Documentos de Académico
Documentos de Profesional
Documentos de Cultura
1.0 PRELIMINARIES
4.1 Wall Mount Bracket Support for 2 units Quadro Compact Cooler (2 lot
tons per unit)
4.2 Others ( Pls. specify if any)
SUB-TOTAL 4
Page 1 of 8
7.0 PLUMBING - Includes Supply, Delivery, Fabrication and Installation of
Plumbing Works to Tapping Point complete with supports and
accessories based on Standard Specifications and Approved Drawings
SUB-TOTAL 8
GRAND TOTAL
Received and considered in the preparation of the BID. I shall be responsible for all the DATA, COST AND INFORMATION filled up in the BID DOCUMENTS including all the
commitment started therein. It is our responsibility to inspect and visit the site to check the actual conditions of the area and premises including commercial and industrial
materials and labor available in the local markets. I shall immediately mobilize and start the work within (3) Days upon received of NOTICE of AWARD and NOTICE To PROCEED and
complete the works ON SCHEDULE SET BY THE MANAGEMENT. We commit to comply all the schedule requirements of milestones, and execute the project in accordance with the
plans and specifications and acceptable engineering methodology and workmanship.
NOTE: All contractors must affix their signature to all of the bid documents.
Page 2 of 8
Project : Proposed Potato Storage and Washing Area
Location : Carmelray, Brgy. Canlubang, City of Calamba, Laguna
Owner : Leslie Corporation
Date : 12-May-2019
Subject : Bid Form
1.0 PRELIMINARIES -
Potato Storage
3.1 Chipping of existing SOG for proposed waste water drainage 1.00 lot - - -
system
3.2 Others ( Pls. specify if any)
Potato Washing
3.3 Chipping of existing SOG for proposed waste water drainage 1.00 lot - - -
system, trench canal and Crate Dumper Pit
3.4 Filling-in of the existing shallow canal with concrete mortar, 1.00 lot - - -
4000psi
3.5 Blocking of 1 unit Area Drain to be replaced by Crate Dumper Pit 1.00 lot - - -
Potato Processing
3.7 Chipping of Existing suspended slab, 1000 x 1000mm Opening 1.00 lot - - -
4.0 EARTHWORKS -
Potato Storage
4.1 Excavation for proposed waste water drainage system cu.m. - - -
4.2 Hauling & Disposal lot - - -
4.3 Grading and Compaction sq.m. - - -
4.4 Gravel Bedding, 100mm thk cu.m. - - -
4.5 Others ( Pls. specify if any)
Potato Washing
4.6 Excavation for proposed waste water drainage system, trench cu.m. - - -
canal and Crate Dumper Pit
4.7 Hauling & Disposal lot - - -
4.8 Grading and Compaction sq.m. - - -
4.9 Gravel Bedding, 100mm thk cu.m. - - -
4.10 Others ( Pls. specify if any)
Page 1 of 8
5.0 CONCRETE -
Potato Storage
5.1 Concrete, 3000psi
5.1.1 100mm high Concrete Base cu.m. - - -
5.2 Rebars
5.2.1 Concrete Base kgs. - - -
5.3 Formworks
5.3.1 1/2" Plywood shts. - - -
5.4 Consumables lot
5.5 Others ( Pls. specify if any)
Potato Washing
5.6 Concrete, 3000psi
5.6.1 200mm high Concrete Base cu.m. - - -
5.6.2 Crate Dumper Pit cu.m. - - -
5.6.3 Trench Canal cu.m. - - -
5.6.4 Junction Box cu.m. - - -
5.7 Rebars
5.7.1 200mm high Concrete Base kgs. - - -
5.7.2 Crate Dumper Pit kgs. - - -
5.7.3 Trench Canal kgs. - - -
5.7.4 Junction Box kgs. - - -
5.8 Formworks, 1/2" Plywood
5.8.1 200mm high Concrete Base kgs. - - -
5.8.2 Crate Dumper Pit kgs. - - -
5.8.3 Trench Canal kgs. - - -
5.8.4 Junction Box kgs. - - -
5.9 Consumables lot - - -
5.10 Others ( Pls. specify if any)
Potato Storage
6.1 Angular framing support for 2-T QCC60 Refrigeration Unit lot - - -
7.0 MASONRY -
Potato Washing
7.1 4" CHB Masonry Zocallo Wall with 10mm Ø Vertical Bar Spaced sq.m. - - -
@ 600mm O.C. and Horizontal Bar in between layers
7.2 Plastering / Skimcoating sq.m. - - -
7.3 Consumables lot - - -
7.4 Others ( Pls. specify if any)
Potato Processing
7.5 4" CHB Masonry Zocallo Wall with 10mm Ø Vertical Bar Spaced sq.m. - - -
@ 600mm O.C. and Horizontal Bar in between layers
7.6 Others ( Pls. specify if any)
8.0 FINISHES -
Potato Storage
8.1 Floor Finishes
8.1.1 4mm thk PolyUrethane (PU) Flooring sq.m. - - -
8.1.2 100 mm rad PolyUrethane (PU) Coving lm - - -
8.1.3 150mm width Demarcation Line lm - - -
8.2 Wall Finishes
8.2.1 4" thk PolyUrethane (PU) Wall w/ bended accs. sq.m. - - -
8.3 Ceiling Finishes
8.3.1 2" thk PolyUrethane (PU) Ceiling sq.m. - - -
8.4 Others ( Pls. specify if any)
Potato Washing
8.5 Floor Finishes
8.5.1 4mm thk PolyUrethane (PU) Flooring sq.m. - - -
8.5.2 100 mm rad PolyUrethane (PU) Coving lm - - -
8.5.3 4mm thk PolyUrethane (PU) Trench Canal lm - - -
8.6 Wall Finishes
8.6.1 2" thk PolyUrethane (PU) Wall w/ bended accs. sq.m.
