de 1-2 a 1-3(left) 3.8 3.2 12.16
de 1-2 a 1-3(right) 0 3.2 0.00
12.16
EJE 1-E
de 1-2 a 1-3(left) 3.8 3.2 12.16
de 1-2 a 1-3(right) 0 3.2 0.00
12.16

AREA TOTAL TARRAJEO B1 1ER NIVEL 227.65

AREA TOTAL TARRAJEO 286.96

BLOQUE 5
EJE 5-A ANCHO ALTURA
DE 5-4 5-5 2.17 1.6 3.47
1 2.5 2.50
5.97

BLOQUE 1 base altura


EJE 1-F (left) 4.7 3.2 15.04

EJE 1-2
AREA 1 (1-B A 1-C 5.05 5.05

AREA 2 (1-C A 1-D 6.09 6.09

AREA 3 (1-D A 1-E 6.11 6.11

AREA 4 (1-E A 1-F 6.43 6.43


23.67

EJE 1-3 BASE ALTURA


AREA 1 (1-B A 1-C) 2 1.85 3.2 11.84

AREA 2 (1-C A 1-D 2 2.05 3.2 13.12

AREA 3 (1-D A 1-E 2 1.85 3.2 11.84

AREA 4 (1-E A 1-F 1 2.05 3.2 6.56

43.36

EJE 1-3´ BASE ALTURA


AREA 1 (1-B A 1-C) 2 2.27 3.4 15.44

AREA 2 (1-C A 1-D 2 5.65 3.2 36.16


51.60

EJE 1-4 BASE ALTURA


AREA 1 (1-B A 1-C) 2 2.8 3.2 17.92

AREA 2 (1-C A 1-D 2 6.2 3.2 39.68


57.60

FONDO DE ESCALERA
1 1.2 3.8 4.56
BLOQUE 4

EJE 4-B BASE ALTURA


DE 4-2 A 4-3 2.95 3.6 10.62
DE 4-3 A 4-4 2.95 3.6 10.62
DE 4-4 A 4-5 2.95 3.6 10.62
31.86
EJE 4-4
DE 4-A A 4-B 2 4.1 3.6 29.52
1 4.1 3.6 14.76
44.28

545.29
VALORIZACION N°04

OBRA :CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA : ALBAÑILERIA
V
SUBCONTRATIST:AVCOC E.I.R.L. A
EJECUTA :CONSORCIO HATUN WASI L
O
PERIODO : DEL 17/08/2019 AL 31/08/2019 R
I
M
Z
EC ANTERIOR
TI
ITEM ESPECIFICACIONES UND METRADO PRECIO PARCIAL PRECIO TOTAL R O METRADO MONTO
A
N
1 MUROS DE ARCILLA DE CABEZA M2 0.00 S/. 28.00 S/. 0.00 ### D 0.00 S/. 0.00
2 MUROS DE ARCILLA DE SOGA M2 0.00 S/. 15.00 S/. 0.00 ### O
1 0.00 S/. 0.00
3 TARRAJEO EN MUROS M2 2258.12 S/. 15.00 S/. 33,871.80### 1094.74 S/. 16,421.05
MURO INTERIOR M2 1354.28
MURO EXTERIOR M2 768.39
PRIMARIO Y RAYADO M2 141.42
4 FONDO DE ESCALERA M2 24.78 S/. 15.00 S/. 371.70 ### 0.00 S/. 0.00
5 TARRAJEO DE CIELO RASO M2 376.42 S/. 15.00 S/. 5,646.30 ### 338.81 S/. 5,082.15
6 DERRAMES ML 473.35 S/. 8.00 S/. 3,786.80 ### 0.00 S/. 0.00
SUBTOTAL S/. 43,676.60
SUBTOTAL
SUBTOTAL S/. 21,503.20
TAMENTO DE TACNA

VALORIZACIÓN 4 ACUMULADO SALDO


METRADO MONTO METRADO MONTO METRADO MONTO
0.00 S/. 0.00 0.00 S/. 0.00 0.00 S/. 0.00
0.00 S/. 0.00 0.00 S/. 0.00 0.00 S/. 0.00
584.92 S/. 8,773.76 1679.65 S/. 25,194.80 578.47 S/. 8,677.00

24.78 S/. 371.70 24.78 S/. 371.70 0.00 S/. 0.00


88.77 S/. 1,331.55 427.58 S/. 6,413.70 -51.16 -S/. 767.40
141.55 S/. 1,132.40 141.55 S/. 1,132.40 331.80 S/. 2,654.40
SUBTOTAL S/. 11,609.41 SUBTOTAL S/. 33,112.60 SUBTOTAL S/. 10,564.00
LOSA TOTAL
BLOQUE 3 103.07

