PRESUPUESTO

Item Descripción Unid. Metrado Precio S/. Parcial S/.


01 TRABAJOS PRELIMINARES
01.01 Limpieza de terreno manual m2 140.00 6.85 959.00
01.02 Trazo y replanteo preliminar m2 54.78 2.65 145.17
02 MOVIMIENTO DE TIERRAS
02.01 Excavacion manual para zapatas m3 29.05 76.20 2,213.61
02.02 Excavacion manual para cimientos m3 21.86 76.20 1,665.73
03.00 OBRAS DE CONCRETO SIMPLE
03.01 Solado CH, 1:12 m3 1.45 35.06 50.84
03.02 Cimiento corrido 1:10 + 20% P.G 6" m3 17.21 282.93 4,869.23
04 OBRAS DE CONCRETO ARMADO
04.01 ZAPATAS
04.01.01 Zapatas - Concreto f'c = 210 kg/cm2 m3 14.53 455.22 6,614.35
04.01.02 Zapatas - Acero fy = 4200 kg/cm2 kg 277.43 6.31 1,750.58
04.02 VIGAS DE CIMENTACION
04.02.01 Vigas de cimentacion - Concreto f'c = 210 kg/cm2 m3 3.51 477.05 1,674.45
04.02.02 Vigas de cimentacion - Acero fy = 4200 kg/cm2 kg 396.11 6.31 2,499.45
04.03 COLUMNAS
04.03.01 Columnas - Concreto f'c = 210 kg/cm2 m3 10.40 554.04 5,762.02
04.03.02 Columnas - acero fy = 4200 kg/cm2 kg 983.93 6.59 6,484.10
04.04 VIGAS
04.04.01 Vigas - Concreto f'c = 210 kg/cm2 m3 10.59 505.27 5,350.81
04.04.02 Vigas - Acero fy = 4200 kg/cm2 kg 1,480.11 6.31 9,339.49
04.05 LOSAS ALIGERADAS
04.05.01 Losas aligeradas - Concreto f'c = 210 kg/cm2 m3 17.81 496.14 8,836.25
04.05.02 Losas aligeradas - Acero fy = 4200 kg/cm2 kg 1,225.89 6.31 7,735.39
04.05.03 Losas aligeradas - Ladrillo hueco 15x30x30 cm und 1,528.95 3.43 5,244.30
05 ALBAÑILERIA
05.01 Muro de ladrillo k.k. arcilla 18 huecos - cabeza 9x12.5x23 m2 42.23 117.54 4,963.13
05.02 Muro de ladrillo k.k. arcilla 18 huecos - soga 9x12.5x23 m2 485.45 73.30 35,583.38
05.03 Muro de ladrillo k.k. arcilla 18 huecos - canto 9x12.5x23 m2 30.94 54.98 1,701.08

Costo directo: 113,442.34


Gastos generales (10%): 11,344.23
Utilidad (7%): 7,940.96

Sub total: 132,727.54


I.G.V 18%: 23,890.96

Total: 156,618.50
COEFICIENTE DE INCIDENCIAS

AGREGADO ACERO DE GG Y
HERRAMIENTA MAQUINARIA Y EQUIPO CEMENTO PORTLAND AGREGADO MADERA IMPORTADA PARA HORMIGON BLOQUE Y
PARTIDA METRADO MANO DE OBRA "47" FINO CONSTRUCCION DÓLAR "30" UTILIDAD
MANUAL "37" IMPORTADO "49" TIPO I "21" GRUESO "05" ENCOFRADO Y CARPINTERIA "42" "38" LADRILLO "17"
"04" CORRUGADO "03" "39"

01.01 140.00 931.00 28.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
01.02 54.78 36.70 1.64 77.79 20.82 0.00 0.00 0.00 6.03 0.00 0.00 2.19 -
02.01 29.05 2,149.12 64.49 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
02.02 21.86 1,617.20 48.53 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -
03.01 1.45 17.76 0.54 3.26 12.37 0.00 0.00 0.00 0.97 15.67 0.00 0.26 -
03.02 17.21 1,185.60 35.62 206.52 1,233.61 921.42 0.00 0.00 0.00 1,254.78 0.00 31.67 -
04.01.01 14.53 928.47 27.90 217.95 3,325.77 1,399.09 688.43 0.00 0.00 0.00 0.00 26.74 -
04.01.02 277.43 380.08 11.10 0.00 0.00 0.00 0.00 1,359.41 0.00 0.00 0.00 0.00 -
04.02.01 3.51 296.63 8.92 54.76 803.40 337.98 166.30 0.00 0.00 0.00 0.00 6.46 -
04.02.02 396.11 542.67 15.84 0.00 0.00 0.00 0.00 1,940.94 0.00 0.00 0.00 0.00 -
04.03.01 10.40 1,627.50 48.78 293.28 2,279.16 1,001.42 492.75 0.00 0.00 0.00 0.00 19.14 -
04.03.02 983.93 1,613.65 49.20 0.00 0.00 0.00 0.00 4,821.26 0.00 0.00 0.00 0.00 -
04.04.01 10.59 1,234.90 37.07 171.56 2,320.80 1,019.71 547.29 0.00 0.00 0.00 0.00 19.49 -
04.04.02 1,480.11 2,027.75 59.20 0.00 0.00 0.00 0.00 7,252.54 0.00 0.00 0.00 0.00 -
04.05.01 17.81 1,931.13 57.88 276.06 3,903.06 1,714.92 920.42 0.00 0.00 0.00 0.00 32.77 -
04.05.02 1,225.89 1,679.47 49.04 0.00 0.00 0.00 0.00 6,006.88 0.00 0.00 0.00 0.00 -
04.05.03 1,528.95 1,192.57 30.58 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4,021.14 0.00 -
05.01 42.23 2,156.86 64.60 0.00 438.72 0.00 135.54 51.94 90.36 0.00 1,809.76 215.35 -
05.02 485.45 16,908.17 504.87 0.00 2,267.04 0.00 699.05 597.10 1,038.86 0.00 11,888.63 1,679.65 -
05.03 30.94 926.65 27.85 0.00 82.92 0.00 25.68 2.48 66.21 0.00 568.06 1.24 -

39,383.87 1,171.63 1,301.17 16,687.66 6,394.54 3,675.46 22,032.53 1,202.43 1,270.46 18,287.59 2,034.94 19,285.20
Sub total 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54 132,727.54
C.I 0.297 0.009 0.010 0.126 0.048 0.028 0.166 0.009 0.010 0.138 0.015 0.145

∑ C.I
1.00
CALCULO DE Ko
COEFICIENTE
INDICE % Ir (Octubre) Io (Agosto) In/Io K
SIMBOLO DE INCIDENCIAS
UNIFICADO
1 2 3 4 = (3)x(2) 5 6 = (5)x(2) 7 = 4/6 (1)x(7)
Mano de obra 47 0.297 100% 580.90 580.90 580.90 580.90 1.000 0.297
Herramienta manual 37 0.185 4.86% 298.08 14.49 297.47 14.46
Maquinaria y equipo 49 0.185 5.41% 293.18 15.86 292.36 15.82 1.019 0.189
Acero 03 0.185 89.73% 469.92 421.66 460.39 413.11
Cemento 21 0.126 100% 401.92 401.92 401.92 401.92 1.000 0.126
Agregado grueso 05 0.086 55.81% 216.12 120.62 216.43 120.79
Agregado fino 04 0.086 32.56% 935.73 304.67 936.12 304.80 1.002 0.086
Hormigon 38 0.086 11.63% 960.95 111.76 948.41 110.30
Madera 42 0.162 5.56% 284.22 15.80 283.79 15.78
Bloque y ladrillo 17 0.162 85.18% 666.77 567.95 671.71 572.16 0.994 0.161
Dólar 30 0.162 9.26% 467.61 43.30 462.48 42.83
GG y utulidad 39 0.145 100% 442.48 442.48 444.64 444.64 0.995 0.145
∑ 1.000 K= 1.003
ANALISIS DE PRECIOS UNITARIOS
Partida 01.01 LIMPIEZA DE TERRENO MANUAL
Rendimiento: 80.00 m2 /día Costo unitario directo por m2 6.85
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.2500 0.0250 16.74 0.42
Peon hh 5.0000 0.5000 12.46 6.23
6.65
Equipo y herramientas
Herramientas manuales %MO 3.0000 6.65 0.20
0.20

Partida 01.02 TRAZO Y REPLANTEO PRELIMINAR


Rendimiento: 500.00 m2 /día Costo unitario directo por m2 2.65
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0016 16.74 0.03
Operario hh 1.0000 0.0160 15.22 0.24
Peon hh 2.0000 0.0320 12.46 0.40
0.67
Materiales
Yeso en bolsas de 20 kg. BOL 0.0500 7.67 0.38
Cordel m 0.1900 0.20 0.04
Madera tornillo pie2 0.0200 5.31 0.11
0.53
Equipo y herramientas
Herramientas manuales %MO 5.0000 0.67 0.03
Wincha de 50 mtrs. pza 0.0025 55.00 0.14
Teodolito y mira hm 1.0000 0.0160 50.00 0.80
Nivel topografico hm 1.0000 0.0160 30.00 0.48
1.45

Partida 02.01 EXCAVACION MANUAL PARA ZAPATAS


Rendimiento: 2.00 m3 /día Costo unitario directo por m3 76.20
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.4000 16.74 6.70
Peon hh 1.3500 5.4000 12.46 67.28
73.98
Equipo y herramientas
Herramientas manuales %MO 3.0000 73.98 2.22
2.22

