Documentos de Académico
Documentos de Profesional
Documentos de Cultura
ISBN 978-3-908156-49-9
Copyrights © Skat, 2013
This document is not intended to be a construction guide and entrepreneurs who consider constructing a VSBK
are strongly advised to contact an experienced local or regional VSBK expert/consultant.
Contents
Acknowledgements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . v
Background . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vi
Purpose of this documentation . . . . . . . . . . . . . . . . . . . . . . . vi
Potentials and limits of this documentation . . . . . . . . . . . . . . . . .vii
Feedback and up-grading of this documentation . . . . . . . . . . . . . .vii
Overview of VSBK. . . . . . . . . . . . . . . . . . . . . . . . . . . . . viii
01. Foundation. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
07. Arch/slab. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
08. Shaft. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
15. Flue-ducts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31
24. Roof . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48
The Vertical Shaft Brick Kiln (VSBK) Skat likes to express sincere thanks to Last but not least Skat, as the partner in
development process documentation started the piloting entrepreneurs from various charge for the technology transfer to South
during its applied Research & Development countries who made the VSBK technology Africa would also like to acknowledge the
stage in 1997 and reached a first important learning and development possible. Only VSBK Project in South Africa which financed
milestone in the legendary “Brick by Brick through the spirit of VSBK pioneers, who the development and publication of this
- The Herculean Task of Cleaning up the were and are prepared to practically test document as well as our consortia partner,
Asian Brick Industry" in 2008. Yet the actual new approaches and at the same time take Swisscontact, who facilitated the project
construction development process has some risks, the VSBK technology could be implementation.
been continued since. In particular the exposed and tested in the practical business
“South – South” VSBK technology transfer environment.
to South Africa lifted the VSBK technology Karl Wehrle
significantly. Additional construction options Skat is also very grateful to all partner Skat Consultancy
have been realized that promote the VSBK organizations and individual professionals
technology as a globally recognized clean from various countries, who each in their
brick production system. However, the result own way contributed towards important
of this process has until now never been “puzzles” in order to up-grade and perfect
systematically documented and updated. the VSBK technology. They made a South-
South technology transfer possible.
Skat would like to express its sincere
appreciation to Swiss Development Special thanks to all those who contributed
Cooperation (SDC) for its continued support to the development and compilation of
to the development of the VSBK technology this documentation, in particular to the
and its adaption to specific local contexts. European experts in energy & environment,
Without this persistent commitment and kiln construction and ceramics, Mr. Max
trust into the involved partners over a period Müller, Germany, Mr. Hans Schmid,
of more than a decade the development Switzerland, Mr. Ekhard Rimpel, Germany,
of the VSBK technology as a technical and and Mr. Alois Müller, Switzerland, as well as
economical viable environment friendly to Mr. Urs Hagnauer, former VSBK Project
alternative to traditional brick production Manager, Nepal.
systems would not have been possible.
This publication is part of the ongoing VSBK technology and thereby building However, latest adaptations to local contexts
efforts of the VSBK technology transfer local VSBK experts while at the same time by local experts in South Africa could not
process from Asia to South Africa. It is part creating and overseeing an international be included in this document since they
of the tasks entrusted to Skat in an overall network of experts and specialists to are being claimed as intellectual property.
process of knowledge transfer. The focus of sustain the VSBK technology as well as its Depending on interest they may be made
this publication are both the main design constant improvements, documentation available through a consultancy contract.
options as well as construction elements and international dissemination, therefore
of the Vertical Shaft Brick Kiln. The VSBK making best use of the investments made by Purpose of this documentation
is the most energy efficient coal fired clay SDC and all other partners.