CIELO RASO MURO


1ER NIVEL 27.02 DORMI 14 ANCHO ALTURA
AREA VOLADO0 27.02 3-C 4 2.7
3-D 4 2.7

2DO NIVEL 76.05


DORMITORIO 4 11
5 11.4
6 11.4 MUROS B3 196.33
7 11.4 1ER NIVEL 122.13
8 11.4 2DO NIVEL 74.2
9 11.4
AREA VOLADO 8.05

MURO DE ALBAÑILERIA
ALACENA
BLOQUE 5

CIELO RASO
1ER NIVEL 111.77
ALMACEN 4.46
DEPOSITO DE MUEBREL 7.43
LIMPIEZA 2.64
PASADIZO 10.30
COCINA 15.12
S.H. DAMAS 3 5.46
S.H. VARONES 3 5.11
COMEDOR 61.25

TOTAL METRADO 111.77


1VAL 91.97

TOTAL 2DA VAL 19.80

MUROS 1ER NIVEL


ALMACEN 27.90
DEPOSITO DE MUEBLES 17.78
LIMPIEZA 3 21.80
PASADIZO ENTRE 5-1 Y 5- 36.78
2 (--I)
COCINA 34.85
SSHH DAMAS 3 16.60
SSHH VARONES 3 17.11
COMEDOR 47.76
220.57
EXTERIOR B5 EJE 5A, 55(L) 59.85
MUROS 2DO NIVEL
EJE 5-4 DE 5-A A 5-B

EN GENERAL 58.71

TOTAL METRADO B5 339.14


1VAL 83.95
255.19

TOTAL METRADO MURO B5 Y B3 535.47


1 VAL 83.95
2 VAL 451.52
MURO B5 281.34 MURO B3 205.5
TECHO B5 15.25 TECHO B3 116.23

RESUMEN MURO LOSA


B5
B3

477.67
MUROS 451.52 118.32
TECHO 122.87
MURO
BLOQUE 5 BASE ALTURA
EJE 5-A
DE 5-2 A 5-3 2.6 3.95 10.27
7.96 7.96
EJE 5-B
DE 5-3 A 5-4 2.6 3.95 10.27
DE 5-4 A 5-5 1.12 3.95 4.42

EJE 5-2
DE 5-A A 5-B 2.25 3.95 8.89
DE 5-B A 5-C 6.25 3.95 24.69

EJE 5-5
DE 5-B A 5-C L 7.2 3.85 27.72

83.95
LOSA
BLOQUE 5
5-A 5-B Y 5-1 5-2 2.5 2.95 7.38
5-B 5-C Y 5-1 5-2 6.25 1.48 9.22
X Y
5-2 Y 5-3 DESSDE 5-A A 5- 8.75 2.8 24.50
5-3 Y 5-4 DESSDE 5-A A 5- 8.75 2.8 24.50
5-4 Y 5-5 DESSDE 5-B A 5- 6.25 4.22 26.38
91.97
CONSORCIO HATUN WASI

SR AVCOC E.I.R.L.
PARTIDA ALBAÑILERIA EN OBRA
PERIODO DEL 19 AL 31 DE AGOSTO

DESCRIPCION

VALORIZACION N° 4 DE LA SEGUNDA QUINCENA DE AGOSTO

CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES


VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL
DEPARTAMENTO DE TACNA

MONTO VALORIZADO A
RETENCION (5%) B

MONTO TOTAL A PAGAR A-B

SUB TOTAL
IGV 18%
TOTAL

SON: TRECE MIL CATORCE CON 14/100 SOLES


IMPORTE

S/. 11,609.41
S/. 580.47

S/. 11,028.93

S/. 11,028.93
S/. 1,985.21
S/. 13,014.14
VALORIZACION N°03

OBRA :CREACION DEL CENTRO DE ATENCION INTEGRAL A POBLACIONES VULNERABLES AFECTADAS POR VIOLENCIA FAMILIAR EN EL DEPARTAMENTO DE TACNA
PARTIDA : ALBAÑILERIA
SUBCONTRATIST:COLLAF CONTRATISTAS GENERALES S.A.C.
EJECUTA :CONSORCIO HATUN WASI
PERIODO : DEL 01/06/2017 AL 20/06/2017

