Construction Health and Safety Plan Revision 00

DAILY CHECKLIST Date 12-05-13

Building: Plot: Date:


To Standard
Description Corrective Measures Date
YES NO
1 PPE (Helmet, Safety Shoes, Jacket) available & utilized
Full Body Safety Harness used where required / Body
2
harness inspections completed.
Scaff Tag System Implemented and scaffolding safe for use
3
including working towers platforms
4 Proper Signage / Lifting Operation in progress etc.
5 ‘Hot Work Permit’ in Place/Being monitored (Daily close-outs)
6 ‘Fire Extinguishers’ in Place / Being monitored
Emergency Evacuation (known to all workforce) signage
7
showing access / egress in place
8 First Aid Box / site clinic contact details
9 Any Hazardous Materials(MSDS Submitted)
Crane Load Certificate / Operators Competency Certificate in
10
place area barricaded
Waste Disposal skips emptied / covered waste management
11
in place
Hand Power Tools electrical connection adequate.
12
Distribution panels in place
13 Excavation Edge / Fall Protection / solid
14 Safe Access & Egress to all working area including signage
15 Appropriate Use of Tools PPE etc.
Plant & equipment’s (Crane, Lifting Equipment) checklists
16
completed
17 Adequate lighting / serviceable
18 Safe Manual Handling techniques
Flammable Liquids / paints / glues (Proper Storing &
19
Stacking) spill kits
Welfare Arrangements (Drinking Water, Shaded Rest Area
20
toilets)
21 House Keeping up to date
22 Signage’s
23 Risk assessments completed and signed
Edge protection complete Solid barricading & covers
24
(openings & edges)

The above list does not exclude or waive any other checklist or legal requirement
List tasks for the day:

List specific hazards related to the tasks:

List safety precautions:

Note: If tasks change, this list and the risk assessment must be revised before proceeding with new / changed task.
A signed attendance register must be attached to this list.
I hereby certify that the above items were checked, and all workers under my supervision received a safe task instruction:

Safety Officer / Engineer Print Date

Foreman / Supervisor / Engineer Print Date

Construction Manager Print Date

HSE Manager Print Date

Health, Safety & Environment Is Everyone’s Business

También podría gustarte