brick production technology. Ever since SDC Through the SDC supported “South – South"
supported the systematic VSBK technology The VSBK technology is not patented. Since VSBK technology transfer to South Africa
transfer from China to India in 1996 a lot its commercial, environmental and social new thinking, new views, new experts and
of local and international VSBK working development was financed by SDC this thereby new potentials were leading to
experience has been accumulated. In its technology is considered an “open source” additional construction options. Awareness
quest to contribute to cleaner clay brick technology. The results of 17 years of of the unique energy and environmental
firing systems, and thereby to a cleaner VSBK design/construction experience and advantages of the VSBK technology is rapidly
environment, SDC also supported the VSBK knowledge from all stages of the various being disseminated at a global level. With
technology transfer to Nepal, Vietnam, VSBK technology transfers have been this document, experts not only in South
Afghanistan, Pakistan and since 2009 to collected and compiled as “VSBK Design Africa but also at global level are enabled
South Africa. Option Guidelines”. to make an educated decision of how to
adapt the VSBK technology and therefore
In the VSBK technology transfer to the This documentation is the result of contribute towards an increased global VSBK
above mentioned countries, except to professional involvement of experienced demand while at the same time reducing the
Vietnam, Skat Consultancy is the only European brick kiln experts with global VSBK greenhouse gas emission from a polluting
international organisation that has been a technology experts and local practitioners/ industrial sector.
constant partner to SDC’s environmental entrepreneurs. Hence this documentation
endeavour since 1996. This professional considers both; the current state-of-art brick The purpose of this documentation is to
trust was continually acknowledged kiln know-how at European level as well provide a general overview of different
by Skat Consultancy with its principle as globally applied practical and technical VSBK construction options and makes it
working strategy; to locally anchor the options. clear that there is no 'One-size-fits-all'. For
17
01 Foundation
02 Unloading mechanism support unit
03 Trolley guide
24 04 Brick corbelling
05 Brick support I-beams
06 Girder system
19 16 07 Arch/slab
15 08 Shaft
18
14 09 Cavity between shaft and shaft support structure
20 06 19 Shaft lid
20 Unloading bars
05
03 04
21 21 Unloading trolley
22 22 Brick unloading system
Function
OPTION 1 : R.C.C. raft foundation
The foundation is the part of the VSBK that is in
direct contact with the ground and through which (Suitable for non-cohesive soils)
structural loads, including the weight of green
bricks, coal storage and movements are being Advantages Disadvantages & Limits
transferred. • Equal load distribution on any • Expensive construction
type of natural grown soil option due to the use of mass
• Employed working personnel concrete and reinforcement
Design principles can work on a clean and safe steel
A universal foundation design for all types of ground platform
is technically and economically not feasible since • Ground water penetration can
key parameters vary according to the local situation be minimized
and context. Therefore, the foundation has to be
professionally designed, case by case and according
to local contexts.
Function
OPTION 1 : M.S. I-beams
The unloading mechanism support unit
accommodates the height of the hydraulic piston Note : M.S. I-beams are installed perpendicular to the arch walls in
or screw, protects the unloading mechanism from order to transfer the load of the bricks setting inside the shaft to the
potentially being blocked during operation and kiln foundation.
bears the load of the entire brick setting inside the
shaft during unloading procedures. Advantages Disadvantages & Limits
• Economical option due to the • Foreign material could fall
Design principles utilisation of the arch wall into the pit structure which
foundations could create complications for
The unloading mechanism support unit must bear
• Can accommodate both unloading procedures and are
the entire brick setting load and its unloading
hydraulic and manual likely difficult to clean
system in such a way that no structural settings/
unloading mechanisms • In areas of high water table,
damages will hinder the unloading operation.
a watertight pit structure
should be ensured in order to
The related pit should be protected from the nearby
avoid water contact with the
filled soil and ground water so that the unloading
unloading mechanism
mechanism can move freely.
