Documentos de Académico
Documentos de Profesional
Documentos de Cultura
I. History of Revisions
Revision No. Revision date Chapter/clause no. & text Reason for
affected revision
R-0 07-07-13 First Issue
R-1 30-08-13 Revised as per client 2nd Issue
comment
R-2 20.11.13 Ch.4-Span Lowering 3rd Issue
deleted from scope, is
covered in separate SQP.
Ch- 4, 7, 14, 15.2, 15.3,
15.6, 15.7, 15.11 Updated
INDEX
CHAPTER PAGE NO.
Construction of Composite welded steel truss girders having span of 34 x
125m + 2 x 32.6m for the Super-structure of Bogibeel Rail-cum-Road Bridge
over the river Brahmaputra near Dibrugarh, Assam in India .......................... 1
1 PURPOSE ..................................................................................................... 8
2 NAME OF PROJECT .................................................................................... 8
3 PROJECT LOCATION .................................................................................. 8
4 SCOPE .......................................................................................................... 9
5 ENVIRONMENTAL & CLIMATIC CONDITION OF PROJECT SITE ............ 9
(a) Climate ............................................................................................... 9
(b) Temperature....................................................................................... 9
(c) Hydrology ......................................................................................... 10
(d) Design Limitation & Consideration ................................................... 10
6 TERMS, DEFINITIONS & ABBREVIATIONS ............................................. 11
7 DESIGN & DRAWINGS REFERENCES ..................................................... 12
8 DESIGN REPORTS ..................................................................................... 13
9 CROSS REFERENCES .............................................................................. 14
10 RESPONSIBILITIES ................................................................................... 14
11 PERSONNEL .............................................................................................. 14
12 ASSUMED DURATION OF THE OPERATION........................................... 15
13 MATERIALS ................................................................................................ 16
14 MOBILIZATION OF EQUIPMENTS ............................................................ 17
15 METHODOLOGY FOR THE LAUNCHING OF FBARICATED TRUSS ...... 19
15.1 Introduction ......................................................................................... 19
15.2 Proposed Launching Method (QAP Clause: 4.1.1) .......................... 19
15.3 Installation of Enabling Structures for Launching .......................... 23
15.3.1 Assembly / Launching Yard.............................................................. 24
22.1.3 A3 Launching Yard Single Truss Page A3/1 – A3/10 ..................... 132
22.1.4 A4 Launching Yard Sledges Phase 0 Page A4/1 – A4/30 .............. 132
22.1.5 A5 Launching Yard Sledges Phase 1 Page A5/1 – A5/28 .............. 132
22.1.6 A6 Deflections Launching Phase 2 Page A6/1 – A6/12 ................. 132
22.2 Attachment B: Methodology Sequence Drawings ......................... 132
22.3 Attachment C: Inspection Plan ........................................................ 132
22.3.1 C1 Inspection Plan Launching........................................................ 132
22.4 Attachment D: Emergency Plan ...................................................... 132
22.4.1 D1 Emergency Plan ....................................................................... 132
22.4.2 D2 Bracing Nose ............................................................................ 132
22.5 Attachment E: Bolts - Torque Moment ........................................... 132
22.5.1 E1 Torque Moment ........................................................................ 132
22.6 Attachment F: Strands Scheme ...................................................... 132
22.6.1 F1 Strands Scheme ....................................................................... 132
22.7 Attachment G: Table of Level .......................................................... 132
22.7.1 G1 Tip of Nose Phase 0 and 1 ....................................................... 132
22.7.2 G2 Connection Piece Phase 0 and 1 ............................................. 132
22.7.3 G3 Tip of Tail Phase 1 ................................................................... 132
22.8 Attachment H : Specification of Major Equipments ...................... 133
22.9 Attachment I : Erection Scheme of Launching Nose..................... 133
22.10 Attachment J : Erection Scheme of Launching Tail ...................... 133
22.11 Attachment K : Erection Scheme of “A” Strut ............................... 133
22.12 Attachment L : Erection Scheme of Connection Member ............. 133
22.13 Attachment M : Erection Scheme of Launching Bearing .............. 133
22.14 Attachment N : Erection Scheme of Pulling Device ...................... 133
22.15 Attachment O : Scheme for Camber Check at Assembly Yard .... 133
22.16 Attachment P : Erection Scheme - Pulling Device Anchor Beam 133
22.17 Attachment Q : Erection Scheme of Brackets ............................... 133
1 PURPOSE
2 NAME OF PROJECT
3 PROJECT LOCATION
• State : Assam
• District : Dibrugarh
• River : Brahmaputra
Geographical Location:
• Longitude 94°45′46″,
• Latitude 27°24′22″ and
• Axis 315°07′05″.
4 SCOPE
(a) Climate
The climate of the project area is humid and tropical. A hot and humid pre-
monsoon from March to mid May, a prolonged southwest monsoon or
rainy season from mid May to September, a pleasant post-monsoon or
retreating monsoon from October to November and a cold pleasant winter
from December to February are the characteristics of the general climate.
(b) Temperature
The hottest months are May to September with mercury reaching 42ºC
during June. The coldest months are December, January and February
when temperature drops to 5ºC. The months, November and March, can
also be quite cold in some years. During the other months, temperature is
more or less moderate and pleasant to bear.
(c) Hydrology
Brahmaputra is a perennial river with maximum discharge of around
73000cumec during monsoon. In the off peak seasons, some part of the
river bed remains dry but it is not possible to identify which part as the
stream changes its course after every monsoon.
• Design Discharge : 73000 cumec
• Design HFL
o With Aggradations : 106.52m
o Without Aggradations : 102.92m
• Low Water Level : 98.30m
Note: The Hydraulic data is an extract from DPR of the project and
provided by NFR. The return period of the highest HFL is taken as 100
years in the DPR.
(d) Design Limitation & Consideration
Maximum wind speed 15 m/s [54km/hr] has been considered during
launching operation if wind speed goes more than the consideration,
launching operation should be stopped and truss will be anchored if wind
speed goes more than 20m/s[72 km/hr].[Detail anchorage arrangement is
elaborated in this SQP in later chapters].
Abbreviations
Document
Index Name of the document
No.
Launching - General Arrangement Drawings
D M-001 Launching Scheme
B M-011 Launching Phase 0.1 - Yard
A M-012 Launching Phase 1.0 - Yard
A M-013 Lowering Truss
A M-021 Launching States Phase1 – 9
A M-022 Launching States Phase 10 -19
A M-023 Launching States Phase 20 -39
A M-024 Launching States Phase 40 + Phase II/29..30
A M-025 Launching States Phase III/1..20 + Phase IV/8..9
Reinforcement Superstructure
B M-101 Reinforcement - Normal Span
B M-102 Reinforcement - Span 40,31,30,21,20,11,2
C M-103 Details Connection Truss Girder
A M-104 Temporary Vertical Truss Member (A-Strut)
A M-105 Temporary Vertical Truss Member (A-Strut) – Alt.