8.7 Others ( Pls. specify if any)
9.0 METAL -
Potato Washing
9.1 Stainless Steel Trench Grating including Framing pc/s. - - -
Page 2 of 8
9.2 Others ( Pls. specify if any)
10.0 DOORS -
Potato Storage
10.1 PolyUrethane (PU) Sliding Door
10.1.1 4mW x 4mH Sliding Door set - - -
10.2 PolyUrethane (PU) Swing Door
10.2.1 1mW x 2.1mH Emergency Exit Door set - - -
10.3 PVC Strip Curtain
10.3.1 4mW x 4mH Sliding Door set - - -
10.4 Others ( Pls. specify if any)
Potato Washing
10.5 PolyUrethane (PU) Sliding Door
10.5.1 4mH x 3mH Sliding Door set - - -
10.6 PVC Strip Curtain
10.6.1 4mW x 4mH Sliding Door set - - -
10.5 Others ( Pls. specify if any)
11.0 PLUMBING -
Potato Storage
11.1 Drainage System
11.1.1 100mmØ PVC Pipe and Fittings Series 1000 lm - - -
11.1.2 25mmØ QCC 60 drain pipe lm - - -
11.2 Plumbing Fixtures
11.2.1 100mmØ Stainless Steel Clean Out, Industrial Type 6.00 pc/s. - - -
11.3 Catch Basins
11.3.1 600 x 600 x 600mm, 4" CHB thk 6.00 unit/s - - -
11.3 Others ( Pls. specify if any)
Potato Washing
11.4 Drainage System
11.4.1 150mm Ø Stainless Steel Pipe and Fittings Sch. 20 lm - - -
11.4.2 100mmØ PVC Pipe and Fittings Series 1000 lm - - -
11.5 Plumbing Fixtures
11.5.1 150mmØ Stainless Steel Trench Drain, Anti-odor with 3.00 pc/s. - - -
removable cover Industrial Type
11.5.2 100mmØ Stainless Steel Trench Drain, Anti-odor with 3.00 pc/s. - - -
removable cover Industrial Type
11.3 Catch Basins
11.3.1 1000 x 1000 x 1000mm, 4" CHB thk 6.00 unit/s - - -
11.3 Others ( Pls. specify if any)
12.0 Electrical -
Potato Storage
12.1 Lighting - - -
12.1.1 Hanger & Supports 1.00 lot - - -
12.1.2 Roughing-ins 1.00 lot - - -
12.1.3 Wiring 1.00 lot - - -
12.1.4 Panel Board 1.00 lot - - -
12.1.4 Fixtures 9.00 set/s - - -
12.1.5 Testing & Comissioning 1.00 lot - - -
12.2 Others ( Pls. specify if any)
13.0 Mechanical -
Potato Washing
13.1 Replacement of 2 units submersible pump 2.00 unit/s - - -
13.2 Others ( Pls. specify if any)
GRAND TOTAL -
Received and considered in the preparation of the BID. I shall be responsible for all the DATA, COST AND INFORMATION filled up in the BID DOCUMENTS including all the
commitment started therein. It is our responsibility to inspect and visit the site to check the actual conditions of the area and premises including commercial and industrial
materials and labor available in the local markets. I shall immediately mobilize and start the work within (3) Days upon received of NOTICE of AWARD and NOTICE To PROCEED and
complete the works ON SCHEDULE SET BY THE MANAGEMENT. We commit to comply all the schedule requirements of milestones, and execute the project in accordance with the
plans and specifications and acceptable engineering methodology and workmanship.
Page 4 of 8
Project : Proposed Potato Storage
Location : Carmelray, Brgy. Canlubang, City of Calamba, Laguna
Owner : Leslie Corporation
Date :
Subject : Bid Form
GRAND TOTAL
Received and considered in the preparation of the BID. I shall be responsible for all the DATA, COST AND INFORMATION filled up in the BID DOCUMENTS including all the
commitment started therein. It is our responsibility to inspect and visit the site to check the actual conditions of the area and premises including commercial and industrial
materials and labor available in the local markets. I shall immediately mobilize and start the work within (3) Days upon received of NOTICE of AWARD and NOTICE To PROCEED and
complete the works ON SCHEDULE SET BY THE MANAGEMENT. We commit to comply all the schedule requirements of milestones, and execute the project in accordance with the
plans and specifications and acceptable engineering methodology and workmanship.
NOTE: All contractors must affix their signature to all of the bid documents.
Page 1 of 8
Project : Proposed Potato Storage
Location : Carmelray, Brgy. Canlubang, City of Calamba, Laguna
Owner : Leslie Corporation
Date :
Subject : Bid Form
GRAND TOTAL
Received and considered in the preparation of the BID. I shall be responsible for all the DATA, COST AND INFORMATION filled up in the BID DOCUMENTS including all the
commitment started therein. It is our responsibility to inspect and visit the site to check the actual conditions of the area and premises including commercial and industrial
materials and labor available in the local markets. I shall immediately mobilize and start the work within (3) Days upon received of NOTICE of AWARD and NOTICE To PROCEED and
complete the works ON SCHEDULE SET BY THE MANAGEMENT. We commit to comply all the schedule requirements of milestones, and execute the project in accordance with the
plans and specifications and acceptable engineering methodology and workmanship.
NOTE: All contractors must affix their signature to all of the bid documents.
Page 1 of 8