Function
OPTION 1 : Recessed MS C-channels
The trolley guide assists in correctly positioning
the trolley for unloading procedures and, when the
unloading trolley is correctly positioned, acts as a Advantages Disadvantages & Limits
safety feature to prevent unevenly loaded trolleys
• Low wear & tear of the • Wall corbellings are required
from toppling.
masonry walls during near ground level, hence the
unloading wall construction becomes
Design principles • Correct positioning of trolleys more labour intensive and
The trolley guides are made with MS C-Channels below the shaft is ensured therefore costly
and are properly anchored into the arch walls. • Trolleys and the unloaded fired
bricks are prevented from
becoming wedged between
the shaft supporting walls
during unloading procedures
Function
OPTION 1 : Two arch wall corbellings
The brick corbellings increase the arch wall distance
for unhindered unloading of the fired bricks and (1st and 2nd , on each side of the arch supporting walls)
movement of the trolley
Advantages Disadvantages & Limits
Design principles • Reduced risk of fired bricks • Arch side wall brick corbelling
tumbling from the unloading construction becomes time
The brick corbelling of a given brick course should
trolley consuming and therefore
ideally not exceed 3cm.
• Less wear & tear due to M.S. costly
C-Channel trolley guides • Could hinder pulling out the
Wall corbellings can be made, but as a matter of
constructed flush with the arch trolley due to the small gap
fact, are optional depending on the quality of green
wall support masonry of 3 cm between the wall and
bricks, firing and operation practices.
the trolley during emergency
unloading
Since the arch masonry walls distance and the shaft
size have different measurements the refractory
shaft corbelling is advisable to avoid damages
during operation.
Function
OPTION 1 : Brick support beam positioned for unloading
The brick support I-beam is the resting place
for unloading bars and the girder system during 6 layers of bricks
operation. Between unloading procedures the beam
Advantages Disadvantages & Limits
supports the entire brick setting load inside the
shaft and transfers it to the arch supporting wall. • Higher unloading capacity, also • The dimensions of the
during emergency situations unloading screw/hydraulic
Design principles • Reduced workload for piston increases due to the
personnel during regular increased lift height
The brick support I-beams must be designed to
operation since less unloading
carry the entire brick setting within the shaft.
procedures are performed for
the same number of bricks
The temperature at the unloading place can at
being unloaded
times be as high as 400°C, which needs to be
• Friendly working environment
considered when estimating the I-beam dimensions.
due to less heat exposure
The I-beams should be completely straight,
• Increased cooling down rate
never even slightly twisted or bent and must be
possibility
positioned parallel to each other.
Function
OPTION 1 : Girder system with side locks
After the trolley is securely positioned beneath the
fired bricks, the Girder system facilitates the release
of the unloading bars and hence the load of the Advantages Disadvantages & Limits
entire brick setting is transferred to the trolley and
• No electricity required • Girder rail prone to bending
the unloading system.
• Less uplift movement of due to heat radiation and
screw/hydraulic piston and constant load
Design principles therefore easier for working • Increases construction time
The girder system needs to be designed in a way personnel due to fixing of all the related
that it is able to carry the entire brick load. Further, metal parts
it has be ensured that the release mechanism
cannot be triggered accidently (or unintentionally)
and the brick load can be transferred onto the
trolley without potentially injuring working
personnel when releasing the system.
Function
OPTION 1 : Arch constructed with brick
The arch/slab structure ensures safe access to
unload the fired bricks. It also distributes the
loads of above build structural and non-structural Advantages Disadvantages & Limits
loads into its supporting walls. Further, air
• Locally available bricks can • Requires an arch mould
entering through this access opening is aiding
be used, therefore reduced • Arch construction will increase
both the combustion and the brick cooling
construction costs the overall kiln construction
process.
time
Design principles
Different Arch types can be designed.