Pulling Device
C M-200 Pulling Device - Overview
C M-201 Pulling Device - Anchor Beam
B M-202 Pulling Device - Const. Pier
0 EW97FS-07 Pulling Device – Construction of Piers - GA (Alt.)
0 EW97FS-08 Pulling Device – Connection Details – (Alt.)
0 EW97FS-09 Pulling Device – Connection Details – (Alt.)
Launching Bearings
B M-300 Sliding Bearings - Overview
E M-301 Sliding Bearings - Detail
Bracket Pier Axis 10,20,30
B M-400 Bracket Pier 10;20;30 - Overview
A M-401 Bracket Pier 10;20;30 - Details
Launching Nose
E M-501 Launching Nose - Side View
Revision No.: 2; Revision Date: 20.11.2013 Page 12 of 134
CEMG
HCC-DSD-VNR Consortium Management System
Segment Quality Plan For The Launching Of Span Truss
HCC N 097 17 007
Document
Index Name of the document
No.
E M-502 Launching Nose - Top and Bottom Chord
E M-503 Launching Nose - Sections
0 M-504 Launching Nose – LN to Low
Launching Sledge & Track
A M-600 Launching Yard - Overview
A M-601 Launching Sledge - Overview
C M-602 Launching Sledge - Details
A M-603 Launching Track (Steel Girder and Temp. Guiding)
B M-604 Launching Track - Pulling Device
0 BB/97/MC/100 Pulling device on Yard Details
C M-605 Launching Track - Pier P 31(v)
0 M-606 Block Foundation 4,50 x 4,50 m – Camber
A M-610 Launching Track - Reinforcement
8 DESIGN REPORTS
9 CROSS REFERENCES
10 RESPONSIBILITIES
Personnel responsible for execution and quality control for enabling and
permanent works shall be as per the responsibilities Matrix laid down in
the Project/Segment Organization Chart.
11 PERSONNEL
- 6 workers for feeding and taking the sliding plates out (2x2
infront of each launching bearing for inserting sliding plates and
1x2 on the back of launching bearing for taking out the plates )
- 2 workers as a handyman
- 1 supervisor
Following skilled workers shall be deployed at pulling pier [i.e. P11, P21,
P31 and P40] for pulling arrangement
- 2 Hydraulic operators
- 1 Electrician
- 1 Lunching Supervisor
13 MATERIALS
• Elastomeric Bearings:
a) Launching Bearings:
• 900 x 150 x 60 mm,
• Spring stiffness 360.00 kN/m,
• Allowable compression >= 15 N/mm2
b) Sledge:
• 400 x 200 x 40 mm,
• Allowable compression >= 15 N/mm2
c) Pulling Device:
• 4 Nos. x [400 x 300 x 30 mm],
• Allowable compression >= 15 N/mm2
• PTFE-Plates:
• t = 5.5 mm,
• Allowable compression >= 15 N/mm²,
• Stainless Steel:
• Yield stress >= 170 N/mm²
• 12MM/GR.SS304L//EN 10088-1/X2CRNI19-11/1.4306
• Strands Type:
• 15.2mm dia uncoated stress relieved low relaxation seven-ply
strand as per IS 14268
Documents supplied with the material shall be checked which includes
material test certificate and suppliers declaration of conformity.
14 MOBILIZATION OF EQUIPMENTS
Once the first truss (for span P39-P40) is completed, the truss will
be jacked up on another set of specially prepared foundations (located
behind P31(v)) to verify the camber (when the truss is supported on four
end supports). Once the camber checks are completed a prefabricated
Nose will be fixed to the front end of the truss. The purpose of the Nose is
to reduce the cantilever bending moments and the reaction on bearings
due to cantilever. During this process of fixing of nose, a launching
bearing will be mounted on P31(v). For further operations of launching,
pier P31(v) will be used as support.
After the Nose erection is complete, the truss is pulled forward with the
help of a pulling device. This pulling device is mounted on a Pier P1 and it
will pull the truss and the nose forward. As the truss moves forward, a
sequential jacking of the truss at P31(v) is done to control excessive
reactions on the sledges. Launching is continued till the nose takes
reaction on the launching bearing mounted on A1. In order to negate the
deflection of the nose tip due to cantilevering, the bottom of the nose is
profiled so that the nose lands freely on the launching bearing in spite of
cantilever deflection.
Launching is continued further till the rear end of the first truss
reaches the foundation for camber checking. At this time the second truss
is moved forward and connected to the rear end of the first truss with a
connection piece welded between the two trusses. The process is
continued till the 10th truss reaches at pier P31(v). At this stage a “Tail”
(which is similar to Nose) is attached at the rear end of the 10th Truss.
This is again to reduce cantilever moments at the rear end. Pulling device
of P1 will be disconnected and pulling device of P11 will be activated. Now
the whole system of 10 trusses will be pulled forward till the rear end of
truss 10 reaches at Pier P10. Pulling device of P11 will be de-activated
and further pulling will be done from P21. The process is repeated till the
first train of 10 trusses reaches at P40.
At the end of this stage, the nose is between P40 and A2 and the
tail is between P29 and P30. Nose is dismantled with the help of land
based crane between P40 and A2. Tail is dismantled with the help of a
floating crane/or by other devices like derrick etc operating on the
launched truss and tail.
Pier bracket is dismantled with floating crane (or a similar device operating
from the previously launched truss). After dismantling part of the Nose,
further launching is done in stages and simultaneously part of the nose is
dismantled. This process is repeated till the Truss T11 reaches the final
bearing locations. Repeating the above process, the third and fourth trains
of trusses (10 Trusses for train 3 and 9 trusses for train 4) are launched.
The first span launching shall be Trial Launching. During first Launching
thorough visual inspection of the Bottom Chords & A-Struts shall be done
when centre of each Chord is at Launching Bearing.
9. Pulling System
11. Cantilever Bracket at Pier P10, P20 and P30 for Nose dismantling
In Assembly yard (Bed 3 & 4), all assembled modules shall be assembled
in vertical position to make the truss. (For detailed assembly procedure
Ref. document no: HCC N 097 17 06, Rev-3)
15.3.2.1 Purpose
In order to shift the completed trusses to the launching position, launching track
(sliding) shall be provided from the assembly yard (Yard 3 and 4) to the
launching position. (Refer Dwg. No – M600 & M603).
