DESIGN DELIVERABLE DOCUMENTS LIST

The Client: VIETNAM JAPAN GAS JSC Doc. No.: 190009-01-PP-DS-000


Project: LONG SON METERING STATION & U/G PIPING Rev.: 00
Item: PIPING, CIVIL, E&I DESIGN PACKAGE

Scope Rev.0 Rev.1


No. Document name Document number Remark
VJG Review IEV JPS Plan Actual Status Plan Actual Status
General Đại hỗ trợ reviw thấy lạ lạ chưa biêt
làm thế nào
1 Technical documents list 190009-02-GE-QC- 001 ??? 19-Jul-19
2 Project Execution Plan 190009-02-GE-QC- 002 Thân 19-Jul-19
3 Project Quality Plan 190009-02-GE-QC- 003 Đạinc 19-Jul-19
4 Process Flow Diagram (PFD)
5 Piping and instrument diagram (P&ID) 190009-02-PP-DW- 004 ✓ ✓ 16-Jul-19 Chèn template vào
One spool drawing (ISOmetric dwg: Pipeline + U/G Pipe chưa triển khai vì chưa
6 190009-02-PP-DW- 005-xxx ✓ 23-Jul-19
Metering station) có tọa độ
7 MTO (Pipe + Metering Station + E&I) 190009-02-PP-MC- 006 ✓ 23-Jul-19
8 Painting specification/ procedure 190009-02-PP-SP- 007 ✓ 23-Jul-19
Đã có size ống ==> chèn template
9 Specification for pipeline 190009-02-PP-SP- 008 ✓ 16-Jul-19
vào
10 Data sheet for pipe (U/G & Metering station) 190009-02-PP-DS- 009 ✓ 16-Jul-19 Template chung.
11 RT Procedure (By Authorised Caompany) 190009-02-PP-SP- 010 ✓ 23-Jul-19 Yêu cầu Cty Thứ 3 nộp
12 Inspection & Test Plan (ITP) 190009-02-PP-SP- 011 ✓ 23-Jul-19
13 Welding procedure specification 190009-02-PP-SP- 012 ✓ 23-Jul-19
14 Project Coordination Procedure 190009-02-PP-SP- 013 Lai 23-Jul-19
15 Detailing Engineering Design Schedule 190009-02-PP-MS- 014 Lưỡng 23-Jul-19
16 Engineering Master Document Register 190009-02-PP-MS- 015 Lưỡng 23-Jul-19

Underground pipeline
1 Pipeline process Philosophy 190009-02-PP-SP- 016 ✓ 16-Jul-19 Không cần thiết cho giai đoạn này
2 Piping route drawing 190009-02-PP-DW- 017 ✓ 23-Jul-19 HOLD
3 Detail pipeline crossing drawing 190009-02-PP-DW- 018 ✓ 23-Jul-19 Bản vẽ typical mặt cắt ngang
4 Pipeline alignment sheet 190009-02-PP-DC- 019 ✓ 23-Jul-19 HOLD
5 Pipeline datasheet ✓ 16-Jul-19
6 Pipeline MTO ✓ 23-Jul-19
7 Pipeline analasys 190009-03-PP-DC- 020 ✓ 11-Jul-19 11-Jul-19 IEV checking
Pipeline roping bend calculation report (Tính độ Tạm tính chiều dài ống là 2km và
8 190009-03-PP-DC- 021 18-Jul-19
cong của ống) đi đường thẳng
Sử dụng chung với Metering
9 Pipeline wall thickness calculation report 190009-03-PP-DC- 022 ✓ 11-Jul-19 11-Jul-19 IEV checking
station
Pipeline weight concrete coating - boyancy
10 190009-03-PP-DC- 023 18-Jul-19 Có không theo bản đồ vệ tinh
calculation report (For across marsh if any)
11 Pipeline gas sizing 190009-03-PP-DC- 024 ✓ 11-Jul-19 11-Jul-19 IEV checking
12 Cathodic protection system calculation 190009-03-PP-DC- 025 ✓ 11-Jul-19 11-Jul-19 IEV checking
13 Datasheet for cathodic protection system 190009-02-PP-DS- 026 ✓ 16-Jul-19

14 Anti corrosion and field joint coating specification 190009-02-PP-SP- 027 ✓ 16-Jul-19

15 Cathodic protection system drawing 190009-02-PP-DW- 028 ✓ 16-Jul-19

1/2
Scope Rev.0 Rev.1
No. Document name Document number Remark
Construction Method Statements for
16 190009-02-PP-MOS- 029 Lai 23-Jul-19
Underground Piping

Metering station
1 Pipe size calculation for Metering Station 190009-02-PP-DC- 030 ✓ 16-Jul-19 Sử dụng chung cho U/G pipelins
2 Filter size calculation 190009-02-PP-DC- 031 ✓ 16-Jul-19
3 PSV size calculation 190009-02-PP-DC- 032 ✓ 11-Jul-19 11-Jul-19 IEV checking
4 Foundation plan/ building plan 190009-02-CV-DW- 033 Lưỡng 23-Jul-19
5 Concrete slab detail 190009-02-CV-DW- 034 Lưỡng 23-Jul-19
6 Rebar concrete detail 190009-02-CV-DW- 035 Lưỡng 23-Jul-19
7 Piping arrangement layout 190009-02-PP-DW- 036 ✓ 23-Jul-19
8 Pipe support detail drawing 190009-02-PP-DW- 037 ✓ 23-Jul-19
9 3D view 190009-02-PP-DW- 038 ✓ 23-Jul-19
Metering station datasheet (Valve + Instrument:
10 190009-02-PP-DS- 039 ✓ 16-Jul-19
PG; PDT; PT; FIT; PZV + Electrical)

E&I
1 Instrument & Control General Specification 190009-02-EE-SP- 040 ✓ 15-Jul-19
2 Single line diagram 190009-02-EE-DW- 041 ✓ 15-Jul-19
3 Layout of cable tray 190009-02-EE-DW- 042 ✓ 18-Jul-19
4 Plot plan of equipment 190009-02-EE-DW- 043 ✓ 18-Jul-19
5 Layout of air piping and analyzer tubing plan 190009-02-EE-DW- 044 ✓ 19-Jul-19
6 Layout of instrument/ equipment wiring plan 190009-02-EE-DW- 045 ✓ 19-Jul-19

7 Instrument datasheets (PG; PDT; PT; FIT; PZV) ✓ 15-Jul-19


E&I MTO (Equipment, cable, cable tray, cable
8 ✓ 15-Jul-19
gland…)
9 Typical instrument hook-up drawing 190009-02-EE-DW- 046 Thân 19-Jul-19

2/2