Está en la página 1de 60

VSBK DESIGN OPTION Guidelines

VSBK Design Option Guidelines

Authors : Heini Müller, Prabin Chhetri, Tobias Müller


Editors : Karl Wehrle, Urs Hagnauer
Proofreader : Madeleine Cannon
Illustrations : Prabin Chhetri, Keshar Joshi
Layout and graphics : Kiirtistudio
First edition : September 2013
Contact : Skat Foundation (info@skat.ch)

ISBN 978-3-908156-49-9
Copyrights © Skat, 2013

This document is not intended to be a construction guide and entrepreneurs who consider constructing a VSBK
are strongly advised to contact an experienced local or regional VSBK expert/consultant.
Contents

Acknowledgements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . v
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vi
Purpose of this documentation . . . . . . . . . . . . . . . . . . . . . . . vi
Potentials and limits of this documentation . . . . . . . . . . . . . . . . .vii
Feedback and up-grading of this documentation . . . . . . . . . . . . . .vii
Overview of VSBK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii

01. Foundation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1

02. Unloading mechanism support unit . . . . . . . . . . . . . . . . . . . . . . . . . . 3

03. Trolley guide. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5

04. Brick corbelling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

05. Brick support I-beams. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

06. Girder system. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11

07. Arch/slab. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

08. Shaft. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

09. Cavity between shaft and shaft support structure. . . . . . . . . . . . . . . 19

10. Shaft support wall. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

VSBK Design Option GUIDELINES \ iii


11. Kiln insulation boxes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

12. Peep-hole pipes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25

13. Outer kiln wall structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26

14. Working platform . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29

15. Flue-ducts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31

16. Shaft top structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33

17. Emission exhaust system. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

18. Flue gas dampers/valves. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36

19. Shaft lid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38

20. Unloading bars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40

21. Unloading trolley . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42

22. Brick unloading system . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43

23. Access to the working platform. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45

24. Roof . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48

iv / VSBK Design Option GUIDELINES


Acknowledgements

The Vertical Shaft Brick Kiln (VSBK) Skat likes to express sincere thanks to Last but not least Skat, as the partner in
development process documentation started the piloting entrepreneurs from various charge for the technology transfer to South
during its applied Research & Development countries who made the VSBK technology Africa would also like to acknowledge the
stage in 1997 and reached a first important learning and development possible. Only VSBK Project in South Africa which financed
milestone in the legendary “Brick by Brick through the spirit of VSBK pioneers, who the development and publication of this
- The Herculean Task of Cleaning up the were and are prepared to practically test document as well as our consortia partner,
Asian Brick Industry" in 2008. Yet the actual new approaches and at the same time take Swisscontact, who facilitated the project
construction development process has some risks, the VSBK technology could be implementation.
been continued since. In particular the exposed and tested in the practical business
“South – South” VSBK technology transfer environment.
to South Africa lifted the VSBK technology Karl Wehrle
significantly. Additional construction options Skat is also very grateful to all partner Skat Consultancy
have been realized that promote the VSBK organizations and individual professionals
technology as a globally recognized clean from various countries, who each in their
brick production system. However, the result own way contributed towards important
of this process has until now never been “puzzles” in order to up-grade and perfect
systematically documented and updated. the VSBK technology. They made a South-
South technology transfer possible.
Skat would like to express its sincere
appreciation to Swiss Development Special thanks to all those who contributed
Cooperation (SDC) for its continued support to the development and compilation of
to the development of the VSBK technology this documentation, in particular to the
and its adaption to specific local contexts. European experts in energy & environment,
Without this persistent commitment and kiln construction and ceramics, Mr. Max
trust into the involved partners over a period Müller, Germany, Mr. Hans Schmid,
of more than a decade the development Switzerland, Mr. Ekhard Rimpel, Germany,
of the VSBK technology as a technical and and Mr. Alois Müller, Switzerland, as well as
economical viable environment friendly to Mr. Urs Hagnauer, former VSBK Project
alternative to traditional brick production Manager, Nepal.
systems would not have been possible.

