Ejercicios PERT
Ejercicios PERT
(C) Trazado A 1 1 2
𝑎 + 4𝑚 + 𝑏 2+4∗2+3
Te(A) = = = 2.16
6 6
𝑎 + 4𝑚 + 𝑏 1+4∗2+2
Te(B) = = = 1.5
6 6
𝑎 + 4𝑚 + 𝑏 1+4∗1+2
Te(C) = = = 1.17
6 6
𝑎 + 4𝑚 + 𝑏 4+4∗4+5
Te(D) = = = 4.17
6 6
𝑎 + 4𝑚 + 𝑏 3+4∗3+4
Te(E) = = = 3.17
6 6
𝑎 + 4𝑚 + 𝑏 4+4∗4+6
Te(F) = = = 4.33
6 6
4 7.7 3.7
2.5 5 2.5 8.7 9.2 0.5
T1 T2 H
T1 T2 H T1 T2 H
B
2 6
1 4 5 7
A D E F
C
12.2 13.7 1.5 17.2 17.2 0
4.2 7.5 3.3
3 T1 T2 H
T1 T2 H T1 T2 H
EL CAMINO CRITICO SE TRAZO DE ACUERDO A HOLGURA= 0
T2-T1= HOLGURA
H(A)=1.84
H(B)=2.5
H(C)=3.16
H(D)=0.16
H(E)=1.16
H(F)=0
ACTIVIDAD METRADO REDIMIENTO CUADRILLA DIAS PREDECESIÓN
EXCAVACION EL
TERRENO
NORMAL A 500 3.5 10 15
EXCAVACION EN
ROCA
FRACTURADA B 1000 6 8 21
EXCAVACION EN
TERRENO
NORMAL C 800 6 8 17 A
TIEMPO
TIEMPO TIEMPO TIEMPO DESVIACION
PROBAB
OPTIMISTA PESIMISTA ESPERADO (te) ESTANDAR
LE
13 15 17 15 0.4444 0.198
18 21 23 21 0.6944 0.482
14 17 18 17 0.4444 0.198
8 10 10.5 10 0.1736 0.030
14 16 17 16 0.2500 0.063
2
15
17
10 16
A C
D E
1 5 6 7
SUCESO 21
3
0.969955633
15 15 0
T1 T2 H
0 0 0
T1 T2 H 15 2 17
0.984863256
10 16
numero de dias= 57
1 8
6 7
32 32 0 42 42 0 58 58 0
21 3 T1 T2 H T1 T2 H T1 T2 H
21 32 11
T1 T2 H
COLUMNAS
B 2
C
8
9
1 4
8 8 0 4
T1 T2 H
3
A
2
0 0 0
T1 T2 H 17 17 0 26 26 0
T1 T2 H T1 T2 H
8
9
1
5 6
4
9
4 17 13
T1 T2 H
NUMERO DE DIAS= 21
6.92
2.630589288
EXCAVACIÓN DE ZAPATA PARA UN VIVIENDA UNIFAMILIAR DE 150 M2
T. PESIMISTA TIEMPO
CLAVE ACTIVIDADES PREDECESORA T. OPTIMISTA (a) T.PROBABLE (m)
(b) ESPERADO
A Limpieza de terreno - 1 3 4 3
Nivelación y perfilado de
B terreno A 2 2.5 3 3
C trazo y replanteo A 1 2 4 2
D excavación de zanjas B-C 2.5 3 5 3
E Vaciado de solado D 2 3 4 3
F Colocación de acero E 3 4 5 4
G Vaciado de concreto F-G 3 5 6 5
PROCEDEREMOS A CALCULAR TIEMPO ESPERADO DE PARA CARA ACTIVIDAD CON LA SIGUIENTE FORMULA:
𝑎 + 4𝑚 + 𝑏
Te(A) =
6
𝑎 + 4𝑚 + 𝑏 1+3∗2+4
Te(A) = = =3
6 6
1
𝑎 + 4𝑚 + 𝑏 2 + 4 ∗ 2.5 + 3 = 3
Te(B) = =
6 6
𝑎 + 4𝑚 + 𝑏
Te(C) = = 1+4∗2+4 = 2
6 6
𝑎 + 4𝑚 + 𝑏 2.5 + 4 ∗ 3 + 5
Te(D) = = =3
6 6
𝑎 + 4𝑚 + 𝑏 2+4∗3+4
Te(E) = = =3
6 6
𝑎 + 4𝑚 + 𝑏 3+4∗4+5
Te(F) = = =4
6 6
𝑎 + 4𝑚 + 𝑏 3+4∗5+6
Te(G) = = =5
6 6
16 16 0
9 9 0 12 12 0
3 3 0 6 6 0 T1 T2 H
T1 T2 H T1 T2 H
T1 T2 H T1 T2 H
5
3 3 4
3 3 6 7 8
1 2 4 5
E F G
A B D
C 21 21 0
2 3 T1 T2 H
5 7 2
T1 T2 H
HALLAREMOS LA HOLGURA
T2-T1= HOLGURA
H(A)=0
H(B)=0
H(C)=2
H(D)=0
H(E)=0
H(F)=0
H(G)=0
T. T.
T.PROBABLE T.