The launching track consists of a steel girder with stainless steel plate on the top.
The steel girder will be supported on concrete
foundations at around 7.8m to 8.0 m c/c. To
account for higher loads during launching
phases, there will be a continuous foundation
for the length of 52 m towards P31(v). The
whole launching track is located in covered
shed. Hence no wind load is acting on the
truss during the launching operation on the
launching track.
Fig: 2-Launching Track
At every anchor foundation of the track, provisions are made for bolting mobile
lateral guiding system. With the help of the guiding system it is possible to push
the truss in lateral direction if necessary (e.g. if the truss shifts out of the centre
line).
15.3.2.2 Installation
The launching level is fixed at 118.156m RL. This level is defined as the level of
the bottom of bottom chord at centre of BJ6. With sledge height of 97.5 mm at
BJ6, the top of sliding track(stainless steel plate) works out to 118.156-
0.0975=118.0585 m RL.
The pre-fabricated track is kept over temporary shims over the foundation
so as to achieve level of 118.0585 m RL at the top of track. After checking the
top levels accurately, grouting of the base of track shall be carried with non
shrink grout of strength (45Mpa) over the foundations.
• The completed track for launching will satisfy the following tolerances.
o Horizontal +/-5 mm
o Vertical +/- 3 mm
• Welds in stainless steel of the track must be ground smooth to facilitate
easy sliding.
• During launching operation, the horizontal gap between the horizontal
guide of sledge and the launching track will be monitored by the workers
and the supervisor at the launching yard. If the track touches the lateral
guiding, the supervisor will inform the launching manager who in turn shall
stop launching. The mobile lateral guiding will be installed at the
corresponding sledge location. A hydraulic jack of 50 T capacities will be
installed between the guiding system and the bottom chord. The truss will
be side shifted as required by activation of the hydraulic jack.
15.3.3.1 Purpose
In order to slide the completed truss from the Vertical assembly Yard, the truss is
erected on sliding blocks called as “Sledges”.
Due to the pre-camber to be provided to the truss, the sledges shall be made of
different heights. There are in total 22 sledges for each truss. The sledges are
located under every node.
The sledges consist of a steel girder with PTFE at the bottom. This PTFE will
slide on the stainless steel plate of the lunching track. On top of the sledges
elastomeric bearings will be placed in order to achieve a uniform distributed load
on the sledge. As the friction between the elastomeric bearing and the bottom
truss chord is greater than the friction between the PTFE and the SS Plate of the
track, the sledge is fixed to truss. Therefore the truss and the sledges will slide
on the launching track.
In order to keep the sledges on the axis of the launching, the launching sledges
on both sides are laterally connected by two steel girders and each sledge is
guided at the top flange of the launching track steel girder.
The camber of the truss will be adjusted by the construction height of the sledges
which are as follows.
The sledges are connected to the truss with wooden wedges at their cross
beams. With this construction, the sledge will be guided (pulled forward) by the
truss even if there is no load on the Sledge.
At the end of launching track there is a sledge run out (refer to drawing M607)
where the sledge can easily be removed during or after the launching.
During launching, the sledges shall be connected by chain hoist / ropes to the
cross beams.
When the sledges are set free they can either be removed from the track or they
can be connected by a rope to the truss in order to move forward to the end of
the track. At the end of launching track the sledge can easily be removed during
or after the launching.
The PTFE may also be applied with soft soap in order to lower the friction
coefficient.
At the sledge run out the launching level will be lowered by 40 mm.
All bolts at the construction joints of the sledges are “non-preloaded” bolts. They
shall be manually tightened according to the Attachment E1. The procedure shall
be recorded.
Revision No.: 2; Revision Date: 20.11.2013 Page 32 of 134
CEMG
HCC-DSD-VNR Consortium Management System
Segment Quality Plan For The Launching Of Span Truss
HCC N 097 17 007
15.3.4.1 Purpose
In order to check and verify the pre-camber, to be achieved after final assembly
of each truss, four foundation blocks with facility to jack up the whole truss are
provided at each corner of the truss. These foundations also accommodate
hydraulic jacks to lift the whole truss. These foundations also support the
launching track.
In order to check the camber of the span truss 4 jacks (4 x 500 t jacks with tilt
saddle) will be assembled at the jacking points of the foundation. In order to
safely transfer the weight of truss, RCC foundation of 4.5x5.1x1.5 m is adopted.
To minimize any settlements and to distribute the loads, rubble soling is also
provided below the foundations. This will ensure that the top of sliding track
remains at 118.0585m RL.
The jacks required for lifting the truss are provided with tilting saddle at top and
safety lock nut. During the lifting operation, the ends of truss are likely to move
outward due to loss of camber due to self weight. To allow such movements, a
steel plate of size 600x400x40 mm with PTFE sheet on top will be placed over
the jack.
118.156m
After the truss is completed, four hydraulic jacks of capacity 500T each are
placed over specified locations on the foundation pads. Steel packing plates shall
be used below each jack. All the packing plates shall be connected to each other
[bolted to each other].
• The span truss will be lifted up for approx. 100 – 150 mm until all the load
of truss is on the four jacks. And a clearly visible gap between the sledge and the
bottom truss at all of the temporary supports (sledges) will be achieved.
• At the end of jacking, it shall be ensured that the four end supports are
almost at same level.
• After the jacking operation is complete, the lock nuts of all the four jacks
shall be engaged to avoid any hydraulic failure.
• Levels of the truss at all nodes shall be taken again and recorded. If the
foundation supports show any settlements, the same shall be suitably
compensated in the residual camber calculations.
15.3.5.1 Purpose
Launching bearing is installed at pier P31(v) to support the truss during launching
operation. The launching bearing is designed to distribute the reactions
uniformly. The launching bearing at the pier P31(v) is also designed for jacking-
up, to control the reactions at various stages of launching as defined in launching
operation.
• To facilitate mounting of the launching bearing, the pile cap is cast over
the piles of the foundation at P31(v).
• Two bearing pedestals of required size are also cast with top of concrete
at -116.341m RL.
• In order to maintain accurate level of the top of anchor plate, the anchor
plate is fixed over pedestal on temporary shims.
• The gap between pedestal and anchor plate is grouted with non shrink
grout.
• Four hydraulic jacks (400T Capacity) are mounted on either side of each
launching bearing to facilitate raising or lowering of the launching bearing at
various stages of launching as explained in launching procedure.