VSBK Design Option GUIDELINES \ v


Background

This publication is part of the ongoing VSBK technology and thereby building However, latest adaptations to local contexts
efforts of the VSBK technology transfer local VSBK experts while at the same time by local experts in South Africa could not
process from Asia to South Africa. It is part creating and overseeing an international be included in this document since they
of the tasks entrusted to Skat in an overall network of experts and specialists to are being claimed as intellectual property.
process of knowledge transfer. The focus of sustain the VSBK technology as well as its Depending on interest they may be made
this publication are both the main design constant improvements, documentation available through a consultancy contract.
options as well as construction elements and international dissemination, therefore
of the Vertical Shaft Brick Kiln. The VSBK making best use of the investments made by Purpose of this documentation
is the most energy efficient coal fired clay SDC and all other partners.
brick production technology. Ever since SDC Through the SDC supported “South – South"
supported the systematic VSBK technology The VSBK technology is not patented. Since VSBK technology transfer to South Africa
transfer from China to India in 1996 a lot its commercial, environmental and social new thinking, new views, new experts and
of local and international VSBK working development was financed by SDC this thereby new potentials were leading to
experience has been accumulated. In its technology is considered an “open source” additional construction options. Awareness
quest to contribute to cleaner clay brick technology. The results of 17 years of of the unique energy and environmental
firing systems, and thereby to a cleaner VSBK design/construction experience and advantages of the VSBK technology is rapidly
environment, SDC also supported the VSBK knowledge from all stages of the various being disseminated at a global level. With
technology transfer to Nepal, Vietnam, VSBK technology transfers have been this document, experts not only in South
Afghanistan, Pakistan and since 2009 to collected and compiled as “VSBK Design Africa but also at global level are enabled
South Africa. Option Guidelines”. to make an educated decision of how to
adapt the VSBK technology and therefore
In the VSBK technology transfer to the This documentation is the result of contribute towards an increased global VSBK
above mentioned countries, except to professional involvement of experienced demand while at the same time reducing the
Vietnam, Skat Consultancy is the only European brick kiln experts with global VSBK greenhouse gas emission from a polluting
international organisation that has been a technology experts and local practitioners/ industrial sector.
constant partner to SDC’s environmental entrepreneurs. Hence this documentation
endeavour since 1996. This professional considers both; the current state-of-art brick The purpose of this documentation is to
trust was continually acknowledged kiln know-how at European level as well provide a general overview of different
by Skat Consultancy with its principle as globally applied practical and technical VSBK construction options and makes it
working strategy; to locally anchor the options. clear that there is no 'One-size-fits-all'. For

vi / VSBK Design Option GUIDELINES


a profitable VSBK business experienced to provide basic rationales and explanations
professionals should be involved who assess where deemed essential. It is sometimes
the appropriateness of a given option to a difficult to precisely and appropriately
given situation and this document aims to be provide sketches and explanations to fully
a valuable resource for decision makers. comprehend detailed construction drawings
of different options. They can be made
Potentials and limits of this available through a consultancy contract
documentation with any of the VSBK technology service
providers.
VSBK construction options are always
linked to, and with the purpose of, brick This document is not intended to be a
firing and its related economics. Although construction guide and entrepreneurs who
numerous VSBK construction options consider constructing a VSBK are strongly
are globally implemented by various advised to contact an experienced local or
organizations, experts and entrepreneurs, regional VSBK expert/consultant.
the authors utilized a two-shaft VSBK design
as reference and purposefully limited the Feedback and up-grading of this
number of possible construction options documentation
in this document in order to focus on
proven practical and economical practices. Any feedback and additional experiences
For individuals with limited access to regarding the various technical options is
high tech solutions and high up-front most welcomed and can be directed to Skat
financial investment, for whatever reasons, Foundation (info@skat.ch). Skat Foundation,
current industrialized 'state of the art' kiln along with the respective experts and
construction materials and techniques need authors, will accordingly secure future
to be down scaled into practical solutions. up-dates to this document and make the
This documentation not only shows practical collected information available to a broader
options but also presents potential future audience, with reference to the source of
options that will require local fine-tuning information.
for viable final adaption to the local context.
It would be way out of the scope of this
document to explain the detailed aspects of
the VSBK construction. This document tries

VSBK Design Option GUIDELINES \ vii


Overview of VSBK

17
01 Foundation
02 Unloading mechanism support unit
03 Trolley guide
24 04 Brick corbelling
05 Brick support I-beams
06 Girder system
19 16 07 Arch/slab
15 08 Shaft
18
14 09 Cavity between shaft and shaft support structure

23 11 10 Shaft support wall


13 10 11 Kiln insulation boxes
12
12 Peep-hole pipes
13 Outer kiln wall structure
14 Working platform
09
15 Flue ducts
08 16 Shaft top structure
17 Emission exhaust system
07
18 Flue gas dampers/valves

20 06 19 Shaft lid
20 Unloading bars
05
03 04
21 21 Unloading trolley
22 22 Brick unloading system

01 23 Access to the working platform


02
24 Roof

viii / VSBK Design Option GUIDELINES


01 Foundation

Function
OPTION 1 : R.C.C. raft foundation
The foundation is the part of the VSBK that is in
direct contact with the ground and through which (Suitable for non-cohesive soils)
structural loads, including the weight of green
bricks, coal storage and movements are being Advantages Disadvantages & Limits
transferred. • Equal load distribution on any • Expensive construction
type of natural grown soil option due to the use of mass
• Employed working personnel concrete and reinforcement
Design principles can work on a clean and safe steel
A universal foundation design for all types of ground platform
is technically and economically not feasible since • Ground water penetration can
key parameters vary according to the local situation be minimized
and context. Therefore, the foundation has to be
professionally designed, case by case and according
to local contexts.

A VSBK should never be constructed on back-


filled soil or landslide-prone areas. Special design
precautions must be taken for areas having a high
ground water table or earthquake experience.

