PLANTILLA SUSTENTACION DE METRADOS

Construcción de Reservorio de 500 m3

Partida 01.03.05.01.03 Zapatas reforzados acero fy=4200 kg/cm2 Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud Total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

Acero circular inferior


Per1= 2*3.1416*7.17=39.14m 1 1/2" 1.00 45.05 45.05
Per2= 2*3.1416*7.19=37.89m 1 1/2" 1.00 45.18 45.18
Per3= 2*3.1416*7.05=36.63m 1 1/2" 1.00 44.30 44.30
Per4= 2*3.1416*6.90=35.37m 1 1/2" 1.00 43.35 43.35
Per5= 2*3.1416*7.22=34.12m 1 1/2" 1.00 45.36 45.36
Per6= 2*3.1416*7.22=32.86m 1 1/2" 1.00 45.36 45.36
Per7= 2*3.1416*6.75=31.60m 1 1/2" 1.00 45.36 45.36
Per8= 2*3.1416*6.60=30.35m 1 1/2" 1.00 41.47 41.47
Per9= 2*3.1416*6.45=29.09m 1 1/2" 1.00 40.53 40.53
Per10= 2*3.1416*6.30=27.83m 1 1/2" 1.00 39.58 39.58

Calculos Acero radial inferior


Long c/uno=3.73m (Autocad)
Per1= 2*3.1416*7.3=45.84m
Cantidad Acero= 45.84/0.20= 157 und 1 1/2" 230.00 3.73 857.90

Metrado Total 0.00 435.55 857.90 0.00 0.00


1,114.74 0.00 248.26 866.48 0.00 0.00

Partida 01.03.05.02.03 Losa de cimentacion acero fy=4200 kg/cm2 Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud Total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"
Acero superior e inferior radial
Per1= 2*3.1416*6.44=40.44m 1 1/2" 1 40.44 40.44
Per1= 2*3.1416*6.23=39.14m 1 1/2" 1 39.14 39.14
Per1= 2*3.1416*6.03=37.89m 1 1/2" 1 37.89 37.89
Per1= 2*3.1416*5.83=36.63m 1 1/2" 1 36.63 36.63
Per1= 2*3.1416*5.63=35.37m 1 1/2" 1 35.37 35.37
Per1= 2*3.1416*5.43=34.12m 1 1/2" 1 34.12 34.12
Per1= 2*3.1416*5.23=32.86m 1 1/2" 1 32.86 32.86
Per1= 2*3.1416*5.03=31.60m 1 1/2" 1 31.60 31.60
Per1= 2*3.1416*4.83=30.35m 1 1/2" 1 30.35 30.35
Per1= 2*3.1416*4.63=29.09m 1 1/2" 1 29.09 29.09
Per1= 2*3.1416*4.43=27.83m 1 1/2" 2 27.83 55.66
Per1= 2*3.1416*4.23=26.58m 1 1/2" 2 26.58 53.16
Per1= 2*3.1416*4.03=25.32m 1 1/2" 2 25.32 50.64
Per1= 2*3.1416*3.83=24.06m 1 1/2" 2 24.06 48.12
Per1= 2*3.1416*3.63=22.81m 1 1/2" 2 22.81 45.62
Per1= 2*3.1416*3.43=21.55m 1 1/2" 2 21.55 43.10
Per1= 2*3.1416*3.23=20.29m 1 1/2" 2 20.29 40.58
Per1= 2*3.1416*3.03=19.04m 1 1/2" 2 19.04 38.08
Per1= 2*3.1416*2.83=17.78m 1 1/2" 2 17.78 35.56
Per1= 2*3.1416*2.63=16.52m 1 1/2" 2 16.52 33.04
Per1= 2*3.1416*2.43=15.27m 1 1/2" 2 15.27 30.54
Per1= 2*3.1416*2.23=14.01m 1 1/2" 2 14.01 28.02
Per1= 2*3.1416*2.03=12.75m 1 1/2" 2 12.75 25.50
Per1= 2*3.1416*1.83=11.50m 1 1/2" 2 11.50 23.00
Per1= 2*3.1416*1.63=10.24m 1 1/2" 2 10.24 20.48
Per1= 2*3.1416*1.43= 8.98m 1 1/2" 2 8.98 17.96
Per1= 2*3.1416*1.23= 7.73m 1 1/2" 2 7.73 15.46
Per1= 2*3.1416*1.03= 6.47m 1 1/2" 2 6.47 12.94
Per1= 2*3.1416*0.83= 5.22m 1 1/2" 2 5.22 10.44
Per1= 2*3.1416*0.63= 3.96m 1 1/2" 2 3.96 7.92
Per1= 2*3.1416*0.43= 2.70m 1 1/2" 2 2.70 5.40
Per1= 2*3.1416*0.23= 1.45m 1 1/2" 2 1.45 2.90
Per1= 2*3.1416*0.03= 0.19m 1 1/2" 2 0.19 0.38

