RESUMEN DE TRANSPORTE

TRANSPORTE DE
VOLUMEN MATERIAL
CANTERA
RELLENO D <= 1 KM D > 1 KM
Material Asfalto 7,616.72 7,616.72 70,873.70
Material Sub Base 22,320.00 22,320.00 294,512.40
Material Base 10,278.00 10,278.00 135,365.80
Material a Eliminar 16,263.00 16,263.00 87,575.44
Material para relleno 45,208.80 45,208.80 602,091.60
Material para enrocado 3,857.45 3,857.45 39,191.70
TRANSPORTE DE MATERIAL PARA ENROCADO
CANTERA 1
MATERIAL
UBICACIÓN UBICACIÓN (KM) 6.620
TRANSPORTADO
ACCESO (KM) 9.700
TRANSPORTE DE
DISTANCIA MATERIAL
VOLUMEN DISTANCIA
INICIO FINAL LONG. C.G. ENROCADO TRANSP. % MATERIAL MOMENTO
TOTAL TRANSP.
-120m
m3 m3 km km m3 TRANSPORTE D <= 1 KM

06+000 06+320 320 6.160 3857.45 3857.45 10.160 10.160 100% 3857.45 39191.69 3857.45 39191.70

3,857.45 3,857.45 39,191.69 3,857.45 39,191.70

VOLUMEN transformacion ET
TRANSPORTE DE
A MATERIAL DERRUMBE
CANTERA
ENROCAR
(m3) D <= 1 KM D > 1 KM >1km = 39,191.70 x 18.5
CANTERA 1 3,857.45 3,857.45 39,191.70 19.88
TOTAL 3,857.45 3,857.45 39,191.70
= 36,471.15
TRANSPORTE DE MATERIAL PARA RELLENO

CANTERA 01
MATERIAL
UBICACIÓN UBICACIÓN (KM) 0.000
TRANSPORTADO
ACCESO (KM) 3.200 TRANSPORTE DE
MATERIAL
VOLUMEN DISTANCIA DISTANCIA
INICIO FINAL LONG. C.G. Rellenos % MATERIAL MOMENTO
TOTAL esp. TRANSP. TRANSP.

m3 m3 km km m3 TRANSPORTE D <= 1 KM D > 1 KM

relleno en terraplen
06+000 07+000 1000 6.50 4317.30 4317.30 9.70 9.70 100% 4317.30 41877.81 4317.30 41877.80
07+000 08+000 1000 7.50 5850.00 5850.00 10.70 10.70 100% 5850.00 62595.00 5850.00 62595.00
08+000 09+000 1000 8.50 5791.50 5791.50 11.70 11.70 100% 5791.50 67760.55 5791.50 67760.60
09+000 10+000 1000 9.50 5908.50 5908.50 12.70 12.70 100% 5908.50 75037.95 5908.50 75038.00
10+000 11+000 1000 10.50 5791.50 5791.50 13.70 13.70 100% 5791.50 79343.55 5791.50 79343.60
11+000 12+000 1000 11.50 5850.00 5850.00 14.70 14.70 100% 5850.00 85995.00 5850.00 85995.00
12+000 13+000 1000 12.50 5908.50 5908.50 15.70 15.70 100% 5908.50 92763.45 5908.50 92763.50
13+000 14+000 1000 13.50 5791.50 5791.50 16.70 16.70 100% 5791.50 96718.05 5791.50 96718.10

45,208.80 45,208.80 602,091.36 45,208.80 602,091.60

TRANSPORTE DE transformacion ET
VOLUMEN MATERIAL DERRUMBE
CANTERA
RELLENO
D <= 1 KM D > 1 KM >1km = 602,091.60 x 17.8
CANTERA 01 45,208.80 45,208.80 602,091.60 13

TOTAL 45,208.80 45,208.80 602,091.60 = 824,402.34


TRANSPORTE DE MATERIAL PARA ELIMINACION

BOTADERO 01
MATERIAL
UBICACIÓN UBICACIÓN (KM) 17.660
TRANSPORTADO
ACCESO (KM) 1.250 TRANSPORTE DE
MATERIAL
VOLUMEN DISTANCIA DISTANCIA
INICIO FINAL LONG. C.G. Rellenos % MATERIAL MOMENTO
TOTAL esp. TRANSP. TRANSP.