ANTERIOR
ITEM ESPECIFICACIONES UND METRADO PRECIO PARCIAL PRECIO TOTAL METRADO MONTO
1 MUROS DE ARCILLA DE CABEZA M2 460.69 S/. 28.00 S/. 12,899.32 40.81 S/. 1,142.68
2 MUROS DE ARCILLA DE SOGA M2 2236.41 S/. 15.00 S/. 33,546.15 361.36 S/. 5,420.40
3 TARRAJEO EN MUROS M2 5181.09 S/. 15.00 S/. 77,716.35 0.00 S/. 0.00
MURO INTERIOR M2 3303.87
MURO EXTERIOR M2 1289.08
PRIMARIO Y RAYADO M2 588.14
4 FONDO DE ESCALERA M2 80.71 S/. 15.00 S/. 1,210.65 0.00 S/. 0.00
5 TARRAJEO DE CIELO RASO M2 1177.73 S/. 15.00 S/. 17,665.95 134.84 S/. 2,022.60
6 DERRAMES ML 1183.35 S/. 9.00 S/. 10,650.15 0.00 S/. 0.00
SUBTOTAL S/. 130,244.55 SUBTOTAL S/. 7,276.00
IGV (18%) S/. 23,444.02 IGV (18%) S/. 1,309.68
TOTAL S/. 153,688.57 TOTAL S/. 8,585.68
TARRAJEO DE MURO TARRAJEO TARRAJEO
ASENTADO DE MURO
PRIMARIO Y
RAYADO INTERIOR EXTERIOR DERRAME CIELO RASO ESCALERA
CABEZA SOGA
BLOQUE 1 152.78 471.09 185.01 1025.88 130.15 317 406.50 19.27
BLOQUE 2 - 187.19 38.24 220.97 150.56 193.2 103.00 -
BLOQUE 3 192.89 348.45 28.47 836.59 445.07 259.9 200.40 24.78
BLOQUE 4 115.02 766.28 223.47 702.74 239.98 199.8 235.70 36.66
BLOQUE 5 - 341.11 112.95 463.90 180.59 208.25 214.78 -
CERCO PERIME. - 55.81 - - 142.73 - - -
SUBESTACION - 66.48 - 53.79 - 5.2 17.35 -
TOTAL 460.69 2236.41 588.14 3303.87 1289.08 1183.35 1177.73 80.71
AMENTO DE TACNA

VALORIZACIÓN 3 ACUMULADO SALDO


METRADO MONTO METRADO MONTO METRADO MONTO
25.77 S/. 721.56 66.58 S/. 1,864.24 394.11 S/. 11,035.08
165.06 S/. 2,475.90 526.42 S/. 7,896.30 1709.99 S/. 25,649.85
545.29 S/. 8,179.35 545.29 S/. 8,179.35 4635.80 S/. 69,537.00

