Está en la página 1de 89

 

 
 
 
 
 
 
 
 
 
 
Cambodia – In Depth Study on
Electricity Cost and Supplies

March 2015

FINAL REPORT

Prepared by:
William Derbyshire, Economic Consulting Associates

Managed & Supported by:


Setha Hong, Lead Consultant G-PSF Project

Financial Supported

 
 
 
 
 
Contents  
   

Contents

Contents  .............................................................................................................................................  1  
Abbreviations  and  acronyms  ......................................................................................................  3  
Executive  Summary  ........................................................................................................................  4  
Introduction   4  
Cambodia’s power sector   4  
Cambodia’s electricity prices   5  
Costs   6  
Tariffs   9  
Consumption   10  
Recommended policy actions   11  
1.   Introduction  ...........................................................................................................................  14  
1.1   Background   14  
1.2   Guide  to  the  report   14  
Part  I  -­‐  Context  ...............................................................................................................................  16  
2.   Cambodia’s  power  sector  ...................................................................................................  17  
2.1   Major  institutions   17  
2.2   Electricity  demand   19  
2.3   Generation  and  power  purchases   24  
2.4   Transmission   29  
2.5   Sub-­‐transmission  and  distribution   31  
3.   Cambodia’s  electricity  prices  ...........................................................................................  32  
3.1   Significance  of  electricity  costs   32  
3.2   Industrial  electricity  tariffs  in  Cambodia   33  
3.3   Competitiveness  of  Cambodia’s  electricity  prices   35  
3.4   Comparison  of  supply  costs   37  
Part  II  -­‐  Analysis  ............................................................................................................................  40  
4.   Costs  ..........................................................................................................................................  41  
4.1   EDC’s  costs   41  
4.2   International  comparisons   50  
4.3   Conclusions  and  recommendations   63  
5.   Tariffs  .......................................................................................................................................  66  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies:  FINAL  REPORT   Page  1  of  89    
March  2015  
 
 
 
Contents  
   

5.1   Principles  of  tariff  design   66  


5.2   Cambodia’s  tariff  structure   67  
5.3   Are  tariffs  cost-­‐reflective?   69  
5.4   Time-­‐of-­‐Use  tariff   70  
5.5   Conclusions  and  recommendations   71  
6.   Consumption  ..........................................................................................................................  73  
6.1   Energy  efficiency   73  
6.2   Self-­‐generation   75  
6.3   Conclusions  and  recommendations   79  
Part  III  -­‐  Recommendations  ......................................................................................................  82  
7.   Recommended  policy  actions  ...........................................................................................  83  
7.1   Short-­‐term  (within  one  year)   83  
7.2   Medium-­‐term  (one  to  three  years)   83  
7.3   Long-­‐term  (over  three  years)   84  
ANNEXES  ..........................................................................................................................................  85  
A1   List  of  persons  met  ...............................................................................................................  86  
 

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies:  FINAL  REPORT   Page  2  of  89    
March  2015  
 
 
 
Abbreviations  and  acronyms  
   

Abbreviations and acronyms

ADB   Asian  Development  Bank  


BOT   Build-­‐Operate-­‐Transfer  
CCC   Cambodia  Chamber  of  Commerce  
CNEE   National  Policy,  Strategy  and  Action  Plan  for  Energy  Efficiency  in  Cambodia  
CPTL   Cambodia  Power  Transmission  Lines  Co  Ltd  
EAC   Electricity  Authority  of  Cambodia  
ECA   Economic  Consulting  Associates  
EDC   Electricité  du  Cambodge  
ERC   Energy  Regulatory  Commission  [Philippines]  
ESCO   Energy  Services  Company  
EVN   Electricity  of  Vietnam  
FIT   Feed-­‐in-­‐Tariff  
G-­‐PSF   Government  –  Private  Sector  Forum  
HV   High  Voltage  (115  kV  and  230  kV)  
IPP   Independent  Power  Producer  
IRR   Internal  Rate  of  Return  
LV   Low  Voltage  (12  kV  and  below)  
MEF   Ministry  of  Economy  and  Finance  
MFI   Multilateral  Financing  Institution  
MME   Ministry  of  Mines  and  Energy  
MOC   Ministry  of  Commerce  
MV   Medium  Voltage  (22  kV  /  35  kV)  
NPT   National  Power  Transmission  Corporation  [Vietnam]  
PBR   Performance-­‐Based  Regulation  
PEA   Provincial  Electricity  Authority  [Thailand]  
PPA   Power  Purchase  Agreement  
RHG   Rice  Husk  Gasifier  
ROE   Return  on  Equity  
TDSP   Trade  Development  Support  Program  
TOR   Terms  of  Reference  
TOU   Time-­‐of-­‐Use  
 

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  3  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Executive Summary

Introduction

This report has been prepared for the Cambodia Chamber of Commerce (CCC)
under the assignment:

In-Depth Study on Electricity Cost and Supplies (TDSP/2012/081/02/1)

The assignment is being funded through the Department of International


Cooperation of the Ministry of Commerce under the Trade Development Support
Program (TDSP) managed by the World Bank.

The purposes of the assignment are to:

❏ Assess the causes of the high prices of electricity supply for larger
industrial and commercial customers in Cambodia.

❏ Develop evidence-based recommendations on policy and regulatory


reforms which can contribute to reducing these high prices.

The analysis in this report draws on publicly-available documents and interviews


conducted in Cambodia with representatives of government, the utility and major
electricity customers.

Cambodia’s power sector

Electricity demand

Cambodia’s power sector is small by regional (and international) standards but


demand has been growing extremely rapidly. Between 2003 and 2014, the annual
growth in electricity sales averaged almost 20% with total sales increasing by over
seven times. The number of customers has grown only slightly more slowly, by 17%
annually or by six times over the same period. Cambodia’s national power
development master plan is currently being updated. While this is not yet public, we
are advised that the master plan envisages continued annual growth rates of 15-20%
to 2020. This implies electricity sales reaching 10,000-13,000 GWh in 2020.

This rapid increase is driven by the expansion of electricity supplies nation-wide.


From electrification rates of just 6.5% of communes (‘khums’) and 5% of households
in 2003, coverage is estimated to have reached 85% of communes and 60% of
households by 2014.

Although there are over 300 licensed distributors of electricity in Cambodia, sales are
dominated by the state-owned utility, EDC. In 2013, EDC was responsible for
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  4  of  89  
March  2015  
 
 
 
Executive  Summary  
   

directly supplying over 500,000 customers with sales of 2,824 GWh (40% and 80% of
the national totals, respectively).

Electricity supply

Up until 2007, supply was almost entirely from oil-fired generation which
represented over 85% of output. With the commissioning of the inter-connectors to
Thailand in 2007 and to Vietnam in 2009, imports replaced much of this domestic
generation, reaching almost two-thirds of supply by 2011. From 2013 onwards, with
the growth of hydro and coal generation in Cambodia, imports in turn have been
scaled back and replaced with these new sources. In 2014, half of generation was
from domestic hydro and coal plants and this is expected to increase to over two-
thirds in 2015, with the share of oil-fired generation reduced to just 5% of the total.

Peak demand on the national grid is substantially below available generating


capacity and contracted imports, indicating a large surplus of generating capacity.
The surplus over peak demand is likely to be temporary if demand growth forecasts
are realised. However, Cambodia also has and is likely to continue to have
mismatches between supply and demand at different times of the year and day.

Until 2007, Cambodia’s transmission network was essentially limited to a ring line
around Phnom Penh. Since then, transmission grids have developed in the north-
west and south and these have now been inter-connected creatiing a national gird.
The grid is now being further inter-connected and expanded. As with generation,
Cambodia has relied heavily on private investors to develop transmission lines on a
BOT basis with EDC contracting to use these lines.

Cambodia’s electricity prices

Cambodia’s electricity tariffs rose rapidly in 2005 following the introduction of the
floating tariff, peaked in 2008 when world oil prices also peaked and then declined
and rose again with oil price. From 2012 onwards, tariffs have reduced with the
growing share of imports, hydro and coal supplies replacing oil-fired generation and
this decline is projected to continue to 2020 under the approved five-year plan.

Despite, this, Cambodia’s tariffs remain high as shown by the comparison below,
calculated assuming a ‘typical’ garment factory as the customer. It is evident that,
even following the recent reductions, Cambodia’s tariff for larger industrial
customers remains above that of both regional comparators and other countries with
similar reliance on garment exports.

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  5  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Figure 1 MV industrial tariffs compared

Source: ECA calculations using data from national electricity regulatory and utilities. The tariff for Cambodia
is that applicable for 2015 for MV customers located in Phnom Penh and Kandal. The tariff for the Philippines
is that applicable for customers served by Meralco using the February 2015 generation charge.

Costs

We show below a comparative breakdown of the cost components of EDC’s retail


tariff against those of these three utilities. It is readily apparent that Cambodia’s
costs of are high relative to those of Vietnam and Thailand but equivalent or lower
than those in the Philippines.

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  6  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Figure 2 Comparative breakdown of retail tariffs

Source: ECA calculations from EDC and EAC data (Cambodia, 2014), EVN data (Vietnam, 2013), EGAT and
PEA data (Thailand, 2013) and Meralco data (Philippines, February 2015). For EDC, the breakdown is of the
tariff for small industrial customers connected to the LV network. For EVN and PEA, the breakdown of the
average retail tariff is shown. For Meralco, the breakdown is of the tariff for small industrial customers
connected to the LV network (General Service A category) with a consumption of 400 kWh monthly. Levies to
fund cross-subsidies are only explicitly identified in the Philippines.

Generation and power purchase costs

At present Cambodia has a surplus of generation during wet months and at night-
time. As a large part of generation and power purchase costs are fixed relative to
output, due to minimum guaranteed quantities included in Power Purchase
Agreements (PPAs) with IPPs, this raises the unit cost relative to countries with
lower capacity margins. Our estimates are that utilising all capacity at its expected
level would allow a reduction in costs in 2015 of around 3.4 USc/kWh for LV
customers (slightly less for higher voltage customers) or 15-20%. EDC is currently
trying to negotiate for the export of surplus generation to Vietnam but it is proving
difficult to agree the terms. It is also possible to relieve this problem to some extent
by encouraging shifting of electricity consumption to night-time hours.

A further contributing factor to costs is the import duties and VAT applied to
electricity imports into Cambodia. We estimate that these are equivalent to
approximately US$ 25 million or 0.5 USc for every kWh sold.

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  7  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Transmission costs

The higher transmission costs can, at least partially, be attributed to a combination of


economies of scale in these activities and to the lower volumes and levels of
utilisation of EDC’s transmission network relative to that in the comparator
countries which will result in higher unit costs, even if the absolute level of costs is
the same. The heavy reliance on BOTs to develop new transmission lines may also be
driving up costs relative to networks financed by state-owned utilities in Thailand
and Vietnam. However, it is difficult to assess the impacts of this given that we lack
the data to break out the costs of these lines from those lines owned by EDC.

Distribution costs

There may be scope for EDC to achieve efficiency gains in electricity distribution. As
an example of the potential magnitude of such efficiency improvements, reducing
the gap between EDC’s distribution costs and those of PEA by half would allow a
reduction in tariffs of around 1 USc/kWh. One of the most obvious drivers of higher
distribution costs appears to be the lower levels of sales and customers per employee
in Cambodia relative to that of the comparator countries. However, the impacts of
this lower labour productivity should not be exaggerated and is partly offset by the
lower salaries in Cambodia.

It may also be that the current distribution margins simply no longer reflect
distribution costs, given they have not been revised for 10 years

System losses

Overall, we conclude that EDC is not performing particularly well or badly relative
to its peers as regards the level of system losses. However, there remains scope for
improvement. While EDC did manage to reduce losses significantly up to 2010, the
level seems to have remained fairly constant since then. As an indication of the
potential impacts on tariffs of reducing system losses, a reduction of two percentage
points from 2013 levels, closing half of the gap between EDC’s losses and those of
EGAT/PEA, would reduce generation and power purchase costs by up to US$ 16
million in generation costs, equivalent to around 0.30 USc/kWh. However, this
might be offset by the current structure of PPAs which mean that lower levels of
purchases translate into largely unchanged total costs.

Financing

EDC’s gearing (debt to equity ratio) is relatively low for a utility investing heavily to
meet rapid growth in demand. Its return on equity (ROE) is also high by the
standard of comparators—reflecting this low gearing and its reliance on operating
profits to fund new investments.

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  8  of  89  
March  2015  
 
 
 
Executive  Summary  
   

There appears to be scope for reducing the costs of financing network investments
by making greater use of borrowing by EDC, particularly from multilateral and
bilateral institutions given the lower rates offered, and by setting, for the purposes of
determining regulated tariffs, an allowed return on equity closer to that of regulated
electricity network utilities elsewhere. Our estimate is that increasing gearing from
48% to 60% and reducing EDC’s return on equity from 26% to 10% would reduce
EDC’s costs by the equivalent of 1.7 USc/kWh or around 10% of the tariff. We do
recognise that EDC is seeking such finance but has been reluctant to turn to some
potential lenders, such as the World Bank, due to poor part experience over the time
required for processing loans. It will also require approval from MEF where entering
into new external loans.

Tariffs

In the absence of a comprehensive study of the costs of supply to different customer


categories, it is difficult to determine whether existing tariffs are cost-reflective. Our
expectation would generally be that industrial customers would have lower tariffs
than domestic customers given their greater level of sales and flatter load or demand
profiles. However, we recognise the validity of EAC’s argument that industrial
customers consume more at times of system peak and so should pay a higher share
of the system’s fixed costs and that Cambodia’s current tariff structure is in line with
that of its neighbours in Thailand and Vietnam.

We do recommend that EAC commission a study of the costs of supply to different


customer categories and that the results are made publicly available. This would
provide a basis for the proper assessment of the cost-reflectivity of tariffs and
whether the current structure should be adjusted.

We also note that the current TOU tariff does not appear adequate to encourage
switching of consumption times and that the differences between peak and off-peak
periods is lower than that in Thailand and Vietnam. We recommend that the
difference between TOU tariffs for peak and off-peak periods is increased to better
reflect cost differences between periods and to make switching cost-effective. This
should benefit industrial customers in the short-term by reducing their costs and in
the longer-term by helping address the problem of excess capacity in night-time
hours. However, current labour law restriction pose a significant barrier to switching
to night-time working and these may need to be reviewed if such a policy is to be
fully successful. For most labour-intensive industries, the savings in electricity costs
from moving consumption to off-peak periods are unlikely, in our estimation, to
outweigh the increased labour costs in most cases even with a much greater
differential between peak and off-peak tariffs.

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  9  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Consumption

There are two main routes by which industrial customers can themselves act to
reduce their electricity costs.. The first is improving the energy efficiency of their
operations, reducing electricity consumption. The second is to substitute for grid
electricity supplies by self-generation.

Energy efficiency

There have been numerous assessments of the potential for improving energy
efficiency in Cambodian industry. However, the impacts to date seem to have been
limited. This seems to be due to a combination of lack of awareness of the
opportunities and reluctance to invest in energy-saving measures. This reluctance
has been attributed to constraints on total borrowing by enterprises and an
unwillingness to use up scarce credit from commercial institutions on investments
with lengthy and uncertain pay-backs.

Case studies of garment factories conducted under the GEF-UNIDO Industrial


Energy Efficiency Cambodia project suggest that savings in electricity costs of 6-8%
are achievable with relatively low up-front investments, equivalent to reducing
electricity tariffs by around 1-1.5 USc/kWh.

The draft National Policy, Strategy and Action Plan on Energy Efficiency in Cambodia
(CNEE) contains an action plan for promoting energy efficiency in industry
including:

❏ Institution of a system of mandatory collection of data on energy


consumption from major industrial users.

❏ Raising awareness of good energy management practices in industrial


enterprises (following the ISO 50001 standard).

❏ Establishing standards on energy efficiency and management in industrial


enterprises and encouraging voluntary compliance with these.

❏ Funding energy audits for small and medium enterprises, training of


technicians and energy auditors.

❏ Providing loans for energy efficiency-improving investments as a catalyst


for the development of a supporting financial sector.

MME is undertaking limited initiatives to promote industrial energy efficiency,


including in some of these areas, but these efforts should be strengthened and
enhanced.

In the longer-term, it will be critical if energy efficiency potential is to be fully


realised, to address the difficulties faced by enterprises in borrowing to fund energy
efficiency investments. The draft national strategy recognises this need but lacks
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  10  of  89  
March  2015  
 
 
 
Executive  Summary  
   

detailed actions. We recommend that Cambodia investigate the potential for


creating a revolving energy efficiency fund, along the lines of Thailand’s well-
established and successful model.

Self-generation using renewable sources

Self-generation using rice husks and other agricultural residues is attractive for
agricultural processing industries when compared to diesel generation. However, it
is less so when compared to current grid electricity tariffs. The costs of self-supply
from co-generation plants using rice husks for fuel is closer to grid-parity costs but
still unlikely to be viable if output is only used for internal purposes. Other
technologies appear unlikely to be competitive with grid supplies for larger
industrial customers given their higher costs and, in the case of solar panels,
intermittent supply. However, these may still be economically attractive for smaller
customers, particularly the use of solar panels for off-grid supplies where the costs of
alternative diesel generation is higher and where intermittency and limited night-
time supplies are less of a concern.

