Le= (W-b)/(2*TANGENTE(ø))
A UTILIZAR : Le=
19.- ALTURA DE AGUA EN EL VERTEDERO DE SALIDA, (M)
H2=(Q / (1.84*W))^(2/3)
Q = M*b*(Ho)^(3/2)
M=
Ho=
Lv = b=
DISEÑO DEL DESAREN
PROYECTO “MEJORAMIENTO DEL SERVICIO DE AGUA PARA EL SISTEMA DE RIEGO EN 25 COMUNIDADES DE
SAN MIGUEL- LA MAR- AYACUCHO”
A UTILIZAR: Lv=
Ls= (W-b1)/(2*TANGENTE(ø))
A UTILIZAR : Ls=
Q=Cd*Ao*(2*g*ho)^(1/2)
A UTILIZAR: Ac=
DISEÑO DEL DESAREN
PROYECTO “MEJORAMIENTO DEL SERVICIO DE AGUA PARA EL SISTEMA DE RIEGO EN 25 COMUNIDADES DE
SAN MIGUEL- LA MAR- AYACUCHO”
Q = Cd*(Ao)*((2*g*h)^0.5)
Carga sobre el orificio
h=hc - (a/2) h=
Q=
V=
V= Q/Ao
DISEÑO FINAL:
LT = 12 m
Le = 3.2 Ld = 5.6
PLANTA
DISEÑO DEL DESAREN
PROYECTO “MEJORAMIENTO DEL SERVICIO DE AGUA PARA EL SISTEMA DE RIEGO EN 25 COMUNIDADES DE
SAN MIGUEL- LA MAR- AYACUCHO”
Lv = 2.2
hc = 0.6
S =4.73%
Le = 3.2 Ld = 5.6
PERFIL
RESUMEN
PROVINCIA : LA MAR
REGIÓN : AYACUCHO
Aliviadero
H S=%
h1
Le Ld Ls
500.000 lt/seg
0.030 cm
20 °C
2.60 gr/cm3
1.00 gr/cm3
0.01003 gr/cm3*seg
4.133 cm/seg
12.36 TRANSICIÓN
27.89 cm/seg
13.94 cm/seg
3.586 m2
1.339 m
2.678 m
L DESARENADOR
E RIEGO EN 25 COMUNIDADES DE LA CUENCA DEL VALLE DE TOROBAMBA EN EL DISTRITO DE
PROVINCIA : LA MAR
REGIÓN : AYACUCHO
1.400 m Ok
2.800 m Ok
12.10 m2
4.32 m
5.40 m
5.60 m
12.5 °
0.60
0.40
0.50
3.131 m
3.20 m
0.21 m
2.00
0.919 OK
1.800
0.250
2.22 m
L DESARENADOR
E RIEGO EN 25 COMUNIDADES DE LA CUENCA DEL VALLE DE TOROBAMBA EN EL DISTRITO DE
PROVINCIA : LA MAR
REGIÓN : AYACUCHO
0.60 m
0.40 m
0.50 m
3.131 m
3.20 m
12.00 m
0.27 m
4.73 %
1.67 m
0.60
1.58 m
0.60 m
0.30 m2
0.50 m
0.60 m
L DESARENADOR
E RIEGO EN 25 COMUNIDADES DE LA CUENCA DEL VALLE DE TOROBAMBA EN EL DISTRITO DE
PROVINCIA : LA MAR
REGIÓN : AYACUCHO
1.37 m
DISEÑO FINAL:
12 m
Ls = 3.2
PLANTA
L DESARENADOR
E RIEGO EN 25 COMUNIDADES DE LA CUENCA DEL VALLE DE TOROBAMBA EN EL DISTRITO DE
PROVINCIA : LA MAR
REGIÓN : AYACUCHO
ys = 0.4
H = 1.4
h1 = 0.265
0.60
Ls = 3.2
PERFIL
N ENTRADA 3.20 m
3.20 m
5.60 m
2.80 m
2.50 m
DESARENADOR 12.00 m
0.15 m
0.15 m
AL DE INGRESO 0.60 m
AL DE SALIDA 0.60 m
01.02. METRADO MEJORAMIENTO DE CANAL DE RIE
POZA DISIPADORA
EMBOQUILLADO
CANAL DE LIMPIA
01.02.02.03.02 CONCRETO f'c=140 kg/cm2 + 30% PM M3
EMBOQUILLADO DE ALIVIADERO
MURO DEL ALIVIADERO
PISO DE CANAL LIMPIEZA
MUROS DE CANAL LIMPIEZA
01.02.02.04 OBRAS DE CONCRETO ARMADO
01.02.02.04.01 CONCRETO f'c=175 kg/cm2 M3
MUROS DE TRANSICION ENTRADA
PISO DE TRANSICION ENTRADA
MUROS DE POZA DISIPADORA
VENTANA DE ALIVIADERO
PISO DE POZA DISIPADORA
MURO TRANSICION SALIDA
PISO TRANSICION SALIDA
DADOS DE ANCLAJE ENTRADA
DADOS DE ANCLAJE SALIDA
01.02.02.04.02 ENCOFRADO Y DESENCOFRADO EN MURO M2
MUROS DE TRANSICION ENTRADA
MUROS DE POZA DISIPADORA
MUROS DE TRANSICION SALIDA
MURO DEL ALIVIADERO
LONGITUD DE MUROS DE CANAL DE LIMPIA
Nota: 02 usos
01.02.02.04.03 ACERO CORRUGADO EN DESARENADOR KG
ACERO DE 3/8"EN EL DESARENADOR
