Está en la página 1de 4

G o o d P r a c t i c e

The long-term performance of a CHP


installation using an aero-derived gas
turbine
V Case Study Summary
The CHP scheme installed at the paper mill
operated by Smith, Stone R Knight Ltd
(SSK) has now been functioning for over
seven years. During the first four years,
prior to a major expansion of the mill's pro-
duction capacity, the installation provided
almost all of the mill's requirements for
electricity and steam, reducing energy

I
costs by more than 30%.

The project involved the installation of a


3.63 MWe gas-turbine driven generating
set and a water-tube heat-recovery boiler.
A supplementary gas burner arrangement
in the boiler inlet gas duct provides the
additional heat necessary to increase steam
prOdUCtion to a m&mum d 22.7 tonneshour.
System availability has been high (greater
than 98%), and overall thermal efficiency
has averaged 74.0% (gross calorific value).
The overall heat:powerratio is 3.28:l.
Host Organisation
Smith, Stone R Knight Ltd
Trevor Street
Nechells
Birmingham
87 5RE
Monitorlng Organisation
Thermal Developments Ltd
The W i n s
North End
Sedgefield
Stockton-on-Tees
Case Study Objectives Investment Cost Cleveland
TS21 2 M
To evaluate the long-term performance and €1.628 million (1984/5 prices). Tel No: 0740 621 614
reliability of a combined heat and power €2.850 million (1993 prices). Dr R Nicholson
(CHP) scheme and to reassess the eco-
nomics of the project, taking account of Savings Achieved Equlpment Manufacturers
current energy prices and installation costs. Cost saving: €819,0OO/year (1993 energy GasTurbine: Waste Heat Boiler:
prices). Centrax Lid GEA lberica
Potentlai Users Gas Turbine Division (agentsfw Del!& C w p d i o n )
Continuous process industries including Primary energy saving: 155 TJ/year. Shaldon Road d o GEb Spiro-Gills
Newton Abbot London Road
paper and board, chemicals, food & drink, Payback Period Devon Pulborough
oil refining, petrochemicals and pharmaceu- TQ12 4SQ west sussex
ticals. Actual payback approximately 3 years.
Tel No: 0626 52251 RH20 1AR
Payback at 1993 prices: 3.5 years. Mr R A Staliard Tel NO:0798 872401
Mr M J Peyser

cc... net cost sauings currently worth


more than E800,000/"xar 99
Project Ratlonale
SSK's Birmingham mill operates continu-
ousiy for 8,400 hours/year, converting
waste paper into packaging materials. in
1984, prior to the instailation of the CHP
scheme, there was no an-site electricity
generation, and steam was provided by
four ageing, oil-fired, sheii boilers. The ener-
Shell bill)^
gy requirements for a miii outpUi of 48,000
tonnedyear were 13 tonneslhour of steam,
and an electricity demand averaging
2.6 MWe.

