Documentos de Académico
Documentos de Profesional
Documentos de Cultura
volumen
compactado f
CANTERA inico final L(m) A(m2) Vc(m3) e
00+000 13+500 13,500.00 3.03 40,905.00 1.2
A 13+500 27+905 14,405.00 3.03 43,647.15 1.2
27+905 42+110 14,205.00 3.03 43,041.15 1.2
C 42+110 49+905 7,795.00 3.03 23,618.85 1.2
49+905 58+800 8,895.00 3.03 26,951.85 1.2
D 58+800 70+000 11,200.00 3.03 33,936.00 1.2
70,000.00 212,100.00
volumen
compactado f
CANTERA inico final L(m) A(m2) Vc(m3) e
00+000 32+500 32,500.00 2.456 79,820.00 1.2
B 32+500 45+000 12,500.00 2.456 30,700.00 1.2
45+000 58+800 13,800.00 2.456 33,892.80 1.2
D 58+800 70+000 11,200.00 2.456 27,507.20 1.2
70,000.00 171,920.00
D1 2300
D2 1000
D 26300
X 12500
PROGRESIVA= 45+000
dato
volumen
f suelto Acceso
c vs (m3) d(m) DMT (m) DMT.V D<=1KM D>1KM
0.95 51,669.47 1800 8,550.00 441,774.00 51,669.47 390,104.53
0.95 55,133.24 1800 9,002.50 496,337.01 55,133.24 441,203.77
0.95 54,367.77 2000 9,102.50 494,882.61 54,367.77 440,514.84
0.95 29,834.34 2000 5,897.50 175,948.00 29,834.34 146,113.66
0.95 34,044.44 1000 5,447.50 185,457.10 34,044.44 151,412.66
0.95 42,866.53 1000 6,600.00 282,919.07 42,866.53 240,052.55
267,915.79 2,077,317.80 267,915.79 1,809,402.01
1.000 6.754
volumen
f suelto Acceso
c vs (m3) d(m) DMT (m) DMT.V D<=1KM D>1KM
0.95 100,825.26 2300 18,550.00 1,870,308.63 100,825.26 1,769,483.37
0.95 38,778.95 2300 8,550.00 331,560.00 38,778.95 292,781.05
0.95 42,811.96 1000 7,900.00 338,214.47 42,811.96 295,402.51
0.95 34,745.94 1000 6,600.00 229,323.18 34,745.94 194,577.25
217,162.11 2,769,406.28 217,162.11 2,552,244.18
1.000 11.753