VSBK Design Option GUIDELINES \ 1


01 Foundation

OPTION 2 : Brick footing OPTION 3 : Pillar foundation


(Suitable for cohesive soils) (Suitable for both cohesive and non-cohesive soils)

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• A Brick entrepreneur can use • Not applicable for all types of • Suitable option for a frame • Generally requires horizontal
his/her own bricks for this grounds and especially not an structure VSBK construction concrete tie-beam connection
foundation option and can optimal option in cases of high • Considerable amounts of
therefore optimize expenses ground water table shuttering material is required
• Requires good brick quality • Depending on the required
depth of the pillars a relatively
expensive construction
method
• Demanding in skill
(preciseness) and supervision

2 / VSBK Design Option GUIDELINES


02 Unloading mechanism support unit

Function
OPTION 1 : M.S. I-beams
The unloading mechanism support unit
accommodates the height of the hydraulic piston Note : M.S. I-beams are installed perpendicular to the arch walls in
or screw, protects the unloading mechanism from order to transfer the load of the bricks setting inside the shaft to the
potentially being blocked during operation and kiln foundation.
bears the load of the entire brick setting inside the
shaft during unloading procedures. Advantages Disadvantages & Limits
• Economical option due to the • Foreign material could fall
Design principles utilisation of the arch wall into the pit structure which
foundations could create complications for
The unloading mechanism support unit must bear
• Can accommodate both unloading procedures and are
the entire brick setting load and its unloading
hydraulic and manual likely difficult to clean
system in such a way that no structural settings/
unloading mechanisms • In areas of high water table,
damages will hinder the unloading operation.
a watertight pit structure
should be ensured in order to
The related pit should be protected from the nearby
avoid water contact with the
filled soil and ground water so that the unloading
unloading mechanism
mechanism can move freely.

VSBK Design Option GUIDELINES \ 3


02 Unloading mechanism support unit

OPTION 2 : R.C.C. load bearing unit


Note : This unit is separated from the kiln structure. It bears the entire
load of the brick setting inside the shaft on its own foundation.

Advantages Disadvantages & Limits


• Pit structure is maintenance • Does not utilise the arch wall
friendly foundation for support, its
construction requires heavy
duty concrete and steel
reinforcement and is therefore
considered expensive
• Only feasible on ground with
sufficient bearing capacity

4 / VSBK Design Option GUIDELINES


03 Trolley guide

Function
OPTION 1 : Recessed MS C-channels
The trolley guide assists in correctly positioning
the trolley for unloading procedures and, when the
unloading trolley is correctly positioned, acts as a Advantages Disadvantages & Limits
safety feature to prevent unevenly loaded trolleys
• Low wear & tear of the • Wall corbellings are required
from toppling.
masonry walls during near ground level, hence the
unloading wall construction becomes
Design principles • Correct positioning of trolleys more labour intensive and
The trolley guides are made with MS C-Channels below the shaft is ensured therefore costly
and are properly anchored into the arch walls. • Trolleys and the unloaded fired
bricks are prevented from
becoming wedged between
the shaft supporting walls
during unloading procedures

VSBK Design Option GUIDELINES \ 5


03 Trolley guide

OPTION 2 : Protruded M.S. C-channels FUTURE OPTION 1: Screwed-on guides

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Wall brick corbelling is • Chances of injuries during • Low construction cost • None
not required, hence the unloading procedures • Simplified trolley locks hence
construction becomes less no movable parts
time consuming and therefore • Easy maintenance
less costly

6 / VSBK Design Option GUIDELINES


04 Brick corbelling

Function
OPTION 1 : Two arch wall corbellings
The brick corbellings increase the arch wall distance
for unhindered unloading of the fired bricks and (1st and 2nd , on each side of the arch supporting walls)
movement of the trolley
Advantages Disadvantages & Limits
Design principles • Reduced risk of fired bricks • Arch side wall brick corbelling
tumbling from the unloading construction becomes time
The brick corbelling of a given brick course should
trolley consuming and therefore
ideally not exceed 3cm.
• Less wear & tear due to M.S. costly
C-Channel trolley guides • Could hinder pulling out the
Wall corbellings can be made, but as a matter of
constructed flush with the arch trolley due to the small gap
fact, are optional depending on the quality of green
wall support masonry of 3 cm between the wall and
bricks, firing and operation practices.
the trolley during emergency
unloading
Since the arch masonry walls distance and the shaft
size have different measurements the refractory
shaft corbelling is advisable to avoid damages
during operation.

VSBK Design Option GUIDELINES \ 7


04 Brick corbelling

OPTION 2 : Corbelling at refractory brick shaft level

Advantages Disadvantages & Limits


• Easy to pull and push the • Protruded M.S. C-channel
trolley due to increased side trolley guides (see 3, option 2)
space must be fixed otherwise the
• Construction of the arch side trolley guide lock becomes too
walls is less time consuming long which could be difficult
and therefore less costly during unloading
• More economical because the • Increased risk of fired bricks
shaft supporting corbelling tumbling from the unloading
layer can be constructed just trolley due to increased side
before the first refractory brick space
layer of the shaft

8 / VSBK Design Option GUIDELINES


05 Brick support I-beams

Function
OPTION 1 : Brick support beam positioned for unloading
The brick support I-beam is the resting place
for unloading bars and the girder system during 6 layers of bricks
operation. Between unloading procedures the beam
Advantages Disadvantages & Limits
supports the entire brick setting load inside the
shaft and transfers it to the arch supporting wall. • Higher unloading capacity, also • The dimensions of the
during emergency situations unloading screw/hydraulic
Design principles • Reduced workload for piston increases due to the
personnel during regular increased lift height
The brick support I-beams must be designed to
operation since less unloading
carry the entire brick setting within the shaft.
procedures are performed for
the same number of bricks
The temperature at the unloading place can at
being unloaded
times be as high as 400°C, which needs to be
• Friendly working environment
considered when estimating the I-beam dimensions.
due to less heat exposure
The I-beams should be completely straight,
• Increased cooling down rate
never even slightly twisted or bent and must be
possibility
positioned parallel to each other.

