Tentative Bar Chart for the work of Washable Apron in IOC Jalandhar Terminal
Nos of Tentative dates for completion of activities
Upto date
S.No Desrciption of activity Qty
progress
days May JUNE
required 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
d Laying of PRC Sleepers on Washable Apron length 515 nos in each track 100%
h Fixing of rails on sleepers with ERC on Washable 335m length 2 track Nil
4
Apron
i Drilling of Holes in Rails End 416 holes nil
15
335m length 2 track nil
j Fixing of Fish plates on joints 6
k Providing and laying 75mm thick Bituminous Concrete 335m length 2 track Nil
8
v Fixing of Rails on PRC Sleepers with ERC 160m for two track Nil
2