Está en la página 1de 2

Lightning protection TA N K S T O R A G E • May 2012

Lightning-related petroleum storage tanks fires are more common


than most people think. To minimise the likelihood of a fire API RP
545 recommends three major modifications to floating roof tanks

recommendations
for reducing risk
A
ccording to a review of 3. Install overhead shield
petroleum storage tank wires above the tank.
fires between 1951 4. Install conductive shunts
and 2003, the number of tank between the roof and
fires reported in the worldwide tank shell (for FRT’s).
media is in the range of 5. Ensure the tank is
15 to 20 fires per year. well grounded.
The extent of the tank fire Methods #1, #2 and #3 are
incidents varies considerably, based on the premise that
ranging from a rim seal fire the protective element will
to multiple, simultaneous full collect the incoming lightning
tank fires. Of the 480 tank strike and divert the energy
fire incidents reported, about to ground. Unfortunately,
one-third are attributed to current flows on Frt from nearby lightning strike there are two undesirable
lightning. Another study, consequences of these
sponsored by 16 oil industry conventional methods:
companies, found that 52 of flows across the roof-to- present at the arc location, 1. Occasionally the protective
55 rim seal fires were caused shell seal during all lightning the vapours may be ignited if element will fail to collect
by lightning, and concluded events, regardless if the strike the arc is sustained for more the strike, and the strike
that ‘lightning is the most terminates either directly than about 5 milliseconds. will terminate directly
common source of ignition.’ on or near the tank. For a The duration of a typical on the tank. (This is a
Until API RP 545 was storage tank without a floating lightning strike is well in worst case scenario.)
published in 2009, the existing roof, there will be lightning- excess of 5 milliseconds. 2. These methods do not
lightning protection standards related current flows across eliminate the root cause of
for the petroleum industry all surfaces of the tank during Conventional protection and ignition, which is current
provided little guidance. The all lightning events, regardless grounding concepts flow across electrical
research performed on behalf if the strike terminates either discontinuities, such as the
of API did provide valuable directly on or near the tank. Conventional lightning roof-shell seal on FRT’s.
insight to understanding the If a lightning-related current protection methods for tanks Regarding method #4, API-
lightning-related ignition encounters an electrical include the following: funded testing proved that
mechanism. The three discontinuity and arcs from 1. Install lightning masts shunts will produce arcs
primary recommendations one conductive surface to around the tank. during lightning events, even
offered in API RP 545 do another, and flammable 2. Install air terminals if the shunts and internal tank
make important first steps to vapours and oxygen are on the tank. wall are clean. Regarding
reducing lightning-related risk method #5, the sheer size
for floating roof tanks (FRT’s). and weight of a tank creates
an excellent connection
The cause to earth, and so adding
grounding electrodes to a
There are two ways in which tank is not effective. Further,
a lightning strike can ignite a whether or not a structure
stored petroleum product: is well grounded does not
1. A direct strike to the determine whether or not it
storage tank containing will be struck by lightning.
the petroleum. (This
is the worst case.) Recommendations
2. A strike terminating near
the storage tank, thus The API RP 545 committee
subjecting the tank to the invested substantial
indirect effects of the strike. resources into directed
According to API-funded research and testing. Two
research, for a FRT there will of the key findings from the
be lightning-related current picture caption to come test programme were that
Example of Rim DAS solution in the field
xxx
May 2012 • TA N K S T O R A G E Lightning protection