Most processing industries operate at relatively low load factors, which means that
the average or unit costs of self-generation are high and may make otherwise
promising technologies uncompetitive with grid electricity supply. Higher load
factors and additional revenues can be achieved if surplus generation can be sold to
the grid. However, in doing so, a balance must be struck between the benefits to the
selling enterprise and the additional costs and risks that may be imposed on the
purchasing utility.

Self-generation could be made more attractive if EDC were to expand its current
programme of purchases by introducing a standard tariff, based on its avoided costs,
and accompanying PPA for purchases of surplus energy from industrial enterprises
with their own electricity generation. By linking the price paid to EDC’s avoided
costs, the net impact on EDC’s costs and tariffs should be zero ensuring fairness to
both parties. In future, if the government adopts a policy of promoting renewable
energy sources, a higher price in excess of avoided costs might be offered.

Recommended policy actions

Short-term (within one year)

Ministry of Economy and Finance

❏ Consider exempting electricity imports from duties and VAT

Ministry of Mines and Energy

❏ Approve the National Energy Efficiency Strategy

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  11  of  89  
March  2015  
 
 
 
Executive  Summary  
   

❏ Speed-up implementation of the identified short-term actions in the


strategy to improve data and raise awareness of industrial energy
efficiency

Electricity Authority of Cambodia

❏ Publish the assessment of EDC’s costs used to determine approved tariffs

❏ Increase the difference between TOU tariffs for peak and off-peak periods
to better reflect cost differences and practice elsewhere in the region
(however, this may need to be accompanied by changes to labour
legislation regarding night-time working if it is to be effective in changing
consumption patterns)

Medium-term (one to three years)

Ministry of Mines and Energy

❏ Investigate the potential for creating a revolving energy efficiency fund to


help industry fund investments

Electricity Authority of Cambodia

❏ Undertake a full analysis of EDC’s transmission and distribution costs


relative to the current allowances

❏ Conduct a study of the costs of supply to different customer categories

Electricitè du Cambodge

❏ Move to a greater reliance on debt financing of new investments making


use of the concessional rates available from multilateral and bilateral
financing institutions and EXIM banks

❏ Introduce a standard tariff, based on its avoided costs, and accompanying


PPA for purchases of surplus energy from industrial enterprises with
their own electricity generation.

Long-term (over three years)

Ministry of Mines and Energy

❏ Actively encourage the expansion of cross-border power trading in the


Greater Mekong Sub-Region and, in particular, the development of
shorter-term trading arrangements

❏ Implement an energy efficiency revolving fund, if prior assessment


considers this feasible

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  12  of  89  
March  2015  
 
 
 
Executive  Summary  
   

Electricity Authority of Cambodia

❏ Revise tariff structures to match the costs of supply for different customer
categories, as necessary

❏ Consider providing incentives for EDC to improve efficiency and reduce


system losses through the application of performance-based regulation

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  13  of  89  
March  2015  
 
 
 
Introduction  
   

1. Introduction

1.1 Background

This   Progress   Report   is   submitted   by   Mr   William   Derbyshire   of   Economic   Consulting  


Associates  Limited  (ECA)  to  the  Cambodia  Chamber  of  Commerce  (CCC).  The  report  has  
been  prepared  under  the  assignment:  

In-­‐Depth   Study   on   Electricity   Cost   and   Supplies  


(TDSP/2012/081/02/1)  

The  assignment  is  being  funded  through  the  Department  of  International  Cooperation  of  
the   Ministry   of   Commerce   under   the   Trade   Development   Support   Program   (TDSP)  
managed  by  the  World  Bank.  

The  purposes  of  the  assignment  are  to:  

❏ Assess  the  causes  of  the  high  prices  of  electricity  supply  for  larger  industrial  
and  commercial  customers  in  Cambodia.  

❏ Develop   evidence-­‐based   recommendations   on   policy   and   regulatory   reforms  


which  can  contribute  to  reducing  these  high  prices.  

These   recommendations   will   be   an   input   to   the   discussions   to   be   held   at   the  


forthcoming   Government   –   Private   Sector   Forum   (G–PSF)   on   how   to   improve   the  
commercial  environment  in  Cambodia.  

1.2 Guide to the report

This  report  has  been  organised  into  the  following  parts:  

Part  I  –  Context    

In   this   part,   we   provide   context   for   the   analysis   and   recommendations   in   the  
remainder  of  the  report.  This  part  contains  two  sections:  

❏ Section   2,   which   provides   an   overview   of   the   power   sector   in  


Cambodia.  

❏ Section   3,   which   compares   the   prices   of   electricity   supply   for   larger  


customers  in  Cambodia  with  regional  benchmarks.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  14  of  89  
March  2015  
 
 
 
Introduction  
   

Part  II  –  Analysis    

In  this  part,  we  analyse  the  potential  causes  of  the  high  costs  of  electricity  supplies  
in   Cambodia.   These   potential   causes   can   be   grouped   into   three   areas,   each   of  
which  we  consider  in  a  separate  section:  

❏ Section   4,   which   looks   at   the   level   of   electricity   supply   costs   in  


Cambodia  and  how  these  might  be  reduced.  

❏ Section  0,  which  looks  at  how  these  costs  are  converted  into  the  actual  
tariffs  paid  by  customers  and  the  extent  to  which  these  reflect  the  costs  
of  supply  to  different  customer  categories.  

❏ Section  6,  which  looks  at  the  efficiency  of  electricity  use  by  customers  
and  the  extent  of  the  contribution  that  individual  customers  can  make  
themselves  to  reducing  their  electricity  costs.  

Part  III  –  Recommendations    

In  this  concluding  part,  we  summarise  our  recommendations  on  actions  to  address  
high   electricity   costs   in   Cambodia.   These   are   organised   by   timing   and   lead  
institution.    

The   analysis   in   this   report   draws   on   publicly-­‐available   documents   and   interviews  


conducted   in   Cambodia   with   representatives   of   government,   the   utility   and   major  
electricity  customers.  A  list  of  interviewees  is  provided  in  Annex  A1.  We  would  like  to  
take  this  opportunity  to  thank  all  those  who  gave  their  time  to  meet.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  15  of  89  
March  2015  
 
 
 
Part  I  -­‐  Context  
   

Part I - Context

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  16  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

2. Cambodia’s power sector

In   this   section   we   describe   Cambodia’s   power   sector   with   a   focus   on   recent  


developments   in   the   supply   mix   and   in   the   level   of   regional   and   national   integration  
which  can  be  expected  to  impact  on  costs.    

We  first  describe  the  main  institutions  in  the  power  sector.  We  then  look  at  the  growth  
in  demand,  then  at  the  supply  mix  (both  generation  in  Cambodia  and  imports),  then  at  
the  transmission  grid  and  finally  at  sub-­‐transmission  and  distribution.    

Box  1  Overview  of  the  electricity  industry  

The   electricity   industry   can   be   broadly   divided   into   four   functions:   (i)   generation   of   electricity;  
(ii)   long-­‐distance   transmission   of   electricity   using   high-­‐voltage   lines   from   generators   to  
distribution  networks;  (iii)  local  distribution  of  electricity  to  final  users  through  medium  and  
low-­‐voltage   lines;   and   (iv)   the   financial   activities   of   buying   electricity   from   generators   and  
selling  it  to  customers,  or  the  retail  supply  of  electricity.    
In  Cambodia,  distribution  and  retail  supply  are  combined  within  entities  and,  therefore,  in  this  
report   we   refer   to   distribution   alone.   However,   Cambodia   does   add   a   further   tier   to   this  
functional   split,   which   is   that   of   sub-­‐transmission.   This   can   be   defined   as   the   onward  
transmission  of  electricity  using  medium-­‐voltage  lines  from  high-­‐voltage  transmission  networks  
to  multiple  low-­‐voltage  local  distribution  networks  in  rural  areas.  

The   definitions   of   high,   medium   and   low-­‐voltage   differ   from   country   to   country.   In   Cambodia,  
high-­‐voltage   (HV)  is  used  to  refer  to  the  115  kV  and  230  kV  voltage  levels,  medium-­‐voltage  
(MV)  to  the  35  kV  and  22  kV  voltage  levels  and  low-­‐voltage   (LV)  to  voltage  levels  of  less  than  
22  kV.  Most  customers  will  be  supplied  at  LV  although  some  large  customers  may  be  supplied  
directly  from  the  MV  network.    

2.1 Major institutions

Ministry of Mines and Energy

The   primary   policy-­‐making   and   planning   entity   for   the   electricity   industry   is   the  
Ministry  of  Mines  and  Energy  (MME).  The  responsibilities  of  MME  include:  

❏ Preparing  policies,  strategies,  rules  and  regulations  for  the  energy  sector.  

❏ Preparing  and  implementing  energy  sector  development  plans.  

❏ Promoting  energy  conservation.  

❏ Setting  technical,  safety  and  environmental  standards.  

❏ Maintaining   and   analysing   data   on   the   supply   and   demand   balance   for  
electricity  and  on  Cambodia’s  energy  resources.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  17  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

❏ Preparing   and   implementing   national   policies   related   to   hydropower  


development.  

❏ Selecting  locations  for  hydropower  projects  and  identifying  priority  projects.  

Electricity Authority of Cambodia

The   Electricity   Authority   of   Cambodia   (EAC)   was   established   under   Cambodia’s  


Electricity  Law,  promulgated  on  2  February  2001.  It  is  an  autonomous  agency  with  its  
own  budget  funded  from  licence  fees.  The  EAC  comprises  a  three-­‐member  commission  
supported  by  a  secretariat.  Its  responsibilities  include:  

❏ Licensing  electricity  enterprises.  

❏ Reviewing  costs  and  approving  tariffs  of  licensed  enterprises.  

❏ Resolving  disputes  between  licensees  and  between  customers  and  licensees.  

❏ Monitoring   and   enforcing   compliance   by   licensees   with   technical   and  


performance  standards.  

Electricité du Cambodge

Electricité   du   Cambodge   (EDC)   is   the   state-­‐owned   electricity   supplier   with  


responsibility  for  the  generation,  purchase,  transmission  and  distribution  of  electricity  
throughout  the  country.  It  was  originally  established  in  1958,  re-­‐established  in  1979  as  
part   of   the   then-­‐Ministry   of   Energy   and   made   responsible   for   electricity   supply   in  
Phnom   Penh.   Supplies   in   other   provincial   cities   were   the   responsibility   of   provincial  
authorities   through   their   departments   of   industry.   In   1996,   EDC   was   reformed   as   an  
autonomous   state-­‐owned   limited   liability   company   with   responsibility   for   electricity  
supply  nation-­‐wide,  absorbing  the  existing  provincial  suppliers.  

EDC   is   jointly-­‐owned   by   MME   and   the   Ministry   of   Economy   and   Finance   (MEF).   Its  
Chairman   is   the   Undersecretary   of   State   for   MME   and   the   Board   of   Directors   also  
includes  representatives  of  MEF,  the  Council  of  Ministers,  the  Ministry  of  Justice,  EDC’s  
employees   and   CCC   as   well   as   EDC’s   Managing   Director.   The   Managing   Director   is   a  
delegate   of   the   Royal   Government   with   responsibility   for   managing   EDC   and   is   the  
equivalent  of  a  Secretary  of  State  within  the  government  hierarchy.    

Other licensees

EDC   is   the   only   entity   licensed   to   conduct   activities   across   the   full   electricity   supply  
chain   including   generation,   transmission,   sub-­‐transmission   and   distribution.   However,  
financial   and   physical   constraints   mean   that   Cambodia   has   always   been   heavily  
dependent   on   private   third   parties   to   generate   electricity   and   sell   this   to   EDC  
(independent  power  producers,  IPPs)  and  to  distribute  electricity,  particularly  in  rural  
areas.   These   third   party   providers   were   formalised   following   the   creation   of   EAC   which  
licensed  them  and  brought  them  under  regulatory  control.  In  more  recent  years,  private  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  18  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

entities  have  also  entered  into  transmission  and  sub-­‐transmission  (although  only  EAC  is  
permitted  to  operate  the  national  transmission  system).    

EDC  is  largely  responsible  for  power  purchase,  transmission  and  sub-­‐transmission  and  
distribution   in   Phnom   Penh   and   major   provincial   towns.   Rural   distribution   is   largely  
undertaken   by   private   licensees.   Private   distribution   licensees   without   their   own  
generating   facilities   purchase   bulk   electricity   supplies   from   EDC’s   sub-­‐transmission  
network,  other  private  licensees  and  from  cross-­‐border  MV  imports  from  Thailand  and  
Vietnam  for  retail  to  final  customers.  

The   number   of   licensees   as   at   end-­‐2013   is   shown   below.   We   also   provide   below   an  


indication  of  the  relative  scale  of  the  different  groups  of  licensees.    

Table  1  Electricity  licensees,  2013  


Licence  type   Valid   at   Smallest  licensee   Largest  licensee  
end   of  
2013  
Consolidated   –   generation,   1   3,339,818,430  kWh  sales  
distribution   and   national   (EDC)   520,378  customers  
transmission  licence    
74,190  kW  capacity  
9,386  km  lines  
Generation  licence   17   70  kW  capacity   338,000  kW  capacity  
Special  purpose  transmission  licence   7   29,154,579  kWh  sales   4,120,170  kWh  sales  
(sub-­‐transmission)   13  km  lines   107  km  lines  
Consolidated   –   special   purpose   7   4,989,681  kWh  sales   89,548,660  kWh  sales  
transmission  and  distribution  licence   4,600  customers   3,952  customers  
Distribution  licence   98   12,077  kWh  sales   62,425,507  kWh  sales  
120  customers   8,475  customers  
Retail  licence   3   1,447,705  kWh  sales  
4,338  customers  
Consolidated   –   generation   and   204   9,802  kWh  sales   36,903,868  kWh  
distribution  licence   25  customers   7,528  customers  
Total   339      
Source:  EAC  

2.2 Electricity demand

Cambodia’s electricity demand is low by regional standards

Cambodia’s   power   sector   is   small   by   regional   (and   international)   standards.   Total  


electricity   sales   in   2014   are   estimated   at   4,312   GWh   or   around   1/25th   of   those   in  
Vietnam  and  1/40th  of  those  in  Thailand.  The  average  electricity  consumption  per  capita  
was   just   280   kWh   annually   compared   to   1,285   kWh   in   Vietnam   and   2,400   kWh   in  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  19  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Thailand.   The   differences   in   average   sales   per   customer   are   less,   but   these   are   still   75%  
higher  in  Vietnam  and  150%  higher  in  Thailand  than  in  Cambodia.  

Figure  3  Cambodia’s  electricity  demand  compared  

 
 
Source:  EAC  /  MME  (Cambodia,  2014  data),  EGAT  /  MEA  /  PEA  (Thailand,  2013  data),  EVN  (Vietnam,  2013  
data)    

Demand is growing very rapidly at up to 20% annually

Electricity   demand   has   been   growing   extremely   rapidly.   Between   2003   and   2014,   the  
annual   growth   in   electricity   sales   averaged   almost   20%   with   total   sales   increasing   by  
over   seven   times.   The   number   of   customers   has   grown   only   slightly   more   slowly,   by  
17%  annually  or  by  six  times  over  the  same  period.  

Cambodia’s   national   power   development   master   plan   is   currently   being   updated   with   a  
draft  under  review  by  MME  at  the  time  of  this  report.  While  this  is  not  yet  public,  we  are  
advised   that   the   master   plan   envisages   continued   annual   growth   rates   of   15-­‐20%   to  
2020.  This  implies  electricity  sales  reaching  10,000-­‐13,000  GWh  in  2020.    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  20  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  4  Electricity  sales  and  customer  numbers,  2003-­‐14  

 
 
Source:  EAC  /  MME  

Demand growth is driven by the expansion of electrification

As   the   close   relationship   between   the   growth   in   demand   and   customer   numbers  
suggests,   this   rapid   increase   is   driven   by   the   expansion   of   electricity   supplies   nation-­‐
wide  rather  than  by  growth  in  demand  among  existing  customers.  From  electrification  
rates   of   just   6.5%   of   communes   (‘khums’)   and   5%   of   households   in   2003,   coverage   is  
estimated   to   have   reached   85%   of   communes   and   60%   of   households   by   2014.  
Expansion   of   electrification   accelerated   from   2009   onwards   with   the   introduction   of  
large-­‐scale   imports   from   Vietnam   and   the   building-­‐out   of   the   rural   sub-­‐transmission  
grid.  The  remaining  unelectrified  areas  are  concentrated  in  the  more  sparsely  populated  
north-­‐east   provinces   and   in   the   mountainous   areas   to   the   south-­‐west   and   north   of  
Cambodia   where   grid   extension   is   less   economic   and   increased   reliance   must   be   placed  
on  off-­‐grid  solutions.    