CLAVE ACTIVIDADES PREDECESORA OPTIMISTA PESIMISTA
(m) ESPERADO
(a) Semanas (b)
A cimentación y muros - 4 5 7 5.2
B instalaciones eléctricas A 3 4 6 4.2
C puesto de losas A 2 3 5 3.2
D puertas y ventanas A 1 2 3 2
E acabados B-C 4 5 6 5
PROCEDEREMOS A CALCULAR TIEMPO ESPERADO DE PARA CARA ACTIVIDAD CON LA SIGUIENTE FORMULA:
𝑎 + 4𝑚 + 𝑏
Te(A) =
6
5.2 9.4 0
5.2 9.4 H
2
0 0 0
0 0 H 5.2 8.4 1 9.4 14.4 0
B
6.2 9.4 H 9.4 14.4 H
ACTIVIDAD PREDECESORA Toptimista(a) T+probable(m) Tpesimista(b)
5 INICIO 1 4
A C E
12.4 14.4 H
HALLAREMOS LA HOLGURA
T2-T1= HOLGURA
H(A)=0
H(B)=0
H(C)=1
H(D)=7.2
H(E)=0
(E) Moldear D 2 2 2
(F) Secar D 1 1 1
(𝑏 − 𝑎)2
𝜎 2 = 𝑉𝑎𝑟(𝐴) = = 0.0278
36
(𝑏 − 𝑎)2
𝜎 2 = 𝑉𝑎𝑟(𝐵) = = 0.1111
36
(𝑏 − 𝑎)2
𝜎 2 = 𝑉𝑎𝑟(𝐶) = =0
𝑎 + 4𝑚 + 𝑏 2+4∗3+4
Te(A) = = =3
6 6
𝑎 + 4𝑚 + 𝑏 2+4∗4+4
Te(B) = = =3
6 6
𝑎 + 4𝑚 + 𝑏 2+4∗2+2
Te(C) = = =2
6 6
𝑎 + 4𝑚 + 𝑏 1+4∗1+1
Te(D) = = =1
6 6
𝑎 + 4𝑚 + 𝑏 2+4∗2+2
Te(E) = = =2
6 6
𝑎 + 4𝑚 + 𝑏 2+4∗2+2
Te(F) = = =1
6 6
𝑎 + 4𝑚 + 𝑏 1 + 4 ∗ 1 + 1
Te(G) = = =1
6 6
𝑎 + 4𝑚 + 𝑏 1 + 4 ∗ 1 + 1
Te(H) = = =1
6 6
8 9 1
T1 T2 H
3 3 0 6 6 0 7 7 0 10 10 0
6F
T1 T2 H T1 T2 H T1 T2 H T1 T2 H
B 9 9 0
E
1 2 4 5T1 T2 H 8 9
A D H
C G
5 6 1 8 9 1 7
3
T1 T2 H T1 T2 H
H(B)=0
(𝜇 )𝑝𝑟𝑜𝑦𝑒𝑐𝑡𝑜 = 𝑡𝑒 (𝐴) + 𝑡𝑒 (𝐵) + 𝑡𝑒(𝐷) +
𝑡𝑒 (𝐸 )+ 𝑡𝑒(𝐻 )
H(C)=1
H(G)=1
H(H)=0
(𝑏 − 𝑎)2
𝑎 + 4𝑚 + 𝑏 6 + 4 ∗ 7 + 8 𝜎 2 = 𝑉𝑎𝑟(𝐼) = = 0.11
Te(I) = = =7 36
6 6
44 44 0
16 16 0
T1 T2 H 7
6 6 0 T1 T2 H 3 34 34 0
T1 T2 H T1 T2 H F(10)
14 16 2
C(10)
T1 T2 H
2 B(8) E(18) 6 9
1 5
A(6)
G(8)
16 16 0 D(10) 42 44 2
46 46 0
T1 T2 H T1 T2 H 8
4
T1 T2 H(2)
H
10
0
53 53 0
I(7)
T1 T2 H
11
EL CAMINO CRITICO SE TRAZO DE ACUERDO A HOLGURA= 0
T2-T1= HOLGURA
H(F)=0
H(G)=2
H(H)=0
H(I)=0
DESVIACION ESTANDAR:
EN ESTE CASO COMO HAY DOS CAMINOS CRITICOS, SE DEBERA UTILIZAR LA DISTRIBUCION CON TIEMPOS DE MAYOR VARIANZA.
LA DISTRIBUCION DEL TIEMPO DE FINALIZACION DEL PROYECTO, DE ACUERDO CON EL TEOREMA CENTRAL DEL LIMITE, SIGUE UNA DISTRIBUCION NORMAL
(63, 3.36).
𝜎 2 = 𝜎𝐴2 + 𝜎𝐶 2 + 𝜎𝐷 2 + 𝜎𝐸 2 + 𝜎𝐹 2 + 𝜎𝐻 2 + 𝜎𝐼 2
𝜎 = √11.32 = 3.36
CON LA INFORMACION OBTENIDA SE PUEDE EFECTUAR CALCULOS PROBABILISTICOS DE TERMINACION DEL PROYECTO. (+5 DIAS)
𝑋−63 68−63
𝑃[ ≤ ] = 𝑃(𝑍 ≤ 1.488) = 0.9306
3.36 3.36