Following the introductionof the Energy Act


(1983), which permitted private generators
to export electricity, SSK perceived that on-
site electricity generation could be an econ-
omic proposition. A feasibility study exam-
ined various CHP options before recom-
mending the instailation of a gas turbine
with a supplementary fired heat-recovery
boiler. This system cioseiy matched the
miii's heat and power requirements. I
08s turbine CUP system
Because of its innovative features and ener-
gy-saving potential, the project received
support from the Energy Efficiency office Tne 3-c1 ng oeiween ine i.ro ne a i o ine When the gas supply is interrupted (or the
(EEO) under the Energy Efficiency 00 er icorporares a cne,mai ca ,-cperar- generator is not available) the entire system
Demonstration Scheme, now replaced by ea aamper sbsrem: :ns a O A S me gas irr- is shut down. All power is then purchased
the Best Practice programme. The CHP c ne e x r a s 10 pass e rner 10 ine 00 er or from ME and the miii's steam requirements
system was independently monitored 10 a o,pass sac< o scnarg ng 10 ain3s- are provided by anernative boilers.
throughout its first year of operation and, in prere S,pcementaq gas o.rnefs n ine
January 1993, was reassessed to deter- 00 er ne: 0 x 1 p'o. oe :ne a301ona neai Operational Experience
mine its long-term reliability and cost-effec- necessaq 10 rase sieam proo,cton 10 a The CHP system was instailed and com-
tiveness. traxm~mol227ioniesno.r. missioned in 1985 with minimal disruption
to production. After only a few weeks of
The CHP System Steam frzm me 00 er gr s p peo 1c me operation, failure of the power take-off shaft
Tie pr n e no.er for me s,siem s an aer3- r o sir 0-101r a n fo o in ine ex si ng 00 - bearing on the gas turbine caused damage
ce' ,eo gas 1-rc r e 'are3 at 3 63 M\h e. Tne er n o s e to the power take-off shaft, gearbox and
1 ~ 0 n es L e eo 0, iai.ra gas SAP eo on generator drive-end bearing. Emergency
a1 nierr-pi 3 e i i r f' E ec:r ca cov.er j Tne CnP eecirca s,siem norma 1 oper- repairs ensured that the set was returned to
p r o i x e o at 1 1 6 J 31'0 fec 12 118 m s 3 s- a:es n cara e A ir :ne M o anos E ec!'c r) fuii load within 18 days, and no production
:o*:cn s)siem p c ME S-ppyano. hner eeclrca gener- losses were incurred.
aion exceeos tne rn 08'3 1 s s,a , econ-
Tne gas 1.rone e x n a s oscrarges 10 a omc 10 expon s-rp s poner 13 ine gro in 1986, after some 9,000 running hours,
:ho-or-m nai.ra-circ+alon (taie'-!40e. none.er f s-rp-s power oecomes aJa - the turbine required extensive refurbish-
heat-rec0.e') 00 er an0 econom se' aoie arr ng tne r gni nen ME p-rcnase ment and modification to overcome a blade
\\ iere I s capao e 0' general ng sieam a: varffs are ionesr. a COII~O oop ensdes ovemeating problem. This work was carried
i r e raie of 10 5 :onnes no-r. :nay gas :-ro ne ovip4r s moo.. aieo :o out with minimal disruption and largeiy at
reo-ce ine exnasi no.\ vale. the manufacturer's expense. An on-line
washing system has also been installed to
clean the compressor blades.

Since 1986 the gas turbine has suffered no


significant unscheduled downtime, and vir-
tuaiiy ail maintenance work has been com-
pleted during miii shutdowns. By the end of
1992 it had operated for almost 61,000
hours, averaging 8,000 running hourslyear,
with an availability of more than 98%. Gas
supply interruptions have been infrequent
and of short duration, so the lack of a sec-
ondary fuel supply has not been a handi-
cap. The gas compressor has proved to be
very reliable, with servicing carried out
annually by the manufacturer.

During the commissioning of a new paper


machine in October 1989, the existing con-
densate system became contaminated with

The paper l.l~l.l...~


- f/n/sh/ngenr
mill Scale from new steam and condensate Mean annual energy use and energy cost savlngs: 19851992 (1993 prlces)
piping. This contamination was carrled
through to the heat-recovery boiler, block-
ing 14 of its water tubes and causing them
to burst. A complete inspection and exten-
1 Energy usage
'000unlts
Unlt cost
p/unN
:osV(Credit]
PO00
sive repairs were therefore necessary. CHP system

Apart from the start-up and compressor- CHP fuel


washing procedures the System is fully Natural gas (therms) 18.0 929.5
automatic, requiring only a visual inspection
and the logging of operating data twice Boiler fuela
daily. One of the successes of this project HFO (therms) 18.8b 16,2
has been the operation of the CHP plant by
previously inexperienced mill staff Power
Purchased (kWh) 15,439 4.3c 663.9
Energy Use Exported (kWh) 942 3.1 (29.2)
Between 1985 and 1989 the CHP system
provided virtually all of the mill's steam and Total energy costs 1,580.4
electricity requirements, generating approx-
imately 27 GWhlyear (3.4 MW) of electricity Purchased powerlpsckaged bollers
and 15 tonneslhour of steam. Output dur-
ing this period increased from 48,000 to
55,000 tonneslyear. In 1989, the three
existing and relatively smdl paper machines
were replaced by a much larger machine
capable of producing 150,000 tonnedyear.
Boilec fueb
HFO (therms)

Power
Purchased (kWh)
I 3,748

40,667
18.8

4.3c
705.7

1,748.7
This significant increase in mill capacity has
more than doubled both electricity and steam
consumption. Purchased electricity has
Total energy costs
~
I ~
2,454.4

increased from almost nothing to 37 GWh/year,


while the balance of the steam demand is
CHP operatlng cost advantage 874.0
met by three new 21 tonnelhour dual-fuel
package boilers. The original shell boilers Notes.
have now been removed. 3 Excludesfud to new boilers operating alongside CHP system.
3 For natural gas and HFO priced equalk on the basis of net calorific value, me energy costs are the same
The overall thermal efficiency of the CHP WFO at 18.8pitherrn gross b equivalent to natural gas at 18.0pitherm gross).
system has averaged 74.0% (gross calorific J Ail-par weighted mean costs.