This   take-­‐off   in   electrification   after   many   years   of   being   among   the   least-­‐electrified  
countries  in  the  world  is  an  impressive  achievement  and  one  on  which  all  concerned  are  
to   be   congratulated.   While   much   remains   to   be   done,   it   means   that   Cambodia’s  
challenge   is   becoming   less   about   expanding   electricity   supply   to   unserved   consumers  
and  more  and  more  about  efficiently  meeting  demand  from  existing  customers.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  21  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  5  Commune  and  household  electrification  rates,  2003-­‐14  

 
 
Source:  EAC  /  MME  

Figure  6  Electrification  coverage,  2014  

 
 
Source:   EAC.   Shaded   areas   are   those   for   which   a   licence   for   electricity   distribution   has   been   issued.   Red   lines  
show  the  extent  of  the  sub-­‐transmission  network  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  22  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Electricitè du Cambodge is the dominant electricity supplier

Although   there   are   over   300   licensed   distributors   of   electricity   in   Cambodia,   sales   are  
dominated   by   the   state-­‐owned   utility,   EDC.   In   2013,   EDC   was   responsible   for   directly  
supplying   over   500,000   customers   with   sales   of   2,824   GWh   (40%   and   80%   of   the  
national   totals,   respectively).   It   also   on   sold   a   further   515   GWh   to   other   electricity  
distributors  connected  to  its  electricity  network.  Most  larger  customers  are  located  on  
EDC’s   network   (its   average   sales   per   customer   are   almost   six   times   those   of   other  
licensees).    

While  EDC  supplies  electricity  in  eleven  isolated  provincial  towns,  the  vast  majority  of  
its   customers   and   sales   are   located   on   the   emergent   national   grid.   As   described   in   more  
detail  later  in  this  section,  this  currently  covers  Phnom  Penh  and  Kandal,  the  southern  
and  north-­‐western  provinces  and  the  west  side  of  the  Tonle  Sap.  

The   rapid   expansion   of   Cambodia’s   electricity   grid   has   seen   a   large   decline   in   the  
relative  importance  of  isolated  mini-­‐grid  systems,  which  were  the  main  sources  of  rural  
electricity   supplies   until   very   recently.   These   mini-­‐grids   use   small   diesel   generators,  
many   of   which   are   old   and   inefficient,   and   are   typified   by   high   costs   and   poor   quality   of  
supply.  In  2003,  there  were  69  such  mini-­‐grids  out  of  77  holders  of  distribution  licences  
with   sales   of   8   GWh   (1%   of   total   sales)   supplying   26,000   customers   (11%   of   total  
customers)1.   By   2013,   the   number   of   isolated   licensees   had   fallen   to   67,   out   of   a   total   of  
310   licensees   authorised   to   distribute   electricity.   While   sales   in   isolated   systems   had  
risen   to   14   GWh   and   the   numbers   of   customers   to   43,500,   this   represented   just   0.3%   of  
total  sales  and  3%  of  total  customers.  

                                                                                                               
1 Source: EAC. The number of isolated mini-grids in 2003 is assumed equal to the number of
consolidated generation and distribution licensees and their sales and customer numbers equal to
those reported for rural areas. Isolated mini-grids are separately identified in 2013 data. These figures
exclude the various licensees located in border areas and importing power from Thailand and
Vietnam at medium voltage.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  23  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  7  Split  of  sales  and  customers,  2013  

Split  of  sales   Split  of  customers  

 
 
 
Source:  EAC  

2.3 Generation and power purchases

Supply is increasingly coming from new hydro and coal capacity

Until  recently,  Cambodia’s  power  sector  comprised  a  set  of  local  grid  systems  grouped  
around   Phnom   Penh   and   major   provincial   cities   with   scattered   isolated   mini-­‐grids  
serving   border   and   some   rural   areas.   The   larger   systems   were   dependent   on   oil-­‐fired  
generation   (both   fuel   oil   and   diesel   power   plants).   This   situation   is   now   rapidly  
changing.  

The  devastation  of  the  1970s  and  1980s  left  the  power  sector  extremely  weak  in  terms  
of   physical   and   financial   resources.   With   economic   recovery   starting   in   the   1990s,   a  
decision  was  taken  to  rely  heavily  on  private  investment  in  new  generating  capacity  in  
the   form   of   Independent   Power   Producers   (IPPs)   developed   on   a   Build-­‐Operate-­‐
Transfer   (BOT)   basis   given   these   constraints.   Initially   these   IPPs   comprised   smaller   oil-­‐
fired   plants   which   could   be   rapidly   deployed   at   relatively   low   up-­‐front   costs.   More  
recently,  much  larger  hydro  and  coal-­‐fired  power  plants  have  been  developed—mainly  
with   Chinese   financing.   The   major   power   plants   (installed   capacity   greater   than   100  
MW)   in   operation   and   under   construction   are   listed   below.   We   understand   that   no  
further   new   large   power   plants   are   planned   or   required   until   2020,   according   to   the  
draft   master   plan   now   under   preparation,   given   the   high   capacity   margin   now   being  
seen  (as  discussed  below).  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  24  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Table  2  Major  power  plants  in  Cambodia  


Name   Type   Capacity  (MW)   Lead  developer   Status  
Kamchay   Hydro   194   Sinohydro  Corporation   Operational  
Stung  Atay   Hydro   120   China   Datang   Operational  
Corporation  
Lower  Stung  Russei  Chrum   Hydro   338   China   Huadian   Operational  
Corporation  
Cambodia  Energy  Limited   Coal   120     Leader   Universal   Operational  
(licensed)   Holdings  (Malaysia)  

Stung  Tatay   Hydro   246   China   National   Heavy   Testing  


Machinery  Corporation  
China   International   Investment   Coal   120   CIIG   (Cambodia)   and   Testing  
Development  Group   Erdos  Hongjun  (China)  
China   International   Investment   Coal   135   CIIG   (Cambodia)   and   Planned   for  
Development  Group   Erdos  Hongjun  (China)   2017  
Lower  Se  San  2   Hydro   400   (200   for   China   Huaneng   Planned   for  
export?)   Corporation   2017/18  
Stung  Cheay  Areng   Hydro   108   Sinohydro  Corporation   Suspended?  
Source:  EAC  and  ECA  research.  Major  power  plants  are  defined  as  those  with  installed  capacity  of  100  MW  or  
greater.  

The  industry  has  also  pursued  a  policy  of  developing  HV  inter-­‐connectors  with  Thailand  
and   Vietnam   to   allow   the   import   of   electricity   to   displace   high-­‐cost   domestic   oil-­‐fired  
generation.   The   first   inter-­‐connector   at   115   kV   with   a   capacity   of   95   MW   (subsequently  
raised   to   135   MW)   linking   Thailand   to   north-­‐west   Cambodia   was   commissioned   in  
2007.  The  second,  at  230  kV  with  a  capacity  of  up  to  200  MW,  linking  Vietnam  to  Phnom  
Penh  was  commissioned  in  2009  although  operating  at  reduced  capacity  initially.    

The  changing  generation  mix  over  time,  given  these  developments,  is  shown  below.  Up  
until  2007,  supply  was  almost  entirely  from  oil-­‐fired  generation  which  represented  over  
85%  of  output.  With  the  commissioning  of  the  inter-­‐connectors  to  Thailand  in  2007  and  
to  Vietnam  in  2009,  imports  replaced  much  of  this  domestic  generation,  reaching  almost  
two-­‐thirds  of  supply  by  2011.  From  2013  onwards,  with  the  growth  of  hydro  and  coal  
generation  in  Cambodia,  imports  in  turn  have  been  scaled  back  and  replaced  with  these  
new  sources.  In  2014,  half  of  generation  was  from  domestic  hydro  and  coal  plants  and  
this   is   expected   to   increase   to   over   two-­‐thirds   in   2015,   with   the   share   of   oil-­‐fired  
generation  reduced  to  just  5%  of  the  total.  

An   implication   of   this   change   is   that   much   existing   commentary   on   Cambodia’s   high  


electricity  costs,  which  have  attributed  this  to  its  reliance  on  oil-­‐fired  generation,  is  now  
outdated.  The  rapid  changes  in  generation  mix  mean  that,  as  we  discuss  in  the  following  
sections,  the  challenge  is  much  more  about  how  to  manage  seasonality  of  hydro  power  
generation  and  temporary  surpluses  of  generation  capacity.    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  25  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  8  Generation  and  power  purchases  by  fuel,  2003-­‐15  

 
 
Source:  ECA  calculations  from  MME  /  EAC  data  

Figure  9  Share  by  fuel  of  generation  and  power  purchases,  2003-­‐15  

 
 
Source:  ECA  calculations  from  MME  /  EAC  data  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  26  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Electricity is almost entirely sourced from IPPs and imports

Electricity   generation   in   Cambodia   is   almost   entirely   from   IPPs.   In   2013,   EDC,   despite  
being   the   dominant   supplier   to   final   customers,   represented   less   than   3%   of   generation  
and  only  around  1%  if  imports  are  included.  These  shares  are  likely  to  have  fallen  still  
further  given  the  additional  IPP  capacity  commissioning  in  2014  and  2015.  

Purchases   from   IPPs   are   under   long-­‐term   power   purchase   agreements   (PPAs).   The  
PPAs  for  new  hydro  power  plants  are  reported  to  range  from  33  to  45  years  in  length  
and  for  new  coal  power  plants  to  be  33  years  in  length.    

We  understand  that  the  PPAs  for  coal  and  hydro  power  plants  developed  on  a  BOT  basis  
include   minimum   quantity   requirements—under   which   EDC   must   pay   for   a   minimum  
quantity  of  energy  whether  or  not  this  is  actually  required  to  meet  demand.  This  creates  
a   guaranteed   revenue   stream   for   the   generator   to   enable   it   to   recover   its   fixed   costs  
(debt  service  and  operating  and  maintenance  costs)  which  do  not  vary  with  output.  It  
also  enables  thermal  power  plants  to  commit  to  a  guaranteed  minimum  volume  of  fuel  
delivery  for  which  they  must  pay  irrespective  of  whether  the  fuel  is  used  or  not.    

For   example,   it   has   been   reported   that   under   the   PPA   for   the   coal   plant   developed   by  
Leader  Universal  Holdings  EDC  must  purchase  the  equivalent  of  86%  of  total  potential  
output  in  each  year,  whether  or  not  this  is  actually  required2.  

Figure  10  Split  of  generation  and  power  purchases,  2013  

 
 
Source:  EAC  

There are now problems of excess generation

The   most   recent   date   for   which   we   have   information   on   national   peak   electricity  
demand  is  2012,  when  demand  peaked  at  575  MW  in  a  year  when  total  energy  supplied  
                                                                                                               
2 JF Apex Securities Bhd (23 September 2009) Leader Universal Holdings Bhd: Cambodia 100 MW Power
Project PPA and IA Signed.
(http://www.leaderuniversal.com/pdf/AnalystCoverage/Apex20090923.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  27  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

was   3,527   GWh,   implying   a   system   load   factor   of   70%3.   Assuming   this   load   factor  
remains   unchanged,   this   would   imply   a   system   peak   demand   in   2014   of   795   MW.   We  
have  been  advised  that  actual  peak  demand  on  the  national  grid  in  2014  was  somewhat  
lower  than  this,  at  around  740  MW.  In  either  case,  this  is  substantially  below  available  
generating   capacity,   reported   at   1,359   MW   in   2014   including   contracted   imports,  
indicating  a  large  surplus  of  generating  capacity.    

With  forecast  annual  demand  growth  of  15-­‐20%,  peak  demand  by  2020  is  projected  to  
be  between  1,800  and  2,400  MW.  By  this  date,  assuming  all  planned  capacity  identified  
in   is   added,   total   installed   generating   capacity   and   contracted   imports   in   Cambodia  
would  reach  2,368  MW.  The  implication  is  that  the  surplus  over  peak  demand  is  likely  to  
be  temporary  if  demand  growth  forecasts  are  realised.    

As   well   as   having   a   temporary   surplus   of   generating   capacity   compared   to   peak  


demand,   Cambodia   also   has   and   is   likely   to   continue   to   have   mismatches   between  
supply   and   demand   at   different   times   of   the   year   and   day.   Hydro   power   output   is  
generally   seasonal—being   greatest   in   the   wet   season   when   water   inflows   are   highest.  
When  reservoirs  are  full  during  this  period  it  will  become  necessary  to  either  generate  
or,   if   demand   is   not   sufficient   to   absorb   this   output,   to   ‘spill’   water   (release   water  
without  generating  electricity).  EDC  is  currently  negotiating  with  Electricity  of  Vietnam  
(EVN)   for   exports   of   hydro   output   during   the   wet   season   when   this   is   in   surplus.  
However,   Vietnam’s   own   electricity   generation   also   follows   a   seasonal   pattern   due   to  
the   large   share   of   hydro   output   and,   hence,   the   value   that   EVN   places   on   additional  
supply  during  the  wet  season  is  low.    

Cambodia   also   has   particular   problems   at   night-­‐time.   During   an   example   day   in   January  
2015   shown   to   us,   night-­‐time   demand   on   the   national   grid   dropped   to   320   MW  
compared  to  morning  and  afternoon  peaks  of  700  MW.  The  same  pattern  (although  at  
lower  levels  of  demand)  can  be  seen  in  the  daily  load  profiles  for  earlier  years  that  are  
publicly  available.  

Coal-­‐fired   power   plants   are   very   inflexible   and   typically   cannot   reduce   output   much  
without   shutting-­‐down.   Given   that   the   process   of   shutting-­‐down   and   restarting   a   coal  
plant  can  take  two  or  more  days,  this  is  generally  to  be  avoided.  It  is  also  not  possible  to  
completely  reduce  imports  over  the  HV  inter-­‐connectors  to  zero.  As  a  result,  Cambodian  
demand   at   night   is   almost   entirely   met   from   the   existing   coal   unit   of   120   MW   and  
reduced   imports.   With   the   commissioning   of   new   coal   power   plants,   night-­‐time  
generation   may   well   exceed   demand   unless   imports   can   be   further   reduced   or   night-­‐
time  demand  raised.  

                                                                                                               
3 Source: EDC. Peak demand represents the maximum demand to be met at a single point in time (in
this case, in one year). Energy sales represent the total demand supplied across the year. The load
factor is the ratio of energy sales to peak demand if sustained for all 8,760 hours in the year (ie, load
factor = energy sales / (peak demand * 8760 hours)). A higher load factor is generally better as it implies a
flatter demand profile and, therefore, less need to retain generating and network capacity which will
only be needed for a few peak hours in each year.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  28  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  11  Average  daily  load  profile  (Phnom  Penh  grid),  2007-­‐12  

 
 
Source:  EDC  

2.4 Transmission

Cambodia has begun to establish a national transmission grid

Until   2007,   Cambodia’s   transmission   network   was   essentially   limited   to   a   ring   line  
around   Phnom   Penh   and   a   connecting   line   to   an   existing   hydro   power   plant.   In   that  
year,  the  commissioning  of  the  inter-­‐connector  from  Thailand  saw  the  start  of  a  north-­‐
western  transmission  grid.  The  southern  grid  began  with  the  inter-­‐connector  between  
Vietnam   and   Phnom   Penh   and   its   extension   to   Sihanoukville.   The   two   grids   have   now  
been   connected   along   the   west   side   of   Tonle   Sap   with   another   line   connecting   to   the  
large  new  hydro  plants  in  Cambodia’s  west,  creating  a  national  transmission  grid  for  the  
first  time.  Further  expansions  are  under  construction  or  planned  to  create  a  second  link  
along   the   east   side   of   Tonle   Sap   and   to   extend   the   transmission   grid   to   Cambodia’s  
north-­‐eastern   provinces.   This   extension,   in   turn,   is   expected   to   lead   to   rapid   demand  
growth  in  these  areas  underpinning  the  demand  forecasts  in  the  updated  master  plan.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  29  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

Figure  12  Growth  of  HV  transmission  grid,  2003-­‐14  

 
 
Source:  EAC  

Figure  13  Cambodia’s  transmission  network,  2014  

 
 
Source:  EAC.  Hollow  red  lines  indicate  operational  230  kV  and  115  kV  lines.  Solid  red  lines  indicate  lines  that  
are  either  under  construction  or  planned  to  2020.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  30  of  89  
March  2015  
 
 
 
Cambodia’s  power  sector  
   

A large part of the grid is owned by private developers

As   with   generation,   Cambodia   has   relied   heavily   on   private   investors   to   develop  


transmission  lines  on  a  BOT  basis  with  EDC  contracting  to  use  these  lines.  As  of  2013,  
EDC  owned  581  km  of  HV  lines  or  45%  of  the  transmission  network  with  the  remainder  
being   owned   by   a   number   of   private   developers.   Of   these,   the   most   significant   are  
Cambodia   Power   Grid   Co   Ltd   (with   294   km   or   23%   of   the   total   length),   which   owns   the  
line   linking   the   north-­‐western   and   southern   grids   along   the   west   side   of   Tonle   Sap,   and  
Cambodia  Power  Transmission  Lines  Co  Ltd  (CPTL,  with  185  km  of  lines  or  14%  of  the  
total   length),   which   owns   the   inter-­‐connector   with   Thailand   supplying   north-­‐west  
Cambodia.  

Multi-­‐lateral   financing   institutions   (MFIs)   such   as   the   Asian   Development   Bank   (ADB)  
and   World   Bank   for   transmission   lines   and   bilateral   donors,   such   as   KfW   of   Germany,  
have  been  active  in  financing  transmission  projects  in  the  past.  Indeed,  ADB  was  one  of  
the   lenders   to   Cambodia   Transmission   Lines   Co   Ltd   for   the   first   HV   inter-­‐connector,   the  
World   Bank   provided   a   loan   to   EDC   to   finance   the   second   with   Vietnam   and   KfW  
financed   part   of   the   southern   transmission   grid.   However,   concerns   have   been  
expressed  over  the  time  taken  to  comply  with  the  environmental  and  social  safeguards  
and  procurement  processes  required  by  these  institutions.    