m3 m3 km km m3 TRANSPORTE D <= 1 KM D > 1 KM

06+000 07+000 1000 6.50 2632.50 2632.50 12.41 12.41 100% 2632.50 32669.33 2632.50 30036.80
07+000 08+000 1000 7.50 1950.00 1950.00 11.41 11.41 100% 1950.00 22249.50 1950.00 20299.50
08+000 09+000 1000 8.50 1930.50 1930.50 10.41 10.41 100% 1930.50 20096.51 1930.50 18166.00
09+000 10+000 1000 9.50 1969.50 1969.50 9.41 9.41 100% 1969.50 18533.00 1969.50 16563.50
10+000 11+000 1000 10.50 1930.50 1930.50 8.41 8.41 100% 1930.50 16235.51 1930.50 14305.00
11+000 12+000 1000 11.50 1950.00 1950.00 7.41 7.41 100% 1950.00 14449.50 1950.00 12499.50
12+000 13+000 1000 12.50 1969.50 1969.50 6.41 6.41 100% 1969.50 12624.50 1969.50 10655.00
13+000 14+000 1000 13.50 1930.50 1930.50 5.41 5.41 100% 1930.50 10444.01 1930.50 8513.50

16,263.00 16,263.00 147,301.83 16,263.00 131,038.80

TRANSPORTE DE transformacion ET
VOLUMEN MATERIAL DERRUMBE
CANTERA
RELLENO
D <= 1 KM D > 1 KM >1km = 131,038.80 x 5.4
BOTADERO 01 16,263.00 16,263.00 131,038.80 8.08
TOTAL 16,263.00 16,263.00 131,038.80
= 87575.435643564
TRANSPORTE DE MATERIAL PARA BASE

CANTERA 02
MATERIAL
UBICACIÓN UBICACIÓN (KM) 0.000
TRANSPORTADO
ACCESO (KM) 3.200 TRANSPORTE DE
MATERIAL
VOLUMEN DISTANCIA DISTANCIA
INICIO FINAL LONG. C.G. Rellenos % MATERIAL MOMENTO
TOTAL esp. TRANSP. TRANSP.

m3 m3 km km m3 TRANSPORTE D <= 1 KM D > 1 KM

relleno en terraplen
06+000 07+000 1000 6.50 1306.69 1306.69 9.70 9.70 100% 1306.69 12674.89 1306.69 12674.90
07+000 08+000 1000 7.50 1293.75 1293.75 10.70 10.70 100% 1293.75 13843.13 1293.75 13843.10
08+000 09+000 1000 8.50 1280.81 1280.81 11.70 11.70 100% 1280.81 14985.48 1280.81 14985.50
09+000 10+000 1000 9.50 1306.69 1306.69 12.70 12.70 100% 1306.69 16594.96 1306.69 16595.00
10+000 11+000 1000 10.50 1280.81 1280.81 13.70 13.70 100% 1280.81 17547.10 1280.81 17547.10
11+000 12+000 1000 11.50 1293.75 1293.75 14.70 14.70 100% 1293.75 19018.13 1293.75 19018.10
12+000 13+000 1000 12.50 1306.69 1306.69 15.70 15.70 100% 1306.69 20515.03 1306.69 20515.00
13+000 14+000 1000 13.50 1208.81 1208.81 16.70 16.70 100% 1208.81 20187.13 1208.81 20187.10

10,278.00 10,278.00 135,365.84 10,278.00 135,365.80

TRANSPORTE DE transformacion ET
VOLUMEN MATERIAL DERRUMBE
CANTERA
RELLENO
D <= 1 KM D > 1 KM >1km = 135,365.80 x 15.6
CANTERA 02 10,278.00 10,278.00 135,365.80 14.58

TOTAL 10,278.00 10,278.00 135,365.80 = 144,835.84


TRANSPORTE DE MATERIAL PARA SUB BASE

CANTERA 03
MATERIAL
UBICACIÓN UBICACIÓN (KM) 0.000
TRANSPORTADO
ACCESO (KM) 3.200 TRANSPORTE DE
MATERIAL
VOLUMEN DISTANCIA DISTANCIA
INICIO FINAL LONG. C.G. Rellenos % MATERIAL MOMENTO
TOTAL esp. TRANSP. TRANSP.