01.02. METRADO MEJORAMIENTO DE CANAL DE RIE
Nro MEDIDAS
Sub Total Total
Veces Largo Ancho Alto Parcial
1.00
81.80 81.80
1.00 14.00 5.10 71.40 71.40
1.00 4.00 1.90 7.60 7.60
1.00 2.95 0.95 2.80 2.80
42.70 42.70
1.00 12.00 3.10 37.20 37.20
1.00 3.00 0.90 2.70 2.70
1.00 2.95 0.95 2.80 2.80
40.19 40.19
1.00 Area = 6.40 1.38 7.78
1.00 Area = 6.40 1.38 7.78
1.00 Area = 17.36 2.75 14.90
1.00 Area = 2.66 2.75 4.61
1.00 3.00 0.90 1.90 5.13
35.52 53.28
1.00 Area = 6.40 6.40
1.00 Area = 6.40 6.40
1.00 Area = 17.36 17.36
1.00 Area = 2.66 2.66
1.00 3.00 0.90 2.70
10.44 15.66
1.00 Area = 17.36 0.50 8.68
1.00 Area = 2.66 0.50 1.33
1.00 3.00 0.9 0.16 0.43
36.59 36.59
E CANAL DE RIEGO MAZOMACHAY
Nro MEDIDAS
Sub Total Total
Veces Largo Ancho Alto Parcial
52.25
15.66
35.52 35.52
1.00 Area = 6.40 6.40
1.00 Area = 6.40 6.40
E CANAL DE RIEGO MAZOMACHAY
Nro MEDIDAS
Sub Total Total
Veces Largo Ancho Alto Parcial
1.00 Area = 17.36 17.36
1.00 Area = 2.66 2.66
1.00 3.00 0.90 2.70
1.86 1.86
1.00 Area = 2.66 0.15 0.40
1.00 Area = 0.54 0.80 0.43
1.00 3.00 0.90 0.15 0.41
1.00 5.20 0.15 0.80 0.62
11.43 11.43
2.00 3.20 0.15 1.37 0.66 1.31
1.00 3.20 2.00 0.15 0.96 0.96
2.00 5.60 0.15 2.37 1.99 3.98
1.00 -2.20 0.15 0.21 -0.07 -0.07
1.00 5.60 3.10 0.15 2.60 2.60
2.00 3.20 0.15 1.20 0.58 1.15
1.00 3.20 2.00 0.15 0.96 0.96
1.00 3.10 0.15 0.20 0.09 0.09
1.00 3.10 0.15 0.95 0.44 0.44
108.78 108.78
4.00 Area = 4.38 4.38 17.50
4.00 Area = 13.26 13.26 53.03
4.00 Area = 3.84 3.84 15.36
2.00 Area = 3.12 3.12 6.24
4.00 Area = 4.16 4.16 16.64
297.05
HOJA DE METRADOS DE ACERO 297.05
E CANAL DE RIEGO MAZOMACHAY
Nro MEDIDAS
Sub Total Total
Veces Largo Ancho Alto Parcial
80.90 80.90
2.00 Area = 4.38 - 4.38 8.75
4.00 Area = 13.26 - 13.26 53.03
2.00 Area = 3.84 - 3.84 7.68
1.00 Area = 3.12 3.12 3.12
2.00 Area = 4.16 4.16 8.32
1.00 1.00
1.00
30.00 30.00
1.00 1.80 1.80 1.80
1.00 1.80 1.80 1.80
2.00 10.80 10.80 21.60
2.00 2.40 2.40 4.80
HOJA DE METRADO DE ACERO
PROYECTO : “MEJORAMIENTO DE SERVICIO DE AGUA PARA EL SISTEMA DE RIEGO EN 25 COMUNIDADES EN LA CUENCA DEL VALLE DE
TOROBAMBA DE LOS DISTRITOS DE SAN MIGUEL Y CHILCAS PROVINCIA DE LA MAR REGIÓN AYACUCHO”
Ø -------> 1/4 '' 3/8 '' 1/2 '' 5/8 '' 3/4 '' 1 ''
kg/m -------> 0.25 0.58 1.02 1.60 2.26 4.04
0.320 0.580 1.020 1.600 2.340 4.100
Corte de acero Nro. Elem Nro. Veces Ø Longitug kg/m Parcial
01.02.02.04.03 ACERO CORRUGADO EN DESARENADOR
ACER DE 3/8"EN EL DESARENADOR KG
TRANSICION ENTRADA VERT. 4.74 16.00 1.00 3/8 '' 4.74 0.58 43.94
TRANSICION ENTRADA HORIZ. 3.20 25.00 1.00 3/8 '' 3.20 0.58 46.40
POZA VERT. 7.84 17.00 1.00 3/8 '' 7.84 0.58 77.25
POZA HORIZ. 3.10 40.00 1.00 3/8 '' 3.10 0.58 71.92
TRANSICION SALIDA VERT. 3.00 16.00 1.00 3/8 '' 3.00 0.58 27.84
TRANSICION SALIDA HORIZ. 3.20 16.00 1.00 3/8 '' 3.20 0.58 29.70
A CUENCA DEL VALLE DE
UCHO”
Total
Sub
Total
Total
297.05 297.05
RESUMEN DE METRADOS DE DESARENADOR