Revision No.: 2; Revision Date: 20.11.2013 Page 37 of 134
CEMG
HCC-DSD-VNR Consortium Management System
Segment Quality Plan For The Launching Of Span Truss
HCC N 097 17 007
•The top of launching bearing on any pier shall be within +/- 1.0 mm.
According to the design the launching level at Pier 31(v) shall be adjusted. For
that following filler plates shall be used for the adjustment of launching level:
Phase -1
Level (mm) Filler Plates (mm)
25 25
120 2 x 60
225 3 x 60 + 20 + 25
320 3 x 60 + 20 + 2 x 60
Phase – 2
Level (mm) Filler Plates (mm)
100 1 x 60 + 2 x 20
80 1 x 60 + 1 x 20
25 25
145 1 x 60 + 1x 25 + 1 x 60
265 1 x 60 + 1 x 25 + 1 x 60 + 2 x 60
100 1 x 60 + 2 x 20
If the measured camber is deviating by more than +/- 10mm, adjustment will be
done in the lifting operation at P31(v) (Rounded to the nearest 5mm)
15.3.6.1 Purpose
In order to reduce the stresses due to the local bending of the bottom chord
vertical temporary beams will be arranged between the bottom chord and top
joint of both sides of the truss. Due to its geometry these members are called “A”
-struts. The “A” - struts are placed in the zones of the maximum vertical forces
due to launching.
Based on the detailed design of launching stages, “A” struts are required for the
first and last trusses of each segment of 10 trusses (9 for last segment).
Launching Nose
Fig-16: A-struts – span 40, 30, 20 and 10 (31, 21, 11 and 1 – location A-
struts mirror images)
15.3.6.2 Installation of A - Struts
At Assembly yard during assembly of span truss in final vertical position, “A” -
struts will be bolted to the top joint and the bottom chord of the truss.
When the launching segment reaches its final location and the single span truss
girder is lowered the “A”- struts will be removed.
All bolts at the construction joints of the A-Strut are “non-preloaded” bolts. They
shall be manually tightened according to the Attachment E1.
• Filler plate of 10mm shall be inserted while doing the connection with top
joint & bottom chord.
• M24, 10.9 grade bolt shall be used for bolt connection
15.3.7.1 Purpose
For the launching process it is necessary to connect the single span truss girders
with each other to form a segment of 10 trusses (9 for last segment).This will be
done at the “connection point” at a distance of 13.16 m behind P 31(v). At the
connection point the last assembled truss (i.e. Tn-1) will be connected to the
already launched segment’s truss (i.e. Tn).
Temporary Connection
Already launched segment’s truss (i.e. Tn)
Fig-18: Temporary Truss Connection – Top Chord: (Detail “A” Top Chord)
• After checking of camber, the two trusses to be joined (Tn and Tn-1) will be
accurately aligned in transverse direction since the trusses may be slightly
off centre during launching.
• Accurate dimensions of the gap between the two trusses shall be taken.
• The already fabricated connection unit shall then be cut as per actual
dimensions.
• The unit will be placed between the two trusses with the help of a
crane/gantry.
• Temporary supports shall be arranged as per Attachment L
•The end faces of the connection piece shall be edge prepared as required.
•The face of assembled truss shall be matched with temporary connection with
the help of jacks
•Welding between the temp connection piece and span truss Tn-1 & Tn shall be
completed.
•The welded portion shall be grinded properly to make the surface smooth,
especially bottom surface which will be in contact with launching bearing during
launching of span truss
The vertical level at both ends shall be same. In order to achieve it, the launched
segment will be lifted, if required, at P31(v). If necessary small adjustments shall
be done with the help of a jack placed on the temporary support.
Allowable vertical tolerance between north end of truss in the yard and south end
of already launched truss - Both ends of the truss: +/- 2mm
In lateral direction adjustments will be done with the help of the lateral guiding at
the camber foundation.
The camber foundation is available at both ends of the truss. If necessary jacks
can be connected with the lateral guiding and the truss can be moved in
transverse direction.
The welds are complete penetrated welds. The welds shall be checked 100 % by
ultrasonic. Defects shall be evaluated according to the same quality class as per
the bridge. The results shall be recorded.
15.3.8.1 Purpose
According to the launching scheme, launching will be done only from the
south embankment. As has been explained, the launching is divided into 4
segments (3 segments of 10 trusses and 1 segment of 9 trusses). In order
to launch the segments to its final position a launching nose at the
beginning and a launching tail at the end of the segment is required.
Length of Nose and Tail is 52 mt. as per the design. The construction of the
nose is similar to the tail. Therefore the explanations given below for the
nose are also applied to the tail.
The nose is a steel truss construction with bottom bracing. The bottom
chord of the nose is box section similar to the bottom chord of the truss. The
other sections of the nose are open sections. In order to disassemble the
nose part by part the nose is bolted. The connection to the superstructure is
also bolted.
At the connection of the bottom chord of the nose with the bottom joint of
truss the bottom flange will be assembled with a smooth alignment.
The stages of erection of nose are also applicable for the assembly of Tail.
The nose will be assembled in front of the launching segment. The first
truss girder of the launching segment (span 40, 30, 20 or 10) will be
assembled at the end of the track at the location of the block foundation for
camber checking (15.560 m next to axis P31(v)).
• After the camber has been checked the truss will be lowered onto the
sledges again.
Afterwards Pre fabricated nose shall be assembled. First the bottom chord
of the nose will be assembled.
• Afterward the top chord, the diagonal members, the cross beams and the
bracing will be assembled. The connections will be bolted.
• All bolts at the construction joints of the nose shall be tightened according
to the Attachment E1. The procedure shall be recorded.
Launching Tail: For the assembling of the launching tail the situation is
slightly different. When the last truss of each launching segment has been
assembled and launched the tail will be assembled. At this the truss is
supported at the Pier P31(v) (level + 100 mm) and at the Pier P1. The tail
will be assembled, as explained above for the nose, with the help of
temporary supports. After the tail has been connected to the truss the
temporary supports will be removed. A check of Deflection of the tail shall
be done and compared to the design values. At the same time it shall be
taken care that the bottom chord of nose is assembled in the same line as
that of the bottom chord of the bridge (no kink in top view between
superstructure and nose).
The distance from the reference line (bridge axis = reference line for
launching) shall be checked and reported at every joint of the bottom chord.
The distance shall be measured at the outer side of the bottom chord.
Allowable tolerances:
15.3.9.1.1 Purpose
The pulling device shall be constructed at Assembly Yard 4 to pull the Truss from
Assembly Yard 3 to the connection point for launching at Assembly Yard 4.
This pulling device has to pull a single truss (~1700 t) to the connection point. A
steel transverse beam between the two launching tracks will be assembled.
Two strand jacks of 200T capacity each will be installed at the locations shown in
drawing No M-604.
Launching
Assembly Bed -4
Camber
Foundation
Extended Foundation for
Pulling at Assembly Yard 4
Fig-30: Pulling Device at Yard – Side View
The strands are running in two lines between the two bottom truss chords – each
at an offset of 1250 mm from the centre line of the bottom chord of truss.
Installation of strand (15.2mm dia uncoated stress relieved low relaxation seven-
ply strand) shall be done manually. Prior to installation of HT strand, they shall be
cut at required length and kept in covered shed to protect from dirt, rust etc.
Marking over the front bearing and rear bearing plate shall be done to ensure
that the strands are threaded in straight line.
15.3.9.1.4 Tolerance:
15.3.9.2.1 Purpose
Two 1000t multi strand jacks (Model K1000 by Freyssisnet) will be used. The
level of the strands will be 680 mm below the bottom chord of the truss.
15.3.9.2.2 Installation
The vertical beam will be assembled by a mobile / floating crane and to access
the pier cap top, light weight ladder shall be provided which will be shifted to
each pier as and when required. The detail scheme of shifting and installation of
the pulling device and construction at piers is enclosed in Attachment N.
The sections used for construction of pulling device at Piers for Jacking
arrangement shall be as per M202. Alternatively, the sections shown in Drg. No.
EW97FS-07, 08, 09 can also be used.
With the use of filler plates the vertical beam will be set on top of the Well Cap
incase of P1 and Fender Wall Top incase of P11, P21, and P31. The beam shall
be anchored on top of the pier cap with SHS 80x8 (refer to the sketch below).
SHS 80x8 is located away from the reinforcement area.
SHS 80x8
The level of the strands is marked at the vertical beam (center line of the
adapter plate of the strand jack). The beam shall be installed according to
this level (680 mm below launching level).
The vertical beam shall be installed vertical. The location in horizontal view
is defined by the line of the strands. The strands run in a line with a lateral
distance of 4.050 mm from the bridge axis.
The gap between the vertical beam and the pier cap shall be filled with
elastomeric bearings (size as mentioned in the related drawings, allowable
Afterward the lateral cross girder between the vertical beams shall be
installed.
Finally the bottom frame will be installed. Elastomeric bearing (bearings size
as mentioned in the related drawings, allowable stress 15 N/mm²) between
the pier and the steel girder shall be installed in the same way as explained
above. It shall be ensured that there is no gap left.
The following loads have been considered in the design of the working
platform:
Now, strand jack shall be erected and bolted to the vertical beam. It shall
be ensured that the assembling of the strand jack will be perpendicular to
the vertical beam at its defined level.
All bolts at the construction joints of the pulling device are “non-preloaded”
bolts. They shall be manually tightened according to the Attachment E1.
- Anchor Beam
The anchor beam will be assembled between the first two bottom cross
girders of the next truss girder to be launched. The anchor beam consists of
a horizontal box girder and vertical girder. Both girders are welded together
and will be assembled as one part. The horizontal girder is supported on the
top flanges of the first two cross girders of the truss. At both the top flanges
elastomeric bearings (Allowable Compression <= 15 N/mm²) shall be
placed before placing the anchor beam.
The level of the strands is marked at the vertical truss (center line of the
adapter plate for the strand anchor). The vertical truss shall be positioned
according to this level (680 mm below launching level).
The anchor beam shall be installed in the line of the truss. The location in
horizontal view is defined by the line of the strands. The strands run in a line
with a distance of 4.050 mm from the bridge axis.
The anchor beam shall be wedged in lateral direction with hard wood. At the
first cross beam the wedges will be assembled between the node of the
truss and the brackets for the stringers. At the end cross beam the anchor
beam will also wedged to the node of the truss. Due to the construction of
the horizontal box girder at that location two additional girders ISHB
150x150 are required in order to wedged it to the stringer bracket.
All bolts at the construction joints of the anchor beam are “non-preloaded”
bolts. They shall be manually tightened according to the Attachment E1.
The procedure shall be recorded.
15.3.10.1 Purpose
The launching bearings (or sliding bearings) are arranged under both side of the
bottom chord of the truss. The bearings are placed on a spherical plate in order
to divide the support reactions equally to the two webs of the bottom chord and to
take over the rotation angle of the superstructure due to the launching.
The launching bearings consist of a welded steel box. The top plate of this box is
a 100 mm thick plate. On top of this plate in the line of the bottom chord’s webs
of the truss, elastomeric bearings 900 x 150 x 40 mm will be placed in order to
obtain a uniform distributed stress between the launching bearing and the
superstructure. On top of the elastomeric bearings a 40 mm thick steel plate will
be fixed. A stainless steel plate (t=12 mm) is welded on top of this plate.
The launching bearing has a length of 5700 mm + 2 x 800 mm for the insertion of
the sliding plates. The total height of the launching bearing from the top of the
final bearings anchor plate is 1750 mm.
Both launching bearing are connected with each other by two beams at distance
of 2000 mm. In the line of the cross beams two lateral guiding are located. The
lateral guiding takes over the lateral forces due to wind and transfer them to the
bearing pedestal. Forces in longitudinal direction due to friction are transferred to
the bearing pedestal by cleats.
During launching process, sliding plates will be inserted between the bottom
flange of the superstructure and the 40 mm steel plate with the welded stainless
steel plate on top. The sliding plates consists of steel plate and 6 numbers of
5.5mm thick PTFE. The PTFE is chambered in the steel plate.
At every pier a working platform will be erected as shown in the sketches’ below:
15.3.10.2 Installation
The launching bearing shall be installed according to the drawings M300 and
M301.
On top of the bearing pedestals the anchor plate of the final bearing will be
installed and grouting will be done as per installation methodology of permanent
bearing. Before concreting of the Pedestals and fixing of the anchor plates, the
centerlines of Pier shall be marked on each Pier with the help of Total Station by
a qualified surveyor. All the corners of the points of pedestals shall then be
marked on top of pier cap with reference to the pier centre line. After ensuring the
correct position of the pedestals, further works of concreting of pedestals be
taken up. The measurements and coordinates shall be recorded. Similar method
shall be adopted for fixing of anchor plates as well. Detailed methodology is
mentioned in SQP for Installation of Spherical Bearings.
Based on the bridge axis the centre line of the bottom truss girder is marked with
red permanent colour on the bearing pedestal. This line shall be the reference for
the installation of the launching bearing.
The top surface of the anchor shall be plain in order to guarantee the load
transfer by contact.