Partida 02.02 EXCAVACION MANUAL PARA CIMIENTOS


Rendimiento: 2.00 m3 /día Costo unitario directo por m3 76.20
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.4000 16.74 6.70
Peon hh 1.3500 5.4000 12.46 67.28
73.98
Equipo y herramientas
Herramientas manuales %MO 3.0000 73.98 2.22
2.22

Partida 03.01 SOLADO CH, 1:12


Rendimiento: 80.00 m2 /día Costo unitario directo por m3 35.06
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.2000 0.0200 16.74 0.33
Operario hh 2.0000 0.2000 15.22 3.04
Oficial hh 1.0000 0.1000 13.97 1.40
Peon hh 6.0000 0.6000 12.46 7.48
12.25
Materiales
Cemento portland tipo I (42.5kg) BOL 0.3790 22.50 8.53
Agua m3 0.0180 10.00 0.18
Hormigon m3 0.1290 83.80 10.81
Regla de madera p2 0.1120 6.00 0.67
20.19
Equipo y herramientas
Herramientas manuales %MO 3.0000 12.25 0.37
Mescladora concreto tambor 18HP 11P3 hm 0.7500 0.0750 30.00 2.25
2.62

Partida 03.02 CIMIENTOS CORRIDOS 1:10 + 30% P.G 6"


Rendimiento: 20.00 m3 /día Costo unitario directo por m3 282.93
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0400 16.74 0.67
Operario hh 2.0000 0.8000 15.22 12.18
Oficial hh 2.0000 0.8000 13.97 11.18
Peon hh 9.0000 3.6000 12.46 44.86
68.89
Materiales
Piedra mediana de 6" m3 0.6050 88.50 53.54
Cemento tipo MS BOL 3.0500 23.50 71.68
Agua m3 0.1840 10.00 1.84
Hormigon m3 0.8700 83.80 72.91
199.97
Equipo y herramientas
Herramientas manuales %MO 3.0000 68.89 2.07
Mescladora concreto tambor 18HP 11P3 hm 1.0000 0.4000 30.00 12.00
14.07
Partida 04.01.01 ZAPATAS CONCRETO F'C = 210 KG/CM2
Rendimiento: 20.00 m3 /día Costo unitario directo por m3 455.22
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0400 16.74 0.67
Operario hh 2.0000 0.8000 15.22 12.18
Oficial hh 2.0000 0.8000 13.97 11.18
Peon hh 8.0000 3.2000 12.46 39.87
63.90
Materiales
Piedra Cancada de 1/2" - 3/4" m3 0.8000 120.36 96.29
Arena gruesa m3 0.5500 86.14 47.38
Cemento tipo MS BOL 9.7400 23.50 228.89
Agua m3 0.1840 10.00 1.84
374.40
Equipo y herramientas
Herramientas manuales %MO 3.0000 63.90 1.92
Vibrador de concreto 4 HP 2.40" hm 0.5000 0.2000 15.00 3.00
Mescladora concreto tambor 18 HP 11P3 hm 1.0000 0.4000 30.00 12.00
16.92

Partida 04.01.02 ZAPATAS - ACERO FY = 4200 KG/CM2


Rendimiento: 180.00 kg /día Costo unitario directo por m2 6.31
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0044 16.74 0.07
Operario hh 1.0000 0.0444 15.22 0.68
Peon hh 1.0000 0.0444 13.97 0.62
1.37
Materiales
Alambre negro N°16 kg 0.0600 5.00 0.30
Acero corrugado fy = 4200 kg/cm2 kg 1.0700 4.30 4.60
4.90
Equipo y herramientas
Herramientas manuales %MO 3.0000 1.37 0.04
0.04

Partida 04.02.01 VIGAS DE CIMENTACION F'C = 210 KG/CM2


Rendimiento: 20.00 m3 /día Costo unitario directo por m3 477.05
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0800 16.74 1.34
Operario hh 1.0000 0.8000 15.22 12.18
Oficial hh 1.0000 0.8000 13.97 11.18
Peon hh 6.0000 4.8000 12.46 59.81
84.51
Materiales
Piedra Cancada de 1/2" - 3/4" m3 0.8000 120.36 96.29
Arena gruesa m3 0.5500 86.14 47.38
Cemento tipo MS BOL 9.7400 23.50 228.89
Agua m3 0.1840 10.00 1.84
374.40
Equipo y herramientas
Herramientas manuales %MO 3.0000 84.51 2.54
Vibrador de concreto 4 HP 2.40" hm 0.3000 0.2400 15.00 3.60
Mescladora concreto tambor 18 HP 11P3 hm 0.5000 0.4000 30.00 12.00
18.14

Partida 04.02.02 VIGAS DE CIMENTACION - ACERO FY = 4200 KG/CM2


Rendimiento: 180.00 kg /día Costo unitario directo por m2 6.31
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0044 16.74 0.07
Operario hh 1.0000 0.0444 15.22 0.68
Peon hh 1.0000 0.0444 13.97 0.62
1.37
Materiales
Alambre negro N°16 kg 0.0600 5.00 0.30
Acero corrugado fy = 4200 kg/cm2 kg 1.0700 4.30 4.60
4.90
Equipo y herramientas
Herramientas manuales %MO 3.0000 1.37 0.04
0.04

Partida 04.03.01 COLUMNAS F'C = 210 KG/CM2


Rendimiento: 10.00 m3 /día Costo unitario directo por m3 554.04
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0800 16.74 1.34
Operario hh 2.0000 1.6000 15.22 24.35
Oficial hh 1.0000 0.8000 13.97 11.18
Peon hh 12.0000 9.6000 12.46 119.62
156.49
Materiales
Piedra Cancada de 1/2" - 3/4" m3 0.8000 120.36 96.29
Arena gruesa m3 0.5500 86.14 47.38
Cemento tipo I BOL 9.7400 22.50 219.15
Agua m3 0.1840 10.00 1.84
364.66
Equipo y herramientas
Herramientas manuales %MO 3.0000 156.49 4.69
Vibrador de concreto 4 HP 2.40" hm 0.3500 0.2800 15.00 4.20
Mescladora concreto tambor 18 HP 11P3 hm 1.0000 0.8000 30.00 24.00
32.89

Partida 04.03.02 COLUMNAS - ACERO FY = 4200 KG/CM2


Rendimiento: 150.00 kg /día Costo unitario directo por m2 6.59
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0053 16.74 0.09
Operario hh 1.0000 0.0533 15.22 0.81
Peon hh 1.0000 0.0533 13.97 0.74
1.64
Materiales
Alambre negro N°16 kg 0.0600 5.00 0.30
Acero corrugado fy = 4200 kg/cm2 kg 1.0700 4.30 4.60
4.90
Equipo y herramientas
Herramientas manuales %MO 3.0000 1.64 0.05
0.05

Partida 04.04.01 VIGAS F'C = 210 KG/CM2


Rendimiento: 10.00 m3 /día Costo unitario directo por m3 505.27
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0800 16.74 1.34
Operario hh 2.0000 1.6000 15.22 24.35
Oficial hh 1.0000 0.8000 13.97 11.18
Peon hh 8.0000 6.4000 12.46 79.74
116.61
Materiales
Piedra Cancada de 1/2" - 3/4" m3 0.8000 120.36 96.29
Arena gruesa m3 0.6000 86.14 51.68
Cemento tipo I BOL 9.7400 22.50 219.15
Agua m3 0.1840 10.00 1.84
368.96
Equipo y herramientas
Herramientas manuales %MO 3.0000 116.61 3.50
Vibrador de concreto 4 HP 2.40" hm 0.3500 0.2800 15.00 4.20
Mescladora concreto tambor 18 HP 11P3 hm 0.5000 0.4000 30.00 12.00
19.70

Partida 04.04.02 VIGAS - ACERO FY = 4200 KG/CM2


Rendimiento: 180.00 kg /día Costo unitario directo por m2 6.31
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0044 16.74 0.07
Operario hh 1.0000 0.0444 15.22 0.68
Peon hh 1.0000 0.0444 13.97 0.62
1.37
Materiales
Alambre negro N°16 kg 0.0600 5.00 0.30
Acero corrugado fy = 4200 kg/cm2 kg 1.0700 4.30 4.60
4.90
Equipo y herramientas
Herramientas manuales %MO 3.0000 1.37 0.04
0.04

Partida 04.05.01 LOSAS ALIGERADAS F'C = 210 KG/CM2


Rendimiento: 12.00 m3 /día Costo unitario directo por m3 496.14
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.2000 0.1333 16.74 2.23
Operario hh 3.0000 2.0000 15.22 30.44
Oficial hh 1.0000 0.6667 13.97 9.31
Peon hh 8.0000 5.3333 12.46 66.45
108.43
Materiales
Piedra Cancada de 1/2" - 3/4" m3 0.8000 120.36 96.29
Arena gruesa m3 0.6000 86.14 51.68
Cemento tipo I BOL 9.7400 22.50 219.15
Agua m3 0.1840 10.00 1.84
368.96
Equipo y herramientas
Herramientas manuales %MO 3.0000 108.43 3.25
Vibrador de concreto 4 HP 2.40" hm 0.3500 0.2333 15.00 3.50
Mescladora concreto tambor 18 HP 11P3 hm 0.5000 0.4000 30.00 12.00
18.75