OPTION 2 : In situ R.C.C. beam and slab FUTURE OPTION 1 : Precast R.C.C. beams with 1 layer of
front bricks attached as insulation and protection
Advantages Disadvantages & Limits Advantages Disadvantages & Limits
• Saves on overall number • Requires shuttering material • Reduces overall kiln • Requires a mechanical lifting
of fired bricks for the kiln • Will increase the overall kiln construction time in case device to place it
construction construction time the pre-fabrication is done in • For achieving economical
• No arch construction skill • Will likely get some damage factories advantages a large number of
required in case of high temperature shafts need to be constructed
exposure (e.g. brick melting
inside the shaft)
Function
OPTION 1 : English bond refractory masonry without
The shaft is the core element of the kiln and has
to accommodate the firing of the bricks as per expansion joints
the appropriate fire schedule as well as to provide
Advantages Disadvantages & Limits
resistance to mechanical wear and tear from
vertical movement of the loaded bricks. • Uniform expansion and • Special masonry skills required
contraction properties • Expansion will develop
Design principles • Uniform thermal mass uncontrolled masonry cracks
properties
The shaft dimension must be designed according to
the dry green brick size and maximum production
capacity.
OPTION 2 : English bond refractory masonry; substituted FUTURE OPTION 1 : English bond refractory brick
with fired bricks in sections with temperatures below masonry with expansion joints
500°C (pre-heating and cooling zone)
Advantages Disadvantages & Limits
Advantages Disadvantages & Limits • Uniform expansion and • Special masonry skills are
• Most economical option under • Chances of shaft damages if contraction properties required and the construction
the condition that the firing the fire position is not properly • Uniform thermal mass system is time consuming,
zone is always maintained at maintained at the centre of properties therefore costly
the centre of the shaft the shaft • Controlled expansion will avoid • Requires special brick blocks or
• Fire position adjustment is uncontrolled masonry cracks, cuttings
limited to refractory masonry hence lower maintenance • Special corner support
area essential to ensure expansion
• Potential damages to fired at defined joints
brick masonry in the pre-
heating zone due to acidic
emissions
< 500oC
> 500oC
< 500oC
Function
OPTION 1 : Unfilled cavity (2-3 cm approx.)
The cavity is required to ensure structurally
independent expansion and contraction of the shaft
structure. Advantages Disadvantages & Limits
• Basically no expenses • Some heat loss due to air
Design principles (However to ensure an equal movement, hence reduced
The main principle for designing this cavitiy is to cavity size it is of advantage insulation value
ensure the structural integrity of the shaft. to place a low cost thermocol • Risk of mortar and other
board. This thermocol board material filling up the cavity if
The top and bottom of this cavity should be closed will melt as soon as the kiln not carefully protected during
with a flexible material after the kiln is fully dried is in operation and a uniform construction
out in order to avoid heat loss. cavity will remain) • Increased heat exposure at the
shaft top area
Function
OPTION 1 : English bond brick masonry in mud mortar
The shaft-support wall ensures the independent
working (expansion/contraction) of the shaft,
reduces lateral pressure and acts as an insulation Advantages Disadvantages & Limits
layer. The chimneys are usually constructed on top
• Low construction cost • Chances of wall sagging due to
of the shaft supporting wall.
• Provides reasonable stability mud mortar shrinkage
for chimney system
Design principles
There are many shaft support wall construction
systems possible, all depending on economical
insulating building materials.
Function
OPTION 1 : Filled with ungraded soil
Kiln insulation boxes are constructed to distribute
the load of insulation material used to minimize
energy losses. They also provide rigidity to the Advantages Disadvantages & Limits
kiln structure and define the size of the working
• Cheapest and easily available • Low insulation value, the heat
platform.
filling material loss is relatively high
• Difficult to avoid water
Design principles penetration during
The box dimensions must be related to the construction
insulation material value to be used and the • Chances of shaft bulging
required working space and type of platform. increases with the frequency
The top of the insulation boxes (platform) should of shutdowns due to repeated
ideally be covered to avoid heat loss. compacting of fine particles
Function
OPTION 1 : M.S. pipes
Peep-hole pipes are narrow openings in the kiln
structure which allow a visual and/or mechanical
fire temperature monitoring. Advantages Disadvantages & Limits
• A straight-forward, practical • Potential of excess air entering
Design principles and economical system for the shaft if the pipes are
Peep-holes must be designed to allow visual fire position/temperature not properly sealed during
monitoring of the fire position and/or insert fire monitoring operation
monitoring equipment (thermocouples) from the
outside of the kiln structure.
Function
OPTION 1 : Load bearing brick masonry with buttresses
The outer kiln wall structure encases the insulation
filling around the shaft supporting walls and
ensures structural rigidity and protection against Advantages Disadvantages & Limits
the elements.
• Can support above built • Buttresses increase the
structures (loading platform, required construction area
Design principles roof, mechanical transporting
The outer kiln wall structure must be designed devices etc.) and green brick
so that it can protect the insulation and the shaft storage
structure against mechanical impact. • Buttresses supporting the
access to platform can reduce
Note : Sufficient weep holes must be provided construction costs
to avoid kiln structure damages due to water
evaporation during the initial firing. These weep
hole should be closed only after the kiln is
completely dried out.
• Slim kiln structure possible • Scaffolding and formwork • Can be prefabricated, hence • Metal corrosion is likely the
since no buttresses are increase the construction costs reduces construction time main problem, hence high
required • Additional cost for • Slimmest structure possible expenses for maintenance work
• Overall construction time reinforcement steel and • Mass pre-fabrication potential • Separate platform for brick
reduction possible concrete storage required
• Relatively unfavourable • Requires a mechanical lifting
construction carbon foot print device to construct it
due to concrete and steel • High-value insulation required,
requirements hence expensive
• Relatively unfavourable
construction carbon foot print
due to steel requirements
Function
OPTION 1 : Partial R.C.C. working platform on buttress
The working platform is constructed for free
movement of personnel and for storage space.
Advantages Disadvantages & Limits
Design principles • Requires less reinforcement • Increased dust exposure
The working platform design is based on both steel due to support by potential
load bearing (buttress) structure or frame masonry buttresses • Time consuming because of
structure options. • Box insulation filling material shuttering work, concrete
can be topped up curing time and de-shuttering
However, the working platform must be open, work
ventilated and provide enough space so that
working personnel can move along and load
green bricks into the shaft without hindrance by
any structure or equipment.
OPTION 2 : Partial R.C.C. working platform on cantilever OPTION 3 : Full R.C.C. working platform
Function
OPTION 1 : Lower and upper flue-duct system
The flue-ducts are the lower section of the shaft
emission exhaust system which systematically constructed with refractory/fired bricks
channels the flue gases into the chimneys.
Advantages Disadvantages & Limits
Design principles • Simple cleaning system • The flue duct system is the
The flue ducts must be designed to function in a possible weakest part of the shaft,
way that all flue gasses are passing through the • Best suited for natural draught hence periodical maintenance
exhaust gas system (natural and forced draught system is required
system) without posing health hazards to working • Cost savings potential if • Time consuming brick cutting
personnel. Further it must be ensured that the constructed with fired bricks work during construction
least amount of excess air can enter the system at
the top of the upper flue ducts during unloading.
Function
OPTION 1 : R.C.C. shaft top anchored on the shaft
The shaft top protects the flue duct system from
mechanical and live load impacts. Further it supporting wall
provides a base for the lid cover and usually also for
Advantages Disadvantages & Limits
natural draught chimneys.
• Allows vertical expansion • None
Design principles movement of the refractory
shaft
The shaft top structure should not disturb a vertical
• Reduced shaft bulging
expansion of the refractory shaft.
probability
It should be designed in such a way that additional
features like flue duct guides, lid-cover base and
chimneys can be securely fixed.
Function
OPTION 1 : Natural draught with flue ducts
The Emission exhaust system is to provide the draft
for proper fire positioning as well as to discharge
exhaust gases at a safe height. Advantages Disadvantages & Limits
• No electricity required, hence • Draught can vary with weather
Design principles an economical option conditions
The emission exhaust system must be designed by • Can be constructed with • Difficult to erect and tie up the
respective experts. material other than metal, i.e. chimneys, especially in high
fired bricks wind prone areas
• High wear and tear of metal
parts due to corrosion from
acidic emissions
OPTION 2 : Forced draught with flue ducts FUTURE OPTION 1 : Natural draught without flue ducts
Note : This system is preferred for multiple shafts.