On top of the anchor plate the bottom part of the launching bearing will be
installed. The bottom part consists mainly of the 100 mm thick base plate and at
it welded cleats.
The centre line of the 100 mm plate shall be in line with red marked reference
line on the bearing pedestal.
The bottom part of the launching bearing will be finally fixed in lateral direction by
putting filler plates or hard wood wedges between the cleat s and the bearing
pedestal.
The main part of the launching bearing will be put on top of the 100 mm plate.
Finally the cross beams will be assembled and bolted. On top of the launching
bearing the elastomeric pads and the 40 mm plate together with the stainless
steel plate will be installed.
The top level of the completely assembled launching bearing shall be checked.
[RL should be 118.1385m]
If the measured level exceeds the tolerances, filler plates shall be installed
underneath the elastomeric pads. The filler plates shall have similar size as the
elastomeric bearings. When the pedestals are cast and anchor plates of
permanent bearings installed, it will be ensured that the levels are not higher than
required. Anchor plate is fixed much before launching bearings.
The point of touching of the Nose and the point of leaving of the tail shall be
marked with paint on the Sliding Bearing during installation of the sliding Bearing.
All bolts at the construction joints of the launching bearing shall be “non-
preloaded” bolts. They shall be manually tightened according to the Attachment
E1. The procedure shall be recorded. [Format No. HCC F 097 10 06, Rev No. 00,
Rev Date - 07.09.2013]
15.3.11.1 Purpose
The loads coming from the launching bearing at Pier bracket (each about
330 t) will be transferred by a RCC column to the pier. Connection dowels
are drilled and fixed on the pier for stability as per drawing M-401. On top of
the concrete column a block out will be assembled in order to concrete and
grout a head plate with shear studs later.
The steel column will be welded to the head plate on site and bolted to the
steel crossbar. The cross bar is anchored to the pier cap with 8 nos of 40
mm dia Mac alloy or equivalent Hi strength bars that are embedded in the
pier cap.
The launching bearing similar to the one used at the other piers will be
added. In order to maintain the required launching level, steel filler plates as
required will be used. The tolerance in the levels between the two launching
bearings shall be within 2mm.
All bolts at the construction joints of the bracket will be non-preloaded bolts.
They shall be manually tightened according to the Attachment E1. The
procedure shall be recorded.
The coving of the steel shall be checked. Coving shall be < l/300 (l = length
between head plate and crossbar.
Limiting Load on
Pressu
Number of Truss Jack Practical
Wt friction Ram area re
Girders @1.05*Design value
@5% Setting
Load
T T T cm2 Kg/cm2 Kg/cm2
Note - If we provide less strands and do not control the total force by jack, the
strands may break if the friction is higher than expected or if there is some
obstruction. We should restrict the maximum force in jacks at every stage by
limiting the hydraulic pressure.
-Multi-Strand Jack
Two 1000 mt capacity jacks will be installed on the vertical beam (reaction
frame) both of the jacks will be connected to one common stressing pump
(EOHP) to ensure the uniform movement of both of the jacks. The pump is
designed in such way that within one hour duration 9-10 mtr of effective
pulling can be done.
The jack will be provided with the front and the rear anchorage. While
pulling operation, the load will be transferred on the rear anchorage and the
front anchorage will be free. After pulling operation is completed the front
wedges will be locked with sufficient pressure (sufficient pressure is the
required pressure that will generate force equal to the frictional forces.
Maximum frictional force is considered as 5% of the total load at given time)
to transfer the load from rear anchor to front anchor and then the piston will
be returned back to its original position. After tightening the grip in the rare
anchor block the above mentioned operation will be repeated.
The stressing pump will be placed on the scaffolding at Pier 1, 11, 21 and
31.Details of stressing pump are shown on the next page.
Strands are checked for their compliance to the specification at the time of
procurement. Strands will not be new for every span launching. The same
strand shall be used. Physical inspection for any damage will be carried out
before every launching process. For this purpose the working loads are kept
within 0.5UTS of strands.
During the installations of the strands they shall be checked for cracks and
fractures. Damaged strands shall be replaced.
The strands must be clean of dirt, rust etc. before they are installed.
Installation of strands shall be done manually. All strands shall be laid over
the bracket hanging below the span truss. The scheme for the strands
(removal and support during launching) is shown in the Attachment F.
Pump will have pressure relief valve, direction control valve, check valve
and lever activation for operation. The connection between jack and pump
will be provided by working ports suitable to operate two jacks
simultaneously as well as if required any one jack at a time without
changing any Hose pipe.
Each jack will have 3 nos. of anchor plates / bearing plates. Hence for 37K15
system 12 nos. is required and for 7 K15 8 nos. of bearing plate is required.
- Wedges
Specially designed wedges with a special alloy steel duly heat treated shall be
used.
Calculation for wedges for 37K15 System with 1000T capacity Multi strand Jack
For the launching process sliding plates will be inserted with the PTFE on the
bottom side of bottom chord of span truss. At this PTFE will be connected to the
stainless steel of the launching bearing. Because the friction between the sliding
plates steel surface and the contact area of the stainless steel / PTFE is much
higher the whole superstructure can be launched forward.
The sliding plates will be inserted at one end of the launching bearing. With the
launching they will be moved forward to the other end of the launching bearing.
There the sliding plates will be taken out again and carried again to the end of
the launching bearing. The weight of one sliding plate is around 10 kg.
In order to lower the friction coefficient the PTFE shall be applied with soft soap.
Both ends of the stainless steel plate are rounded so that sliding plates can be
easily inserted. The procedure of inserting the sliding plates is shown on the next
page.
The top plate of the lateral guiding which is bolted to the vertical beam will be
shifted for 150 mm and bolted again. Between the guiding and the bottom chord
a hydraulic jack (2 x 50 t) will be placed and the superstructure will be pushed
back to the designed line. The designed line of the superstructure shall be
marked on the launching bearing.
Parking Position
The launching process will be finished, when the axis of the first end cross beam
of the first truss (span 40, 30, 20, 10) reaches the centerline of the launching
bearing / bearing axis.
The axis shall be marked on the truss as well as on the launching bearing and for
P40 Location it should be marked over launching nose which will match with the
axis line marked over launching bearing.
Longitudinal fixing
Due to the fact that the whole launching level is a straight line in the horizontal
alignment no special longitudinal fixing in the parking position is required.
After the above mentioned position is reached the pressure in the strand jack can
be realized.
At all launching bearings the gap between the bottom flange of the bottom chord
and the lateral guiding of the launching bearing shall be blocked with filler plates
or hard wood wedges.