2.5 Sub-transmission and distribution

Rural sub-transmission and distribution is also characterised by large-scale


private participation

Cambodia’s   grid   electrification   strategy   envisages   that,   ultimately,   each   provincial   town  
will  be  served  by  a  HV  sub-­‐station  drawing  power  from  the  national  transmission  grid.  
This  will  be  transported  to  rural  communities  using  a  network  of  MV  sub-­‐transmission  
lines   connected   to   the   transmission   sub-­‐station   and   following   major   roads.   Distribution  
within   rural   communities   will   be   the   responsibility   of   private   licensees   who   will   buy  
bulk  power  supplies  from  EDC  and  retail  it  to  final  customers.  

While  the  national  grid  is  still  under  development,  the  build-­‐out  of  the  sub-­‐transmission  
network   is   already   well-­‐advanced.   As   can   be   seen   from   Figure   6,   above,   the   network  
now  covers  almost  all  of  the  more  densely-­‐populated  areas  of  Cambodia.    

A  large  part  of  the  sub-­‐transmission  network  has  been  developed  by  private  investors  
for  reasons  of  EDC’s  limited  financial  capacity  and  to  increase  the  speed  of  expansion.  As  
of   2013,   private   sub-­‐transmission   licensees   owned   2,050   km   of   MV   lines,   mostly   in  
Kandal,   Kampong   Cham,   Kampong   Chhnang   and   Kampong   Thom   provinces.   This  
compares   to   EDC’s   total   MV   line   length   of   5,940   km   (which   includes   distribution   and  
well   as   sub-­‐transmission   lines).   There   are   also   incentives   built   into   bulk   power   tariffs  
for   private   licensees   to   construct   their   own   MV   connections   to   the   sub-­‐transmission  
network  rather  than  waiting  for  EDC  to  do  so.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  31  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

3. Cambodia’s electricity prices

In   this   section,   we   review   how   the   level   of   Cambodia’s   electricity   prices   compares  
internationally.   This   report   is   focused   on   the   costs   of   electricity   supply   to   larger  
industrial  customers  in  Cambodia.  The  discussion  of  electricity  prices  in  this  section  and  
elsewhere   in   this   report,   therefore,   focuses   on   these   customers   and   prices   to   other  
customer   categories   are   only   considered   inasmuch   as   they   impact   on   industrial   tariffs  
(eg,   through   the   tariff   structure,   as   discussed   in   Section   0).   As   these   larger   customers  
are   generally   located   in   areas   supplied   directly   by   EDC,   we   have   also   focused   on   the  
tariffs  applied  by  EDC  for  sales  from  the  national  grid.  

3.1 Significance of electricity costs

During   the   course   of   this   study,   we   have   met   with   representatives   of   garment  
manufacturers,  larger  rice-­‐mills  and  a  steel  maker.  Key  points  from  these  interviews  of  
relevance  to  this  study  are:  

❏ Garment   manufacturing:   Electricity   costs   are   a   relatively   small   part   (~4-­‐


5%)  of  total  costs  for  garment  manufacturers4.  However,  they  form  a  much  
larger  part  of  controllable  costs  (~50%  of  costs  are  associated  with  imports  
of   textiles   and   fabrics   and   ~30%   with   labour).   Given   that   garment  
manufacturers  operate  on  very  small  margins,  a  reduction  in  electricity  costs  
can   deliver   a   large   gain   to   the   industry.   The   impact   on   footwear  
manufacturers,  which  is  a  rapidly-­‐growing  part  of  the  sector,  would  be  even  
more   pronounced   as   electricity   is   a   higher   proportion   of   costs   for   these  
firms.   Based   on   information   provided   to   us,   we   estimate   that   current  
electricity  costs  are  around  US$  0.02  per  garment5.    

❏ Rice-­‐milling   and   processing:   Electricity   costs   are   very   significant   as   a   share  


of  total  costs  for  rice-­‐millers  and  packagers.  A  2012  survey  estimates  that  for  
rice   mills   using   electricity,   its   costs   are   around   US$   20   per   tonne   of   milled  
rice   representing   around   4%   of   the   milled   rice   price   and   75%   of   milling  

                                                                                                               
4 This is slightly lower than the figures reported by a 2009 survey conducted by the International
Finance Corporation (IFC). That survey estimated that energy costs on average represent around
16.7% of total production costs and electricity represented 53% of energy costs, or 9% of total costs.
However, there was a very wide range around these averages. Source: BDLink Cambodia, November
2009, Energy Performance in the Cambodia Garment Sector: A Benchmarking Survey, Report for IFC
(http://betterwork.com/cambodia/wp-content/uploads/2013/05/Energy-Performance-in-the-
Cambdia-Garment-Sector.pdf).
5 This would represent around 2% of the factory gate price and 1.5% of the landed cost in the USA

according to a 2009 study of comparative garment costs. The same study estimates that fabric costs
represent 55% of the landed cost of Cambodian exports in the USA and labour costs 4% of the landed
cost. Source: Nathan Associates, September 2009, Cost Competitiveness of Pakistan’s Textiles and Apparel
Industry, Report for USAID
(https://egateg.usaid.gov/sites/default/files/Cost%20Competitiveness%20of%20Pakistan%E2%80%
99s%20Textiles%20and%20Apparel%20Industry.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  32  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

costs6.   Further   electricity   is   required   for   processing   and   packaging   milled  


rice  for  sale.    

❏ Steel   manufacture:   Electricity   costs   represent   around   one-­‐third   of   total  


costs   of   steel   manufacturing 7 .   The   high   electricity   tariffs   (currently   19  
USc/kWh)   are   a   major   constraint   on   competitiveness   of   domestic   industry  
relative  to  imports.    

What   these   interviews   illustrate   is   the   importance   of   reducing   electricity   costs   for  
industry  if  Cambodia’s  targets  for  economic  growth  are  to  be  achieved.  

3.2 Industrial electricity tariffs in Cambodia

The  current  electricity  tariffs  for  industrial  and  commercial  customers  located  in  Phnom  
Penh,  Kandal  and  Kampong  Speu  provincial  town  and  served  by  EDC  are  shown  below.  
Different   tariffs   apply   in   other   provincial   towns   but,   in   general,   are   at   similar   levels.  
Tariffs   are   expressed   as   the   sum   of   the   bulk   power   cost   (generation   or   purchase   plus  
transmission)   to   EDC   and   an   allowance   for   EDC’s   distribution   costs.   This   structure  
results   from   the   adoption,   between   2005   and   2013,   of   a   ‘floating’   tariff   under   which   the  
tariff   was   reset   each   month   based   on   EDC’s   actual   power   purchase   costs   plus   the  
allowed  distribution  margin.  In  2014,  this  reverted  to  a  ‘fixed’  tariff  under  which  tariffs  
are   set   annually   using   EDC’s   projected   costs   of   power   purchase   in   response   to  
complaints   about   the   volatility   of   tariff   levels   and   consequent   difficulties   in   budgeting  
by  customers.  

                                                                                                               
6 Source: SNV, 20 August 2012, Waste to Energy for the Rice Milling Sector in Cambodia: Baseline Study,
Report for the EU (http://www.snvworld.org/download/publications/baseline_report-
in_line_indicators_v2_final_with_snv_template.pdf). This is supported by the Government’s Policy
Document on Promotion of Paddy Rice and Export of Milled Rice, which reports the cost of electricity
for milling as being US$ 23 representing 4% of the milled rice price
(http://www.foodsecurity.gov.kh/sites/default/files/Rice-Policy-Eng.pdf).
7 Based on the information provided to us on electricity bills, tariffs and annual production of steel,

the specific electricity consumption would be around 1,000 kWh per tonne of crude steel. This
appears high by international standards—a modern Electric Arc Furnace using scrap metal would
consume around 300-350 kWh per tonne of crude steel. The differences may represent inefficient use
of electricity or may be due to the small scale of production, the use of older equipment and the
inclusion of electricity costs associated with other parts of the production process.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  33  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

Table   3   Industrial   electricity   tariffs   (Phnom   Penh,   Kandal   and   Kampong   Speu),  
2015  
Customer  category   Bulk  power  cost   Distribution   Tariff  
(USc/kWh)   margin   (USc/kWh)  
(USc/kWh)  
Small  commercial  and  industrial   15.70   3.60   19.30  
(connected  to  public  network  at  0.22  kV  /  0.38  
kV)  
Medium  commercial  and  industrial   15.70   2.80   18.50  
(connected   to   substation   by   LV   feeder,  
monthly  consumption  >20,000  kWh)  
Large  commercial  and  industrial   15.70   2.40   18.10  
(connected   to   substation   by   MV   /   LV   feeder,  
monthly  consumption  >50,000  kWh)  
MV-­‐connected  commercial  and  industrial   15.70   2.00   17.70  
(connected   to   MV   network,   monthly  
consumption  >80,000  kWh)  
Source:  EAC  

With  the  reduction  in  the  share  of  oil-­‐fired  generation  in  total  costs  and,  consequently,  
the  exposure  of  EDC  to  changes  in  world  oil  prices,  EAC  has  approved  a  five-­‐year  tariff  
plan  to  2020.  This  provides  for  staged  reductions  in  tariffs  over  the  period  in  line  with  
expected   falls   in   the   costs   of   electricity   supply   as   well   as   the   introduction   of   a   new  
subsidised  tariff  for  smaller  rural  customers  (with  monthly  consumption  of  less  than  10  
kWh—a   subsidised   rate   already   applies   for   urban   customers   with   monthly  
consumption  of  less  than  50  kWh).  The  plan  is  indicative  rather  than  binding  in  nature  
and  can  be  adjusted  if  EDC’s  costs  change.  

The  path  of  tariffs  for  customers  connected  at  the  MV  level  is  shown  below  (tariffs  for  
other  customer  groups  follow  the  same  profile).  Tariffs  rose  rapidly  in  2005  following  
the  introduction  of  the  floating  tariff,  peaked  in  2008  when  world  oil  prices  also  peaked  
and   then   declined   and   rose   again   with   oil   price.   From   2012   onwards,   tariffs   have  
reduced  with  the  growing  share  of  imports,  hydro  and  coal  supplies  replacing  oil-­‐fired  
generation   and   this   decline   is   projected   to   continue   to   2020   under   the   approved   five-­‐
year  plan.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  34  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

Figure  14  MV  industrial  tariffs,  2003-­‐20  

 
 
Source:   EAC   decisions.   The   tariff   for   2005-­‐13,   when   a   floating   rate   applied,   is   the   unweighted   average   of   the  
monthly  tariff.  

3.3 Competitiveness of Cambodia’s electricity prices

Selection of comparator countries

We  have  compared  Cambodia’s  current  electricity  prices  to  those  in  countries  that  we  
consider   to   have   similar   environments   to   Cambodia   and   those   which   might   be  
considered   direct   competitors   to   Cambodia   in   the   field   of   garments   manufacture—the  
dominant  export  industry  in  Cambodia8.    

Within   the   category   of   neighbouring   countries,   we   have   included   Lao   PDR,   Myanmar,  
the   Philippines,   Thailand   and   Vietnam.   Within   the   category   of   other   emerging  
economies   which   are   garment-­‐dependent,   we   have   included   Bangladesh,   Lesotho   and  
Sri   Lanka.   A   summary   of   the   macro-­‐economic   position   of   these   comparator   countries  
relative  to  Cambodia  is  provided  in  Table  4,  below.  

                                                                                                               
8 In 2012, garments manufacture represented 30% of GDP and 70% of exports (source: IMF).
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  35  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

Table  4  Summary  of  comparator  countries  


Country   Population   GDP  per  capita   Garment  exports    
  millions   US$   US$  million   %  GDP  

Cambodia   14.9   1,028   5,095   32.5%  


Bangladesh   154.7   1,033   23,501   14.5%  
Lao  PDR   6.6   1,594   -­‐-­‐   -­‐-­‐  
Lesotho   1.9   1,190   418   18.4%  
Malaysia   29.5   10,457   4,586   1.5%  
Myanmar   50.5   1,113   438   0.8%  
Philippines   97.5   2,790   1,558   0.6%  
Sri  Lanka   20.7   3,204   4,511   6.8%  
Thailand   67.9   5,676   4,100   1.1%  
Vietnam   88.8   1,901   17,230   10.1%  
Source:  IMF  (population  and  GDP),  WTO  (garment  exports)  

Definition of a ‘typical’ customer

Tariff   structures   can   be   very   different   across   countries.   Depending   on   the   country,  
tariffs  may  include:  

❏ Energy  charges:  for  each  unit  (kWh9)  consumed.  These  may  vary  by  time  of  
day  or  year  and  by  the  voltage  level  of  connection.  

❏ Peak  or  maximum  demand  charges:  for  peak  power  (kW)  drawn  from  the  
system  or,  in  some  cases,  for  the  demand  drawn  at  the  time  of  system  peak.  
These  will  typically  vary  by  the  voltage  level  of  connection.  

❏ Contracted  demand  charges:  for  the  contracted  capacity  of  the  customer’s  
connection  (in  kW  or  kVA).  This  will  differ  from  the  actual  demand  drawn.  

❏ Power   factor   charges:   charged   where   the   customer’s   power   factor   fails   to  
meet  the  minimum  requirements  established  by  the  supplying  utility.  

❏ Customer  service  or  fixed  or  standing  charges:  recovering  the  direct  costs  
of  managing  the  customer’s  account  such  as  metering  and  billing.  

Other  charges  may  also  be  applied.  

                                                                                                               
9 Energy is measured in kWh, which is the product of ‘real’ power, measured in kW, and time (1 kW
supplied for 1 hour is equal to 1 kWh). Real or usable power in alternating current (AC) systems,
which is expressed in kW, differs from ‘apparent’ power, which is expressed in kVA and represents
the maximum capacity that can be supplied. The difference is due to the nature of AC supply under
which watts (W) and volts (V) can follow different cycles and peak at different points. The
relationship between the two is given by the power factor which measures the difference in the peaks
of the two cycles (1 kVA multiplied by the power factor is equal to 1 kW). It is generally desirable to
have the power factor as close to one as possible.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  36  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

A   simple   comparison   of   energy   charges   across   countries   is,   therefore   potentially   very  
misleading.  Instead,  it  is  necessary  to  construct  a  small  set  of  ‘typical’  customers  with  an  
assumed  consumption  volume,  load  or  demand  profile  and  voltage  level  of  connection  
which  can  then  be  used  to  estimate  a  total  bill  by  applying  the  approved  tariff  for  that  
customer  type.  The  total  bill  can  then  be  divided  by  assumed  consumption  to  obtain  an  
average  tariff  or  supply  cost,  expressed  as  a  cost  per  kWh.  

For   these   calculations,   we   have   defined   a   ‘typical’   garments   factory   as   follows,   using  
data  from  a  detailed  energy  audit  of  a  Cambodian  manufacturer.    

Table  5  ‘Typical’  garment  factory  electricity  use  


Item   Units   Value  
Production  (t-­‐shirts)   millions  /  year   20.256  
Employees     5,000  
Electricity  consumption   kWh  /  month   408,750  
Working  hours   06.15  –  22.15   16  
(two  shifts)  
Peak  power  consumption   kW   900  
Power  factor     0.9  
Source:   ECA   based   on   data   from   Energy   Conservation   Center   of   Japan  
(https://www.eccj.or.jp/cooperation/2-­‐1-­‐1/2005-­‐2006/10.pdf).   Peak   power   consumption   is   calculated   from  
electricity  consumption  assuming  340  working  days  per  year.  

3.4 Comparison of supply costs

Using  our  typical  garment  factory,  we  have  calculated  average  tariffs  or  costs  of  supply  
for   larger   industrial   customers   across   our   comparator   countries.   These   are   shown   in  
Figure  15,  below.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  37  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

Figure  15  MV  industrial  tariffs  compared  

 
 
Source:   ECA   calculations   using   data   from   national   electricity   regulatory   and   utilities.   The   tariff   for  
Cambodia  is  that  applicable  for  2015  for  MV  customers  located  in  Phnom  Penh  and  Kandal.  The  tariff  for  the  
Philippines  is  that  applicable  for  customers  served  by  Meralco  using  the  February  2015  generation  charge.  

It   is   evident   that,   even   following   recent   reductions,   Cambodia’s   tariff   for   larger  
industrial   customers   remains   above   that   of   both   regional   comparators   and   other  
countries  with  similar  reliance  on  garment  exports  in  their  economy.  The  average  cost  
of  electricity  supply  in  Cambodia  is  one-­‐quarter  higher  than  that  in  Thailand,  one-­‐third  
higher   than   that   in   Vietnam   and   Malaysia   and   almost   double   that   in   Sri   Lanka   and  
Bangladesh.  This  will  continue  to  leave  Cambodia  at  a  competitive  disadvantage  unless  
these  costs  can  be  reduced.    

We   have   also   calculated   relative   tariffs   for   our   ‘typical’   larger   industrial   customer,   a  
small  industrial  customer  receiving  supply  directly  from  the  LV  network  and  a  domestic  
customer.   Our   assumed   small   industrial   customer   is   based   on   a   small   food   processor   in  
Phnom  Penh,  which  produces  soy  sauce,  soya  milk  and  fish  sauce.  This  customer  has  a  
monthly  consumption  of  830  kWh  and  a  maximum  demand  of  8  kW.    

