Está en la página 1de 4

CALENDARIO DE AVANCE DE OBRA VALORIZADO

CONSTRUCCION DE CERCO PERIMETRICO DE LA PARCELA DEMOSTRATIVA DE PALANCA DE PROPIEDAD DE LA


MUNICIPALIDAD DISTRITAL DE PAUCAS, DISTRITO DE PAUCAS, PROVINCIA DE HUARI, REGION ANCASH

PLAZO DE EJECUCION 60 DIAS CALENDARIO

MES 1 MES 2
ITEM PARTIDAS UND COSTO
COSTO S/. % COSTO S/. %
01 OBRAS PROVISIONALES
01.01 CAMPAMENTO PROVISIONAL DE OBRA glb 700.00 700.00 100.00% 0.00 0.00%
01.02 CARTEL DE OBRA 2.40x3.60 und 850.00 850.00 100.00% 0.00 0.00%
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS glb 1,500.00 1,500.00 100.00% 0.00 0.00%
02 SEGURIDAD Y SALUD
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y glb 1,000.00 1,000.00 100.00% 0.00 0.00%
02.02 EQUIPO DE PROTECCION INDIVIDUAL und 2,673.40 2,673.40 100.00% 0.00 0.00%
02.03 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 448.80 448.80 100.00% 0.00 0.00%
02.04 CAPACITACION EN SEGURIDAD Y SALUD glb 1,200.00 1,200.00 100.00% 0.00 0.00%
02.05 RECURSOS P/RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE glb 271.33 271.33 100.00% 0.00 0.00%
03 TRABAJOS PRELIMINARES
03.01 LIMPIEZA DEL TERRENO MANUAL m2 2,125.20 2,125.20 100.00% 0.00 0.00%
03.02 TRAZO, NIVELACION Y REPLANTEO m2 1,558.48 1,558.48 100.00% 0.00 0.00%
04 MOVIMIENTO DE TIERRAS
04.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS Y ZAPATAS m3 6,013.44 6,013.44 100.00% 0.00 0.00%
04.02 EXCAVACION EN EXPLANACION PARA CIRCULACION INTERNA m3 5,482.96 5,482.96 100.00% 0.00 0.00%
04.03 RELLENO COMPACTADO CON MATERIAL PROPIO PISON MANUAL m3 1,272.18 526.60 41.39% 745.58 58.61%
04.04 PERFILADO Y COMPACTADO DE TERRENO m2 458.30 458.30 100.00% 0.00 0.00%
04.05 ELIMINACION DE MATERIAL EXCEDENTE DE EXCAVACION CON MAQUINARIA m3 7,860.64 7,860.64 100.00% 0.00 0.00%
05 OBRAS DE CONCRETO SIMPLE
05.01 SOLADO PARA ZAPATAS E=4'' C:H, 1:10 m2 254.27 254.27 100.00% 0.00 0.00%
05.02 CONCRETO 1:10+30% PG, PARA CIMIENTO CORRIDO m3 23,412.00 23,412.00 100.00% 0.00 0.00%
05.03 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO m2 13,975.86 3,750.83 26.84% 10,225.03 73.16%
05.04 CONCRETO CICLOPEO PARA SOBRECIMIENTO, 1:8+25% PM m3 8,592.26 3,831.18 44.59% 4,761.08 55.41%
CALENDARIO DE AVANCE DE OBRA VALORIZADO

