CRON OGRAMA VALO RIZADO DE E JECUCION DE O

L O C AL I D A D D E Y A N G A S
PROYECTO : “CREACION DE LAS CONDICIONES DE TRANSITABILIDAD EN LA AV. SAN MARCELO, VIA DE ACCESO A LA CAPITAL DEL DISTRITO, LO
ENTIDAD : MUNICIPALIDAD DISTRITAL DE SANTA ROSA DE QUIVES
DISTRITO : SANTA ROSA DE QUIVES
PROVINCIA : CANTA
DPTO : LIMA

PISTAS Y VEREDAS
ITEM DESCRIPCION DE PARTIDA MES 1 MES 2 MES 3
01 PISTAS S/. 202,499.88 S/. 740,512.60 S/. 35,402.60
01.01 INSTALACIONES PROVISIONALES S/. 56,717.20 S/. 7,165.15 S/. 6,934.02
01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, MAQUINARIAS Y HERRAMIEN S/. 38,908.52
01.01.02 CARTEL DE OBRA 7.20 x 3.60 S/. 5,206.42
01.01.03 CAMPAMENTO Y PATIO DE MANIOBRAS S/. 5,437.11
01.01.04 FLETE TERRESTRE S/. 7,165.15 S/. 7,165.15 S/. 6,934.02
01.02 OBRAS PRELIMINARES S/. 64,751.67
01.02.01 DESBROCE Y LIMPIEZA EN ZONAS NO BOSCOSAS S/. 17,435.71
01.02.02 TRAZO, NIVELES Y REPLANTEO S/. 47,315.96
01.03 MOVIMIENTO DE TIERRAS S/. 79,878.82 S/. 488,392.05
01.03.01 EXCAVACIONES S/. 79,376.18 S/. 27,476.37
01.03.01.01 EXCAVACION HASTA SUBRASANTE MAT. SUELTO C/TRACTOR 140/160HP S/. 79,376.18 S/. 27,476.37
01.03.02 RELLENOS S/. 502.64 S/. 460,915.68
01.03.02.01 RELLENO COMPACTADO CON MATERIAL PROPIO C/EQUIPO S/. 502.64 S/. 7,539.58
01.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE DM=2 km S/. 453,376.10
01.04 PAVIMENTACION
01.04.01 CONFORMACION Y COMPACTACION SUB RASANTE C/MOTONIV. 125HP
01.04.02 SUB BASE GRANULAR e=0.15 m FACTOR DE COMPACTACION = 1.25
01.04.03 BASE GRANULAR E=0.20 m FACTOR DE COMPACTACION=1.25
01.04.04 IMPRIMACION ASFALTICA (DOSIF.0.30 GL/M2-TANQUE 1800GL)
01.04.05 CARPETA ASFALTICA EN CALIENTE DE 2"
01.05 SARDINEL SUMERGIDO S/. 1,152.19 S/. 244,955.40 S/. 19,798.58
01.05.01 EXCAVACION MANUAL DE ZANJAS PARA SARDINELES S/. 1,152.19 S/. 21,891.64

Página 1
PISTAS Y VEREDAS
ITEM DESCRIPCION DE PARTIDA MES 1 MES 2 MES 3
01.05.02 SARDINEL SUMERGIDO f'c=175 kg/cm2 S/. 128,690.76 S/. 19,798.58
01.05.03 ENCOFRADO Y DESENCOFRADO DE SARDINEL SUMERGIDO S/. 90,165.12
01.05.04 JUNTA PARA SARDINEL SUMERGIDO S/. 4,207.88
01.06 SEÑALIZACION Y REDUCTORES DE VELOCIDAD S/. 8,670.00
01.06.01 SEÑALIZACION HORIZONTAL S/. 8,670.00
01.06.01.01 PINTURA DE BORDE DE VEREDA S/. 8,670.00
01.06.01.02 DEMARCACION DE PAVIMENTOS (LINEA AMARILLA DISCONTINUA A=0.15m
01.06.01.03 DEMARCACION DE PAVIMENTOS (LINEA BLANCA CONTINUA) A=0.15m
01.06.01.04 PINTURA DE PAVIMENTOS (SIMBOLOS Y LETRAS)
01.06.02 SEÑALIZACION VERTICAL
01.06.02.01 SEÑALES PREVENTIVAS (0.60m X 0.60m)
01.06.02.02 SEÑALES reglamentarias (0.60m x 0.90m)
01.06.03 REDUCTORES DE VELOCIDAD
01.06.03.01 REDUCTOR DE VELOCIDAD TIPO RESALTO
02 OBRAS DE PROTECCION S/. 19,685.09 S/. 234,551.99 S/. 457,555.02
02.01 MUROS DE SOSTENIMIENTO S/. 19,685.09 S/. 154,563.19 S/. 262,241.75
02.01.01 EXCAVACION EN MUROS DE SOSTENIMIENTO S/. 4,943.93 S/. 6,356.48
02.01.02 CONCRETO f'c=210 kg/cm2 PARA MUROS DE SOSTENIMIENTO S/. 42,635.17
02.01.03 ENCOFRADO Y DESENCOFRADO PARA MUROS DE SOSTENIMIENTO S/. 37,331.56
02.01.04 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 S/. 72,910.01 S/. 182,275.02
02.01.05 JUNTA DE DILATACION PARA MUROS S/. 3,507.53 S/. 452.58
02.01.06 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO
02.01.07 CONCRETO f'c=100 Kg/Cm2 SOLADOS S/. 2,580.83 S/. 74,844.12
02.01.08 MATERIAL FILTRANTE
02.01.09 GEOTEXTIL NO TEJIDO CLASE 2 S/. 8,652.80
02.01.10 TUBERIA CORRUGADA PERFORADA HDPE D=6"
02.01.11 TUBO PVC SAP DE 3"
02.01.12 RELLENO COMPACTADO C/ MATERIAL PROPIO CON EQUIPO
02.02 OBRAS DE ARTE, DRENAJE Y DEFENSA RIBEREÑA S/. 79,988.80 S/. 195,313.27
02.02.01 DEMOLICION DE ALCANTARILLAS S/. 2,689.08