This   comparison   is   provided   for   a   smaller   number   of   countries   in   the   same   region   as  
Cambodia.  It  shows  that  Cambodia’s  tariffs  across  all  categories  are  higher  than  those  in  
Thailand  and  Vietnam,  although  less  than  those  in  the  Philippines  for  LV  customers.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  38  of  89  
March  2015  
 
 
 
Cambodia’s  electricity  prices  
   

Figure  16  Relative  tariffs  compared  


Average  tariff  

 
 
 
Source:   ECA   calculations   from   EAC   (Cambodia,   2015),   MEA   (Thailand,   2015),   EVN   (Vietnam,   2015)   and  
Meralco  (Philippines,  February  2015)  published  tariffs.  

We   now   turn   to   reviewing   why   costs   in   Cambodia   are   so   high   and   the   potential   to  
reduce  these.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  39  of  89  
March  2015  
 
 
 
Part  II  -­‐  Analysis  
   

Part II - Analysis

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  40  of  89  
March  2015  
 
 
 
Costs  
   

4. Costs

In   this   section,   we   review   the   composition   of   EDC’s   costs   and   compare   these   with   those  
of  a  number  of  a  number  of  regional  utilities.  Based  on  this,  we  draw  conclusions  on  the  
potential   to   reduce   the   costs   of   electricity   supply   by   EDC   and   the   policies   required   to  
achieve  this.  

We   initially   estimate   the   costs   of   generation   and   power   purchases,   transmission   and  
distribution  to  EDC.  We  then  look  at  the  impacts  of  system  losses  and  EDC’s  financing  
mix   on   these   costs.   This   is   followed   by   international   comparisons   and   finally   our  
conclusions  and  policy  recommendations.  

4.1 EDC’s costs

Generation and power purchases

EDC’s  costs  of  generation  and  power  purchase  are  not  separately  identified  in  the  tariff  
decisions  published  by  EAC.  However,  from  these  decisions  it  is  possible  to  identify  the  
estimated  combined  cost  of  generation  and  transmission  for  industrial  customers  on  the  
Phnom  Penh  and  Kandal  grids  (the  ‘bulk  power  cost’)  as  the  tariff  for  these  customers  is  
expressed   as   the   sum   of   this   bulk   power   cost   plus   a   charge   for   use   of   EDC’s   distribution  
network10.  

We   show   below   the   bulk   power   cost   included   in   tariffs.   In   2003   and   2004   and   again  
from   2014,   the   cost   is   the   projected   average   cost   for   the   year.   From   2005   until   2013,  
when  a  ‘floating’  tariff  applied,  it  is  the  average  of  the  actual  monthly  costs  reported  as  
being  paid  by  EDC.  As  can  be  seen,  the  bulk  power  cost  peaked  in  2008  when  oil  prices  
reached   their   historic   maximum   and   has   declined   by   around   20%   since   then   to   an  
estimated  cost  of  15.7  USc/  kWh  for  2015.  

                                                                                                               
10 This charge was established at 2.0 USc/kWh for MV-connected customers in 2005 following the
introduction of a floating tariff and has remained unchanged since then.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  41  of  89  
March  2015  
 
 
 
Costs  
   

Figure  17  Bulk  power  supply  costs,  2003-­‐15  

 
 
Source:  EAC  

We  have  compared  this  bulk  power  cost  with  our  own  estimates  of  the  average  cost  to  
EDC   of   power   purchases   and   its   own   generation   in   2011,   2012   and   2013.   This   is  
calculated  as  the  costs  of  power  and  fuel  purchases,  import  duties  and  depreciation  of  
generation   assets11  in   each   year,   as   reported   in   EDC’s   audited   financial   statements,  
divided   by   the   total   volumes   of   electricity   purchased   and   generated   by   EDC.   This   will  
slightly   understate   the   costs   of   generation   and   purchases   as   it   does   not   allow   for   the  
impacts  of  electrical  losses  in  the  transmission  system,  but  these  can  be  assumed  to  be  
small  (the  majority  of  losses  are  incurred  in  the  distribution  system).    

These   estimates   suggest   that   the   average   cost   of   generation   and   power   purchases   by  
EDC   in   these   years   is   around   14   USc/kWh   with   the   resulting   implied   cost   of  
transmission  being  around  3-­‐3.5  USc/kWh.  

                                                                                                               
11 Assumed to equal depreciation of ‘plant and equipment’.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  42  of  89  
March  2015  
 
 
 
Costs  
   

Figure  18  Breakdown  of  bulk  power  costs,  2011-­‐13  

 
 
Source:  ECA  calculations  from  EDC  audited  financial  statements  

We  have  also  estimated  the  average  generation  cost  to  EDC  in  2014  and  2015.  We  note  
that  public  data  is  limited  on  generation  costs.  EAC  ceased  to  publish  the  average  costs  
of   power   purchases   from   individual   generation   licensees   in   2007   and   of   imports   in  
2010.  Only  limited  and  inconsistent  information  on  the  charges  applicable  under  more  
recent   PPAs   is   available   from   media   reports   and   analyses   by   external   parties.   For   our  
estimates,   we   have   used   information   from   EDC’s   audited   financial   statements   on   the  
costs   in   2013   of   power   purchases   by   source12.   The   resulting   estimates   for   2014   and  
2015  power  purchase  costs  are  shown  below.    

                                                                                                               
12 A copy of these statements was provided to us by EDC. The most recent statements available on
EDC’s website are for 2012, included in the Annual Report for that year. These omit the notes to the
statements which contain the detailed information needed for analysis of EDC’s costs and financial
position.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  43  of  89  
March  2015  
 
 
 
Costs  
   

Table  6  Estimated  average  cost  of  EDC  generation  and  purchases,  2014-­‐15  
Type   Average  cost   2014   2015  
  (USc/kWh)   GWh   US$  million   GWh   US$  million  
(estimated)   (forecast)  
Vietnam  HV  imports   9.89   1,372   135.8   1,039   102.8  
Thailand  HV  imports   13.81   580   80.1   533   73.7  
Hydro   7.48   1,760   131.6   2,307   172.5  
Coal   7.76   754   58.5   1,816   140.9  
Oil  /  other   28.01   407   113.9   277   77.7  
Total     4,873   519.9   5,972   567.5  
Weighted  average  cost  (USc/kWh)     10.67     9.50  
Source:  ECA  calculations  from  EDC  and  EAC  data.  Import  duties  of  7%  and  VAT  of  10%  are  applied  to  the  
cost  of  HV  imports.  

These   estimates   suggest   that   the   expansion   of   coal   and   hydro   generation   should   have  
led  to  average  generation  and  power  purchase  costs  falling  to  around  10  USc/kWh  from  
2014   onwards.   However,   the   approved   industrial   and   commercial   tariffs   for   2014-­‐15  
appear  to  use  an  estimated  generation  cost  of  12-­‐13  USc/kWh.    

From  discussions  with  industry  representatives,  we  understand  that  this  higher  cost  in  
part   reflects   the   high   level   of   installed   capacity   relative   to   peak   demand   and   the  
minimum   quantity   provisions   in   existing   PPAs,   as   described   in   the   preceding   Section  
2.3,   which   lead   to   EDC   paying   for   capacity   and   energy   not   required   to   meet   current  
demand.  This  then  drives  up  the  average  costs.  

As   a   simple   example   of   this,   total   purchases   from   oil-­‐fired   and   other   generation   in   2013  
were  754  GWh,  at  a  total  cost  of  US$  211  million  or  an  average  of  28  USc/kWh.  In  2014,  
total  purchases  from  these  generators  fell  to  407  GWh.  However,  costs  will  have  fallen  
less   than   proportionally   as   much   of   these   costs   will   relate   to   fixed   costs   or   capacity  
charges   under   PPAs   that   do   not   vary   with   actual   output.   In   the   extreme,   where   total  
costs  are  unchanged,  the  average  cost  of  purchases  from  these  generators  would  have  
risen  to  52  USc/kWh  offsetting  the  benefits  of  reducing  the  share  of  oil-­‐fired  generation  
in  total  supplies.    

Transmission

As  described  above,  we  estimate  the  average  cost  of  transmission  in  Cambodia  at  3-­‐3.5  
USc/kWh,   representing   the   difference   between   the   bulk   power   cost   included   in   tariffs  
and   the   actual   average   costs   of   generation   and   power   purchases   of   EDC   in   the   period  
from   2011   to   2013.   This   cost   has   been   falling   over   the   period   but   three   years   is   too  
short  a  time  to  draw  conclusions  as  to  whether  this  is  likely  to  be  a  sustained  reduction.  

We  are  not  able,  from  the  available  data,  to  estimate  what  proportion  of  this  cost  can  be  
attributed   to   EDC’s   own   networks   and   what   proportion   to   payments   to   BOT   project  
owners.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  44  of  89  
March  2015  
 
 
 
Costs  
   

Sub-transmission and distribution

The   costs   of   EDC’s   sub-­‐transmission   and   distribution   network   can   also   be   estimated  
from   the   approved   tariffs   for   industrial   customers.   These   allow   a   margin   of   2.0  
USc/kWh   for   customer   connected   directly   to   EDC’s   MV   network,   implying   that   this   is  
the   average   cost   of   the   MV   distribution   network.   For   the   smallest   customers,   the  
applicable   margin   is   3.6   USc/kWh,   implying   that   the   average   cost   of   the   LV   distribution  
network   is   1.6   USc/kWh.   We   note   that   the   margin   allowed   for   MV   customers   has  
remained  unchanged  since  2005  and  for  LV  customers  since  2006,  implying  either  that  
the  costs  of  distribution  have  not  changed  in  10  years  or  that  these  margins  no  longer  
reflect   costs.   In   the   absence   of   a   detailed   cost   breakdown   for   EDC,   we   are   not   able   to  
determine  which  of  these  is  the  case.  

System losses

System   losses   represent   the   difference   between   energy   generated   and   purchased   and  
that   ultimately   supplied   to   customers.   They   comprise   both   technical   losses,   which   arise  
from   the   electrical   properties   of   transmission   and   distribution   networks   and  
commercial   losses   which   represent   errors   in   metering   and   billing   and   the   theft   of  
electricity.   System   losses   must   be   compensated   by   increased   supply   and,   therefore,  
come  at  a  cost.  However,  it  is  also  not  realistic  nor  economic  to  reduce  them  to  zero—
even  the  best-­‐run  electricity  systems  will  have  losses  of  3-­‐4%.  

Technical  losses  will  generally  be  higher  where  networks  operate  at  lower  voltages,  at  
lower  load  factors,  over  longer  distances  and  use  older  equipment.  The  level  of  technical  
losses  is  estimated  from  modelling  of  the  electricity  system  and  commercial  losses  are  
then   estimated   as   the   difference   between   total   losses   and   these   estimated   technical  
losses.  

The   level   of   system   losses   on   EDC’s   networks   are   shown   below.   These   are   calculated   as  
the   difference   between   total   energy   purchased   and   generated   and   that   sold,   whether   to  
final  customers  or  to  other  licensees  for  resale.  No  breakdown  appears  to  be  available  
between   estimated   technical   and   commercial   losses.   Losses   have   declined   over   time,  
falling   to   just   under   10%   from   2010   onwards   when   the   inter-­‐connector   to   Vietnam  
commissioned  and  remaining  at  this  level  subsequently  (the  figure  for  2012  appears  to  
be  a  statistical  error).  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  45  of  89  
March  2015  
 
 
 
Costs  
   

Figure  19  EDC  system  losses,  2003-­‐13  

 
 
Source:  ECA  calculations  from  EAC  data.  The  2012  value  appears  to  be  a  statistical  error  

Alongside   losses   in   the   transmission   and   distribution   of   electricity,   there   are   also   losses  
arising  from  the  failure  to  collect  payments  for  billed  energy.  These  result  in  lower  than  
expected   cash   inflows   which   must   be   compensated   for   by   either   increasing   tariffs   to  
paying   customers   or   by   reducing   expenditures   and   ultimately   service   quality.   EDC’s  
collection   efficiency   appears   very   good—in   2011,   allowances   for   bad   debts   represented  
just   0.39%   of   annual   revenues   from   electricity   sales   and   this   had   fallen   to   0.27%   by  
2013.  

Financing

EDC  finances  its  own  investments  from  a  mix  of  external  borrowing  and  internal  cash  
generation  from  operations.  A  summary  breakdown  of  investing  and  financing  activities  
from   2011   to   2013   is   provided   below.   As   can   be   seen,   internal   cash   generation  
represents  around  60%  of  financing  in  each  year.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  46  of  89  
March  2015  
 
 
 
Costs  
   

Table  7  Financing  of  EDC’s  investing  activities,  2011-­‐13  


KHR  billions   2011   2012   2013  
Repayments  of  borrowings   3.0   69.6   79.1  
Purchases  of  property,  plant  and  equipment   68.9   140.1   217.6  
financed  by        
Proceeds  from  borrowings   22.9   74.3   124.4  
Other   7.1   2.4   0.3  
Cash  flows  from  operations   42.0   133.1   172.0  
share  in  total  financing   58%   63%   58%  
Source:   EDC   audited   financial   statements.   The   ‘other’   category   represents   net   government   grants   and  
proceeds  from  the  sale  of  fixed  assets.  

EDC’s   outstanding   long-­‐term   debt   takes   the   form   of   borrowing   from   the   World   Bank  
(10%   of   long-­‐term   debt   as   of   December   2013),   ADB   (27%),   KfW   (8%),   MEF   (16%),  
China   EXIM   Bank   (35%)   and   India’s   EXIM   Bank   (3%)13.   External   loans   are   onlent  
through  MEF  at  interest  rates   from  2%   up   to   6.5%   (most   loans  carry   an   interest   rate  of  
2%  or  4%)  and  for  a  term  of  12  to  30  years  (most  loans  are  for  a  term  of  15  years).    

We  show  below  basic  financial  statistics  on  EDC  for  2011  to  2013.  These  are  the  level  of  
gearing  (debt  to  equity  ratio),  the  return  on  assets  which  can  be  compared  to  the  cost  of  
financing   and   the   return   on   equity   which   provides   an   indication   of   the   overall  
profitability  of  EDC.  It  is  apparent  that  EDC  is  generating  very  high  rates  of  return  and  
profits—consistent  with  a  heavy  reliance  on  internal  financing  of  investments.  

Table  8  EDC’s  financial  position,  2011-­‐13  


KHR  billions   2011   2012   2013  
Borrowings  (including  current  portion)   761.4   1,103.8   1,369.8  
Equity   989.7   1,192.2   1,495.5  
Debt:Equity  ratio     43%   48%   48%  
(debt  /  debt+equity)  
Non-­‐current  assets   1,428.1   1,847.2   2,170.5  
Operating  profit   233.2   291.6   400.6  
Return  on  assets     16.3%   15.8%   18.5%  
(operating  profit  /  non-­‐current  assets)  
Profit  before  tax   192.4   257.7   387.1  
Return  on  equity     19.4%   21.6%   25.9%  
(profit  before  tax  /  equity)  
Source:  ECA  calculations  from  EDC  audited  financial  statements  

                                                                                                               
13 Loans from the World Bank, ADB and KfW are for distribution network rehabilitation during the
1990s and construction of HV transmission lines and rural MV sub-transmission lines from 2000
onwards. The loan from MEF is for rural sub-transmission lines constructed between 2011 and 2014.
Loans from China EXIM Bank are for rural sub-transmission lines and a new HV transmission line.
The loan from India EXIM Bank is for a new HV transmission line.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  47  of  89  
March  2015  
 
 
 
Costs  
   

As  previously  noted,  historically,  EDC  has  reduced  its  up-­‐front  financing  requirements  
by   a   heavy   reliance   on   BOT   projects.   There   is   little   available   information   on   which   to  
estimate  the  costs  of  financing  through  BOTs  relative  to  that  of  EDC  directly  financing  its  
own  investments.  The  various  BOT  contracts  have  been  directly  negotiated  rather  than  
competitively  tendered,  and  there  is  little  public  information  on  the  assumed  costs  and  
financing   arrangements   applied   in   these   negotiations   or   any   means   of   verifying   that  
these  are,  indeed,  least-­‐cost.    

It   is   possible   to   make   a   very   limited   estimate   of   the   relative   cost   of   financing   of   BOT  
projects.   The   ADB   provided   a   loan   to   CPTL   to   help   finance   the   construction   of   the   inter-­‐
connector   to   Thailand   and   the   transmission   line   serving   north-­‐west   Cambodia.   In   its  
due   diligence   documentation,   ADB   calculated   that   the   internal   rate   of   return   (IRR)   for  
the  project  is  15.3%14.  Based  on  the  documentation,  of  the  total  project  cost,  75%  was  to  
be  financed  by  loans.  Assuming  an  average  debt  financing  cost  of  10%  which  appears  to  
be   that   applied   in   the   documentation,   this   would   imply   a   return   on   equity   of   around  
30%.  By  comparison,  funding  the  line  from  EDC’s  own  resources  at  a  return  on  equity  of  
20%  and  from  borrowing  from  multilateral  institutions  at  4%,  as  EDC  is  eligible  to  do,  
would  have  implied  a  financing  cost  of  8%  or  half  that  of  the  estimated  actual  cost.  For  
this  particular  project,  the  implied  savings  from  using  public  rather  than  BOT  financing  
would  have  been  around  US$  1.6  million  annually,  equivalent  to  a  saving  of  2  USc/kWh  
on  forecast  2015  import  volumes  of  74  GWh15.    