Advantages Disadvantages & Limits Advantages Disadvantages & Limits
• Uniform draught, hence better • Requires electricity, including a
• Elongated firing curve • Anti corrosive material
fire position control back-up system • Uniform draught required for the hood
• One chimney can be used for • Exhaust gas temperatures
• User friendly draught control • Potential of increased hood
multiple shafts must be maintained to avoid • One Shaft - one chimney system maintenance
• Brick quality is likely to be corrosion of metal parts • During loading, emissions can
more uniform • Increased maintenance costs
be extracted separately
• Inbuilt shaft lid, hence reduced
health hazard
Function
OPTION 1 : M.S. sheet flat dampers
Flue gas dampers/valves regulate the air flow
within the system, therefore steering the
appropriate fire schedule and ensuring a clean Advantages Disadvantages & Limits
working environment while loading the bricks.
• Are an economical option • Probability of excess air
• User friendly to operate and entering
Design principles repair • High corrosion potential
The upper and lower flue duct system requires
two independent valves/dampers each, hence
4 valves/dampers are required per shaft.
OPTION 2 : M.S. sheet butterfly dampers OPTION 3 : Valves for forced draught system
Function
OPTION 1 : M.S. sheet lid/elements
The shaft lid supports the efficiency of the counter
current air flow principle (energy efficiency) and
ensures a clean working and general environment Advantages Disadvantages & Limits
on a VSBK.
• Is an economical option • High corrosion potential
Design principles
Shaft lid should be designed user-friendly as well as
light weight, fire and preferably corrosion resistant
materials.
Function
OPTION 1 : M.S. square bars
The unloading bars support the brick setting inside
the shaft during regular operation and transfer the
brick setting load to the brick support I-beams. Advantages Disadvantages & Limits
• Lighter than M.S. I-bars • High chance of brick breakages
Design principles due to reduced flange width
An unloading bar should be designed light weight,
small in cross section and must be able to resist
high heat stresses under constant load of approx.
4 tons.
Function
OPTION 1 : M.S. trolleys
The unloading trolley is used to unload the fired
bricks and to transport them to the unloading
stations. Advantages Disadvantages & Limits
• Locally available and • Trolley weight increases with
Design principles economical fabrication larger shaft size
The unloading trolley should be designed in such a • Light weight trolleys can
way that it can bear the brick setting load without be designed when using
warping or bending. a hydraulic unloading
mechanism
It must be as light as possible but strong enough to
handle emergency situations .
Function
OPTION 1 : Screw jack mechanism
The brick unloading system raises and lowers the
trolley and the brick settings inside the shaft. Note : Screw must be fabricated with high carbon steel.
Function
OPTION 1 : Ramp/staircase
Is the means to transport green bricks and coal up
to the working platform level for an uninterrupted
firing process. Advantages Disadvantages & Limits
• Possibly the most economical • Drudgery work for employed
Design principles construction option personnel
The main design parameter is to transport dry • Requires no electricity • High green brick handling
green bricks from the ground level to the working • Depending on gradient angle, damage potential
platform level in the most economical way, ensuring mechanical equipment can be
that the green brick quality is not compromised. used to carry bricks
OPTION 4 : Gantry
Function
OPTION 1 : High-end level
The roof protects the kiln structure and working
personnel from the elements such as rain, sun (Corrugated/plain plastic roofing sheets or P.V.C. corrugated/plain
and wind. sheets on sloped M.S. pipe trusses and purlins)
(Sloped concrete or ferro-cement roof)
Design principles
Advantages Disadvantages & Limits
Roof should be designed as economically as
• Is resistant to damaging • Is an expensive roof
possible while at the same time ensuring that
emissions
the kiln remains dry, green bricks and working
personnel are protected.