VSBK Design Option GUIDELINES \ 9


05 Brick support I-beams

OPTION 2 : Brick support I-beam positioned for


unloading 4 layers of bricks (including a lower arch and
reduced overall kiln height)

Advantages Disadvantages & Limits


• Due to the decreased lift • Unloading difficulties during
height the dimensions of the emergency situations; hence
unloading screw/hydraulic an experienced & disciplined
piston decreases working crew is required
• Decreases overall construction • Increased workload for
costs due to the reduced kiln personnel during regular
height operation since more
unloading procedures are
performed for the same
number of bricks being
unloaded
• Increased heat exposure to
working personnel

10 / VSBK Design Option GUIDELINES


06 Girder system

Function
OPTION 1 : Girder system with side locks
After the trolley is securely positioned beneath the
fired bricks, the Girder system facilitates the release
of the unloading bars and hence the load of the Advantages Disadvantages & Limits
entire brick setting is transferred to the trolley and
• No electricity required • Girder rail prone to bending
the unloading system.
• Less uplift movement of due to heat radiation and
screw/hydraulic piston and constant load
Design principles therefore easier for working • Increases construction time
The girder system needs to be designed in a way personnel due to fixing of all the related
that it is able to carry the entire brick load. Further, metal parts
it has be ensured that the release mechanism
cannot be triggered accidently (or unintentionally)
and the brick load can be transferred onto the
trolley without potentially injuring working
personnel when releasing the system.

When a hydraulic unloading system is in place the


whole girder system is not required.

VSBK Design Option GUIDELINES \ 11


06 Girder system

OPTION 2 : Girder system with wedge locks


(MS square rod/wedge)

Advantages Disadvantages & Limits


• Cost effective • None
• No electricity required
• Less uplift movement of
screw/hydraulic piston and
therefore easier for working
personnel

12 / VSBK Design Option GUIDELINES


07 Arch/slab

Function
OPTION 1 : Arch constructed with brick
The arch/slab structure ensures safe access to
unload the fired bricks. It also distributes the
loads of above build structural and non-structural Advantages Disadvantages & Limits
loads into its supporting walls. Further, air
• Locally available bricks can • Requires an arch mould
entering through this access opening is aiding
be used, therefore reduced • Arch construction will increase
both the combustion and the brick cooling
construction costs the overall kiln construction
process.
time
Design principles
Different Arch types can be designed.

Concrete beams and arches; in situ or


prefabricated; are viable alternatives to brick
arches. A few of them are shown as options in
this document.

Being arch, beam or slab, the fundamental


design criteria is that the structure is safely
bearing the load placed on top of it. Concrete
based structures should not be exposed to
temperatures above 300°C.

VSBK Design Option GUIDELINES \ 13


07 Arch/slab

OPTION 2 : In situ R.C.C. beam and slab FUTURE OPTION 1 : Precast R.C.C. beams with 1 layer of
front bricks attached as insulation and protection
Advantages Disadvantages & Limits Advantages Disadvantages & Limits
• Saves on overall number • Requires shuttering material • Reduces overall kiln • Requires a mechanical lifting
of fired bricks for the kiln • Will increase the overall kiln construction time in case device to place it
construction construction time the pre-fabrication is done in • For achieving economical
• No arch construction skill • Will likely get some damage factories advantages a large number of
required in case of high temperature shafts need to be constructed
exposure (e.g. brick melting
inside the shaft)

14 / VSBK Design Option GUIDELINES


07 Arch/slab

FUTURE OPTION 2 : Precast R.C.C. arch with 1 layer of


front bricks attached

Advantages Disadvantages & Limits


• Reduces overall kiln • Requires a mechanical lifting
construction time in case device to place it
the pre-fabrication is done in • For achieving economical
factories advantages a large number of
shafts need to be constructed

VSBK Design Option GUIDELINES \ 15


08 Shaft

Function
OPTION 1 : English bond refractory masonry without
The shaft is the core element of the kiln and has
to accommodate the firing of the bricks as per expansion joints
the appropriate fire schedule as well as to provide
Advantages Disadvantages & Limits
resistance to mechanical wear and tear from
vertical movement of the loaded bricks. • Uniform expansion and • Special masonry skills required
contraction properties • Expansion will develop
Design principles • Uniform thermal mass uncontrolled masonry cracks
properties
The shaft dimension must be designed according to
the dry green brick size and maximum production
capacity.