Calculos Acero radial


Per1= 2*3.1416*7.15=44.902m
Cantidad Acero= 39.14/0.25= 179 und
Superior 1 5/8" 179.00 6.44 1,152.76
Long c/uno (Autocad) = 6.50m
Inferior 1 5/8" 179.00 6.00 1,074.00
Long c/uno (Autocad) = 5.00m

Metrado Total 0.00 0.00 991.99 2,226.76 0.00


4,497.92 0.00 0.00 1,001.91 3,496.01 0.00

Partida 01.03.05.03.03 Muro reforzado acero fy=4200 kg/cm2 Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

acero vertical 2 5/8" 177.00 4.57 1,617.78


Per= 2*3.1416*7.00=43.96m
Cantidad Acero= 43.96/0.25= 177 und

acero vertical refuerzo inferior 1 1/2" 177.00 2.00 354.00

Acero horizontal 2 1/2" 27.00 43.96 2,373.84


Metrado Total 0.00 0.00 2,727.84 1,617.78 Err:522
5,295.03 0.00 0.00 2,755.12 2,539.91 Err:522
Partida 01.03.05.04.03 Viga acero fy=4200 kg/cm2 Unidad Kg
Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

acero longitudinal
Per= 2*3.1416*7.15=44.58m 1 1/2" 2.00 44.58 89.16
1 4.00 44.58 178.32
estribos 1 1/4" 222.00 1.20 266.40
Cantidad Acero= 44.58/0.20= 222 und
Longitus c/estribo = 1.20m

Metrado Total 266.40 0.00 89.16 178.32 0.00


436.61 66.60 0.00 90.05 279.96 0.00

Partida 01.03.05.05.04 Losa maciza acero fy=4200 kg/cm2 Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

radial Superior 1 3/8" 169.00 1.40 236.60


Per= 2*3.1416*6.75=42.39m
Cantidad Acero= 42.39/0.25= 169 und
Longitud c/estribo = 1.40m
radial Inferior
Longitud con Autocad = 6.41m 1 3/8" 49.00 6.41 314.09
Longitud con Autocad = 6.41m 1 3/8" 49.00 5.41 265.09
Longitud con Autocad = 6.41m 1 3/8" 49.00 4.66 228.34

