GEO-FRONTIERS
2005
GEOTECHNICAL SPECIAL PUBLICATIONS 130-142 AND GRI-I8
January 24-26, 2005
Austin, Texas
SPONSORED BY
The Geo-Institute of the American Society of Civil Engineers
Geosynthetic Materials Association
of the Industrial Fabrics Association International
Geosynthetic Institute
EDITED BY
Ellen M. Rathje, Ph.D, P.B
ASCE
Published by the American Society of Civil EngincersGSP 131 Contemporary Issues in Found:
Engineering
GEOGRID-REINFORCED AND PILE-SUPPORTED ROADWAY
EMBANKMENT
Reinaldo Vega-Meyer', Member, ASCE; Yong Shao’, PhD. Member, ASCE
* Senior Project Manager-International Division, Tensar Earth Technologies, Inc.,
5883 Glenridge Dr., Suite 200, Atlanta, GA. 30328 (USA); PH (404) 250-1290; FAX
(404) 250-9185; email: rvegameyer@tensarcorp.com
* Senior Geotechnical Engineer, Moreland-Altobelli Associates, Inc., 2211 Beaver
Ruin Rd, Suite 190, Atlanta, GA. 30071 (USA); PH (770) 263-5945; FAX (770)
263-0166; email: yshao@moreland-altobelli.com
ABSTRACT
Settlement is one of the major concerns in roadway embankment construction in
areas where soft soil deposits constitute the major portion of subsurface soil. A pile
foundation system is an effective way to support an embankment in order to minimize
total settlement. In recent years, geosynthetic reinforcement has been successfully
incorporated with pile foundations to improve settlement performance. Referred to a8
Load Transfer Platform (LTP), or Geosynthetic Reinforced Platform (GRP), the
system combines vertical piles and horizontal geosynthetics to form a relatively stiff
platform that transfers embankment load to a deeper, competent bearing layer. The
Beosynthetic layers serve as the tensioned platform that bridges over the piles and
reduces the differential settlement at top of the platform, which in tum reduces the
differential settlement of the embankment.
After a brief discussion of the system mechanism, this paper focuses on a case study
of a roadway embankment supported by a geogrid-reinforced platform and precast
concrete piles in Colon City, Republic of Panama. The embankment, a MSE
(Mechanically Stabilized Earth) retaining wall with a maximum height of 3.2 meters,
was built on a 1.0-meter thick geogrid reinforced crushed stone LTP, which is
supported by 30 cm diameter precast piles. Piles penetrate through 6 meters of
organic clay to a very dense sandy silt bearing layer, 10 meters below the existing
ground surface. Due to the complexity of the system a numerical method was used to
model the system and evaluate settlement behavior. This paper presents a detailed
discussion of the project information, the design methodology and the numerical
modeling. In addition, field instrumentation is also presented in comparison with the
design and analysis.GSP 131 Contemporary Issues in Foundation Engineering
INTRODUCTION
‘When building an embankment over a soft soil deposit, engineers face a challenging
problem: how to effectively reduce the settlement so that the structures on top of the
embankment only experience a tolerable amount of deformation during their service
life. To achieve this objective, several different ways have been practiced throughout
the years; they are: conventional embankments on a selected granular material (over-
excavation and replacement), piled embankments, piled embankments containing a
continuous concrete slab, and piled embankments with a geosynthetic-reinforced
platform system (GRP).
A typical configuration of a GRP or LTP supported embankment is shown in Figure
1. The addition of the reinforcement in the LTP system increases the stiffness of the
platform that enables higher percent load transfer fiom the soil to the piles and,
therefore, reduces the differential settlement between pile caps so that no significant
settlement occurs at the top of the embankment.
Geosynthetic-reinforced
fill platform
Small size
Pile caps
Firm soil or bedrock Vertical piles
Figure 1. Geosynthetic-Reinforced and Pile-Supported (GRP) Embankments
Evolved from conventional piled embankments, the GRP system results in a more
uniform distribution of the settlement in between piles due to the bridging function of
geosynthetic reinforcements. In addition, the GRP system generally does not require
battered piles, close pile spacing or large pile caps, which makes it more
economically competitive. Figure 2 shows a comparison between the percent
coverage by pile caps requirements for two systems: Concrete Pile System (CPS,
Rathmayer, 1975) and Geosynthetic Reinforced Platform System (GRP, Han, 1999).
‘The percent coverage herein is defined as the percentage of the total area of pile caps
or columas to that of foundation footprint. In this figure, the design percentage of pile
cap coverage for thirteen actual geosynthetic-reinforced and pile-supported earth
platforms are plotted for comparison purposes. It is shown that the required percent
coverage of pile (caps) with geosynthetic is lower than the suggested by Rathmayer
for the conventional pile-supported embankments, and is consistently less than 20%.