Está en la página 1de 1

Date 17.05.

19
Tentative Bar Chart for the work of Washable Apron in IOC Jalandhar Terminal
Nos of Tentative dates for completion of activities
Upto date
S.No Desrciption of activity Qty
progress
days May JUNE
required 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 Dismentling of existing track with rails and 500m completed except


sleepers of any type by removing of all fittings , stacking of
leading and stacking of all released material in the releaded materials 6
stacking ground
2 Excavation & removal of Mulba and levelling of 500m 335m length in
Yard washable apron 4
completed
3 P.Way materials availablity at site 100%

4 Washable Apron 335m


a Providing and laying WBM in both the track 335m 100%

b Providing and laying 100mm CC 335m 100%

c Providing and laying M 25 CC/RCC cast in Situ 335m 100%

d Laying of PRC Sleepers on Washable Apron length 515 nos in each track 100%

e Spacing of PRC Sleepers @ 650mmmc/c 515 nos in each track Nil


3

g Provinding Anti corrosive paint to Rails 335m length 2 track Nil


4

h Fixing of rails on sleepers with ERC on Washable 335m length 2 track Nil
4
Apron
i Drilling of Holes in Rails End 416 holes nil
15
335m length 2 track nil
j Fixing of Fish plates on joints 6

k Providing and laying 75mm thick Bituminous Concrete 335m length 2 track Nil
8

l Providing and laying M 15 CC 335m length 2 track Nil 4


m Application of Epoxy Paint 335m length 2 track Nil 2
5 Assembling ,linking , complete 60 kg 1 in 8.5, T/out one Job Nil
on PRC sleepers
i Excavation & removal of Mulba and levelling of one Job Nil
2
area under T/O
ii Placing of PRC Sleepers one Job Nil 2
iii Fixing of rails on T/O one Job Nil 3
6 Linking of ballasted Track beyond washable 160m for two track Nil
Apron
i Excavation & removal of Mulba and levelling of bed 160m for two track Nil
2

ii Placing of PRC Sleepers 160m for two track Nil 2


iii Laying of Rails along the tracks 160m for two track Nil 1
iv Provinding Anti corrosive paint to Rails 160m for two track Nil
1

v Fixing of Rails on PRC Sleepers with ERC 160m for two track Nil
2

vi Drilling of Holes in Rails End 160m for two track Nil


4
160m for two track Nil
vii Fixing of Fish plates on joints 2

Fabrication and Fitting of Dead End


7 2nos Nil 4
8 Spreading of ballast on ballasted Track 160m in both track Nil
6
9 Constrcution of Drains at washable Apron both 335m length both side one side work in
10
side progress
10 335m length both side
Providing Steel Grating on Drains on both side Nil 5

11 Finishing and winding up the site one Job Nil 5


NOTE: 1. Activities shown above are subject to arrangment of materials such as Bituminous concrete materials, concrete,ballast and other Machinery, Equipments ans required staff.
2. Any other activity left and noticed during the work will be entered lator on.

También podría gustarte