4.56 S/. 68.40 4.56 S/. 68.40 76.15 S/. 1,142.25


202.61 S/. 3,039.15 337.45 S/. 5,061.75 840.28 S/. 12,604.20
0.00 S/. 0.00 0.00 S/. 0.00 1183.35 S/. 10,650.15
SUBTOTAL S/. 12,274.88 SUBTOTAL S/. 19,550.88 SUBTOTAL S/. 110,693.67
IGV (18%) S/. 2,209.48 IGV (18%) S/. 3,519.16 IGV (18%) S/. 19,924.86
TOTAL S/. 14,484.36 TOTAL S/. 23,070.04 TOTAL S/. 130,618.53
RESIDENTE DE OBRA
asentado e ladrillos
bloque 4 BLOQUE 2 PURO MURO DE SOG
2do nivel
EJE 4-1 ancho altura area EJE 2-2 ancho
desde 4-A´ a 4-A 1.4 3.8 5.32 De 2-A¨a 2-A 0.57
desde 4-A a columneta 1.93 3.8 7.33 de 2 - A a columneta 2.53
desde columneta a 4-B 0.65 3.8 2.47 de columneta a columneta 1.99
1.28 1.48 1.89
17.02 eje 2-4
EJE 4-2 ancho altura area de 2-b a columneta 0.98
desde 4-A´ a 4-A 1.22 2.34 2.85
desde 4-A a columneta 1.93 3.8 7.33 eje 2-5 ancho
desde columneta a 4-B 1.93 3.8 7.33 De 2-A¨a 2-A 0.57
17.52 de 2 - A a columneta
EJE 4-4 ancho altura area de columneta a 2 -B 4.04
desde 4-A´ a 4-A 1.22 2.34 2.85 de 2B a 2C 2.15
desde 4-A a columneta 1.93 3.8 7.33
desde columneta a 4-B 1.93 3.8 7.33 EJE 2-A' ancho
17.52 2-2 a 2-3 3.05
EJE 4-5 ancho altura area 2-3 a 2-4 2.16
desde 4-A´ a 4-A 1.22 1.37 1.67 2-4 a columnetea 1.1
desde 4-A a columneta 1.93 3.8 7.33 de columneta a 2-5 1.8
desde columneta a 4-B 1.93 3.8 7.33
16.34 EJE 2-B
EJE 4-6 ancho altura area de 2-4 a 2-5 3.52
desde 4-A´ a 4-A 1.22 2.34 2.85
desde 4-A a columneta 1.93 3.8 7.33 EJE 2-c
desde columneta a 4-B 1.93 3.8 7.33 de 2-2 a 2-3 3.98
17.52 de 2-3 a 2-4 0.72
EJE 4-7 ancho altura area de 2-4 a 2-5 2.51
desde 4-A´ a 4-A 1.22 3.8 4.64
desde 4-A a columneta 1.93 3.8 7.33
desde columneta a 4-B 1.93 3.8 7.33
19.30 1er nivel
EJE 4-A' ancho altura area eje 2-1
desde 4-5 a 4-6 2.05 1.8 3.69 de 2-A a 2-B 0.88
desde 4-6 A 4-7 1.86 1.8 3.35 1.3
7.04 1.63
EJE 4-B ancho altura area
4-1 A 4-2 2.4 3.8 9.12 eje 2-2
4-2 A 4-7 14.9 3.8 56.62 de 2-A a 2-B 3.8

CABEZA 40.81 eje 2-5


SOGA 137.20 de 2-A a columneta 2.6
de columneta a 2-B 2.84

eje 2-A
de 2-1 a 2-2 2.47
de 2-2 a 2-3 2.74
de 2-3 a 2-4 2.1
de 2-4 a 2-5 1.44

eje 2-c
de 2-2 a columnete 4.78
despues de 2-3
de 2-4 a 2-5 2.52

CABEZA 0.00
SOGA 124.22
tado e ladrillos c
PURO MURO DE SOGA BLOQUE 5 bloque 5
2do nivel entre 5-A y volado; 5-1 y
altura area eje 5-A ancho altura area 5-2
2.21 1.26 desde 5-1 a 5-2 2.19 0.98 2.15 entre 5-A y volado; 5-2 y
0.85 2.15 desde 5-2 a 5-3 2.04 0.98 2.00 5-3
2.34 4.66 4.15 entre VOLADO y volado;
8.07 5-3 y 5-4
eje 5-B entre 5-B y volado; 5-4 y
2.31 2.26 desde 5-1 a 5-2 1.32 2.42 3.19 5-5
DESE 5-2 a 5-3 1.17 2.42 2.83
altura area desde 5-3 a 5-4 1.17 1.05 1.23
1.79 1.02 7.25 bloque 2
1er paño
2.31 6.35 eje 5-C 2do paño
2.31 4.97 7.76 0.98 7.60
12.34
altura area eje 5-5
2.94 8.97 desde 5-a a 5-b 1.22 2.42 2.95
0.97 2.10
0.97 1.07 eje 5-4
2.97 5.35 1.74 2.42 4.21
17.48
eje 5-2
2.74 9.64 1.74 2.42 4.21

2.52 10.03
2.52 1.81 total ssoga 30.38
2.52 6.33
18.17

1er nivel cero perimetrico


69.56
1.58 1.39
1.58 2.05
1.58 2.58
6.02

2.35 8.93

2.04 5.30
2.04 5.79
11.10
1.38 3.41
1.28 3.51
1.28 2.69
2.4 3.46
13.06

2.35 11.23

2.35 5.92
224.16

40.81 total caeza 1er nivel


361.36 total soga 1er nivel

cabeza total 6.45


soa total 227.85
tarrajeo 43.28
cielo raso
ancho(eje x) largo(eje y)
ntre 5-A y volado; 5-1 y 4.15 2.95 12.24
5-2
ntre 5-A y volado; 5-2 y 4.15 2.8 11.62
5-3
entre VOLADO y volado; 4.75 2.8 13.30
5-3 y 5-4
entre 5-B y volado; 5-4 y 1.45 4.22 6.12
5-5
43.28

bloque 2
7.9 4.89 38.63
7.9 3.35 26.47

total tarrajeo 43.28