However,   against   this   needs   to   be   set   the   benefits   of   the   likely   greater   speed   of  
development   of   the   project   on   a   private   sector   basis   and,   therefore,   the   more   rapid  
access  to  lower-­‐cost  imported  electricity  provided  to  customers.  We  provide  below  the  
timelines   to   operation   of   two   major   cross-­‐border   transmission   lines   in   Cambodia   for  
which  information  is  publicly  available.  The  first  is  the  230  kV  inter-­‐connection  between  
Vietnam   and   the   Phnom   Penh   grid   which   was   funded   by   a   World   Bank   loan.   Project  
preparation  began  in  1999,  the  World  Bank  loan  became  effective  in  2005  and  the  line  
became   operational   in   2009.   The   second   is   the   115   kV   inter-­‐connector   between  
Thailand   the   Cambodia’s   north-­‐west   region   which   was   initially   financed   using  
temporary   loans   and   developers’   equity   and   subsequently   partly   refinanced   with   an  
Asian  Development  Bank  (ADB)  loan.  The  original  co-­‐operation  agreement  was  signed  
in   2000,   the   specific   agreements   for   investment   in   the   line   in   2005   and   the   line   became  
operational  at  the  end  of  2008.    

This   comparison   should   neither   be   taken   as   conclusive   nor   as   any   criticism   of   the  
entities   involved.   In   particular,   it   should   be   noted   that   the   World   Bank   and   ADB   are  
required,  as  lenders  of  public  funds,  to  ensure  proper  compliance  with  environmental,  
social   and   procurement   safeguards   which   adds   inevitable   complexity   and   time   to  
approvals  processes.  It  should  also  be  noted  that  the  World  Bank  project  was  far  more  
extensive   than   a   transmission   line   alone,   including   large   rural   electrification  
components,   and   these   would   further   impact   on   processing   and   approvals  
requirements.   Nevertheless,   the   comparison   does   indicate   the   potential   differences   in  

                                                                                                               
14 ADB, June 2007, Proposed Loan: CPTL, Power Transmission Project (Cambodia): Report and
Recommendations of the President (http://www.adb.org/projects/documents/cptl-power-
transmission-project-rrp)
15 Calculated as the difference in annuitised costs assuming a 30-year project life and initial

investment cost of US$ 25 million.


 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  48  of  89  
March  2015  
 
 
 
Costs  
   

speed   of   response   which   have   led   EDC   to   favour   BOTs   and   similar   financing   in   recent  
years,  although  at  significantly  higher  financial  costs.  

In  discussions  with  the  World  Bank  and  ADB,  we  understand  that  both  institutions  are  
seeking   to   streamline   approvals   processes.   For   the   period   covered   by   the   current  
Country  Partnership  Strategy16,  ADB  does  not  propose  to  commit  concessional  funds  to  
the   energy   sector   although   it   will   provide   loans   through   its   private   sector   ‘window’   if  
requested.   The   World   Bank   is   currently   discussing   with   government   its   future  
programme   of   support   and   areas   of   activity   and   this   may   provide   an   opportunity   to  
involve  itself  in  the  energy  sector.  

Box  2  Example  timelines  for  electricity  transmission  projects  in  Cambodia  

Vietnam   –   Phnom   Penh   230   kV   inter-­‐connector  


World  Bank:  Rural  Electrification  and  Transmission  Project17  
September  1999:  Agreement  for  financial  assistance  for  project  preparation  

October  2002:  Project  Information  Document  issued  (outline  design)  

November  2003:  Project  Appraisal  Document  issued  (detailed  design)  

December  2003:  World  Bank  Board  approval  

March  2005:  Loan  effectiveness  

June  2009:  Transmission  line  operational  

Thailand   –   Battambang   and   Siem   Reap   115   kV   inter-­‐connector  


Asian  Development  Bank  –  CPTL  Power  Transmission  Project18    
February  2000:  Cambodia  –  Thailand  power  sector  cooperation  agreement  

July  2002:  EGAT  –  EDC  power  purchase  agreements  signed  

April   2005:   A.S.K.   Co   Ltd   –   EDC   BOT   and   power   transmission   agreements   signed   (rights  
transferred  from  EGAT)  

July  2005:  BOT  contract  and  PTA  novated  from  A.S.K.  Co  Ltd  to  CPTL  

January  2006:  ADB  permanent  financing  requested  

March  2006:  Construction  started  (with  temporary  financing)  

June  2007:  ADB  Board  approval  

December  2007:  Commercial  operations  date  

                                                                                                               
16 ADB (November 2014), Cambodia: Country Partnership Strategy, 2014-18
(http://www.adb.org/sites/default/files/institutional-document/150147/cps-cam-2014-2018.pdf)
17 Information obtained from project-related documents published on the World Bank’s website

(http://www.worldbank.org/projects/P064844/rural-electrification-transmission-project?lang=en)
18 Information obtained from project-related documents published on the ADB’s website

(http://www.adb.org/projects/40914-014/documents)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  49  of  89  
March  2015  
 
 
 
Costs  
   

July  2008:  Loan  effectiveness  

July  2009:  Loan  closing  

4.2 International comparisons

In   this   section,   we   present   a   comparison   of   EDC’s   costs   with   three   international  


comparators:   EVN;   the   Provincial   Electricity   Authority   (PEA),   the   distribution   utility  
serving   Thailand   outside   the   greater   Bangkok   area;   and   Meralco,   the   distribution   utility  
serving   greater   Manila.   These   utilities   have   been   selected   as   also   supplying   emerging  
markets   within   the   South-­‐East   Asian   region   and   being   ones   for   which   cost   data   is  
publicly   available   and   verifiable.   It   should   be   noted   that,   of   these   utilities,   only   EVN  
faces  a  similar  challenge  to  that  of  EDC  in  meeting  rapid  growth  in  demand.  In  the  last  
10   years,   EVN’s   electricity   sales   have   grown   at   12.7%   annually   while   PEA’s   have   grown  
at  4.8%  and  Meralco’s  at  3.6%.  

These  comparisons  are  for  the  costs  of  supply  at  low  voltage,  including  all  distribution  
costs.  They  also  use  a  mix  of  sources  and  definitions  depending  on  which  is  most  readily  
available.  As  such,  they  are  not  directly  comparable  to  the  MV  tariffs  shown  in  Figure  15,  
earlier  in  this  report.  

Cambodia’s costs are significantly higher than those in Thailand and Vietnam,
although lower than those in the Philippines

We  show  below  a  comparative  breakdown  of  the  cost  components  of  EDC’s  retail  tariff  
against   those   of   these   three   utilities.   While   the   data   used   is   inevitably   inconsistent  
across  the  different  entities,  it  is  possible  to  draw  a  number  of  conclusions.  It  is  readily  
apparent  that:  

❏ Cambodia’s   costs   of   generation   and   power   purchase   are   high   relative   to  


those  of  Vietnam  and  Thailand  but  equivalent  to  those  in  the  Philippines.  

❏ The   costs   of   transmission   in   Cambodia   are   higher   than   those   in   all   three  
comparators.    

❏ The  costs  of  distribution  in  Cambodia  are  also  high  relative  to  Thailand  and  
Vietnam  but  less  than  in  the  Philippines.    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  50  of  89  
March  2015  
 
 
 
Costs  
   

Figure  20  Comparative  breakdown  of  retail  tariffs  

 
 
Source:  ECA  calculations  from  EDC  and  EAC  data  (Cambodia,  2014),  EVN  data  (Vietnam,  2013),  EGAT  and  
PEA  data  (Thailand,  2013)  and  Meralco  data  (Philippines,  February  2015).  For  EDC,  the  breakdown  is  of  the  
tariff  for  small  industrial  customers  connected  to  the  LV  network.  For  EVN  and  PEA,  the  breakdown  of  the  
average   retail   tariff   is   shown.   For   Meralco,   the   breakdown   is   of   the   tariff   for   small   industrial   customers  
connected  to  the  LV  network  (General  Service  A  category)  with  a  consumption  of  400  kWh  monthly.  Levies  to  
fund  cross-­‐subsidies  are  only  explicitly  identified  in  the  Philippines.  

The key driver of higher generation costs in Cambodia appears to be the low
level of demand relative to capacity

Generation   and   power   purchase   costs   will   ultimately   depend   on   the   mix   of   supply   in  
each  country.  In  this  regard,  Cambodia  is  now  well-­‐placed  given  the  recent  expansion  of  
hydro   and   coal   capacity   which   would   generally   be   expected   to   be   lower-­‐cost   than   gas  
and   oil-­‐fired   capacity.   Its   generation   mix   and   those   of   the   comparator   countries   is  
shown  below.  On  the  basis  of  domestic  generation  alone,  Thailand  in  particular  would  
be  expected  to  have  much  higher  costs  than  Cambodia  given  its  reliance  on  natural  gas  
in  its  fuel  mix.    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  51  of  89  
March  2015  
 
 
 
Costs  
   

Figure  21  Generation  mixes  compared  

 
 
Source:   MME/EAC   (Cambodia,   2015),   EVN   (Vietnam,   2013),   EPPO   (Thailand,   2014)   and   DOE   (Philippines,  
2013).  

However,   there   are   a   number   of   factors   that   are   likely   to   drive   up   Cambodia’s  
generation  costs  relative  to  those  of  comparator  countries.    

As   we   have   discussed   above,   at   present   Cambodia   has   a   surplus   of   generation   during  


wet  months  and  at  night-­‐time.  As  a  large  part  of  generation  and  power  purchase  costs  
are   fixed   relative   to   output,   this   raises   the   unit   cost   relative   to   countries   with   lower  
capacity   margins.   Low   levels   of   demand   also   force   Cambodia   to   build   smaller-­‐sized  
plants  which  will  tend  to  have  higher  average  costs  (Cambodia  is  currently  building  120  
MW  and  135  MW  coal  plants  whereas  Vietnam  is  using  unit  sizes  of  600  MW).    

EDC   is   currently   trying   to   negotiate   for   the   export   of   surplus   generation   to   Vietnam   but  
it   is   proving   difficult   to   agree   the   terms.   It   is   also   possible   to   relieve   this   problem   to  
some  extent  by  encouraging  shifting  of  electricity  consumption  to  night-­‐time  hours.  

Based   on   our   estimates   of   generation   costs   in   Table   6,   utilising   all   capacity   at   its  
expected  level  would  allow  a  reduction  in  costs  in  2015  of  around  3.4  USc/kWh  for  LV  
customers  (slightly  less  for  higher  voltage  customers)  or  15-­‐20%  19.    

A   further   contributing   factor   will   be   the   import   duties   and   VAT   applied   to   electricity  
imports   into   Cambodia.   We   estimate   that   the   cost   of   these   is   equivalent   to  

                                                                                                               
19 Our calculations of potential cost reductions assume an LV industrial tariff of 19.30 USc/kWh, as
approved for 2015.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  52  of  89  
March  2015  
 
 
 
Costs  
   

approximately   US$   25   million   or   0.5   USc   for   every   kWh   sold.   Removing   them   would  
allow  a  reduction  in  LV  tariffs  of  around  2.5%.    

There  are  also  factors  outside  the  control  of  Cambodia’s  government  which  will  partly  
explain  the  cost  differences  seen.  Cambodia  is  rapidly  developing  new  capacity  to  meet  
demand  growth.  In  other  countries,  much  of  the  generating  capacity  is  older  and  either  
already   depreciated   or   was   built   at   costs   below   the   current   equivalent   which   will  
reduce   their   costs   relative   to   Cambodia.   We   also   note   that   Vietnam   has   historically  
subsidised   electricity   generation   which   will   further   reduce   its   relative   costs.   Most  
notably,   the   state-­‐owned   Vietnam   Coal   and   Minerals   Corporation   has   supplied   coal   to  
the  electricity  industry  at  prices  around  two-­‐thirds  of  world  market  levels.  

However,   the   impact   of   these   other   factors   on   costs   in   Cambodia   relative   to   those   of  
other   countries   should   not   be   exaggerated.   Cambodia   is   not   unique   in   much   of   its  
capacity   being   relatively   recent—around   half   of   Vietnam’s   generating   capacity   was  
added  in  the  last  five  years  compared  to  around  60%  (including  contracted  imports)  in  
Cambodia.   The   impacts   of   subsidies   in   Vietnam   on   relative   cost   levels   are   also   declining  
as  world  coal  prices  fall  and  Vietnamese  production  becomes  unable  to  meet  demand,  
necessitating  imports.  

Higher transmission costs also appear to be primarily due to lower levels of


demand

The   higher   transmission   costs   can,   at   least   partially,   be   attributed   to   a   combination   of  


economies  of  scale  in  these  activities  and  to  the  lower  volumes  and  levels  of  utilisation  
of  EDC’s  transmission  network  relative  to  that  in  the  comparator  countries  which  will  
result   in   higher   unit   costs,   even   if   the   absolute   level   of   costs   is   the   same.   This   is  
illustrated  below.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  53  of  89  
March  2015  
 
 
 
Costs  
   

Figure  22  Levels  of  utilisation  of  transmission  lines  compared  

 
 
Source:  ECA  calculations  from  EDC  and  EAC  data  (Cambodia,  2013),  EVN  data  (Vietnam,  2013)  and  EGAT  
data  (Thailand,  2013).  Data  is  not  available  for  the  Philippines.  

The  heavy  reliance  on  BOTs  to  develop  new  transmission  lines  may  also  be  driving  up  
costs   relative   to   networks   financed   by   state-­‐owned   utilities   in   Thailand   and   Vietnam.  
However,  it  is  difficult  to  assess  the  impacts  of  this  given  that  we  lack  the  data  to  break  
out  the  costs  of  these  lines  from  those  lines  owned  by  EDC.    

There   are   also   country-­‐specific   factors   which   may   impact   on   the   comparisons.   In  
Vietnam,   regulated   transmission   charges   are   considered   by   many   to   be   set   at   a   level  
below   the   full   costs   of   the   transmission   company   which   means   that   the   low   charge  
shown  may  not  fully  reflect  the  actual  costs20.  In  Thailand,  the  transmission  function  is  
integrated   with   those   of   generation   and   power   purchases.   Therefore,   the   low   costs  
shown   might   partly   be   due   to   decisions   on   the   allocation   of   shared   costs   between  
generation  and  transmission  activities.  

Overall,  we  expect  average  transmission  costs  to  fall  as  utilisation  of  the  network  grows  
but   cannot   readily   estimate   the   impacts   given   the   lack   of   data   on   EDC’s   own  
transmission  costs  and  those  of  its  contracts  with  transmission  BOTs.  

Higher distribution costs in Cambodia are less easy to explain

While   the   relative   size   of   EDC’s   distribution   business   is   much   smaller   than   that   of   the  
comparators,   the   level   of   utilisation   of   its   distribution   network   would   appear   to   be  
                                                                                                               
20 For example, the approved charge allows for a return of only 1% on equity.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  54  of  89  
March  2015  
 
 
 
Costs  
   

higher  than  that  for  Thailand  and  Vietnam.  Therefore,  this  alone  would  not  explain  the  
higher  costs  seen  in  Cambodia21.    

Figure  23  Levels  of  utilisation  of  distribution  lines  compared  

 
 
Source:   ECA   calculations   from   EDC   and   EAC   data   (Cambodia,   2014),   EVN   data   (Vietnam,   2013),   PEA   data  
(Thailand,  2013)  and  Meralco  data  (Philippines,  2013).  

This  does  suggest  that,  if  low  utilisation  is  not  driving  up  costs,  then  there  may  be  scope  
for   EDC   to   achieve   efficiency   gains   in   electricity   distribution.   As   an   example   of   the  
potential  magnitude  of  such  efficiency  improvements,  reducing  the  gap  between  EDC’s  
distribution  costs  and  those  of  PEA  by  half  would  allow  a  reduction  in  tariffs  of  around  1  
USc/kWh.    

One   of   the   most   obvious   drivers   of   higher   distribution   costs   appears   to   be   the   lower  
levels   of   sales   and   customers   per   employee   in   Cambodia   relative   to   comparator  
countries.  However,  the  impacts  of  this  lower  labour  productivity  is  offset  by  the  lower  
salaries  in  Cambodia.  The  costs  of  salaries  and  other  employee  benefits  were  equivalent  
to   0.75   USc/kWh   in   2013   or   4%   of   EDC’s   revenues.   A   halving   of   these   costs   would,  
therefore,   only   deliver   a   reduction   in   tariffs   of   around   0.4   USc/kWh   or   2%   for   LV  
customers.    

It  may  also  be  that  the  current  margins  simply  no  longer  reflect  distribution  costs,  given  
they   have   not   been   revised   for   10   years.   A   detailed   cost   analysis   would   help   assess  
whether  this  is  the  case.  

                                                                                                               
21 It is noticeable that Meralco has both the highest cost and the greatest level of network utilisation,
indicating that this is not the only explanation of relative costs.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  55  of  89  
March  2015  
 
 
 
Costs  
   

Figure  24  Employee  productivity  compared  


Sales  per  employee  

 
 
Customers  per  employee  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  56  of  89  
March  2015  
 
 
 
Costs  
   

Source:  ECA  calculations  from  EDC  and  EAC  data  (Cambodia,  2014),  PEA  data  (Thailand,  2013)  and  Meralco  
data   (Philippines,   2013)   and   reported   values   from   AF   Mercados   (Vietnam,   2012).   Data   for   Vietnam   is   for  
Power  Corporations  (distribution  companies)  only.  

System losses

A   comparison   of   system   losses   is   provided   below.   EDC’s   system   losses   are   similar   to  
those  of  EVN  but  significantly  above  those  of  Thailand  and  the  Philippines.  The  figures  
for  the  Philippines  are  not  directly  comparable  to  those  for  the  other  countries  as  they  
only  relate  to  distribution  losses  and  do  not  include  losses  on  the  transmission  system.  
If  these  were  included,  the  level  for  system  losses  would  be  likely  to  be  comparable  to  
those  in  Cambodia  and  Vietnam.  

Figure  25  System  losses  compared  

 
 
Source:   Source:   ECA   calculations   from   EDC   and   EAC   data   (Cambodia,   2014),   EVN   data   (Vietnam,   2013),  
EGAT   and   PEA   data   (Thailand,   2013)   and   Meralco   data   (Philippines,   February   2015).   For   Meralco,   only  
distribution  system  losses  are  shown.  

EDC’s   network   has   historically   operated   at   lower   voltages   than   those   of   the   comparator  
utilities   shown   here,   all   of   which   include   significant   lengths   of   HV   lines   which   should  
reduce   losses.   Against   this,   much   of   EDC’s   network   is   relatively   new   or   was   relatively  
recently  rehabilitated  which  should  reduce  EDC’s  own  losses.    

Overall,  we  conclude  that  EDC  is  not  performing  particularly  well  or  badly  relative  to  its  
peers   as   regards   the   level   of   system   losses.   However,   there   remains   scope   for  
improvement.  While  EDC  did  manage  to  reduce  losses  significantly  up  to  2010,  the  level  
seems   to   have   remained   fairly   constant   since   then.   By   contrast,   even   in   a   relatively  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  57  of  89  
March  2015  
 
 
 
Costs  
   

mature  network  with  older  equipment,  Meralco,  for  example,  has  continued  to  achieve  
large  improvements  over  time.    

It   is   worth   noting   that   Meralco   is   unique   among   these   utilities   in   operating   under   a  
performance-­‐based   regulation   (PBR)   regime   which   includes   incentives   to   reduce  
system  losses.  The  Energy  Regulatory  Commission  (ERC)  sets  an  allowed  cap  on  system  
losses   which   is   used   to   calculate   the   amount   of   the   associated   costs   that   can   be  
recovered   from   tariffs22.   Meralco   bears   the   additional   cost   if   actual   losses   exceed   this  
cap  and  retains  the  savings  if  it  reduces  losses  below  the  cap.  The  effectiveness  of  this  
mechanism  in  encouraging  improvements  in  system  losses  can  be  seen  below.  

Figure  26  Meralco’s  system  losses  and  regulated  cap,  2003-­‐13  

 
 
Source:  Meralco  

As   an   indication   of   the   potential   impacts   on   tariffs   of   reducing   system   losses,   a  


reduction   of   two   percentage   points   from   2013   levels,   closing   half   of   the   gap   between  
EDC’s   losses   and   those   of   EGAT/PEA,   would   reduce   generation   and   power   purchases  
required   to   meet   demand   in   2015   by   around   130   GWh23.  This  could  allow  savings  of  up  
to   US$   16   million   in   generation   costs,   equivalent   to   around   0.30   USc/kWh   or   2%   of  
tariffs.   However,   these   benefits   might   be   partly   offset   by   the   current   structure   of   power  
purchase  costs  which  mean  that  lower  levels  of  purchases  due  to  reduced  system  losses  
translate  into  largely  unchanged  total  costs  and  higher  average  costs—as  is  the  case  at  
present   where   demand   for   electricity   does   not   fully   utilise   all   contracted   generating  
capacity.  

                                                                                                               
22 The current cap is set at 8.5% for all private distribution utilities which primarily serve urban areas
and 12% for electric cooperatives which serve most smaller urban and rural areas.
23 This assumes all reductions in system losses result in a reduction in the generation required to meet

an unchanged level of demand. In practice, some part of these losses, if commercial in nature, would
be likely to be converted into increased metered sales of electricity (eg, by correcting metering errors
or charging for electricity that was previously stolen). This will increase billed sales but not reduce
generation requirements.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  58  of  89  
March  2015  
 
 
 
Costs  
   

Financing

EDC   is   heavily   reliant   on   BOTs   for   financing   of   new   generation   and   transmission  
investment  and  more  so  than  comparator  countries.  In  2015,  new  coal  and  hydro  BOT  
projects   are   expected   to   represent   around   70%   of   energy   supplied.   In   Vietnam,   by  
contrast,  purchases  from  BOTs  and  other  non-­‐EVN  generators  represent  around  55%  of  
total   supplies   and   in   Thailand   around   60%   of   supplies   (including   from   BOT   projects  
located  in  Lao  PDR)24.  Cambodia  is  unique  in  the  region,  as  far  as  we  are  aware,  in  using  
BOTs  to  fund  transmission  projects.    

This  decision  to  rely  heavily  on  BOT  financing  of  major  new  projects  will  tend  to  raise  
costs   relative   to   the   alternative   of   EDC   financing   investments   using   its   own   funds   and  
borrowing  from  multilateral  and  bilateral  financing  institutions.  However,  these  lower  
costs  need  to  be  offset  against  the  likely  longer  development  time  required  for  projects  
funded  directly  by  EDC  given  the  requirements  of  multilateral  institutions.  It  is  also  the  
case  that  funding  from  multilateral  institutions  may  well  not  be  available  for  new  coal  
and   hydro   projects   in   any   event—these   are   seen   as   very   controversial   and   difficult   to  
support  by  the  World  Bank  and  ADB  in  particular.  But  these  institutions  are  willing  to  
lend  for  transmission   and   distribution  investments  if  opportunities  are  available,  as  has  
been  evident  in  Cambodia  in  the  past  and  currently  in  Vietnam.  

We   show   the   composition   of   financing   of   debt   service   and   new   investments   for   each,  
below.  For  Vietnam,  for  better  comparability  with  EDC,  we  show  the  financing  mix  used  
by   the   transmission   utility,   the   National   Power   Transmission   Corporation   (NPT)   as  
much  of  EVN’s  financing  activities  are  related  to  generation  assets  which  EDC  does  not  
directly   finance   itself.   EDC’s   financing   mix   appears   closer   to   that   of   the   more   mature  
utilities  in  Thailand  and  the  Philippines  despite  its  need  for  rapid  expansion  which,  we  
would   expect,   would   tend   to   be   financed   more   from   debt   to   be   repaid   from   future  
increased  sales  rather  than  funding  from  current  customers.  This  is  the  case  for  NPT  in  
Vietnam.  

                                                                                                               
24 The majority of power generation in the Philippines is now privatised including that belonging to
the former state-owned generating utility. However, this is not on a BOT basis but rather through the
sale of existing assets.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  59  of  89  
March  2015  
 
 
 
Costs  
   

Figure  27  Financing  of  investments  compared  

 
 
Source:  ECA  calculations  from  audited  financial  statements  for  EDC  (Cambodia,  2013),  NPT  (Vietnam,  2013),  
PEA  (Thailand,  2013)  and  Meralco  (Philippines,  2013)  

Looking   at   financing   statistics,   EDC’s   gearing   (debt   to   equity   ratio)   is   higher   than   that  
for   both   PEA   and   Meralco.   However,   as   noted   above,   these   are   both   relatively   mature  
utilities.   EDC’s   gearing   is   much   lower   than   that   of   NPT   which   is   more   comparable   given  
that   it   is   also   investing   heavily   to   meet   rapid   growth   in   demand.   What   is   also   noticeable  
is  that  EDC’s  return  on  equity  (ROE)  is  much  higher  than  that  of  PEA  and  NPT.  Although  
it  is  below  that  of  Meralco,  these  figures  are  not  directly  comparable  as  the  return  for  
Meralco  includes  both  profits  on  its  regulated  network  business  and  on  its  unregulated  
power  generation  business  (which  has  no  equivalent  in  EDC).    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  60  of  89  
March  2015  
 
 
 
Costs  
   

Figure  28  Gearing  and  returns  compared  

 
 
Source:  ECA  calculations  from  audited  financial  statements  for  EDC  (Cambodia,  2013),  NPT  (Vietnam,  2013),  
PEA  (Thailand,  2013)  and  Meralco  (Philippines,  2013)  

It   is   worth   considering   the   returns   earned   by   regulated   electricity   networks   in   other  


countries,   which   are   around   6%   to   8%   in   real   (excluding   inflation)   terms   or   8.5%   to  
10.5%  in  nominal  terms  (including  inflation)  for  Cambodia25.    

                                                                                                               
25 The year-on-year change in the Consumer Price Index for Phnom Penh in November 2014 (the most
recent date for which data is available) was 2.36%. Source: National Bank of Cambodia
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  61  of  89  
March  2015  
 
 
 
Costs  
   

Table  9  Regulatory  decisions  on  return  on  equity  for  electricity  companies  
Country:  Activity   Approved  ROE   Source  
nominal  /  real  
USA:  Electricity  distribution     10.02%  /  8.44%   Concentric   Energy   Advisors,   8  
(average,  2013)   May   2014,   Authorized   Return   on  
Equity:  Volume  II  
Canada:  Electricity  distribution     8.32%  /  7.29%    
(average,  2013)  
Canada:  Electricity  transmission     8.39%  /  7.36%    
(average,  2013)  
Germany:  Electricity  transmission   9.05%  /  6.39%   BNetzA  decision  
(new  installations,  2011)  
Australia:  Electricity  distribution   8.69%  /  5.94%   Australian   Energy   Regulator,  
(Aurora  Energy,  2012)   April   2012,   Final   Distribution  
Determination:   Aurora   Energy   Pty  
Ltd,  2012-­‐13  to  2016-­‐17  
Philippines:   Electricity   17.09%  /  8.43%   Energy  Regulatory  Commission,  9  
transmission   (ERC  mid-­‐point  estimate,  2009)   September  2009,  Regulatory  Reset  
for  NGCP:  Position  Paper  
Singapore:  Electricity  generation   9.08%  /  6.39%   Energy   Market   Authority,   22  
(Vesting   contract   price   September   2014,   Review   of  
parameter,  2015-­‐16)   Vesting  Contract  Price  Parameters:  
Final  Determination  Paper  
Source:   As   noted.   Adjustments   to   real   values   are   made   using   the   inflation   estimate   defined   by   the   regulatory  
agency  in  their  decision  or,  where  not  available,  the  annual  average  change  in  CPI  for  the  relevant  year  

It   does   appear   that   there   is   scope   for   reducing   the   costs   of   financing   network  
investments  by  making  greater  use  of  borrowing  by  EDC,  particularly  from  multilateral  
and  bilateral  institutions  given  the  lower  rates  offered,  and  by  setting,  for  the  purposes  
of  determining  regulated  tariffs,  an  allowed  return  on  equity  closer  to  that  of  regulated  
electricity   network   utilities   elsewhere.   Our   estimate   is   that   increasing   gearing   from  
48%  to  60%  and  reducing  EDC’s  return  on  equity  from  26%  to  10%  would  reduce  EDC’s  
costs  by  the  equivalent  of  1.7  USc/kWh  or  around  10%  of  the  tariff.  

We  do  recognise  that  EDC  is  seeking  such  finance  but  has  been  reluctant  to  turn  to  some  
potential   lenders,   such   as   the   World   Bank,   due   to   poor   part   experience   over   the   time  
required   for   processing   loans.   It   will   also   require   approval   from   MEF   where   entering  
into  new  external  loans.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  62  of  89  
March  2015  
 
 
 
Costs  
   

4.3 Conclusions and recommendations

In  this  section,  we  have  reviewed  the  components  of  EDC’s  costs  and  compared  these  to  
regional  utilities.  We  conclude  that:  

❏ Oil-­‐fired   generation,   which   historically   drove   Cambodia’s   high   electricity  


costs,   has   by   now   been   almost   entirely   displaced   by   imports   and   domestic  
hydro   and   coal-­‐fired   generation.   The   use   of   hydro   and   coal   generation   is  
expected   to   continue   to   increase,   now   displacing   imports   and   further  
reducing  costs.  

❏ However,   these   reductions   are   not   fully   realised   in   tariffs   at   present,   in   large  
part   due   to   the   excess   capacity   relative   to   demand   at   certain   times   of   the  
year  and  day  and,  due  to  restrictive  PPAs,  the  need  to  continue  to  pay  for  this  
capacity   even   when   not   required.   Our   estimates   are   that   increasing  
utilisation  could  reduce  generation  costs  by  around  3  USc/kWh.    

❏ EDC’s   estimated   transmission   costs   are   noticeably   higher   than   those   for  
regional  comparators.  This  may  be  due  to  low  levels  of  utilisation  and,  hence,  
higher   average   costs.   But   the   reliance   on   BOTs   to   finance   many   lines   may  
also   be   driving   up   costs—our   own   estimates   are   that   the   associated   higher  
financing  costs  may  represent  a  higher  charge  of  up  to  2  USc/kWh  relative  to  
EDC-­‐financed  transmission  lines.  

❏ EDC’s   distribution   margins   are   also   higher   than   those   for   regional  
comparators.   This   cannot   be   explained   by   lower   levels   of   utilisation   of  
distribution  networks  in  Cambodia.  It  may  represent  inefficiencies  in  EDC’s  
operations   (for   example,   labour   productivity   appears   much   lower   than   in  
comparators).  It  may  also  be  due  to  margins  moving  out  of  line  with  actual  
costs,   given   they   have   not   been   adjusted   for   10   years.   In   either   case,   there  
appears  to  be  scope  for  reductions  in  the  margin  included  in  tariffs.  

❏ EDC   has   reduced   system   losses   over   time.   However,   these   now   appear   to  
have   stagnated.   Further   reductions   should   be   possible,   although   the   benefits  
will  be  limited  so  long  as  reductions  in  demand  do  not  lead  to  corresponding  
reductions  in  generation  costs.  

❏ EDC   relies   heavily   on   its   own   cash   flows   from   operations   to   fund  
investments.  Increasing  the  share  of  debt  in  the  financing  mix  should  allow  it  
to   reduce   financing   costs.   EDC’s   return   on   equity   is   also   high   relative   to  
similar   entities   internationally.   We   estimates   that   reducing   the   return   on  
equity   used   to   calculated   tariffs   and   raising   gearing   could   deliver   cost  
reductions  equivalent  to  around  1.5  USc/kWh.  

❏ A   general   comment   is   that   detailed   information   on   EDC’s   costs   and   how  


these   relate   to   approved   tariffs   is   lacking.   EAC   and   EDC   publish  
comprehensive  physical  data  on  sales,  output,  capacities,  line  lengths  and  so  
forth  but  little  financial  data.  This  makes  it  hard  to  assess  how  well  current  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  63  of  89  
March  2015  
 
 
 
Costs  
   

tariffs  reflect  costs,  the  relative  efficiency  of  EDC  and  the  extent  to  which  cost  
reductions  are  feasible.  

Our  recommendations  follow  from  these  conclusions.  They  are  that:  

❏ EAC   should   publish   in   full   its   assessment   of   EDC’s   costs   used   to  


determine   tariffs,   to   allow   a   better   understanding   by   stakeholders   of   the  
relationship   between   tariffs   and   costs   and   to   help   assess   EDC’s   relative  
efficiency  and  scope  for  cost  reductions.  

❏ An   immediate   reduction   in   costs   could   be   achieved   by   exempting  


electricity   imports   from   duties   and   VAT.   Previous   analyses   has   also  
identified  this  as  a  means  of  rapidly  lowering  electricity  costs.  However,  the  
falling   share   of   imports   in   the   supply   mix   means   that   the   impacts   are   also  
declining.   Our   estimate   is   that   such   an   exemption   would   lower   costs   in   2015  
by  around  0.5  USc/kWh.  

❏ EDC   should   continue   to   pursue   an   agreement   with   Vietnam   allowing  


exports   of   surplus   generation   in  the  wet  season  and  at  night-­‐time.  In  the  
longer   term,   Cambodia   should   actively   encourage   the   expansion   of  
cross-­‐border   power   trading   in   the   Greater   Mekong   Sub-­‐Region,   under  
the   institutional   arrangements   already   in   place 26 ,   and   in   particular   the  
development   of   shorter-­‐term   trading   arrangements.   This   will   provide   a  
means  for  Cambodia  to  better  balance  supply  and  demand  on  its  electricity  
system.  

❏ Future  power  planning  needs  to  recognise  the  trade-­‐offs  between  cost  
and  flexibility.  The  further  development  of  large-­‐scale  hydropower  projects  
should,   in   particular,   be   constrained   unless   these   have   the   capability   to  
reliably  generate  in  dry  seasons  and  to  limit  output  in  wet  seasons.  The  use  
of  smaller  coal-­‐fired  units  or  ones  with  greater  operating  flexibility  should  be  
considered.    