Further, the following design criteria should be


considered to allow for trouble-free brick firing:

• Heat resistance of the shaft walling material in the


central firing zone up to 1200°C
• Acidic emission resistance in the pre-heating zone
• Structural expansion properties
• Perfect verticality
• Self supporting structure

16 / VSBK Design Option GUIDELINES


08 Shaft

OPTION 2 : English bond refractory masonry; substituted FUTURE OPTION 1 : English bond refractory brick
with fired bricks in sections with temperatures below masonry with expansion joints
500°C (pre-heating and cooling zone)
Advantages Disadvantages & Limits
Advantages Disadvantages & Limits • Uniform expansion and • Special masonry skills are
• Most economical option under • Chances of shaft damages if contraction properties required and the construction
the condition that the firing the fire position is not properly • Uniform thermal mass system is time consuming,
zone is always maintained at maintained at the centre of properties therefore costly
the centre of the shaft the shaft • Controlled expansion will avoid • Requires special brick blocks or
• Fire position adjustment is uncontrolled masonry cracks, cuttings
limited to refractory masonry hence lower maintenance • Special corner support
area essential to ensure expansion
• Potential damages to fired at defined joints
brick masonry in the pre-
heating zone due to acidic
emissions

< 500oC

> 500oC

< 500oC

VSBK Design Option GUIDELINES \ 17


08 Shaft

FUTURE OPTION 2 : Prefabricated fire resistance


refractory concrete elements
Note : This possible future option requires professional overall kiln
construction planning and practical detail designs.

Advantages Disadvantages & Limits


• Reduced shaft construction • Requires a mechanical lifting
time device to place it
• The shape of the element can • Skill to maintain the total
be both vertical or horizontal verticality of the shaft is
required
• Fire resistant refractory
concrete is considered
expensive
• Will develop uncontrolled
cracks if no expansion joints
are provided

18 / VSBK Design Option GUIDELINES


Cavity between shaft and
09 shaft support structure

Function
OPTION 1 : Unfilled cavity (2-3 cm approx.)
The cavity is required to ensure structurally
independent expansion and contraction of the shaft
structure. Advantages Disadvantages & Limits
• Basically no expenses • Some heat loss due to air
Design principles (However to ensure an equal movement, hence reduced
The main principle for designing this cavitiy is to cavity size it is of advantage insulation value
ensure the structural integrity of the shaft. to place a low cost thermocol • Risk of mortar and other
board. This thermocol board material filling up the cavity if
The top and bottom of this cavity should be closed will melt as soon as the kiln not carefully protected during
with a flexible material after the kiln is fully dried is in operation and a uniform construction
out in order to avoid heat loss. cavity will remain) • Increased heat exposure at the
shaft top area

VSBK Design Option GUIDELINES \ 19


Cavity between shaft and
09 shaft support structure

OPTION 2 : Filled cavitiy FUTURE OPTION 1 : Filled cavity


(Calcium silicate board) (Stone wool or glass wool insulation blanket/board)

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Easy to install since they are • Damage potential if exposed • Cost benefit factor is good • Risk of sagging when fixing
available as self supporting to contact with water insulation blankets to a vertical
boards • Could be a costly option surface
depending on selected
material quality

20 / VSBK Design Option GUIDELINES


10 Shaft support wall

Function
OPTION 1 : English bond brick masonry in mud mortar
The shaft-support wall ensures the independent
working (expansion/contraction) of the shaft,
reduces lateral pressure and acts as an insulation Advantages Disadvantages & Limits
layer. The chimneys are usually constructed on top
• Low construction cost • Chances of wall sagging due to
of the shaft supporting wall.
• Provides reasonable stability mud mortar shrinkage
for chimney system
Design principles
There are many shaft support wall construction
systems possible, all depending on economical
insulating building materials.

Note : Using a 'K-value' calculator for selecting the


size of the most economical insulation material/
structure is recommended.

Note : If a shaft is constructed with expansion joints,


the shaft corners must be supported to ensure
correct expansion direction. (see 8, future option 1)

VSBK Design Option GUIDELINES \ 21


10 Shaft support wall

FUTURE OPTION 1 : Vermiculite concrete FUTURE OPTION 2 : Insulation bricks walls


Note : Vermiculite can also be used as insulation material between
both structures; the shaft and the supporting wall.
Advantages Disadvantages & Limits
Note : It is necessary to consult professionals who are experienced
in practical application of vermiculite concrete technology for a kiln • Potential of slim kiln structure • Insulation bricks are expensive
construction. and cost reduction. • Insulation bricks have reduced
load bearing capacity
Advantages Disadvantages & Limits
• Low thermal conductivity • Is an expensive insulation
material, hence good material
insulation • Vermiculite concrete has
• Can be precast or constructed reduced load bearing capacity
in-situ
• Does not require any further
insulation or structure, except
a protection layer, e.g steel
• The kiln size can be reduced,
hence material and labour cost
can be reduced

22 / VSBK Design Option GUIDELINES


11 Kiln insulation boxes

Function
OPTION 1 : Filled with ungraded soil
Kiln insulation boxes are constructed to distribute
the load of insulation material used to minimize
energy losses. They also provide rigidity to the Advantages Disadvantages & Limits
kiln structure and define the size of the working
• Cheapest and easily available • Low insulation value, the heat
platform.
filling material loss is relatively high
• Difficult to avoid water
Design principles penetration during
The box dimensions must be related to the construction
insulation material value to be used and the • Chances of shaft bulging
required working space and type of platform. increases with the frequency
The top of the insulation boxes (platform) should of shutdowns due to repeated
ideally be covered to avoid heat loss. compacting of fine particles

Note : Filling material should be as dry as possible.