N-3
N-1 N-2
According to the design the end of the nose will pass the axis of the
launching bearing for about 3.00 m before it touches the launching bearing.
At this the following deflections are expected (cantilever of 128 m):
The point of touching of the Nose and the point of leaving of the tail shall be
marked with paint on the Sliding Bearing during installation of the sliding
Bearing.
If the nose touches the launching bearing earlier (i.e. before the axis of
launching bearing), a jack (50 t) shall be put underneath the launching
bearing as shown in the following sketches. When the nose touches the
launching bearing the jack will be lifted in order to prevent the launching
bearing from tilting. When the whole launching bearing is loaded the jack
will be released.
50 Tonne
Hydraulic Jack
Before the nose touches the launching bearing, the lateral guiding will be
assembled [Ref. Drg No M-301] in shifted position. At this there is a gap of
170 mm between the guiding and the bottom chord. (Refer detail of Lateral
Guiding in Cl. 15.6)
Due to the fact that the launching will not executed at wind speed exceeding
15 m/s the maximum expected lateral deflection is lower (about 15²/20² x
162 mm ~ 91 mm).
When the nose passes the second lateral guiding (in the line of launching)
the lateral guiding [Ref. Drg No M-301] will be shifted to the launching
position.
If necessary a jack (50 t) will be placed between the lateral guiding and the
bottom flange of the nose at one launching bearing. At the other launching
bearing the lateral guiding will be assembled in the launching position. With
the help of the jack the nose will be pushed until the central line of the
bottom chord meets the reference line at the launching bearing. Then the
other lateral guiding (at the same launching bearing) shall be shifted to the
launching position. Finally the jack will be removed and the lateral guiding
will be shifted and bolted in launching position as well.
At the tip of the nose a steel girder for jacking the nose is assembled.
This steel girder ends about 3.50 m in front of the nose. If there should be
any further deflection of the nose – deviating from the design calculation –
and nose reaches the launching bearing below the designed level.
In such condition, launching must be stoped about 300mm before the nose
reaches the launching bearing. Before the launching continues, a 50 t
capacity jack with arrangement as given in Drg. M-504 shall be placed on
top of the temporary steel support [as shown in figure below]. On top of the
arrangement sliding plates with PTFE shall be placed. Then the nose will be
jacked up so that bottom level of nose match with the top level of launching
bearing and the launching train will be launched forward. Detailed sequence
is provided in M-504.
Jack removed
Launching of the nose will be done over this arrangement. When the nose
reaches the launching bearing, jacks will lowered until the nose is supported
on the launching bearing. After the nose touches the launching bearing the
launching will proceed as described before. Procedure shall be recorded as
per ‘CHECKLIST FOR DEFLECTION DURING LAUNCHING PHASE-0’
[Format No. HCC F 097 10 08, Rev No. 00, Rev Date - 07.09.2013] and
‘CHECKLIST FOR LAUNCHING PHASE-1-4’ [Format No. HCC F 097 10
09, Rev No. 00, Rev Date - 07.09.2013].
Workers at the launching bearing have to take care that the insertion
of sliding plates is continuous.
According to design, the tail will lose contact with launching bearing before
the end of tail will reach the axis of the launching bearing (similar to the
described procedure for the nose).
If the tail doesn’t lose contact with launching bearing in that situation the
launching will be stopped about 300 mm before the end of the tail reaches
the axis of the launching bearing.
PHASE 0: This stage covers the operations to be carried out on the first
truss of every train till the first truss reaches Pier P1. Thus this stage is
common for all the four trains of trusses.
This phase also explains the dismantling process for the tail of segments
2, 3 and 4.These operations are done at different pier nos as listed below
In this stage a detailed work procedure for the launching stage for the first
truss of every train till the first truss reaches Pier P1. Thus this stage is
common for all the four trains of trusses. A detailed step by step
procedure along with important observations and checks are detailed
below.
• The Main Truss at this stage is at level 0.00 and the x distance is
considered as 0.00m in longitudinal direction. The launching nose
is totally 52 m in length and weighs about 200 T.
• Install Launching Bearing at P31(v) with top RL of stainless plate at
RL 118.1385m
• Launching Nose is erected on temporary supports to facilitate
erection of individual components of the Nose.
• The Nose is erected temporary support with bottom of nose in
straight portion at launching level RL118.156.
• Once the Nose is erected and all the connection bolts are torque,
the temporary supports below the nose, except the support over
Pier P31(v), are removed.
• Install 8 hydraulic jacks [400t capacity] below launching bearings
(two per bearing), lift simultaneously the launching bearing by
25mm, new level of launching bearing will be 118.1635m (top of
SS plate)
• Check the vertical alignment of the Nose.
• Now the tip of nose is at x=52.00m. With support on pier P31(v)
(over hanging by 52.00-15.66=36.34m from Pier P31(v).
• Check the deflection at the tip of Nose using and compare with
the design value according to attachment G1
• Erect the Anchor beam at the front end of the Truss. Install Pulling
device on Pier P1 along with strand jacks, and strands.
• Due to overhang of the Nose, sledges LS109 and LS 110 are free.
Remove the sledges LS 109 and LS 110
• Fill out the Inspection Plan(Check List)
• Shim plates below P31(v) bearing=1x25 thk
• Launch 38.01 m. at this stage the Nose tip is over A1. However
since the cantilever span is only 74.35 m the Nose will not touch
the launching bearing at A1
• Launch up to X= 52.0. Sledges 100 and 101 are free but should
remain in place.
• Launch up to X= 58.1. Sledges 100 to 102 are free but to remain
in place.
• Load is on launching bearing at P31(v) and sledge 103
Step 1.0
Step 1.1A
• With the help of strand jacks and pulling system in yard, pull the
Truss T2 forward up to the connection point.
• At the end of pulling, the c/c of end cross beams of truss T1 and
Truss T2 will be at 3.4m c/c.
• It is likely that the truss T2 is out of axis in transverse direction by
few mm during pulling operation due to the clearance at lateral
guiding system.
• Align the Truss T2 (if required rear end of T1 also) and bring them
in their true axis. (Max tolerance 2.0 mm).
• Accurately measure the gap between ends of the trusses T1
and T2. It is to be noted that the gaps will be different for top
chord and bottom chords due to pre-camber.
• In order to account for the actual gaps, the connection piece will be
fabricated with slightly higher length (say 1450 mm instead of
1400 mm for bottom chord).
• Trim the pre-fabricated connection piece to the actual dimensions.
• Fit up the connection piece on temporary supports.
• Weld the connection piece as per specifications.