Partida 04.05.02 LOSAS ALIGERADAS - ACERO FY = 4200 KG/CM2


Rendimiento: 180.00 kg /día Costo unitario directo por m2 6.31
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0044 16.74 0.07
Operario hh 1.0000 0.0444 15.22 0.68
Peon hh 1.0000 0.0444 13.97 0.62
1.37
Materiales
Alambre negro N°16 kg 0.0600 5.00 0.30
Acero corrugado fy = 4200 kg/cm2 kg 1.0700 4.30 4.60
4.90
Equipo y herramientas
Herramientas manuales %MO 3.0000 1.37 0.04
0.04

Partida 04.05.03 LOSAS ALIGERADAS LADRILLO HUECO 15x30x30 cm


Rendimiento: 1600.00 und /día Costo unitario directo por m3 3.43
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0005 16.74 0.01
Operario hh 1.0000 0.0050 15.22 0.08
Oficial hh 1.0000 0.0050 13.97 0.07
Peon hh 10.0000 0.0500 12.46 0.62
0.78
Materiales
Ladrillo para techo de 15x30x30 cm 8 hueco und 1.0500 2.50 2.63
2.63
Equipo y herramientas
Herramientas manuales %MO 3.0000 0.78 0.02
0.02

Partida 05.01 MURO DE LADRILLO K.K. ARCILLA 18 HUECOS - CABEZA 9x12.5x23


Rendimiento: 6.45 m2 /día Costo unitario directo por m2 117.54
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.1240 23.50 2.91
Operario hh 1.0000 1.2403 21.10 26.17
Peon hh 0.9000 1.1163 19.70 21.99
51.08
Materiales
Alambre negro N°8 kg 0.2500 4.60 1.15
Clavos con cabeza 2 1/2", 3", 4" kg 0.0220 3.70 0.08
Arena gruesa m3 0.0644 49.90 3.21
Ladrillo k.k. de arcilla 18 huecos 9x12.5x23 unid 68.030 0.63 42.86
Cemento portland tipo MS (42.5kg) BOL 0.4536 22.90 10.39
Agua m3 0.0141 10.00 0.14
Madera tornillo - andamio pie2 0.4030 5.31 2.14
59.97
Equipo y herramientas
Herramientas manuales %MO 3.0000 51.08 1.53
Andamio metalico hm 0.5000 0.6202 8.00 4.96
6.49
Partida 05.02 MURO DE LADRILLO K.K. ARCILLA 18 HUECOS - SOGA 9x12.5x23
Rendimiento: 9.46 m2 /día Costo unitario directo por m2 73.30
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0846 23.50 1.99
Operario hh 1.0000 0.8457 21.10 17.84
Peon hh 0.9000 0.7611 19.70 14.99
34.83
Materiales
Alambre negro N°8 kg 0.2500 4.60 1.15
Clavos con cabeza 2 1/2", 3", 4" kg 0.0220 3.70 0.08
Arena gruesa m3 0.0289 49.90 1.44
Ladrillo k.k. de arcilla 18 huecos 9x12.5x23 unid 38.870 0.63 24.49
Cemento portland tipo MS (42.5kg) BOL 0.2039 22.90 4.67
Agua m3 0.0075 10.00 0.08
Madera tornillo - andamio pie2 0.4030 5.31 2.14
34.05
Equipo y herramientas
Herramientas manuales %MO 3.0000 34.83 1.04
Andamio metalico hm 0.5000 0.4228 8.00 3.38
4.43

Partida 05.03 MURO DE LADRILLO K.K. ARCILLA 18 HUECOS - CANTO 9x12.5x23


Rendimiento: 11.00 m2 /día Costo unitario directo por m2 54.98
Descripción recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de obra
Capataz hh 0.1000 0.0727 23.50 1.71
Operario hh 1.0000 0.7273 21.10 15.35
Peon hh 0.9000 0.6545 19.70 12.89
29.95
Materiales
Clavos con cabeza 2 1/2", 3", 4" kg 0.0220 3.70 0.08
Arena gruesa m3 0.0166 49.90 0.83
Ladrillo k.k. de arcilla 18 huecos 9x12.5x23 unid 29.150 0.63 18.36
Cemento portland tipo MS (42.5kg) BOL 0.1171 22.90 2.68
Agua m3 0.0039 10.00 0.04
Madera tornillo - andamio pie2 0.4030 5.31 2.14
24.13
Equipo y herramientas
Herramientas manuales %MO 3.0000 29.95 0.90
0.90
METRADOS

01 TRABAJOS PRELIMINARES

01.01 LIMPIEZA DE TERRENO MANUAL


7.00 m x 20.00 m = 140.00 m2

01.02 TRAZO NIVELACION Y REPLANTEO


Decripcion n° veces Largo (m) Acncho (m) Unidad (m2)Parcial (m2)
Cimientos
Seccion 1-1, 2-2, 3-3, 4-4, 5-5, 6-6, 9- 1 26.27 0.50 13.14
9, 10-10
Seccion 7-7, 8-8 1 19.88 0.40 7.95
Seccion 11-11, 12-12, 13-13, 14-14,
1 7.73 0.60 4.64
16-16, 17-17
Zapatas 54.78
Z-1 (1.20 x 1.20) 5 1.20 1.20 7.20
Z-2 (1.30 x 1.30) 8 1.30 1.30 13.52
Z-3 (1.90 x 1.20) 1 1.90 1.20 2.28
Z-4 (2.50 x 1.30) 1 2.50 1.30 3.25
Z-5 (1.50 x 1.20) 1 1.50 1.20 1.80
Z-6 (1.00 x 1.00) 1 1.00 1.00 1.00

02 MOVIMIENTO DE TIERRAS

02.02 EXCAVACION MANUAL PARA ZAPATAS


Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
Z-1 (1.20 x 1.20) 5 - 1.20 1.20 1.00 7.20
Z-2 (1.30 x 1.30) 8 - 1.30 1.30 1.00 13.52
Z-3 (1.90 x 1.20) 1 - 1.90 1.20 1.00 2.28
29.05
Z-4 (2.50 x 1.30) 1 - 2.50 1.30 1.00 3.25
Z-5 (1.50 x 1.20) 1 - 1.50 1.20 1.00 1.80
Z-6 (1.00 x 1.00) 1 - 1.00 1.00 1.00 1.00

02.02 EXCAVACION MANUAL PARA CIMIENTOS


Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
Seccion 1-1, 2-2, 3-3, 4-4, 5-5, 6-6, 9- 1 - 26.27 0.50 0.85 11.16
9, 10-10
Seccion 7-7, 8-8 1 - 19.88 0.40 0.85 6.76 21.86
Seccion 11-11, 12-12, 13-13, 14-14,
1 - 7.73 0.60 0.85 3.94
16-16, 17-17

03 OBRAS DE CONCRETO SIMPLE


03.01 SOLADO CH, 1:12
Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
Z-1 (1.20 x 1.20) 5 - 1.20 1.20 0.05 0.36
Z-2 (1.30 x 1.30) 8 - 1.30 1.30 0.05 0.68
Z-3 (1.90 x 1.20) 1 - 1.90 1.20 0.05 0.11
1.45
Z-4 (2.50 x 1.30) 1 - 2.50 1.30 0.05 0.16
Z-5 (1.50 x 1.20) 1 - 1.50 1.20 0.05 0.09
Z-6 (1.00 x 1.00) 1 - 1.00 1.00 0.05 0.05

03.02 CIMIENTO CORRIDO 1:10 + 20% P.G 6"


Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
Seccion 1-1, 2-2, 3-3, 4-4, 5-5, 6-6, 9- 1 - 26.27 0.50 0.70 9.19
9, 10-10
Seccion 7-7, 8-8 1 - 19.88 0.40 0.60 4.77 17.21
Seccion 11-11, 12-12, 13-13, 14-14,
1 - 7.73 0.60 0.70 3.25
16-16, 17-17
17.21
Seccion 11-11, 12-12, 13-13, 14-14,
1 - 7.73 0.60 0.70 3.25
16-16, 17-17

04 OBRAS DE CONCRETO ARMADO


04.01 ZAPATAS

04.01.01 ZAPATAS - CONCRETO F'C = 210 KG/CM2


Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
Z-1 (1.20 x 1.20) 5 - 1.20 1.20 0.50 3.60
Z-2 (1.30 x 1.30) 8 - 1.30 1.30 0.50 6.76
Z-3 (1.90 x 1.20) 1 - 1.90 1.20 0.50 1.14
14.53
Z-4 (2.50 x 1.30) 1 - 2.50 1.30 0.50 1.63
Z-5 (1.50 x 1.20) 1 - 1.50 1.20 0.50 0.90
Z-6 (1.00 x 1.00) 1 - 1.00 1.00 0.50 0.50

04.01.02 ZAPATAS - ACERO FY = 4200 KG/CM2


L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/2"
Z-1 (1.20 x 1.20)
(L: 1.20)
a) L° elementos
1.20 - 0.02 - 0.02 = 1.16
1.16/0.20 = 5.80 ½” 10 5.80 1.16 67.28 67.63
b) L. elemento
1.20 - 0.02 - 0.02 = 1.16

Z-2 (1.30 x 1.30)


(L: 1.30)
a) N° elementos
1.30 - 0.02 - 0.02 = 1.26
1.26/0.20 = 6.30 ½” 16 6.30 1.26 127.00 129.54
b) L. elemento
1.30 - 0.02 - 0.02 = 1.26

Z-3 (1.90 x 1.20)