VSBK Design Option GUIDELINES \ 23


11 Kiln insulation boxes

OPTION 2 : Filled with graded brick gravel

Advantages Disadvantages & Limits


• In relation to the insulation • Difficult to maintain proper
value it is a good and material grading during filling
economical filling material process
• Enhanced insulation properties • Difficult to avoid water
due to creation of micro-pores penetration during
• Decreased risk of shaft bulging construction

24 / VSBK Design Option GUIDELINES


12 Peep-hole pipes

Function
OPTION 1 : M.S. pipes
Peep-hole pipes are narrow openings in the kiln
structure which allow a visual and/or mechanical
fire temperature monitoring. Advantages Disadvantages & Limits
• A straight-forward, practical • Potential of excess air entering
Design principles and economical system for the shaft if the pipes are
Peep-holes must be designed to allow visual fire position/temperature not properly sealed during
monitoring of the fire position and/or insert fire monitoring operation
monitoring equipment (thermocouples) from the
outside of the kiln structure.

Further, they should be positioned in a way


that they do not bend under the weight of the
insulation filling.

The exactness of the fire schedule plotting


increases with the number of built-in peep-hole
pipes.

The respective batch height and the soil shrinkage


defines the position and distance of the peep-
hole pipes.

VSBK Design Option GUIDELINES \ 25


13 Outer kiln wall structure

Function
OPTION 1 : Load bearing brick masonry with buttresses
The outer kiln wall structure encases the insulation
filling around the shaft supporting walls and
ensures structural rigidity and protection against Advantages Disadvantages & Limits
the elements.
• Can support above built • Buttresses increase the
structures (loading platform, required construction area
Design principles roof, mechanical transporting
The outer kiln wall structure must be designed devices etc.) and green brick
so that it can protect the insulation and the shaft storage
structure against mechanical impact. • Buttresses supporting the
access to platform can reduce
Note : Sufficient weep holes must be provided construction costs
to avoid kiln structure damages due to water
evaporation during the initial firing. These weep
hole should be closed only after the kiln is
completely dried out.

26 / VSBK Design Option GUIDELINES


13 Outer kiln wall structure

OPTION 2 : Concrete frame structure with in-filled brick OPTION 3 : Metal


masonry

Advantages Disadvantages & Limits Advantages Disadvantages & Limits

• Slim kiln structure possible • Scaffolding and formwork • Can be prefabricated, hence • Metal corrosion is likely the
since no buttresses are increase the construction costs reduces construction time main problem, hence high
required • Additional cost for • Slimmest structure possible expenses for maintenance work
• Overall construction time reinforcement steel and • Mass pre-fabrication potential • Separate platform for brick
reduction possible concrete storage required
• Relatively unfavourable • Requires a mechanical lifting
construction carbon foot print device to construct it
due to concrete and steel • High-value insulation required,
requirements hence expensive
• Relatively unfavourable
construction carbon foot print
due to steel requirements

VSBK Design Option GUIDELINES \ 27


13 Outer kiln wall structure

FUTURE OPTION 1 : Load bearing brick masonry without


buttresses

Advantages Disadvantages & Limits


• Potential of slim kiln structure. • Separate platform structure
• No bulky insulation boxes required for movement and
required storage
• High-value insulation material
required, hence is considered
expensive

28 / VSBK Design Option GUIDELINES


14 Working platform

Function
OPTION 1 : Partial R.C.C. working platform on buttress
The working platform is constructed for free
movement of personnel and for storage space.
Advantages Disadvantages & Limits
Design principles • Requires less reinforcement • Increased dust exposure
The working platform design is based on both steel due to support by potential
load bearing (buttress) structure or frame masonry buttresses • Time consuming because of
structure options. • Box insulation filling material shuttering work, concrete
can be topped up curing time and de-shuttering
However, the working platform must be open, work
ventilated and provide enough space so that
working personnel can move along and load
green bricks into the shaft without hindrance by
any structure or equipment.

Note : In case of a slim VSBK structure, e.g. metal,


a separate platform structure is required.

VSBK Design Option GUIDELINES \ 29


14 Working platform

OPTION 2 : Partial R.C.C. working platform on cantilever OPTION 3 : Full R.C.C. working platform

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Box insulation filling material • Increased reinforcement steel • Adds considerable rigidity to • High construction cost
can be topped up and concrete requirement, the kiln structure • Due to the settling of the box
hence an expensive option • Mechanical green brick insulation filling material a
• Time consuming because transportation possible gap is created in between the
of shuttering requirement, • Low dust working environment insulation fill and the platform
concrete curing time and achievable • Adds weight to the foundation
de-shuttering work • Decreased heat loss at
• Increased dust exposure platform level
potential

30 / VSBK Design Option GUIDELINES


15 Flue-ducts

Function
OPTION 1 : Lower and upper flue-duct system
The flue-ducts are the lower section of the shaft
emission exhaust system which systematically constructed with refractory/fired bricks
channels the flue gases into the chimneys.
Advantages Disadvantages & Limits
Design principles • Simple cleaning system • The flue duct system is the
The flue ducts must be designed to function in a possible weakest part of the shaft,
way that all flue gasses are passing through the • Best suited for natural draught hence periodical maintenance
exhaust gas system (natural and forced draught system is required
system) without posing health hazards to working • Cost savings potential if • Time consuming brick cutting
personnel. Further it must be ensured that the constructed with fired bricks work during construction
least amount of excess air can enter the system at
the top of the upper flue ducts during unloading.