Página 2
PISTAS Y VEREDAS
ITEM DESCRIPCION DE PARTIDA MES 1 MES 2 MES 3
02.02.02 EXCAVACION EN ALCANTARILLAS S/. 1,881.29
02.02.03 EXCAVACION EN CUNETAS S/. 5,409.69
02.02.04 RELLENO EN ALCANTARILLAS CIRCULARES TMC S/. 2,363.73
02.02.05 ENCOFRADO Y DESENCOFRADO NORMAL EN ALCANTARILLAS S/. 4,985.95
02.02.06 ENCOFRADO Y DESENCOFRADO NORMAL EN CUNETAS S/. 11,196.00
02.02.07 CONCRETO f'c=210 kg/cm2 PARA ALCANTARILLAS S/. 10,303.46
02.02.08 CONCRETO f'c=210 kg/cm2 PARA CUNETAS S/. 17,607.16
02.02.09 TUBERIA METALICA CORRUGADA CIRCULAR DIAM=0.90 M S/. 21,596.12
02.02.10 REJILLA METALICA S/. 1,869.00
02.02.11 RELLENO COMPACTADO CON MATERIAL PROPIO C/EQUIPO S/. 87.32 S/. 349.27
02.02.12 GAVION CAJA (Zn-5AI-MM) S/. 194,964.00
02.02.13 ESTABILIDAD DE TALUD
02.02.14 BARANDAS METALICAS
03 VEREDAS S/. 90,905.62 S/. 35,184.04
03.01 DEMOLICION DE VEREDAS DE 0.10m S/. 18,510.00
03.02 CONFORMACION DE SUBRASANTE PARA VEREDAS S/. 14,475.00
03.03 BASE GRANULAR PARA VEREDAS E= 0.10 M. S/. 24,015.00
03.04 CONCRETO Fc= 175 kg/cm2 EN VEREDAS S/. 23,456.02 S/. 35,184.04
03.05 ENCOFRADO Y DESENCOFRADO P/VEREDAS S/. 10,449.60
04 PREVENCION Y MITIGACION AMBIENTAL S/. 2,085.86 S/. 2,959.81 S/. 3,359.25
04.01 PREVENCION Y MITIGACION AMBIENTAL S/. 1,589.86 S/. 1,589.86 S/. 1,538.57
04.02 EDUCACION AMBIENTAL Y CAPACITACION S/. 873.95 S/. 1,008.40
04.03 MONITOREO AMBIENTAL S/. 229.42
04.04 CONTINGENCIA S/. 102.86
04.05 ABANDONO
04.06 RIEGO DE AREA DE TRABAJO S/. 496.00 S/. 496.00 S/. 480.00
05 SEGURIDAD Y SALUD EN EL TRABAJO
05.01 EQUIPOS DE PROTECCION INDIVIDUAL
05.02 SEÑALIZACION TEMPORAL DE SEGURIDAD
06 VARIOS S/. 12,730.32 S/. 21,737.92 S/. 4,951.61