(L: 1.90)
a) N° elementos
1.90 - 0.02 - 0.02 = 1.86
1.86/0.20 = 9.30 ½” 1 9.30 1.16 10.79 11.00
b) L. elemento
1.20 - 0.02 - 0.02 = 1.16
(L: 1.20)
a) N° elementos
1.20 - 0.02 - 0.02 = 1.16
1.16/0.20 = 5.80
b) L. elemento
½” 1 5.80 1.86 10.79 11.00
1.90 - 0.02 - 0.02 = 1.86

Z-4 (2.50 x 1.30)


(L: 2.50)
a) N° elementos
2.50 - 0.02 - 0.02 = 2.46
½” 1 12.30 1.26 15.50 15.81
2.46/0.20 = 12.30
b) L. elemento
1.30 - 0.02 - 0.02 = 1.26
(L: 1.30)
a) N° elementos
1.30 - 0.02 - 0.02 = 1.26
1.26/0.20 = 6.30
b) L. elemento
(L: 2.50)
a) N° elementos
2.50 - 0.02 - 0.02 = 2.46
½” 1 12.30 1.26 15.50 15.81
2.46/0.20 = 12.30
b) L. elemento
1.30 - 0.02 - 0.02 = 1.26
(L: 1.30)
a) N° elementos
1.30 - 0.02 - 0.02 = 1.26
1.26/0.20 = 6.30
b) L. elemento
½” 1 6.30 2.46 15.50 15.81
2.50 - 0.02 - 0.02 = 2.46

Z-5 (1.50 x 1.20)


(L: 2.50)
a) N° elementos
1.50 - 0.02 - 0.02 = 1.46
1.46/0.20 = 7.20 ½” 1 7.20 1.16 8.35 8.52
b) L. elemento
1.20 - 0.02 - 0.02 = 1.16
(L: 1.30)
a) N° elementos
1.20 - 0.02 - 0.02 = 1.16
1.16/0.20 = 5.80
b) L. elemento
1.50 - 0.02 - 0.02 = 1.46 ½” 1 5.80 1.46 8.47 8.64

Z-6 (1.00 x 1.00)


(L: 1.00)
a) N° elementos
1.00 - 0.02 - 0.02 = 0.96
0.96/0.20 = 4.80 ½” 2 4.80 0.96 9.22 9.48
b) L. elemento
1.00 - 0.02 - 0.02 = 0.96

277.43

04.02 VIGAS DE CIMENTACION


04.02.01 VIGAS DE CIMENTACION - CONCRETO F'C = 210 KG/CM2
Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
VC-1 (30 x 15)
Eje C-C/2-2 y 7-7 1 - 14.21 0.15 0.30 0.64

VC-1 (30 x 15)


Eje B’-B’/6’-6’ y 7-7 1 - 2.50 0.15 0.30 0.11

VC-1 (30 x 15)


Eje B-B/2-2 y 4-4 1 - 6.81 0.15 0.30 0.31

VC-1 (30 x 15)


Eje A’-A’/3-3 y 6-6 1 - 7.00 0.15 0.30 0.32

VC-1 (30 x 15)


Eje A-A/2-2 y 3-3 1 - 3.66 0.15 0.30 0.16
3.51
VC-2 (30 x 25)
Eje 2-2 1 - 6.25 0.25 0.30 0.47

VC-2 (30 x 25)


Eje 3-3 1 - 6.00 0.25 0.30 0.45

VC-2 (30 x 25)


Eje 6-6 1 - 6.05 0.25 0.30 0.45

VC-2 (30 x 25)


Eje 4-4/A’-A’ y C-C 1 - 5.10 0.25 0.30 0.38

VC-2 (30 x 25)


Eje 7-7/B’-B’ y C-C 1 - 2.90 0.25 0.30 0.22

04.02.02 VIGAS DE CIMENTACION - ACERO FY = 4200 KG/CM2


L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/2"
Fierros Principales
VC-1 (30 x 15)
Eje C-C/2-2 y 7-7 ½” 1 4 16.17 64.68 65.97
VC-1 (30 x 15)
Eje B’-B’/6’-6’ y 7-7 ½” 1 4 3.11 12.44 12.70
VC-1 (30 x 15)
Eje B-B/2-2 y 4-4 ½” 1 4 7.52 30.08 30.68
VC-1 (30 x 15)
Eje A’-A’/3-3 y 6-6 ½” 1 4 7.96 31.84 32.48
VC-1 (30 x 15)
Eje A-A/2-2 y 3-3 ½” 1 4 4.12 16.48 16.81
VC-2 (30 x 25)
Eje 2-2 ½” 1 4 6.96 27.84 28.40
VC-2 (30 x 25)
Eje 3-3 ½” 1 4 6.96 27.84 28.40
VC-2 (30 x 25)
Eje 6-6 ½” 1 4 6.96 27.84 28.40
VC-2 (30 x 25)
Eje 4-4/A’-A’ y C-C ½” 1 4 5.81 23.24 23.70
VC-2 (30 x 25)
Eje 7-7/B’-B’ y C-C ½” 1 4 3.36 13.44 13.71

L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/4"
Estribos
VC-1 (30 x 15)
Eje C-C/2-2 y 7-7
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30 ¼” 1 25.44 0.89 22.64 5.66
3.66 – 1.30 = 2.36/0.25 =9.44
E = 9.44 + 6 + 10 = 25.44
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 3.15)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.15 – 1.30 = 1.85/0.25 =7.40
E = 7.40+ 6 + 10 = 23.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11 ¼” 1 23.40 0.89 20.83 5.21
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 2.20)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.20 – 1.30 = 0.90/0.25 = 3.60
E = 3.60 + 6 + 10 = 19.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 1.65) ¼” 1 19.60 0.80 17.44 4.36
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
E = 3.60 + 6 + 10 = 19.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 1.65) ¼” 1 19.60 0.80 17.44 4.36
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
1.65 – 1.30 = 0.35/0.25 = 1.40
E = 1.40+ 6 + 10 = 17.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L:3.55)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00 ¼” 1 17.40 0.89 15.49 3.87
1.30
3.55 – 1.30 = 2.25/0.25 =9.00
E = 9.00+ 6 + 10 = 25.00
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89

¼” 1 25.00 0.89 22.25 5.56

VC-1 (30 x 15)


Eje B’-B’/6’-6’ y 7-7
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 2.50)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.50 – 1.30 = 1.20/0.25 =4.80 ¼” 1 20.80 0.89 18.51 4.63
E = 4.80 + 6 + 10 = 20.80
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89

VC-1 (30 x 15)


Eje B-B/2-2 y 4-4
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.66 – 1.30 = 2.36/0.25 =9.44 ¼” 1 25.44 0.89 22.64 5.66
E = 9.44 + 6 + 10 = 25.44
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 3.15)
a) N° elementos
5@.10 = 10 : 1.00
1.30
3.66 – 1.30 = 2.36/0.25 =9.44 ¼” 1 25.44 0.89 22.64 5.66
E = 9.44 + 6 + 10 = 25.44
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 3.15)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.15 – 1.30 = 1.85/0.25 =7.40
E = 7.40+ 6 + 10 = 23.40
b) L. elemento
L=0.89
¼” 1 23.40 0.89 20.83 5.21

VC-1 (30 x 15)


Eje A’-A’/3-3 y 6-6
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.15)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.15 – 1.30 = 1.85/0.25 =7.40 ¼” 1 23.40 0.89 20.83 5.21
E = 7.40+ 6 + 10 = 23.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
(L: 2.20)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.20 – 1.30 = 0.90/0.25 = 3.60
E = 3.60 + 6 + 10 = 19.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15 ¼” 1 19.60 0.80 17.44 4.36
L=0.89
(L: 1.65)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
1.65 – 1.30 = 0.35/0.25 = 1.40
E = 1.40+ 6 + 10 = 17.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89
¼” 1 17.40 0.89 15.49 3.87

VC-1 (30 x 15)


Eje A-A/2-2 y 3-3
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
3@.05 = 6 : 0.30
VC-1 (30 x 15)
Eje A-A/2-2 y 3-3
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.66 – 1.30 = 2.36/0.25 =9.44 ¼” 1 25.44 0.89 22.64 5.66
E = 9.44 + 6 + 10 = 25.44
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.15 – 0.02 – 0.02 = 0.11
L=0.26+0.26+0.11+0.11+0.15
L=0.89

VC-2 (30 x 25)


Eje 2-2
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30 ¼” 1 24.60 1.09 26.81 6.70
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15
L=1.09
(L: 2.80)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.80 – 1.30 = 1.50/0.25 =6.00
E = 6 + 6 + 10 = 22.00
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21 ¼” 1 22.00 1.09 23.98 6.00
L=0.26+0.26+0.21+0.21+0.15
L=1.09

VC-2 (30 x 25)


Eje 3-3
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30 ¼” 1 24.60 1.09 26.81 6.70
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15
L=1.09
(L: 2.80)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.80 – 1.30 = 1.50/0.25 =6.00
E = 6 + 6 + 10 = 22.00
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15
L=1.09
(L: 2.80)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.80 – 1.30 = 1.50/0.25 =6.00
E = 6 + 6 + 10 = 22.00
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21 ¼” 1 22.00 1.09 23.98 6.00
L=0.26+0.26+0.21+0.21+0.15 L=1.09

VC-2 (30 x 25)