The flue duct system should be constructed with


acid-resistant materials since acidic gases are
released during the firing process.

VSBK Design Option GUIDELINES \ 31


15 Flue-ducts

FUTURE OPTION 1 : Lower and upper flue-duct system


constructed with refractory castables

Advantages Disadvantages & Limits


• Reduced construction time • Limited to countries with fire
• Best suited for forced draught resistant concrete casting
system experience
• Calibration of individual flue
openings possible
• Economic viability increases
with numbers

32 / VSBK Design Option GUIDELINES


16 Shaft top structure

Function
OPTION 1 : R.C.C. shaft top anchored on the shaft
The shaft top protects the flue duct system from
mechanical and live load impacts. Further it supporting wall
provides a base for the lid cover and usually also for
Advantages Disadvantages & Limits
natural draught chimneys.
• Allows vertical expansion • None
Design principles movement of the refractory
shaft
The shaft top structure should not disturb a vertical
• Reduced shaft bulging
expansion of the refractory shaft.
probability
It should be designed in such a way that additional
features like flue duct guides, lid-cover base and
chimneys can be securely fixed.

The expansion gap must be sealed with flexible


material to avoid heat loss after the kiln is fully
dried out.

VSBK Design Option GUIDELINES \ 33


17 Emission exhaust system

Function
OPTION 1 : Natural draught with flue ducts
The Emission exhaust system is to provide the draft
for proper fire positioning as well as to discharge
exhaust gases at a safe height. Advantages Disadvantages & Limits
• No electricity required, hence • Draught can vary with weather
Design principles an economical option conditions
The emission exhaust system must be designed by • Can be constructed with • Difficult to erect and tie up the
respective experts. material other than metal, i.e. chimneys, especially in high
fired bricks wind prone areas
• High wear and tear of metal
parts due to corrosion from
acidic emissions

34 / VSBK Design Option GUIDELINES


17 Emission exhaust system

OPTION 2 : Forced draught with flue ducts FUTURE OPTION 1 : Natural draught without flue ducts
Note : This system is preferred for multiple shafts.
Advantages Disadvantages & Limits Advantages Disadvantages & Limits
• Uniform draught, hence better • Requires electricity, including a
• Elongated firing curve • Anti corrosive material
fire position control back-up system • Uniform draught required for the hood
• One chimney can be used for • Exhaust gas temperatures
• User friendly draught control • Potential of increased hood
multiple shafts must be maintained to avoid • One Shaft - one chimney system maintenance
• Brick quality is likely to be corrosion of metal parts • During loading, emissions can
more uniform • Increased maintenance costs
be extracted separately
• Inbuilt shaft lid, hence reduced
health hazard

VSBK Design Option GUIDELINES \ 35


18 Flue gas dampers/valves

Function
OPTION 1 : M.S. sheet flat dampers
Flue gas dampers/valves regulate the air flow
within the system, therefore steering the
appropriate fire schedule and ensuring a clean Advantages Disadvantages & Limits
working environment while loading the bricks.
• Are an economical option • Probability of excess air
• User friendly to operate and entering
Design principles repair • High corrosion potential
The upper and lower flue duct system requires
two independent valves/dampers each, hence
4 valves/dampers are required per shaft.

Valves and dampers should be designed so that


least amount of flue-gasses can pass when they
are completely shut.

Damper slots must be constructed so that no


excess air can enter into the emission exhaust
system.

36 / VSBK Design Option GUIDELINES


18 Flue gas dampers/valves

OPTION 2 : M.S. sheet butterfly dampers OPTION 3 : Valves for forced draught system

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Are an economical option • High corrosion potential • Easier to control the airflow • Expensive air flow
• User friendly to operate • Replacement only possible • Air flow meter gauge can be management system
• Reduced probability of excess during shaft closure, hence installed • High corrosion potential
air expensive if green bricks with >1%
moisture content are loaded
• Potential excess air problems
if gap between refractory shaft
(flue duct channel opening)
and valve mouth is not sealed

VSBK Design Option GUIDELINES \ 37


19 Shaft lid

Function
OPTION 1 : M.S. sheet lid/elements
The shaft lid supports the efficiency of the counter
current air flow principle (energy efficiency) and
ensures a clean working and general environment Advantages Disadvantages & Limits
on a VSBK.
• Is an economical option • High corrosion potential

Design principles
Shaft lid should be designed user-friendly as well as
light weight, fire and preferably corrosion resistant
materials.

38 / VSBK Design Option GUIDELINES


19 Shaft lid

OPTION 2 : Stainless steel sheet

Advantages Disadvantages & Limits


• Lower corrosion potential • Expensive option

VSBK Design Option GUIDELINES \ 39


20 Unloading bars

Function
OPTION 1 : M.S. square bars
The unloading bars support the brick setting inside
the shaft during regular operation and transfer the
brick setting load to the brick support I-beams. Advantages Disadvantages & Limits
• Lighter than M.S. I-bars • High chance of brick breakages
Design principles due to reduced flange width
An unloading bar should be designed light weight,
small in cross section and must be able to resist
high heat stresses under constant load of approx.
4 tons.

Note : Unloading bars are to be considered


operation wear-and-tear material.