Página 3
PISTAS Y VEREDAS
ITEM DESCRIPCION DE PARTIDA MES 1 MES 2 MES 3
06.01 LIMPIEZA FINAL DE OBRA
06.02 REUBICACION DE POSTES DE ALUMBRADO S/. 5,570.10
06.03 NIVELACION DE BUZONES AL NIVEL DE RASANTE EN PAVIMENTOS S/. 7,160.22 S/. 4,773.48
06.04 NIVELACION DE CAJAS DE AGUA S/. 10,362.30
06.05 NIVELACION DE CAJAS DE DESAGUE S/. 6,602.14 S/. 4,951.61
COSTO DIRECTO S/. 237,001.15 S/. 1,090,667.94 S/. 536,452.52
GASTOS GENERALES (8%) S/. 18,960.09 S/. 87,253.44 S/. 42,916.20
UTILIDADES (7%) S/. 16,590.08 S/. 76,346.76 S/. 37,551.68
SUB TOTAL ### ### ###
IGV (18%) S/. 49,059.24 S/. 225,768.26 S/. 111,045.67
SUPERVISION (5%CD) S/. 11,850.06 S/. 54,533.40 S/. 26,822.63
PRESUPUESTO TOTAL DE LA OBRA ### ### ###
AVANCE POR MES EN PORCENTAJES 4.32% 19.90% 9.79%
ACUMULADO 4.32% 24.22% 34.00%

Página 4
RIZADO DE E JECUCION DE OBRAS
AL I D A D D E Y A N G A S
CELO, VIA DE ACCESO A LA CAPITAL DEL DISTRITO, LOCALIDAD DE YANGAS Y ANEXOS”

PISTAS Y VEREDAS
MES 4 MES 5 MES 6 MES 7 MES 8
S/. 7,165.15 S/. 6,934.02 S/. 366,143.48 S/. 1,049,368.54 S/. 274,366.57
S/. 7,165.15 S/. 6,934.02 S/. 7,165.15 S/. 7,165.15 S/. 5,778.35

S/. 7,165.15 S/. 6,934.02 S/. 7,165.15 S/. 7,165.15 S/. 5,778.35

S/. 358,978.33 S/. 1,042,203.39 S/. 158,885.28


S/. 81,035.38
S/. 175,993.62 S/. 43,998.40
S/. 101,949.33 S/. 178,411.32
S/. 88,921.37
S/. 730,872.30 S/. 158,885.28

Página 5
PISTAS Y VEREDAS
MES 4 MES 5 MES 6 MES 7 MES 8

S/. 109,702.94
S/. 77,810.94

S/. 12,247.20
S/. 65,263.39
S/. 300.35
S/. 22,682.80
S/. 18,661.60
S/. 4,021.20
S/. 9,209.20
S/. 9,209.20
S/. 828,322.23 S/. 503,791.93 S/. 501,699.62 S/. 50,737.12
S/. 647,359.93 S/. 503,791.93 S/. 421,846.62 S/. 24,119.45

S/. 330,422.60 S/. 319,763.81 S/. 330,422.60


S/. 128,586.47 S/. 74,663.11
S/. 188,350.86 S/. 109,365.01

S/. 30,258.03 S/. 5,043.01

S/. 12,837.37 S/. 2,567.47

S/. 17,872.09 S/. 11,170.06


S/. 30,456.53
S/. 5,338.91
S/. 180,962.30 S/. 79,853.00 S/. 26,617.67

Página 6
PISTAS Y VEREDAS
MES 4 MES 5 MES 6 MES 7 MES 8

S/. 115,206.00
S/. 65,756.30
S/. 79,853.00 S/. 26,617.67

S/. 3,300.81 S/. 1,436.21 S/. 509.31 S/. 252.76


S/. 1,384.71
S/. 1,042.02 S/. 1,008.40 S/. 67.23
S/. 309.22 S/. 299.24 S/. 309.22 S/. 39.90
S/. 132.86 S/. 128.57 S/. 132.86 S/. 12.86
S/. 200.00
S/. 432.00
S/. 5,324.00
S/. 3,324.00
S/. 2,000.00
S/. 18,491.29

Página 7
PISTAS Y VEREDAS
MES 4 MES 5 MES 6 MES 7 MES 8
S/. 18,491.29

S/. 844,112.19 S/. 512,162.16 S/. 868,352.41 S/. 1,100,358.42 S/. 292,857.86
S/. 67,528.98 S/. 40,972.97 S/. 69,468.19 S/. 88,028.67 S/. 23,428.63
S/. 59,087.85 S/. 35,851.35 S/. 60,784.67 S/. 77,025.09 S/. 20,500.05
### ### ### ### ###
S/. 174,731.22 S/. 106,017.57 S/. 179,748.95 S/. 227,774.19 S/. 60,621.58
S/. 42,205.61 S/. 25,608.11 S/. 43,417.62 S/. 55,017.92 S/. 14,642.89
### ### ### ### ###
15.40% 9.34% 15.84% 20.07% 5.34%
49.40% 58.75% 74.59% 94.66% 100.00%