Eje 6-6
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
¼” 1 24.60 1.09 26.81 6.70
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15
L=1.09
(L: 1.65)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
1.65 – 1.30 = 0.35/0.25 =1.40
E = 1.40 + 6 + 10 = 17.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15 ¼” 1 17.40 1.09 18.97 4.74
L=1.09

VC-2 (30 x 25)


Eje 4-4/A’-A’ y C-C
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 4.50)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00 ¼” 1 28.80 1.09 31.40 7.85
1.30
4.50 – 1.30 = 3.20/0.25 =12.80
E = 12.80 + 6 + 10 = 28.80
b) L. elemento
L=1.09
(L: 1.70)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
1.70 – 1.30 = 0.40/0.25 =1.60
E = 1.60 + 6 + 10 = 17.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21 ¼” 1 17.60 1.09 19.18 4.80
(L: 1.70)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
1.70 – 1.30 = 0.40/0.25 =1.60
E = 1.60 + 6 + 10 = 17.60
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21 ¼” 1 17.60 1.09 19.18 4.80
L=0.26+0.26+0.21+0.21+0.15
L=1.09

VC-2 (30 x 25)


Eje 7-7/B’-B’ y C-C
Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 2.90)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
2.90 – 1.30 = 1.60/0.25 =6.40 ¼” 1 22.4 1.09 24.42 6.11
E = 6.40 + 6 + 10 = 22.40
b) L. elemento
0.30 – 0.02 – 0.02 = 0.26
0.25 – 0.02 – 0.02 = 0.21
L=0.26+0.26+0.21+0.21+0.15
L=1.09

396.11

04.03 COLUMNAS
04.03.01 COLUMNAS - CONCRETO F'C = 210 KG/CM2
Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
C-1 (25 x 25) 10 - 0.25 0.25 3.45 2.16
C-2 (25 x 25) 8 - 0.25 0.25 3.45 1.70
C-3 (50 x 25) 2 - 0.50 0.25 3.45 0.86
10.40
C-4 (30 x 25) 1 - 0.30 0.25 3.45 0.26
C-5 (40 x 15) 1 - 0.40 0.15 3.45 4.00
C-6 (25 x 15) 11 - 0.25 0.15 3.45 1.42

04.03.02 COLUMNAS - ACERO FY = 4200 KG/CM2


L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
3/8" 1/2" 5/8"
Fierros principales
C-1 (25 x 25) 5/8" 10 4 5.10 240.00 316.20
C-2 (25 x 25) 1/2" 8 4 5.00 160.00 163.20
5/8" 2 44 5.10 40.80 63.24
C-3 (50 x 25)
1/2" 2 4 5.00 40.00 40.80
C-4 (30 x 25) 1/2" 1 6 5.00 30.00 30.06
C-5 (40 x 15) 1/2" 1 6 5.00 30.00 30.06
C-6 (25 x 15) 3/8" 11 4 4.00 176.00 98.56

L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/4" 3/8"
Estribos
C-1 (25 x 25)
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.45 – 1.10 = 2.35/0.25 =9.40
3/8" 10 21.40 0.91 194.74 109.05
E = 9.40 + 2 + 10 = 21.40
b) L. elemento
0.25 – 0.02 – 0.02 = 0.19
0.25 – 0.02 – 0.02 = 0.19
L=0.19+0.19+0.19+0.19+0.15
L=0.91

C-2 (25 x 25)


Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60 1/4" 8 24.60 0.91 179.09 44.77
b) L. elemento
0.25 – 0.02 – 0.02 = 0.19
0.25 – 0.02 – 0.02 = 0.19
L=0.19+0.19+0.19+0.19+0.15
L=0.91

C-3 (50 x 25)


Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.45 – 1.10 = 2.35/0.25 =9.40
E = 9.40 + 2 + 10 = 21.40 3/8" 2 21.40 1.41 60.35 33.79
b) L. elemento
0.50 – 0.03 – 0.03 = 0.44
0.25 – 0.03 – 0.03 = 0.19
L=0.44+0.44+0.19+0.19+0.15
L=1.41

C-4 (30 x 25)


Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60 1/4" 1 24.60 1.01 24.85 6.21
b) L. elemento
0.30 – 0.03 – 0.03 = 0.24
0.25 – 0.03 – 0.03 = 0.19
L=0.24+0.24+0.19+0.19+0.15
L=1.01
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60 1/4" 1 24.60 1.01 24.85 6.21
b) L. elemento
0.30 – 0.03 – 0.03 = 0.24
0.25 – 0.03 – 0.03 = 0.19
L=0.24+0.24+0.19+0.19+0.15
L=1.01

C-5 (40 x 15)


Ø1/4”
3@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
3@.05 = 6 : 0.30
5@.10 = 10 : 1.00
1.30
3.45 – 1.30 = 2.15/0.25 =8.60
E = 8.60 + 6 + 10 = 24.60 1/4" 1 24.60 1.01 24.85 6.21
b) L. elemento
0.40 – 0.03 – 0.03 = 0.34
0.15 – 0.03 – 0.03 = 0.09
L=0.34+0.34+0.09+0.09+0.15
L=1.01

C-6 (25 x 15)


Ø1/4”
1@.05, 5@.10, Rto.@.25
(L: 3.45)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.45 – 1.10 = 2.35/0.25 =9.40
E = 9.40 + 2 + 10 = 21.40 1/4" 11 21.40 0.71 167.13 41.78
b) L. elemento
0.25 – 0.03 – 0.03 = 0.19
0.15 – 0.03 – 0.03 = 0.09
L=0.19+0.19+0.09+0.09+0.15
L=0.71

983.93

04.04 VIGAS
04.04.01 VIGAS - CONCRETO F'C = 210 KG/CM2
Descripcion n° veces n° elem. Largo (m) Ancho (m) Alto (m) Unidad (m3)Parcial (m3)
VP – 101 – 201
(25 x 30) 2 - 7.00 0.25 0.30 1.05

VP – 102 – 202
(25 x 30) 4 - 7.00 0.25 0.30 2.10

VP – 103 – 203 2 - 5.85 0.25 0.50 1.47


(25 x 50) 2 - 1.15 0.25 0.30 0.18
VP – 104 – 204 2 - 5.05 0.25 0.50 1.27
(25 x 50) 2 - 1.95 0.25 0.30 0.30
VP – 105 – 205
(25 x 30) 2 - 3.45 0.25 0.30 0.52

VS – 101 – 201
(25 x 20) eje C-C/2-2 y 7-7 2 - 14.21 0.25 0.20 1.42 10.59

VS – 101 – 201
(25 x 20) eje B–B/2-2 y 4-4 2 - 6.81 0.25 0.20 0.68

VS – 101 – 201
(25 x 20) eje A’–A'/3-3 y 6-6 2 - 7.00 0.25 0.20 0.70
10.59

VS – 101 – 201
(25 x 20) eje A’–A'/3-3 y 6-6 2 - 7.00 0.25 0.20 0.70

VS – 101 – 201
(25 x 20) eje A–A/5-5 y 6-6 2 - 1.65 0.25 0.20 0.17

VS – 101 – 201
(25 x 20) eje A–A/2-2 y 3-3 2 - 3.66 0.25 0.20 0.37

VS – 101 – 201
(25 x 20) eje B’–B’/6-6 y 7-7 2 - 3.55 0.25 0.20 0.36

04.04.02 VIGAS - ACERO FY = 4200 KG/CM2


L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/2" 5/8"
Fierros principales
1/2" 2 2 7.42 29.68 30.27
1/2" 2 2 1.47 5.88 6.00
VP – 101 – 201 5/8" 2 2 2.35 9.40 14.57
(25 x 30) 1/2" 2 2 1.26 5.04 5.14
1/2" 2 2 1.40 5.60 5.71
1/2" 2 2 1.65 6.60 6.73
5/8" 2 2 7.42 29.68 46.00
1/2" 4 2 7.42 59.36 60.55
VP – 102 – 202 5/8" 4 2 2.35 18.80 29.14
(25 x 30) 1/2" 4 2 1.47 11.76 12.00
1/2" 4 2 1.65 13.20 13.46
5/8" 4 2 7.42 59.36 92.01
5/8" 2 2 7.42 29.68 46.00
VP – 103 – 203 1/2" 2 1 7.42 14.84 15.14
(25 x 50) 1/2" 2 2 2.86 11.44 11.67
1/2" 2 2 2.85 11.40 11.63
5/8" 2 2 6.27 25.08 38.87
5/8" 2 2 7.42 29.68 46.00
VP – 104 – 204 1/2" 2 1 7.42 14.84 15.14
(25 x 50) 1/2" 2 3 3.66 21.96 22.40
1/2" 2 2 2.30 9.20 9.38
5/8" 2 2 5.47 21.88 33.91
1/2" 2 2 3.87 15.48 15.79
VP – 105 – 205 1/2" 2 2 1.51 6.04 6.16
(25 x 30) 1/2" 2 2 1.46 5.84 5.96
1/2" 2 2 1.70 6.80 6.94
5/8" 2 2 3.87 15.48 24.00

