DH = 12 1/4 IN
% POROSIDAD 20% 0.2
FACTOR = 1029.4
CR = ((DH^2)/1029,4)*(1-%POROSIDAD)
CR = ((12 1/4^2)/1029,4)*(1-0,20)
CR = 0.1166 BBL/FT
DH = 12 1/4
% POROSIDAD = 40% 0.4
FACTOR = 144
CR = ((DH^2)/1029,4)*0,7854*(1-%POROSIDAD)
CR = ((12 1/4^2)/1029,4)*0,7854*(1-0,40)
CR = 0.4911 FT^3
CONTROL DE PERFORACION
MW in = 9 PPG
MW out = 9.7 PPG
Q= 530 GPM
DH = 17 1/2 IN
FACTOR DE FLOTACION
DETERMINAR EL BF PARA UN MW DE 15 PPG
MW = 15 PPG
BF = 1 - (MW/65,5)
BF = 1 - (15/65,5)
BF = 0.7710
DETERMINAR PIE DE TUBERIA SECA QUE DEBEN SER SACADO PARA PERDER EL
SOBRE BALANCE
DATOS:
CANT. SB = 150 PSI
CAP. TUB. 0.0773 BBL/FT
DES. TUB. = 0.0075 BBL/FT
MW = 11.5
DATOS:
CANT. S.B. = 150 PSI
CAP. TDR = 0.0773 BBL/FT
CAP. T = 0.1776 BBL/FT
DT = 0.0075 BBL/FT
MW = 11.5
POTENCIA HIDRAULICA
DETERMINAR HHP:
DATOS:
P= 2950 PSI
Q= 520 GPM
HHP = (P * Q)/1714
HHP =(2950 * 520) /1714
HHP = 894.9825
DETERMINAR DE LA PRESION HIDROSTATICA CUANDO SE SACA TUBERIA
FUERA DEL POZO
DATOS:
TIRO = 5
SACADO
PLPT = 92
DT = 0.0075 BBL/FT
CTR= 0.00773 BBL/FT
MW = 11.5
PASO 1 BD = #TS*PLPT*DT
BD = 5 * 92 * 0,0075
BD = 3.45 BBL
PASO 2 PH = (BD/(CTR-DT)*0,052*MW
PH = (3,45 / (0,00773 - 0,0075) * 0,052 * 11,5
PH = 8970 PSI
DATOS:
#TS = 5
PLPT = 92
DT = 0.0075 BBL/FT
CTR = 0.001776 BBL/FT
CDC = 0.0773 BBL/FT
DATOS:
OD = 8 IN
ID = 2 5/7 IN
CAPACIDAD:
CAP = ID^2/1029,4
CAP = 8^2/1029,4
CAP = 0.0622 BBL/FT
DESPLAZAMIENTO:
DES = (OD^2-ID^2)/1029,4
DES = (8^2-2 5/^2)/1029,4
DES = 0.0550 BBL/FT
PESO: