2 Total furnace ( water walls ) mock-up was not done which resulted in for trimming & rebeveling it
site has modfied 3 days
lot of msimatches & misalignment in water wall tube to tube fitup took more time
5 Economiser mdoules inlet hedaer stubs are wrongly oreiented & site has modfied 3 days
welded
6 All the piping are sent with out 100% RT & SR Site has done the same 3 days 50% was done in site
2 As all the supplies have got delayed, all the preshut actvities were taken up in the shut which has incread the shut scope enormously & lead to
extended duration