L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
3/8" 1/2"
VS – 101 – 201 1/2" 2 4 16.13 129.04 131.62
(25 x 20) eje C-C/2-2 y 7-7 3/8" 2 1 16.03 32.06 17.95
VS – 101 – 201 1/2" 2 4 7.48 59.84 61.04
(25 x 20) eje B–B/2-2 y 4-4 3/8" 2 1 7.48 14.96 8.38
VS – 101 – 201 1/2" 2 4 7.92 63.36 64.63
(25 x 20) eje A’–A'/3-3 y 6-6 3/8" 2 1 7.92 15.84 8.87
VS – 101 – 201 1/2" 2 4 1.99 15.92 16.24
(25 x 20) eje A–A/5-5 y 6-6 3/8" 2 1 1.99 3.98 2.23
VS – 101 – 201 1/2" 2 4 4.08 32.64 39.17
(25 x 20) eje A–A/2-2 y 3-3 3/8" 2 1 4.08 8.16 4.57
VS – 101 – 201 1/2" 2 4 3.97 31.76 32.40
(25 x 20) eje B’–B’/6-6 y 7-7 3/8" 2 1 3.97 7.94 4.45
L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
3/8"
Estribos
VP – 101 – 201 (25 x 30)
Ø3/8”
1@.05, 4@.10, 3@.15, Rto.@.25
(L: 3.45)
a) N° elementos
1@.05 = 2 : 0.10
4@.10 = 8 : 0.80
3@.15 = 6 : 0.90
1.80
3.45 – 1.80 = 1.65/0.25 =6.60 3/8" 2 22.60 0.93 42.04 23.54
E = 6.60 + 2 + 8 + 6 = 22.60
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15
L=0.93
(L: 2.80)
a) N° elementos
1@.05 = 2 : 0.10
4@.10 = 8 : 0.80
3@.15 = 6 : 0.90
1.80
2.80 – 1.80 = 1.00/0.25 = 4
E = 4 + 2 + 8 + 6 = 18
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
3/8" 2 18.00 0.93 33.48 18.75
L=0.22+0.22+0.17+0.17+0.15
L=0.93

VP – 102 – 202 (25 x 30)


Ø3/8”
1@.05, 4@.10, 3@.15, Rto.@.25
(L: 3.45)
a) N° elementos
1@.05 = 2 : 0.10
4@.10 = 8 : 0.80
3@.15 = 6 : 0.90
1.80
3.45 – 1.80 = 1.65/0.25 =6.60 3/8" 4 22.60 0.93 84.07 47.08
E = 6.60 + 2 + 8 + 6 = 22.60
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15
L=0.93
(L: 1.65)
a) N° elementos
1@.05 = 1 : 0.05
4@.10 = 4 : 0.10
3@.15 = 3 : 0.15
0.30
1.65 – 0.30 = 1.35/0.25 = 5.40
E = 5.40 + 1 + 4 + 3 = 13.40
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
3/8" 4 13.40 0.93 49.85 27.91
L=0.22+0.22+0.17+0.17+0.15
L=0.93
(L: 0.90)
a) N° elementos
1@.05 = 1 : 0.05
4@.10 = 4 : 0.10
1.65 – 0.30 = 1.35/0.25 = 5.40
E = 5.40 + 1 + 4 + 3 = 13.40
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
3/8" 4 13.40 0.93 49.85 27.91
L=0.22+0.22+0.17+0.17+0.15
L=0.93
(L: 0.90)
a) N° elementos
1@.05 = 1 : 0.05
4@.10 = 4 : 0.10
3@.15 = 3 : 0.15
0.30
0.90 – 0.30 = 0.60/0.25 = 2.40
E = 2.40 + 1 + 4 + 3 = 10.40
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15
L=0.93
3/8" 4 10.40 0.93 38.69 21.67

VP – 103 – 203 (25 x 50)


Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 4.85)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
4.85 – 1.10 = 3.38/0.25 =13.52
3/8" 2 25.52 1.33 67.88 38.01
E = 13.52 + 2 + 10 = 25.52
b) L. elemento
0.50 – 0.04 – 0.04 = 0.42
0.25 – 0.04 – 0.04 = 0.17
L=0.42+0.42+0.17+0.17+0.15
L=1.33
(L: 0.90)
a) N° elementos
1@.05 = 1 : 0.05
5@.10 = 5 : 0.50
0.55
0.90 – 0.55 = 0.35/0.25 = 1.40
E = 1.40 + 1 + 5 = 7.40
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15 3/8" 2 7.40 0.93 13.76 7.71
L=0.93

VP – 104 – 204 (25 x 50)


Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 4.30)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
4.30 – 1.10 = 3.20/0.25 =12.80 3/8" 2 24.80 1.33 65.97 36.94
E = 12.80+ 2 + 10 = 24.80
b) L. elemento
0.50 – 0.04 – 0.04 = 0.42
0.25 – 0.04 – 0.04 = 0.17
L=0.42+0.42+0.17+0.17+0.15
L=1.33
(L: 1.70)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
4.30 – 1.10 = 3.20/0.25 =12.80 3/8" 2 24.80 1.33 65.97 36.94
E = 12.80+ 2 + 10 = 24.80
b) L. elemento
0.50 – 0.04 – 0.04 = 0.42
0.25 – 0.04 – 0.04 = 0.17
L=0.42+0.42+0.17+0.17+0.15
L=1.33
(L: 1.70)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
1.70 – 01.10= 0.60/0.25 = 2.40
E = 2.40 + 2 + 10 = 14.40
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15 3/8" 2 14.40 0.93 26.78 15.00
L=0.93

VP – 105 – 205 (25 x 30)


Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 2.90)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
2.90 – 1.10 = 1.80/0.25 =7.20
3/8" 2 19.20 0.93 35.71 20.00
E = 7.20+ 2 + 10 = 19.20
b) L. elemento
0.30 – 0.04 – 0.04 = 0.22
0.25 – 0.04 – 0.04 = 0.17
L=0.22+0.22+0.17+0.17+0.15
L=0.93

VS – 101 – 201
(25 x 20) eje C-C/2-2 y 7-7
Ø3/8” 3/8" 2 22.24 0.73 32.47 18.18
1@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.66 – 1.10 = 2.56/0.25 =10.24
E = 10.24+ 2 + 10 = 22.24
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L: 3.15)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00 3/8" 2 20.20 0.73 29.49 16.52
1.10
3.15 – 1.10 = 2.05 /0.25 = 8.20
E = 8.20 + 2 + 10 = 20.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L:2.20)
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00 3/8" 2 20.20 0.73 29.49 16.52
1.10
3.15 – 1.10 = 2.05 /0.25 = 8.20
E = 8.20 + 2 + 10 = 20.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L:2.20)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
2.20 – 1.10 = 1.10/0.25 = 4.40
E = 4.40+ 2 + 10 = 16.40
3/8" 2 16.40 0.73 23.94 13.41
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L: 1.65)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
1.65 – 1.10 = 0.55/0.25 = 2.20
E = 2.20+ 2 + 10 = 14.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15 3/8" 2 14.20 0.73 20.73 11.61
L=0.73
(L: 3.55)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.55 – 1.10 = 2.25/0.25 =9.80
E = 9.80+ 2 + 10 = 21.80
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
3/8" 2 21.80 0.73 31.83 17.82

VS – 101 – 201
(25 x 20) eje B–B/2-2 y 4-4
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.66 – 1.10 = 2.56/0.25 =10.24
3/8" 2 22.24 0.73 32.47 18.18
E = 10.24+ 2 + 10 = 22.24
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L: 3.15)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.15 – 1.10 = 2.05 /0.25 = 8.20
E = 8.20 + 2 + 10 = 20.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
L=0.73
(L: 3.15)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.15 – 1.10 = 2.05 /0.25 = 8.20
E = 8.20 + 2 + 10 = 20.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73 3/8" 2 20.20 0.73 29.49 16.52

VS – 101 – 201
(25 x 20) eje A’–A'/3-3 y 6-6
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.15) 3/8" 2 20.20 0.73 29.49 16.52
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.15 – 1.10 = 2.05 /0.25 = 8.20
E = 8.20 + 2 + 10 = 20.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L:2.20)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
2.20 – 1.10 = 1.10/0.25 = 4.40
E = 4.40+ 2 + 10 = 16.40 3/8" 2 16.40 0.73 23.94 13.41
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73
(L: 1.65)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
1.65 – 1.10 = 0.55/0.25 = 2.20
E = 2.20+ 2 + 10 = 14.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12 3/8" 2 14.20 0.73 20.73 11.61
L=0.12+0.12+0.17+0.17+0.15
L=0.73

VS – 101 – 201
(25 x 20) eje A–A/5-5 y 6-6
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 1.65)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
VS – 101 – 201
(25 x 20) eje A–A/5-5 y 6-6
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 1.65)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
1.65 – 1.10 = 0.55/0.25 = 2.20
3/8" 2 14.20 0.73 20.73 11.61
E = 2.20+ 2 + 10 = 14.20
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73

VS – 101 – 201
(25 x 20) eje A–A/2-2 y 3-3
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.66)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10 3/8" 2 22.24 0.73 32.47 18.18
3.66 – 1.10 = 2.56/0.25 =10.24
E = 10.24+ 2 + 10 = 22.24
b) L. elemento
L=0.73

VS – 101 – 201
(25 x 20) eje B’–B’/6-6 y 7-7
Ø3/8”
1@.05, 5@.10, Rto.@.25
(L: 3.55)
a) N° elementos
1@.05 = 2 : 0.10
5@.10 = 10 : 1.00
1.10
3.55 – 1.10 = 2.25/0.25 =9.80
3/8" 2 21.80 0.73 31.83 17.82
E = 9.80+ 2 + 10 = 21.80
b) L. elemento
0.25 – 0.04 – 0.04 = 0.17
0.20 – 0.04 – 0.04 = 0.12
L=0.12+0.12+0.17+0.17+0.15
L=0.73