valuel. The conversion of fuel to eiectricib is


17.3%, giving a heat to power r a t i i o f
3.28:l Environmental Beneflt Cost Savings and Paybsck
The project has reduced the emission of The mean annual energy costs for 1985-
The CHP system has reduced national pri- carbon dioxide by some 28,000 1992, excluding those incurred bytheaddi-
mary energy consumption by 155 TJiyear tonneslyear, or 50% at the original mill out- tional boiler plant, are shown in the accom-
(5,900 tonnes coal equivalent). Site energy put. This assumes that the CHP plant's panying table for both the CHP system and
consumption is shown in the accompany- electricity generation displaces that provid- pre-CHP operation. They are based on tyo-
ing table. ed by a coal-fired power station. ical 1993 prices.

5.0 The capital cost of the project in 1984/85


was E l ,628 million and, despite consider-
able variations in fuel prices in the early
years of operation, the simple payback
period achieved at SSK was approximately
4.0 3 years.
c
v1
The CHP system reduces energy costs by
-0
._ f874,000/year. Against this must be set
5
3
II)
3.0 the associated maintenance costs. These
have averaged f70,000/year (1993 prices),
0
0 excluding the one-off cost of some
>. f200,000 associated with boiler repairs in
P
0 1989. Allowing f15,000/year for avoided
-5 2.0 maintenance on the almost unused shell
boilers, the net additional maintenance cost
c
is f55,OW/ywar.
2
Net cost savings are therefore
f819,000/year.

For a similar installation in 1993 the capital


cost would be approximately f2.850 million
giving a payback period of 3 . 5 years,
1982 1983 1984 1985 1986 1987 1988 lQ8B 19YO 1991 19Lr assuming that current energy prices remain
unchanged.
nith, Stone & Knlghtennual energy costs and savlngs
1
Comments from Smith, Stone & Knlght
Smith, Stone & Knight is vey conscious of
the effect of energy costs on miii profitability
and, in the late 1970% gave priority to
reducing these costs by installing a
Monitoring and Targeting system. This
proved most effective, within the limits of
the system, but did not achieve the main
objective of reducing total energy usage to
100 therms of primay energy per tonne of
paper sold.

In 1984/85, after a feasibility study, the


company decided to invest in the first aero-
derived turbine used for CHP in the UK. A
turbine failure shortly after initial start-up
was quicWy repaired and, apart from boiler
problems during the installation of a new
paper machine in 1989, the plant as a
whole has operated most satisfactorily wRh
a very high level of availability. With the
exception of start-up the plant is fully auto-
matic, requiring only a visual inspection
once or twlce evey 24 hours.
Smith, Stone & Knlght Ltd
This has proved to be a very worthwhile
and cost-effective project, with net cost
savings currently worth more than Smith, Stone &Knight Ltd
f800,000/year. Mill output, however, has Smith, Stone & Knight Ltd is a wholly
increased three-fold since the inkial install- owned subsidiay of the Roermond Group.
ation, and the CHP plant no longer meets The company's paper mill at Necheils,
total mill requirements for steam and elec- Birmingham produces 150,000 tonnedyear
tricity The company is therefore consider- of packaging materials from w a t e paper.
ing a second installation to meet these The company places considerable emph-
enhanced requirements. asis on improving both the quality of its
prcducts and its levels of energy efficiency.

Mr Alan Clarke
Works Electrical Engineer
Smith, Stone & Knight Ltd

The project described here was selected as an example of Good Practice, which is one element of the Energy Efficiency Office's
IEEO) Best Practice programme, an initiative aimed at advancing and promoting ways of improving the efficiency with which energy is
used in the UK.

This case study replaces the original Expanded Project Profile No 188. More details of the long-term performance of this and
two other gas-turbine-based CHP projects sre avallable ss General Information Report 20. For further copies of this Case
Study or other Best Practice programme publications, please contact the Energy Efficiency Enquiries Bureau, ETSU, Hsrwell,
Oxfordshire. OX1 1 ORA. Tel No: 0235 436747. Telex No: 83135. Fax No: 0235 432923.

For buildings-related projects, please contact: Enquiries Bureau, Building Research Energy Conservation Unit (BRECSU),
Building Research Establishment, Garston, Watford WD2 7JR. Tel No: 0923 664258. Fax No: 0923 664787.

Information on participation In the Best Practice programme and on energy efficiency generally is also available from your
Regional Energy Efficiency Office.
e Cmnncamngh, h i t Pr~ntwJms1 m 4

También podría gustarte