of bypass conductors) RP 545, the consequences of


should be implemented vapour ignition from a direct
immediately. Installation strike are too great to risk.
of bypass conductors is The Dissipation Array
inexpensive compared to the System (DAS) is a lightning
other recommendations, and strike avoidance system
can be done on in-service that will minimize the risk
tanks. Installing RGA’s on of a strike terminating on
FRT’s will eliminate the arcing the protected structure.
at the shunts and other The DAS continuously
roof-shell interfaces caused dissipates the charge that
by the slow components accumulates during a
of the lightning stroke. thunderstorm, leaving that
Therefore, installing RGA’s structure without significant
will substantially reduce or charge. Measurements of
eliminate the risk of lightning- DAS performance made by
electrical field strength inside customers have shown that
and outside of DAS protected a thunderstorm’s electrical
area
field strength, as shown in
Figure 2, can be substantially
(1) when lightning current reduced by a DAS, thus
passes through shunts at discouraging upward
the roof-shell interface, it streamers being launched
will result in arcing under from the protected structure.
all conditions; and (2) it is The DAS usess an
the slow component of the electrostatic phenomenon
lightning stroke which ignites called ‘point discharge’ to
flammable vapours. Therefore, transfer the charge from the
when the slow component site into the atmosphere. Point
of a lightning stroke passes rim DAS and conic DAS on floating and fixed roof tanks discharge is the phenomenon
through any roof-shell that occurs when a sharp
interface, if flammable conventional conductors grounded point is exposed
vapours are present they will and retractable conductors related tank fires on FRT’s. to a strong electrostatic
likely be ignited. As a result, wound on spring-tensioned field. Current flow via
API RP 545 recommends three reels. Because an FRT is Recommendation for direct strike point discharge increases
major modifications to FRT’s: most at-risk when the roof protection exponentially with the increase
1. Install submerged shunts is high, it is desirable to in field strength. When large
between the roof and shell have the bypass conductors The worst case scenario for amounts of ions are produced,
every 3 meters around be as short as possible to a petroleum storage tank it creates a shielding space
the roof perimeter, and provide the lowest possible is for a lightning strike to charge usually recognized
remove any existing impedance. Retractable terminate directly on the tank. as corona. The DAS creates
above-seal shunts. bypass conductors will always Considering that an average massive ionisation during
2. Electrically insulate all seal be as short as possible lightning strike contains about a thunderstorm, thereby
assembly components when the FRT roof is high. 30,000 amperes and that the constantly discharging
(including springs, The Retractable Grounding 95th percentile of all strikes the protected area and
scissor assemblies, seal Assembly (RGA) is a contain 80,000 amperes or eliminating the condition that
membranes, etc.), and all retractable bypass conductor less, there is plenty of current creates upward streamers.
gauge and guide poles, made specifically for available at the strike terminus
from the tank roof. FRT’s. Since it is the slow to create undesirable arcing. If Reducing the risk
3. Install bypass conductors components of lightning the arcing occurs in a location
between the roof and shell strokes which ignite where flammable vapours Because conventional lightning
no more than every 30 flammable vapours, and and oxygen are present, the protection methods do not
meters around the tank bypass conductors safely vapours will be ignited. Even eliminate the direct and
circumference. These carry these slow components, if the tank is a closed system secondary effects associated
bypass conductors should modification #3 (installation or is fully compliant with API with every lightning strike,
be as short as possible they are not adequate to
and evenly spaced around protect petroleum storage
the roof perimeter. facilities. For petroleum
Modifications #1 and #2 storage tanks with floating
both require substantial design roofs, it is imperative that
changes and overhauling they be made compliant to API
of new and existing tanks. RP 545. Bypass conductors
Modifications #1 and #3 are between the roof and tank
methods to bond the roof and shell on FRT’s should be
shell on FRT’s. Modification of the retractable type, to
#3, installation of bypass provide the lowest possible
conductors, is relatively easy impedance between the roof
and inexpensive to implement and shell. To eliminate direct
when compared to the other strike concerns, a DAS should
modifications, and can be be installed on the structure
implemented immediately. to prevent the worst case
To meet the bypass situation – a direct strike
conductor requirements, tank terminating directly on the
owners can choose between “Tank Explosion
picture at night
caption to come- Colonial Pipeline Tank Farm Greensboro, tank – from occurring. n
NC June, 13, 2010”
xxx

También podría gustarte