• Complete required tests on welds.
• Grind the welds carefully, especially the bottom sliding surface of
the bottom chord.
Revision No.: 2; Revision Date: 20.11.2013 Page 106 of 134
CEMG
HCC-DSD-VNR Consortium Management System
Segment Quality Plan For The Launching Of Span Truss
HCC N 097 17 007
Step 1.1B.
Step 1.2
Note: when any sledge is expected to free and it is not free then will move
truss forward and make that sledge free then remove.
Step 1.3A
Step 1.3B
Step 1.4A
Step 1.4B
Step 1.5
Step 1.6A
Step 1.6B
Step 1.6C
Step 1.6D
Step 1.6E
Step 1.7
Step 1.8
Step 1.9
Step 1.10
Step 1.11
Step 1.12
• At this stage the Nose in front will touch Launching bearing at Pier
P11.
• Now the System is free from Pier P31(v) and further launching will
continue as explained above till the Truss T1 reaches the final
position.
Step 1.13
Step 1.14
Tail for other segments are dismantled in similar way as for segment 1
Due to already launched segment, tip of Nose for Launching train 2 cannot
be launched beyond P30. Similar situation is there for Launching train 3 at
Pier P20 and Launching train 4 at Pier P10.
1. For dismantling of tip portion following are the two different conditions.
The general procedure of the dismantling is shown in the sketches on the next
pages for the first 6 stages
The dismantling of the tail will be done part by part with the help of a mobile /
floating crane.
Dismantling of the tail should be done from the tip of the tail proceeding towards
the main truss.
Dismantling should be done bay by Bay (bay is the portion between the nodes of
the Tail).
Each bay of the tail (portion between the nodes of the Tail) should be dismantled
with the following sequences for the members of the bay.
• Bottom Chord
Only after dismantling all the members in one bay, we proceed to dismantle the
next bay.
The trusses in the launching segments are connected to each other with
connection piece welded to either of the truss. After launching segments reaches
its final position, it is 10 span continuous beams with nose and tail overhanging
at either end of launching segment. As per design each truss has to behave as
simply supported structure resting on the permanent bearings. To assure above
structural behavior, the connections pieces between two trusses shall be cut so
as to separate each of the truss from others.
Following are the preconditions considered for design of cutting and lowering
operations.
- The stroke of jacks [600T capacity] in one stage should be more than
300mm in order to do the lowering operation it should be done in two stages as
maximum stroke length is 200mm.
- Forces in the connection joints due to the hooking moment during lowering
should be smaller than during launching. Stresses in the structural members
should be smaller than 90 % of the allowable stress.
1. 4 x 600 t jacks with tilt saddle and fixing collar for span lowering
2. 4 x 600 t jacks with tilt saddle and fixing collar for Stress release
In the following procedure the bearings axes of the piers are called as follows:
Axis-1 Axis-2
Step 3.1
Step 3.2
• Place Jacks (2x600 t at the jacking points) at axis 40.1 and remove
launching bearing at axis 40.2 The jacks shall be hydraulically synchronized.(axis
40.1 is the front cross beam of truss T2 and axis 40.2 is rear cross beam of truss
T1)
Step 3.3
Step 3.4
• Operate Jacks at Axis 40-1 raise level by 180 mm above launching level
(In Synchronised mode).
• Operate Jacks at axis 39-1 (In Synchronized mode) and lower it by 137
mm below launching level.
Step 3.5
• Add Jacks (2x 500 t) at axis 39-2 (to eliminate the shear forces in the
connection piece). Activate the jacks to ensure force in Jack should be 4000 kN
(In Synchronized mode).
Step 3.6
• Lower Span 40 to the final level. (Refer separate Procedure for Lowering
and Bearing Installations Methodology).
The procedure of the other spans is similar to as described above for the span
40. Only the lifting and lowering values shall be adjusted according to Drawing
M013.
16 CORROSION PROTECTION
The Repair procedure for any damage on painting surface due to launching and
associated activities shall be carried out as per document for ‘REPAIR ROCEDURE
FOR PAINTING’ HCC P 097 17 07, which has been submitted to the Client for
approval.
Truss Girder
The welds at the downside of the bottom truss chords bottom flange shall be
grinded in the workshop. Before each launching stage this has to be checked
again for the latest assembled truss girder.
Same shall be done for the nose. Especially at the bolted connection the edges
shall be smoothed.
18 CHECKING SETTLEMENT
Height controls at the top of the launching bearing shall be done before every
launching step. Measuring points shall be set at the bearing axis of the pedestal.
The measured values shall be recorded before every launching step.
This job will be done – if necessary – in parking position. At this time the
maximum load at the launching bearing is about 4700 kN. Therefore a jack with a
capacity of at least 500 t shall be used at each launching bearing.
Before each launching stage and as a precondition for the approval of the
launching operation by the launching manager the Inspection Plan added
as Attachment C to this Segment Quality Plan shall be filled out and
signed.
All safety and precaution shall be taken care as per Project Occupational
Health & Safety Management Plan (HCC N 097 15 001).
Environnent: -
21 EMERGENCY PLAN
At this errors /mistakes that might happen during the launching operation
are mentioned. For each of this errors / mistakes the actions to be taken in
such a case are mentioned.
22 ATTACHMENTS:
22.1 Attachment A: Extracts from Structural Analysis
22.1.1 A1 Bearing Forces Launching Phase 2 Page A1/1 – A1/8
22.1.2 A2 Bearing Forces Launching Phase 0-1 Page A2/1 – A2/15
22.1.3 A3 Launching Yard Single Truss Page A3/1 – A3/10
22.1.4 A4 Launching Yard Sledges Phase 0 Page A4/1 – A4/30
22.1.5 A5 Launching Yard Sledges Phase 1 Page A5/1 – A5/28
22.1.6 A6 Deflections Launching Phase 2 Page A6/1 – A6/12
22.2 Attachment B: Methodology Sequence Drawings
22.3 Attachment C: Inspection Plan
22.3.1 C1 Inspection Plan Launching
22.4 Attachment D: Emergency Plan
22.4.1 D1 Emergency Plan
22.4.2 D2 Bracing Nose
22.5 Attachment E: Bolts - Torque Moment
22.5.1 E1 Torque Moment
22.6 Attachment F: Strands Scheme
22.6.1 F1 Strands Scheme
22.7 Attachment G: Table of Level
22.7.1 G1 Tip of Nose Phase 0 and 1
22.7.2 G2 Connection Piece Phase 0 and 1
22.7.3 G3 Tip of Tail Phase 1
23 DISTRIBUTION
24 RECORDS