40 / VSBK Design Option GUIDELINES


20 Unloading bars

OPTION 2 : M.S. I-bars OPTION 3 : Reinforced M.S. square bars

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Stronger than M.S. square bars • Heavier than M.S. square bars • Can be used for larger shaft • High chance of brick breakages
• Less chance of brick breakages and therefore rarely used for dimension due to reduced flange width
due to bigger flange width larger shaft dimension

VSBK Design Option GUIDELINES \ 41


21 Unloading trolley

Function
OPTION 1 : M.S. trolleys
The unloading trolley is used to unload the fired
bricks and to transport them to the unloading
stations. Advantages Disadvantages & Limits
• Locally available and • Trolley weight increases with
Design principles economical fabrication larger shaft size
The unloading trolley should be designed in such a • Light weight trolleys can
way that it can bear the brick setting load without be designed when using
warping or bending. a hydraulic unloading
mechanism
It must be as light as possible but strong enough to
handle emergency situations .

42 / VSBK Design Option GUIDELINES


22 Brick unloading system

Function
OPTION 1 : Screw jack mechanism
The brick unloading system raises and lowers the
trolley and the brick settings inside the shaft. Note : Screw must be fabricated with high carbon steel.

Advantages Disadvantages & Limits


Design principles
• No electricity required • Complex and time consuming
The unloading mechanism must be capable of
• An electro motor can be (retro) fabrication process
bearing the entire brick setting load inside the shaft
fitted to mechanically operate • Maintenance of nut is high as
and to lift it to the point where the support bars
the screw jack mechanism it is made of cast-iron
can be retracted during the unloading of the bricks
• Accident prone system and
without the threat of sudden failure.
hard work for personnel
Both screw jack and hydraulic unloading system are
in general designed to carry and lift up to 30 tons of
weight (bricks and trolley).

VSBK Design Option GUIDELINES \ 43


22 Brick unloading system

OPTION 2 : Hydraulic mechanism

Advantages Disadvantages & Limits


• Easy to handle, working • Requires electricity, including a
personnel are not exposed to back-up system
hard work and falling coal • Expensive lubricants required
• No girder system required, • Requires special dust
hence construction time and protection
cost saving
• Fewer workers required
• Manual power pack can be
applied in case of power
failure
• Trolley track can be narrowed
and therefore trolley
movement is easier

44 / VSBK Design Option GUIDELINES


23 Access to the working platform

Function
OPTION 1 : Ramp/staircase
Is the means to transport green bricks and coal up
to the working platform level for an uninterrupted
firing process. Advantages Disadvantages & Limits
• Possibly the most economical • Drudgery work for employed
Design principles construction option personnel
The main design parameter is to transport dry • Requires no electricity • High green brick handling
green bricks from the ground level to the working • Depending on gradient angle, damage potential
platform level in the most economical way, ensuring mechanical equipment can be
that the green brick quality is not compromised. used to carry bricks

VSBK Design Option GUIDELINES \ 45


23 Access to the working platform

OPTION 2 : Conveyor belt OPTION 3 : Lift

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Reduces drudgery • High dry green brick handling • Reduced drudgery • Requires power (electricity or
• Less workforce required damage potential • Less workforce required fuel generator) to operate
when compared to manual • High wear and tear, hence high when compared to manual
transportation system maintenance and repair cost transportation system
• Very efficient and swift potential • Low green brick damage
transportation system • Requires power (electricity or potential
fuel generator) to operate
• Potential of falling green bricks
increases the risk of injury

46 / VSBK Design Option GUIDELINES


23 Access to the working platform

OPTION 4 : Gantry

Advantages Disadvantages & Limits


• Reduced drudgery • High initial investment
• Less workforce required • Only economical for large
compared to any other system numbers of shafts
• Low green brick damage • Requires power (electricity or
potential fuel generator) to operate
• Mechanized loading of green • Requires considerable platform
bricks into gantry cage possible space

VSBK Design Option GUIDELINES \ 47


24 Roof

Function
OPTION 1 : High-end level
The roof protects the kiln structure and working
personnel from the elements such as rain, sun (Corrugated/plain plastic roofing sheets or P.V.C. corrugated/plain
and wind. sheets on sloped M.S. pipe trusses and purlins)
(Sloped concrete or ferro-cement roof)
Design principles
Advantages Disadvantages & Limits
Roof should be designed as economically as
• Is resistant to damaging • Is an expensive roof
possible while at the same time ensuring that
emissions
the kiln remains dry, green bricks and working
personnel are protected.

A roof monitor is essential to ensure proper


ventilation that reduces the accumulation of
harmful emissions. The height of the roof should
be enough for the fire master to work efficiently
above the shaft top for loading bricks.

48 / VSBK Design Option GUIDELINES


24 Roof

OPTION 2 : Normal range level OPTION 3 : Budget level


(Colour coated roof sheets/corrugated/plain, galvanized iron sheets (Biodegradable materials: Bamboo mats or clay roofing tiles on timber
on sloped M.S. pipe trusses and purlins) or bamboo trusses and purlins)

Advantages Disadvantages & Limits Advantages Disadvantages & Limits


• Is an economical solution • Requires frequent • Is a low cost and functional • Requires regular replacement/
maintenance due to corrosion roofing option repair due to relative short
problems lifespan of material
• Potential of rain leaking exists

VSBK Design Option GUIDELINES \ 49


Note

También podría gustarte