1480.11

04.05 LOSAS ALIGERADAS


04.05.01 LOSAS ALIGERADAS - CONCRETO F'C = 210 KG/CM2
Primero, segundo y tercer Piso
“Paño 1”
v Longitud para determinar la cantidad de vigetas
2.50 – 0.25 = 2.25
1 ml = 2.5 vigetas
2.25 ml = x
x = 5.63 vigetas
v Calculo de la longitud de vigetas
1.90 + 3.80 – 0.125 – 0.125 – 0.25 = 5.20 m
- ) Volumen de vigetas
LxAx H
5.20 x 0.10 x 0.15 = 0.078 m3
- ) Volumen de vigetas
0.078 x 5.63 = 0.44 m3
- ) Volumen total de vigetas
0.44 m3 x 3 = 1,32 m3

“Paño 2”
v Longitud para determinar la cantidad de vigetas
2.50 – 0.25 = 2.25
1 ml = 2.5 vigetas
2.25 ml = x
x = 5.63 vigetas
v Calculo de la longitud de vigetas
3.91 + 3.40 - 0.125 – 0.125 – 0.25 = 6.81
- ) Volumen de vigetas
LxAx H
6.81 x 0.10 x 0.15 = 0.10m3
- ) Volumen de vigetas
0.10 x 5.63 = 0.56 m3
- ) Volumen total de vigetas
0.56 m3 x 3 = 1.68 m3

“Paño 3”
v Longitud para determinar la cantidad de vigetas
0.65
1 ml = 2.5 vigetas
0.65 ml = x
x = 1.63 vigetas
v Calculo de la longitud de vigetas
3.91+3.40+2.45+1.90+3.80-0.125–0.125–0.25–0.25–0.25-0.25 = 14.21 m
- ) Volumen de vigetas
LxAx H
14.21 x 0.10 x 0.15 = 0.21 m3
- ) Volumen de vigetas
0.21 x 1.63 = 0.35 m3
- ) Volumen total de vigetas
0.35 m3 x 2 = 1,05 m3

“Paño 4”
v Longitud para determinar la cantidad de vigetas
0.55
1 ml = 2.5 vigetas
0.55 ml = x
x = 1.38 vigetas
v Calculo de la longitud de vigetas
3.91+3.40+2.45+1.90-0.125–0.125–0.25–0.25–0.25 = 10.66 m
- ) Volumen de vigetas
LxAx H
10.66 x 0.10 x 0.15 = 0.16 m3
- ) Volumen de vigetas
0.16 x 1.38 = 0.22 m3
- ) Volumen total de vigetas
0.22 m3 x 3 = 0,66 m3

“Paño 5”
v Longitud para determinar la cantidad de vigetas
1.9
1 ml = 2.5 vigetas
1.90 ml = x
x = 4.75 vigetas
v Calculo de la longitud de vigetas
2.45 + 1.90 - 0.125 - 0.125 - 0.25 = 3.85 m
- ) Volumen de vigetas
LxAx H
3.85 x 0.10 x 0.15 = 0.058 m3
- ) Volumen de vigetas
0.058 x 4.75 = 0.28 m3
- ) Volumen total de vigetas
0.28 m3 x 3 = 0,84 m3

“Paño 6”
v Longitud para determinar la cantidad de vigetas
2.8
1 ml = 2.5 vigetas
2.80 ml = x
x = 7.00 vigetas
v Calculo de la longitud de vigetas
3.91 - 0.125 - 0.125 = 3.66 m
- ) Volumen de vigetas
LxAx H
3.66 x 0.10 x 0.15 = 0.055 m3
- ) Volumen de vigetas
0.055 x 7.00 = 0.39 m3
- ) Volumen total de vigetas
0.39 m3 x 3 = 1,17 m3

“Paño 7”
v Longitud para determinar la cantidad de vigetas
0.9
1 ml = 2.5 vigetas
0.90 ml = x
x = 2.25 vigetas
v Calculo de la longitud de vigetas
1.90 - 0.125 - 0.125 = 1.65 m
- ) Volumen de vigetas
LxAx H
1.65 x 0.10 x 0.15 = 0.025 m3
- ) Volumen de vigetas
0.025 x 2.25 = 0.056 m3
- ) Volumen total de vigetas
0.056 m3 x 3 = 0,168 m3
V° Losita
Área de cada paño para la losita
Paño 1 = 2.50 m x 6.15 m = 15.38 m2
Paño 2 = 2.50 m x 7.56 m = 18.90 m2
Paño 3 = 0.65 m x 15.71 m + 0.25 m x 4.05 m = 11.22m2
Paño 4 = 0.55 m x 11.91 m + 0.25 m x 3.65 m = 7.46 m2
Paño 5 = 2.15 m x 4.60 m = 9.89m2
Paño 6 = 3.30 m x 4.16 m = 7.46 m2
Paño 7 = 1.15 m x 2.15 m = 2.47m2
Área total de la losita
AT = 15.38 + 18.90 + 11.22 + 7.46 + 9.89 + 7.46 + 2.47 = 72.78 m2
Volumen de la losita
V = 72.78 m2 x 0.05 m = 3.64 m3 x 3 = 10,92 m3
Volumen total de concreto en losa aligerada primer y segundo piso
VT = 1,32 + 1.68 + 1,05 + 0,66 + 0,84 + 1,17 + 0,168 + 10,92 = 17,81 m3

04.05.02 LOSAS ALIGERADAS - ACERO FY = 4200 KG/CM2


L: Diametro
Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
3/8" 1/2"
1/2" 3 5.63 1.03 17.31 17.66
Paño 1 1/2" 3 5.63 5.90 99.65 101.64
1/2" 3 5.63 3.33 56.16 57.28
1/2" 3 5.63 1.33 22.38 22.83
1/2" 3 5.63 7.50 126.68 129.21
1/2" 3 5.63 2.55 43.07 43.93
Paño 2
1/2" 3 5.63 2.45 41.38 23.17
3/8" 3 5.63 2.45 41.38 42.21
1/2" 3 5.63 1.03 17.31 17.66
1/2" 3 1.63 1.03 5.01 5.11
1/2" 3 1.63 16.15 78.97 80.55
1/2" 3 1.63 4.15 20.29 20.70
Paño 3 1/2" 3 1.63 2.15 10.51 10.72
1/2" 3 1.63 2.45 11.98 12.22
3/8" 3 1.63 2.45 11.98 6.71
1/2" 3 1.63 1.03 5.01 5.11
1/2" 3 1.38 2.68 11.07 11.30
1/2" 3 1.38 12.35 51.13 52.15
1/2" 3 1.38 2.15 8.90 9.08
Paño 4 1/2" 3 1.38 2.55 10.56 10.77
1/2" 3 1.38 2.45 10.14 10.35
3/8" 3 1.38 2.45 10.14 5.68
1/2" 3 1.38 1.03 4.26 4.35
1/2" 3 4.75 2.93 41.68 42.51
Paño 5 1/2" 3 4.75 4.60 65.55 66.86
1/2" 3 4.75 1.03 14.68 14.97
1/2" 3 7.00 1.43 29.93 30.52

Paño 6
1/2" 3 7.00 4.10 86.10 87.82
Paño 6 1/2" 3 7.00 2.45 51.45 52.48
3/8" 3 7.00 2.45 51.45 28.81
1/2" 3 7.00 1.03 21.63 22.06
1/2" 3 2.25 2.10 14.18 14.46
Paño 7
1/2" 3 2.25 2.50 16.88 17.21

L: Diametro
Paño 1 Descripcion ø n° veces n° elem. Unidad (ml) Parcial (kg)
1/4"

1/4" 2 24.40 2.45 119.56 29.89


a) n° elementos
6.15 - 0.025 - 0.025 = 6.10
6.10/0.25 = 24.40
b) L. elemento
2.50 - 0.025 - 0.025 = 2.45

1/4" 2 30.04 2.45 147.20 36.80


a) n° elementos
7.56 - 0.025 - 0.025 = 7.51
7.51/0.25 = 30.04
b) L. elemento

a) 1/4" 2 62.64 0.60 75.17 18.79


n° elementos
15.71 - 0.025 - 0.025 = 15.66
15.66/0.25 = 62.64
b) L. elemento

a) 1/4" 2 47.44 0.50 47.44 11.86


n° elementos
11.91 - 0.025 - 0.025 = 11.86
11.86/0.25 = 47.44
b) L. elemento

a) 1/4" 2 18.20 2.10 76.44 19.11


n° elementos
4.60 - 0.025 - 0.025 = 4.55
4.55/0.25 = 18.20
b) L. elemento

a) 1/4" 2 16.44 3.25 106.86 26.72


n° elementos
4.16 - 0.025 - 0.025 = 4.11
4.11/0.25 = 16.44
b) L. elemento

1/4" 2 8.40 1.10 18.48 4.62


a) 1/4" 2 8.40 1.10 18.48 4.62
n° elementos
2.15 - 0.025 - 0.025 = 2.10
2.10/0.25 = 8.40
b) L. elemento 1225.89

04.05.03 LOSAS ALIGERADAS - LADRILLO HUECO 15x30x30 cm

PAÑO 1
Area a techar: 2.25 x 5.20 = 11.70 m2
Total de ladrillos: 11.70 x 8.33 = 97.46 und

PAÑO 2
Area a techar: 2.25 x 6.81 = 15.32 m2
Total de ladrillos: 15.32 x 8.33 = 127.64 und

PAÑO 3
Area a techar: 0.65 x 14.21 = 9.24 m2
Total de ladrillos: 9.24 x 8.33 = 76.97 und