m3 m3 km km m3 TRANSPORTE D <= 1 KM D > 1 KM

06+000 07+000 1000 6.50 2817.90 2817.90 9.70 9.70 100% 2817.90 27333.63 2817.90 27333.60
07+000 08+000 1000 7.50 2790.00 2790.00 10.70 10.70 100% 2790.00 29853.00 2790.00 29853.00
08+000 09+000 1000 8.50 2762.10 2762.10 11.70 11.70 100% 2762.10 32316.57 2762.10 32316.60
09+000 10+000 1000 9.50 2817.90 2817.90 12.70 12.70 100% 2817.90 35787.33 2817.90 35787.30
10+000 11+000 1000 10.50 2762.10 2762.10 13.70 13.70 100% 2762.10 37840.77 2762.10 37840.80
11+000 12+000 1000 11.50 2790.00 2790.00 14.70 14.70 100% 2790.00 41013.00 2790.00 41013.00
12+000 13+000 1000 12.50 2817.90 2817.90 15.70 15.70 100% 2817.90 44241.03 2817.90 44241.00
13+000 14+000 1000 13.50 2762.10 2762.10 16.70 16.70 100% 2762.10 46127.07 2762.10 46127.10

22,320.00 22,320.00 294,512.40 22,320.00 294,512.40

TRANSPORTE DE transformacion ET
VOLUMEN MATERIAL DERRUMBE
CANTERA
RELLENO
D <= 1 KM D > 1 KM >1km = 294,512.40 x 15.6
CANTERA 03 22,320.00 22,320.00 294,512.40 14.58
TOTAL 22,320.00 22,320.00 294,512.40
= 315,116.15
TRANSPORTE DE MATERIAL PARA ASFALTO

CANTERA 04
MATERIAL
UBICACIÓN UBICACIÓN (KM) 0.000
TRANSPORTADO
ACCESO (KM) 2.300 TRANSPORTE DE
MATERIAL
VOLUMEN DISTANCIA DISTANCIA
INICIO FINAL LONG. C.G. Rellenos % MATERIAL MOMENTO
TOTAL esp. TRANSP. TRANSP.

m3 m3 km km m3 TRANSPORTE D <= 1 KM D > 1 KM

relleno en terraplen
00+000 01+000 1000 0.50 539.38 539.38 2.80 2.80 100% 539.38 1510.26 539.38 1510.30
01+000 02+000 1000 1.50 539.38 539.38 3.80 3.80 100% 539.38 2049.64 539.38 2049.60
02+000 03+000 1000 2.50 544.83 544.83 4.80 4.80 100% 544.83 2615.18 544.83 2615.20
03+000 04+000 1000 3.50 544.83 544.83 5.80 5.80 100% 544.83 3160.01 544.83 3160.00
04+000 05+000 1000 4.50 550.28 550.28 6.80 6.80 100% 550.28 3741.90 550.28 3741.90
05+000 06+000 1000 5.50 539.38 539.38 7.80 7.80 100% 539.38 4207.16 539.38 4207.20
06+000 07+000 1000 6.50 550.28 550.28 8.80 8.80 100% 550.28 4842.46 550.28 4842.50
07+000 08+000 1000 7.50 544.83 544.83 9.80 9.80 100% 544.83 5339.33 544.83 5339.30
08+000 09+000 1000 8.50 539.38 539.38 10.80 10.80 100% 539.38 5825.30 539.38 5825.30
09+000 10+000 1000 9.50 550.28 550.28 11.80 11.80 100% 550.28 6493.30 550.28 6493.30
10+000 11+000 1000 10.50 539.38 539.38 12.80 12.80 100% 539.38 6904.06 539.38 6904.10
11+000 12+000 1000 11.50 544.83 544.83 13.80 13.80 100% 544.83 7518.65 544.83 7518.70
12+000 13+000 1000 12.50 550.28 550.28 14.80 14.80 100% 550.28 8144.14 550.28 8144.10
13+000 14+000 1000 13.50 539.38 539.38 15.80 15.80 100% 539.38 8522.20 539.38 8522.20

7,616.72 7,616.72 70,873.65 7,616.72 70,873.70

TRANSPORTE DE transformacion ET
VOLUMEN
CANTERA MATERIAL DERRUMBE
RELLENO
D <= 1 KM D > 1 KM >1km = 70,873.70 x 12.5
CANTERA 04 7,616.72 7,616.72 70,873.70 13.68
TOTAL 7,616.72 7,616.72 70,873.70
= 64,760.33