CONSTRUCCION DE CERCO PERIMETRICO DE LA PARCELA DEMOSTRATIVA DE PALANCA DE PROPIEDAD DE LA


MUNICIPALIDAD DISTRITAL DE PAUCAS, DISTRITO DE PAUCAS, PROVINCIA DE HUARI, REGION ANCASH

PLAZO DE EJECUCION 60 DIAS CALENDARIO

MES 1 MES 2
ITEM PARTIDAS UND COSTO
COSTO S/. % COSTO S/. %
06 ESCALERA DE MAMPOSTERIA DE PIEDRA
06.01 CONCRETO 1:10 + 30% P.G, PARA CIMIENTO. m3 280.32 280.32 100.00% 0.00 0.00%
06.02 RELLENO APISONADO CON MATERIAL DE PRESTAMO m3 638.25 638.25 100.00% 0.00 0.00%
06.03 ASENTADO DE MANPOSTERIA DE PIEDRA, MEZCLA C:H 1:6+75% DE PIEDRA m3 1,328.47 1,328.47 100.00% 0.00 0.00%
06.04 ENCOFRADO Y DESENCOFRADO NORMAL m2 1,210.68 1,210.68 100.00% 0.00 0.00%
07 OBRAS DE CONCRETO ARMADO
07.01 ZAPATAS
07.01.01 ACERO fy=4,200 KG/CM2 - ZAPATAS kg 262.34 262.34 100.00% 0.00 0.00%
07.01.02 CONCRETO PARA ZAPATAS F'c=210 KG/CM2 m3 1,146.39 1,146.39 100.00% 0.00 0.00%
07.02 COLUMNAS
07.02.01 ACERO fy= 4200 KG/CM2 - COLUMNAS kg 4,244.00 4,244.00 100.00% 0.00 0.00%
07.02.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS m2 11,520.72 3,473.81 30.15% 8,046.91 69.85%
07.02.03 CONCRETO PARA COLUMNAS F'c=210 KG/CM2 m3 6,722.36 6,722.36 100.00% 0.00 0.00%
07.03 LOSAS MECIZAS
07.03.01 ACERO fy= 4200 KG/CM2 - LOSAS MACIZAS kg 960.27 960.27 100.00% 0.00 0.00%
07.03.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA LOSA MACIZA m2 973.28 973.28 100.00% 0.00 0.00%
07.03.03 CONCRETO PARA LOSAS MACIZAS F'c=210 KG/CM2 m3 1,433.02 1,433.02 100.00% 0.00 0.00%
08 REVOQUES, ENLUCIDOS Y MOLDURAS
08.01 TARRAJEO DE SOBRECIMIENTOS Y COLUMNAS,E=1.5 CM, C:A 1:5 m2 10,392.62 0.00 0.00% 10,392.62 100.00%
09 CIELORRASOS
09.01 TARRAJEO DE CIELORRASO,E=1.5 CM, C:A 1:4 m2 599.52 0.00 0.00% 599.52 100.00%
10 PINTURA
10.01 PINTURA DE SOBRECIMIENTOS Y COLUMNAS, LATEX 02 MANOS m2 4,052.27 0.00 0.00% 4,052.27 100.00%
10.02 PINTURA DE CIELORRASOS, LATEX 02 MANOS m2 209.28 0.00 0.00% 209.28 100.00%
11 CARPINTERIA METALICA
CALENDARIO DE AVANCE DE OBRA VALORIZADO

CONSTRUCCION DE CERCO PERIMETRICO DE LA PARCELA DEMOSTRATIVA DE PALANCA DE PROPIEDAD DE LA


MUNICIPALIDAD DISTRITAL DE PAUCAS, DISTRITO DE PAUCAS, PROVINCIA DE HUARI, REGION ANCASH

PLAZO DE EJECUCION 60 DIAS CALENDARIO

MES 1 MES 2
ITEM PARTIDAS UND COSTO
COSTO S/. % COSTO S/. %
11.01 PUERTA METALICA DE 3.00x3.20 m (SEGUN DISEÑO) und 6,655.60 0.00 0.00% 6,655.60 100.00%
11.02 MALLA METALICA Nª10 INC/INSUMOS m2 100,073.69 25,415.54 25.40% 74,658.15 74.60%
11.03 TUBO DE FIERRO GALV. 3'' m 8,900.93 3,258.11 36.60% 5,642.82 63.40%
CALENDARIO DE AVANCE DE OBRA VALORIZADO

CONSTRUCCION DE CERCO PERIMETRICO DE LA PARCELA DEMOSTRATIVA DE PALANCA DE PROPIEDAD DE LA


MUNICIPALIDAD DISTRITAL DE PAUCAS, DISTRITO DE PAUCAS, PROVINCIA DE HUARI, REGION ANCASH

PLAZO DE EJECUCION 60 DIAS CALENDARIO

MES 1 MES 2
ITEM PARTIDAS UND COSTO
COSTO S/. % COSTO S/. %
12 CERRAJERIA
12.01 CERRADURA PARA PUERTA PRINCIPAL PESADA und 234.88 0.00 0.00% 234.88 100.00%
12.02 BISAGRA DE FIERRO PARA PUERTA und 325.56 0.00 0.00% 325.56 100.00%
13 FLETE TERRESTRE
13.01 FLETE TERRESTRE glb 9,800.73 9,800.73 100.00% 0.00 0.00%
COSTO DIRECTO 251614.30 125,065.00 126,549.30
GASTOS GENERALES (16.44%) 41373.21 20564.57 20808.64
UTILIDAD (8%) 20129.14 10005.20 10123.94
SUB TOTAL 313116.65 155,634.77 157,481.88
IMPUESTO (IGV 18%) 56361.00 28014.26 28346.74
TOTAL PRESUPUESTO 369477.65 183649.03 185828.62
PORCENTAJE VALORIZADO MENSUAL 49.71% 50.29%
PORCENTAJE ACUMULADO VALORIZADO MENSUAL 49.71% 100.00%