Circular
Perimet 1 = 2*3.1416*6.75 = 36.76 1 3/8" 2.00 42.39 84.78
Perimet 1 = 2*3.1416*6.45 = 36.76 1 3/8" 2.00 40.51 81.01
Perimet 1 = 2*3.1416*6.15 = 36.76 1 3/8" 2.00 38.62 77.24
Perimet 1 = 2*3.1416*5.85 = 36.76 1 3/8" 2.00 36.76 73.52
Perimet 2 = 2*3.1416*5.55 = 34.87 1 3/8" 2.00 34.87 69.74
Perimet 3 = 2*3.1416*5.25 = 32.99 1 3/8" 2.00 32.99 65.98
Perimet 4 = 2*3.1416*4.95 = 31.10 1 3/8" 2.00 31.10 62.20
Perimet 5 = 2*3.1416*4.65 = 29.22 1 3/8" 1.00 29.22 29.22
Perimet 6 = 2*3.1416*4.35 = 27.33 1 3/8" 1.00 27.33 27.33
Perimet 7 = 2*3.1416*4.05 = 25.45 1 3/8" 1.00 25.45 25.45
Perimet 8 = 2*3.1416*3.75 = 23.56 1 3/8" 1.00 23.56 23.56
Perimet 9 = 2*3.1416*3.45 = 21.68 1 3/8" 1.00 21.68 21.68
Perimet 10 = 2*3.1416*3.15 = 19.79 1 3/8" 1.00 19.79 19.79
Perimet 11 = 2*3.1416*2.85 = 17.91 1 3/8" 1.00 17.91 17.91
Perimet 12 = 2*3.1416*2.55 = 16.02 1 3/8" 1.00 16.02 16.02
Perimet 13 = 2*3.1416*2.25 = 14.14 1 3/8" 1.00 14.14 14.14
Perimet 14 = 2*3.1416*1.95 = 12.25 1 3/8" 1.00 12.25 12.25
Perimet 15 = 2*3.1416*1.65 = 10.37 1 3/8" 1.00 10.37 10.37
Perimet 16 = 2*3.1416*1.35 = 8.48 1 3/8" 1.00 8.48 8.48
Perimet 17 = 2*3.1416*1.05 = 6.6 1 3/8" 1.00 6.60 6.60
Perimet 18 = 2*3.1416*0.75 = 4.71 1 3/8" 1.00 4.71 4.71
Perimet 19 = 2*3.1416*0.45 = 2.83 1 3/8" 1.00 2.83 2.83
Perimet 20 = 2*3.1416*0.15 = 0.94 1 3/8" 1.00 0.94 0.94

Metrado Total 0.00 1,799.88 0.00 0.00 0.00


1,025.93 0.00 1,025.93 0.00 0.00 0.00

Partida 01.03.05.06.03 Artesa de Reservorio Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

acero Figura 1 1 3/8" 8.00 1.60 12.80


long = 1.60m
acero Figura 2 1 3/8" 3.00 1.50 4.50
long = 1.50m
acero Figura 3 1 3/8" 7.00 3.31 23.17
long = 3.31m
estribos
Cantidad Acero= 34.50/0.20= 173 und
Longitus c/estribo = 1.20m

Metrado Total 0.00 40.47 0.00 0.00 0.00


23.07 0.00 23.07 0.00 0.00 0.00
PLANTILLA SUSTENTACION DE METRADOS

Construcción de Caseta de valvulas

Partida 01.03.05.07.03 ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS-- Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud Total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

acero longitudinal 1 1/2" 6.00 4.33 25.98

Estribos 1 1/2" 114.00 1.20 136.80

Metrado Total 136.80 0.00 25.98 0.00 0.00


60.44 34.20 0.00 26.24 0.00 0.00

Partida 01.03.05.08.03 ACERO ESTRUCTURAL TRABAJADO PARA VIGAS-- Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud Total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

Acero longitudinal (V 0.25x0.40) 3 1/2" 3.00 6.10 54.90


Acero longitudinal (V 0.25x0.40) 3 1/2" 2.00 5.20 31.20
Acero longitudinal (V 0.25x0.40) 3 1/2" 2.00 1.80 10.80
Acero longitudinal (V 0.25x0.40) 3 1/2" 2.00 1.80 10.80
Acero longitudinal (V 0.25x0.40) 3 1/2" 1.00 3.30 9.90
Acero longitudinal (V 0.25x0.40) 3 3/8" 4.00 0.20 2.40
Acero estribos (V 0.25x0.40) 3 1/4" 10.00 1.04 31.20
Acero estribos (V 0.25x0.40) 3 1/4" 28.00 1.50 126.00
Acero longitudinal (V 0.25x0.17) 2 1/2" 4.00 9.00 72.00
Acero estribos (V 0.25x0.17) 2 1/4" 180.00 1.50 540.00

Metrado Total 697.20 2.40 189.60 0.00


367.16 174.30 1.37 191.50 0.00 0.00

Partida 01.03.05.09.03 Losa maciza acero fy=4200 kg/cm2 Unidad Kg


Grafico Descripcion Cant. Diam. Cantidad Longitud Longitud Total
elem. 1/4" 3/8" 1/2" 5/8" 3/4"

Loza acero principal 1 1/2" 28.00 10.10 282.80


Acero amarre 1 1/4" 36.00 6.30 226.80

Metrado Total 226.80 0.00 282.80 0.00


342.33 56.70 0.00 285.63 0.00 0.00