PAÑO 4
Area a techar: 0.55 x 10.66 = 5.86 m2
Total de ladrillos: 5.86 x 8.33 = 48.81 und
PAÑO 5
Area a techar: 1.90 x 3.85 = 7.32 m2
Total de ladrillos: 7.32 x 8.33 = 60.98 und

PAÑO 6
Area a techar: 2.80 x 3.66 = 10.25 m2
Total de ladrillos: 10.25 x 8.33 = 85.38 und

PAÑO 7
Area a techar: 0.90 x 1.65 = 1.49 m2
Total de ladrillos: 1.49 x 8.33 = 12.41 und

Parcial (und) 509.65 x 3 = 1528,95 und

05 ALBAÑILERIA
05.01 MURO DE CABEZA LADRILLO K.K. ARCILLA 18 HUECOS
Descripcion Longitud Altura Parcial M2
Primer nivel
Eje 3 - 3 entre eje A - B 1.65 2.7 4.455
2.6 2.5
Eje 6 - 6 entre eje B' - C menos P5 4.7
0.75 2.4
Eje 6 - 6 donde se ubica la V2 0.65 1 0.65
2.9 2.7
Eje 7 - 7 entre eje B' - C menos area de V1 4.79
1.9 1.6
Segundo nivel
Eje 3 - 3 entre eje A - B 2.55 2.4 6.12
Eje 3 - 3 entre eje B - C 2.45 2.4 5.88
tercer nivel
Eje 3 - 3 entre eje A - B 2.55 2.4 6.12
Eje 3 - 3 entre eje B - C 2.45 2.4 5.88
Azotea
Eje 3 - 3 entre eje A - B 1.65 2.2 3.63

Total 42.23

05.02 MURO SOGA DE LADRILLO K.K. ARCILLA 18 HUECOS


Descripcion Longitud Altura Parcial M2
Primer nivel
Eje A - A entre eje 1 - 2 1.75 3.1 5.425
Eje A -A entre eje 2 - 3 4 2.8 11.2
Eje A - A entre eje 3 - 5 4.4 3.1 13.64
Eje A - A entre eje 5 - 6 1.85 2.9 5.365
Eje A - A entre eje 6 - 8 5.1 3.1 15.81
Eje B - B muro cocina 3.2 3 9.6
Eje B - B muro baño 1.15 3 3.45
Eje B' - B' muro estudio 2.75 3 8.25
Eje C - C entre eje 1 - 2 1.75 3.1 5.425
Eje C - C entre eje 2 - 3 4 2.9 11.6
Eje C - C entre eje 3 - 4 3 2.8 8.4
Eje C - C entre eje 4 - 5 1.9 2.8 5.32
Eje C - C entre eje 5 - 6 1.85 2.8 5.18
Eje C - C entre eje 6 - 7 3.65 2.8 10.22
Eje C - C entre eje 8' - 8 1.45 3.2 4.64
Eje 1 - 1 entre eje A - C 6.25 3.1 19.375
2.8 2.7
Eje 2 - 2 entre eje A - B menos area de V5 5
1.6 1.6
3.55 2.8
Muro divisor de terraza - comedor menos area de M1 6.1475
2.05 1.85
Eje 4 - 4 entre eje A' - B 1.65 2.7 4.455
Muro costado de P2 entrada 0.55 2.8 1.54
Eje 8 - 8 entre eje B' - C 2.75 3.2 8.8

2 2.8
Eje A' - A' entre eje 3 - 4 muro escalera menos V4 4.95
1 0.65
Eje A' - A' entre eje 3 - 4 muro baño 1 2.2 2.2
Eje A' - A' entre eje 4 -5 donde se ubica V 1.9 1 1.9
Eje A' - A' entre eje 5 - 6 1.85 2.8 5.18
Muro divisor de baño - escalera 1.15 2.8 3.22

Descripcion Longitud Altura Parcial M2


Segundo nivel
Eje A - A entre eje 2 - 3 4 2.5 10
Eje A - A entre eje 5 - 6 1.85 2.5 4.625
Eje B - B entre eje 2 - 3 3 2.5 7.5
Eje B' - B' entre eje 4 - 5 1.2 2.5 3
Eje B' - B' entre eje 6' - 7 2.6 2.5 6.5
Eje C - C entre eje 2 - 3 4 2.5 10
Eje C - C entre eje 3 - 4 3 2.5 7.5
Eje C - C entre eje 4 - 5 1.9 2.5 4.75
Eje C - C entre eje 5 - 6 1.85 2.5 4.625
Eje C - C entre eje 6 - 7 2.75 2.5 6.875
2.8 2.4
Eje 2 - 2 entre eje A - B menos V6 3.465
2.1 1.55
3.45 2.4
Eje 2 - 2 entre eje B - C menos V6 5.025
2.1 1.55
Eje 4 - 4 entre eje A' - B' 2.22 2.4 5.328
Eje 4 - 4 entre eje B' - C 1.9 0.95 1.805
Eje 5 - 5 entre eje A - B' 3.2 2 6.4
Eje 5 - 5 entre eje B' - C 1.75 2 3.5
Eje 6 - 6 muro de baño 1.62 2 3.24
3 2.5
Eje A' - A' entre eje 3 - 4 menos dos V12 4.9
2 1.3
1.9 2.5
Eje A' - A' entre eje 4 - 5 menos V11 4.35
1 0.4
Muro closet dormitorio I 0.6 2.5 1.5
Muro closet dormitorio II 1.15 2.25 2.5875
Muro donde se ubica V9 terraza 1 0.95 0.95
Muro diagonal y costado de P10 del baño 1.68 2.5 4.2
Muro closet dormitorio principal 0.6 2.5 1.5
Muro diagonal del dormitorio princial 1.67 2.5 4.175
3.1 2.5
Muro del balcon menos M2 4.975
1.5 1.85

Descripcion Longitud Altura Parcial M2


Tercer nivel
Eje A - A entre eje 2 - 3 4 2.5 10
Eje A - A entre eje 5 - 6 1.85 2.5 4.625
Eje B - B entre eje 2 - 3 3 2.5 7.5
Eje B' - B' entre eje 4 - 5 1.2 2.5 3
Eje B' - B' entre eje 6' - 7 2.6 2.5 6.5
Eje C - C entre eje 2 - 3 4 2.5 10
Eje C - C entre eje 3 - 4 3 2.5 7.5
Eje C - C entre eje 4 - 5 1.9 2.5 4.75
Eje C - C entre eje 5 - 6 1.85 2.5 4.625
Eje C - C entre eje 6 - 7 2.75 2.5 6.875
2.8 2.4
Eje 2 - 2 entre eje A - B menos V6 3.465
2.1 1.55
3.45 2.4
Eje 2 - 2 entre eje B - C menos V6 5.025
2.1 1.55
Eje 4 - 4 entre eje A' - B' 2.22 2.4 5.328
Eje 4 - 4 entre eje B' - C 1.9 0.95 1.805
Eje 5 - 5 entre eje A - B' 3.2 2 6.4
Eje 5 - 5 entre eje B' - C 1.75 2 3.5
Eje 6 - 6 muro de baño 1.62 2 3.24
3 2.5
Eje A' - A' entre eje 3 - 4 menos dos V12 4.9
2 1.3
1.9 2.5
Eje A' - A' entre eje 4 - 5 menos V11 4.35
1 0.4
Muro closet dormitorio I 0.6 2.5 1.5
Muro closet dormitorio II 1.15 2.25 2.5875
Muro donde se ubica V9 terraza 1 0.95 0.95
Muro diagonal y costado de P10 del baño 1.68 2.5 4.2
Muro closet dormitorio principal 0.6 2.5 1.5
Muro diagonal del dormitorio princial 1.67 2.5 4.175
3.1 2.5
Muro del balcon menos M2 4.975
1.5 1.85
Azotea
Eje A - A entre eje 2 - 3 4 2.3 9.2
Eje A' - A' entre eje 3 - 4 3 2.3 6.9
2.05 2.3
Eje B - B muro dormitorio de servicio men 3.35
1.05 1.3
2.1 2.3
Eje B - B entre eje 3 - 4 menos V14 3.27
1.2 1.3
Eje C - C muro del baño 1 2.3 2.3
Muro del baño costado de la P12 0.4 2.3 0.92
2.8 2.3
Eje 2 - 2 entre eje A - B menos V13 3.605
2.1 1.35
3.45 2.3
Eje 2 - 2 entre eje B - C menos V16 7.535
1 0.4
Muro entre almacen - dorm. De servicio 3.15 2.3 7.245
muro entre baño - lavanderia 2.7 2.3 6.21
Eje 3 - 3 entre eje A - A' 0.9 2.3 2.07
Total 485.45

05.03 MURO CANTO DE LADRILLO K.K. ARCILLA 18 HUECOS


Descripcion Longitud Altura Parcial M2
Azotea
Eje A - A entre eje 5 - 6 1.85 1 1.85
Eje C - C 11.35 1 11.35
Contorno proyeccion terraza 5.55 1 5.55
Eje B' - B' 2.75 1 2.75
Eje 7 - 7 entre eje B' - C 2.9 1 2.9
Eje 6 - 6 1.81 1 1.81
Muro diagonal 1.78 1 1.78
Eje A' - A' entre eje 4 - 5 2.05 1 2.05
Eje 5 - 5 entre eje A - A' 0.9 1 0.9
Total 30.94