❏ A   fuller   analysis  of  EDC’s  transmission  and  distribution  costs  should  be  
undertaken  relative  to  the  current  allowances   included   in   tariffs   and   the  
two  brought  into  alignment.  

❏ Consideration  should  be  given  to  providing  incentives  for  EDC  to  improve  
efficiency   and   reduce   system   losses   through   the   application   of  
performance-­‐based   regulation,   along   the   lines   of   the   system   loss   cap  
applied  to  Meralco,  for  example.  This  might  start  by  targeting  system  losses  
and,  if  successful,  be  expanded  to  other  cost  components.  This  does  assume  
that   EDC’s   management   and   employees   are   motivated   to   respond   to   the  
profit  incentives  inherent  in  such  regulatory  methodologies.  

❏ EDC   should   move   to   a   greater   reliance   on   debt   financing   of   new  


investments   making   use   of   the   concessional   rates   available   from  
multilateral   and   bilateral   financing   institutions   and   EXIM   banks.   The   use   of  
                                                                                                               
26 See http://www.adb.org/publications/series/proceedings-meetings-gms-regional-power-trade-
coordination-committee-rptcc for a description of the current status of regional institutions.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  64  of  89  
March  2015  
 
 
 
Costs  
   

BOTs   to   fund   network   investments   should   be   avoided   given   the   higher  


financing  costs  these  impose.  

❏ In   approving   tariffs,   EAC   should   allow   EDC   to   earn   a   return   on   equity  


consistent   with   international   and   regional   comparators.  This  would  be  
around  10%  in  comparison  to  the  current  levels  of  25%.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  65  of  89  
March  2015  
 
 
 
Tariffs  
   

5. Tariffs

In  this  section,  we  look  at  how  the  costs  of  electricity  supply  are  converted  into  tariffs.  
Our   focus   is   on   whether   the   existing   tariff   structure   is   cost-­‐reflective   and,   if   not,   what  
would   be   the   impacts   of   changes   in   the   structure   on   the   prices   paid   by   industrial  
customers.   We   also   look   at   the   recently   introduced   Time-­‐of-­‐Use   (TOU)   tariff   and   its  
potential  benefits  to  industrial  customers.  

5.1 Principles of tariff design

The   general   principle   is   that   tariffs   should   reflect   the   costs   of   supply   to   different  
customer   categories.   Deviations   from   this   principle   in   the   form   of   subsidies   may   be  
necessary   to   achieve   social   objectives   (such   as   lowering   electricity   prices   for   poorer  
households)   but   these   should   be   kept   limited   in   nature,   be   clearly   defined   and   be  
funded  in  the  least  distortionary  manner  possible.  Deviations  may  also  be  necessary  to  
reflect   externalities   not   captured   in   existing   costs   of   supply,   such   as   the   use   of   a   carbon  
tax  to  reflect  the  costs  imposed  by  greenhouse  gas  emissions,  but  this  goes  beyond  the  
scope  of  the  current  report.  

Simplifying,  there  are  three  main  determinants  of  the  share  of  costs  to  be  allocated  to  
any  individual  customer:  

❏ The   voltage   level   of   supply.   Supply   at   lower   voltages   requires   the   use   of  
more   network   assets   and   incurs   higher   levels   of   system   losses   (which  
increase  as  voltage  reduces).  Therefore,  other  things  being  equal,  a  customer  
supplied  at  a  lower  voltage  level  should  face  a  higher  tariff.  

❏ The  concidence  of  timing  between  the  peak  demand  of  the  customer  and  
system   peak   demand.   An   electricity   system   (generating   capacity   and  
networks)   is   sized   to   meet   peak   demand   on   the   system   as   a   whole.   During  
off-­‐peak   periods,   much   of   this   capacity   is   not   needed   to   meet   system  
demand.   Therefore,   the   costs   of   constructing   and   maintaining   this   capacity  
should  be  allocated  to  those  customers  contributing  the  most  to  system  peak  
demand—which  drives  the  need  for  it.    

❏ The   size   of   the   customer.   The   costs   of   metering,   billing   and   other   customer-­‐
related   services   do   not   increase   in   line   with   sales   but   instead   are   largely  
fixed.   Therefore,   customers   with   lower   levels   of   sales   should   generally  
expect  to  face  higher  unit  charges  (in  kWh)  for  these  services.  

We   illustrate   the   relationship   between   timing   of   demand   and   costs   below,   in   stylised  
form.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  66  of  89  
March  2015  
 
 
 
Tariffs  
   

Figure  29  The  cost-­‐demand  relationship  illustrated  

 
 
Source:  ECA  

Tariffs  will  also  be  affected  by  the  level  of  direct  and  cross-­‐subsidies  in  the  system.  We  
define  direct  subsidies  as  those  funded  from  external  sources,  such  as  the  government  
budget.   These   will   lower   tariffs   relative   to   costs   for   those   customers   receiving   the  
subsidy  but  not  affect  the  tariffs  of  others.  At  present,  there  are  no  direct  subsidies  for  
electricity   customers   in   Cambodia.   Cross-­‐subsidies   are   those   funded   within   the  
electricity  industry.  These  will  raise  tariffs  above  costs  for  those  customers  funding  the  
subsidy  and  reduce  them  for  those  receiving  it.    

5.2 Cambodia’s tariff structure

We   compare   below   the   relative   tariffs   in   Cambodia   for   large   and   small   industrial   and  
residential  customers  located  in  Phnom  Penh.  As  can  be  seen  the  LV  industrial  tariff  is  
around   9%   higher   than   that   for   large   MV   industrial   customers   and   the   middle   block   for  
domestic   (household)   customers.   We   understand   that   this   middle   block   is   broadly   in  
line   with   the   assumed   average   cost   of   supply   to   domestic   customers.   The   lower   block   is  
set  15%  below  this  and  the  upper  block  15%  above  to  provide  a  small  cross-­‐subsidy  to  
smaller   domestic   customers   (assumed   to   correlate   to   low-­‐income   households).  
According   to   EAC,   there   is   no   cross-­‐subsidy   from   industrial   to   domestic   customers   (a  
point  we  discuss  further  below).    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  67  of  89  
March  2015  
 
 
 
Tariffs  
   

Figure  30  Relative  EDC  tariffs,  2015  

 
 
Source:  EAC.  Tariffs  shown  are  for  Phnom  Penh  

We   show   below   similar   calculations   for   the   Philippines,   Thailand   and   Vietnam.   As   can  
be  seen,  Cambodia’s  tariff  structure  is  similar  to  that  in  Thailand  and  Vietnam.  Indeed,  
domestic  tariffs  are  closer  to  industrial  tariffs  in  Cambodia  than  in  both  these  countries,  
implying   less   use   of   cross-­‐subsidies   from   industrial   to   domestic   customers   in   Cambodia  
than   in   Vietnam   and   Thailand   (consistent   with   EAC’s   statements   on   cross-­‐subsidy  
arrangements).   The   difference   between   LV   and   MV   industrial   tariffs   is   also   similar   in  
each  of  these  three  countries.    

The   Philippines   shows   very   different   relationships   between   tariffs.   The   charges   to   LV  
customers  are  much  higher  than  those  for  MV  customers.  It  is  not  clear  whether  this  is  
due  to  different  relationships  between  the  costs  of  supply  at  different  voltage  levels  in  
the   Philippines   and   elsewhere   or   different   regulatory   perspectives   on   the   desirable  
relationships  between  MV  and  LV  tariffs  and  costs  of  supply.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  68  of  89  
March  2015  
 
 
 
Tariffs  
   

Figure  31  Tariff  structures  compared  

 
 
Source:   ECA   calculations   from   EAC   (Cambodia,   2015),   MEA   (Thailand,   2015),   EVN   (Vietnam,   2015)   and  
Meralco  (Philippines,  February  2015)  published  tariffs.  

5.3 Are tariffs cost-reflective?

According   to   EAC,   there   has   been   no   study   to   date   of   the   relative   costs   of   supply   to  
different  customer  categories.  Therefore,  it  is  difficult  to  say  whether  the  current  tariff  
structure  is  cost-­‐reflective  or  not.  Comparisons  with  other  countries  can  help  but,  as  we  
show   above,   are   not   conclusive   given   that   these   countries   may   themselves   have   tariff  
structures  that  are  not  cost-­‐reflective  and  potentially  very  different  cost  structures.  

We   do   note   that   domestic   tariffs   in   Cambodia   are   below   those   of   LV   industrial  


customers.   We   might   expect   the   relationship   to   be   reversed   given   the   higher   levels   of  
consumption   of   the   latter   group.   EAC   have   explained   that   they   consider   the   current  
relationship  to  be  cost-­‐reflective  as  most  of  the  consumption  by  industrial  customers  is  
during  the  working  day  when  the  system  peak  load  occurs  (see  Figure  11).  Therefore,  
industrial   customers   can   be   considered   to   contribute   more   to   system   peak   than  
domestic  customers,  who  are  assumed  to  largely  use  electricity  in  the  evenings.  Based  
on   this,   EAC   considers   industrial   customers   should   pay   a   higher   tariff   reflecting   their  
greater   contribution   to   the   fixed   costs   associated   with   providing   capacity   to   meet   the  
system   peak.   However,   we   understand   that   this   assessment   is   largely   based   on  
anecdotal  evidence  rather  than  any  systematic  collection  and  analysis  of  data.  It  should  
be   noted   that   the   same   relationship   between   LV   industrial   and   domestic   tariffs   holds   in  
the  other  countries  included  in  the  comparison  above.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  69  of  89  
March  2015  
 
 
 
Tariffs  
   

Overall,   in   the   absence   of   a   cost-­‐of-­‐service   study   which   determines   the   ‘true’   cost   of  
supply   to   different   customer   categories,   it   is   difficult   to   draw   conclusions   on   the   cost-­‐
reflectivity   of   current   tariffs.   The   available   evidence   suggests   that   the   current   tariff  
relationships  are  in  line  with  those  in  the  region  and  can  be  justified  by  reference  to  the  
profile   and   timing   of   consumption   by   different   customer   types,   but   reliable   data   to  
support  this  is  missing.  

5.4 Time-of-Use tariff

EAC  introduced  in  2014  a  TOU  tariff  for  industrial,  commercial  and  agricultural  users.  
This   applies   a   lower   tariff   than   the   standard   tariff   for   consumption   in   off-­‐peak   hours  
(21:00  to  07:00)  and  a  higher  tariff  for  consumption  in  peak  hours  (07:00  to  21:00).  The  
tariff   is   intended   to   provide   an   incentive   for   larger   users   in   particular   to   shift   electricity  
use   to   night-­‐time   when   Cambodia   currently   faces   a   problem   of   excess   consumption  
while  reducing  consumption  at  peak  times  and,  therefore,  the  need  to  retain  expensive  
capacity   to   meet   demand   at   these   times.   The   differential   between   peak   and   off-­‐peak  
differs  slightly  by  customer  category  but  is  around  4  USc/kWh  or  20%.  

From   our   interviews,   it   appears   that   take-­‐up   of   the   TOU   tariff   has   been   very   low   with  
only  one  customer  (a  cement  factory)  reported  to  have  seriously  considered  switching.  
This   is   attributed   to   the   difficulties   in   introducing   three-­‐shift   working   (ie,   night-­‐time  
working)  in  Cambodia.  Labour  laws  require  that  employers  provide  accommodation  or  
transport  for  night-­‐time  workers.  General  practice  is  to  pay  night-­‐time  work  at  200%  of  
the  day-­‐time  rate.  From  our  interviews,  these  additional  labour  costs  are  considered  to  
more  than  offset  any  savings  in  electricity  costs  from  switching  to  night-­‐time  working.    

EAC  have  advised  that  the  current  differential  between  peak  and  off-­‐peak  periods  was  
determined   based   on   judgement   as   to   what   value   would   be   sufficient   to   encourage  
switching   to   off-­‐peak   hours   without   lowering   tariffs   to   levels   that   would   be  
unsustainable.  The  current  difference  appears,  from  the  limited  information  available  to  
us,   to   be   less   than   the   expected   difference   in   EDC’s   costs.   Indeed,   if   there   is   excess  
supply  at  night,  then  the  cost  of  meeting  additional  demand  at  this  time  would  be  close  
to   zero   (as,   otherwise,   generators   will   need   to   either   be   shut   down   incurring   costs   or,   if  
hydro  power  plants,  to  spill  water).  It  is  also  lower  than  the  differences  seen  in  Thailand  
(of  4.6  USc/kWh  or  35%)  and  Vietnam  (11.2  USc/kWh  or  67%).    

We   provide   below   an   indicative   estimate   of   what   a   cost-­‐reflective   TOU   tariff   for  


Cambodia  might  look  like.  The  difference  between  day  and  night-­‐time  tariffs  is  around  
16   USc/kWh   or   65%,   comparable   to   that   in   Vietnam.   However,   even   with   this   much  
larger   difference   between   consumption   times,   the   savings   from   shifting   consumption   to  
off-­‐peak  periods  are  unlikely  to  be  sufficient  to  outweigh  the  increased  labour  costs.  

For  our  example  large  garment  factory  (see  Section  3.2),  we  estimate  that  under  a  TOU  
tariff   of   this   type,   the   savings   from   shifting   the   majority   of   output   to   off-­‐peak   periods  
would   be   around   20%   or   US$   16,000   monthly   (compared   to   around   8%   or   US$   5,000  
under   the   current   TOU   tariff).   However,   with   an   assumed   5,000   employees,   this   is  
equivalent  to  US$  3  per  employee  per  month  or  just  2%  of  the  current  minimum  wage  
of   US$   128   per   month   for   garment   workers.   These   savings   are   clearly   insufficient   to  
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  70  of  89  
March  2015  
 
 
 
Tariffs  
   

offset  the  additional  labour  costs  incurred  under  current  Cambodian  law  and  practices  
for  night-­‐time  working.  Assuming  a  100%  mark-­‐up  for  night-­‐time  working,  we  estimate  
these   additional   labour   costs   would   come   to   at   least   US$   420,000   monthly   given   that  
two-­‐thirds  of  working  time  would  now  take  place  at  night.      

While   the   actual   savings   on   electricity   costs   and   how   these   relate   to   increased   labour  
costs   will   differ   from   firm   to   firm   and   industry   to   industry,   we   expect   that   this   result  
will   hold   more   generally.   The   evidence,   therefore,   suggests   that   a   larger   differential  
between   peak   and   off-­‐peak   periods   can   be   supported.   However,   under   current   labour  
legislation   in   Cambodia,   this   is   unlikely   to   make   switching   production   to   off-­‐peak  
periods   financially   attractive   for   labour-­‐intensive   industrial   customers   such   as   garment  
manufacturers.  

Box  3  Estimating  TOU  tariffs  for  Cambodia  


We  have  carried  out  a  simplified  calculation  of  the  relative  costs  of  supply  in  peak  and  off-­‐peak  
periods  in  Cambodia  as  a  basis  for  estimating  what  a  more  cost-­‐reflective  TOU  tariff  structure  
might  look  like.  

We  assume  that,  in  off-­‐peak  (night-­‐time)  hours,  the  marginal  generator  will  in  future  be  a  coal-­‐
fired  plant.  The  marginal  cost  of  this  generation  in  these  hours  is  the  fuel  cost,  as  there  is  excess  
supply   and,   therefore,   no   capacity   constraints.   We   estimate   this   fuel   cost   as   being   3.30  
USc/kWh,   assuming   Australian   coal   imports   with   a   FOB   price   of   60.6   US$/tonne   (the   average  
for  March  201527),  a  transport  cost  of  20  US$/tonne  and  a  coal  plant  thermal  efficiency  of  35%.  
To   this   we   add   transmission   and   distribution   costs   of   5.15   USc/kWh   (for   supply   to   an   MV-­‐
connected  industrial  customer)  to  obtain  an  off-­‐peak  cost  of  supply  of  8.45  USc/kWh.  

The   additional   capacity   and   other   costs   to   be   recovered   during   peak   (day-­‐time)   hours   are  
calculated  as  the  average  MV  industrial  tariff  (of  17.70  USc/kWh)  less  the  assumed  off-­‐peak  cost  
of   supply,   adjusted   upwards   as   these   additional   costs   are   only   recovered   over   14   peak   hours  
(from  07h00  to  21h00)  instead  of  a  24-­‐hour  period.  This  adjusted  additional  cost  is  then  added  
to  the  off-­‐peak  cost  of  supply  to  give  the  estimated  cost  of  supply  in  peak  hours,  which  is  24.31  
USc/kWh.    

Our   example   large   customer   has   an   assumed   demand   of   900   kW   and   an   assumed   monthly  
consumption  of  408,750  kWh.  At  the  current  average  MV  tariff  of  17.70  USc/kWh,  the  monthly  
electricity  bill  is,  therefore,  US$  72,349.  If  the  same  customer  is  assumed  to  switch  to  off-­‐peak  
working  and  that  off-­‐peak  hours  represent  10  hours  of  each  day  in  the  month,  then  our  example  
customer  will  consume  270,000  kWh  during  off-­‐peak  hours,  at  a  tariff  of  8.45  USc/kWh,  and  the  
remaining   138,750   kWh   during   peak   hours,   at   a   tariff   of   21.95   USc/kWh.   The   resulting   monthly  
electricity  bill  under  TOU  tariffs  would  be  US$  53,272.    

5.5 Conclusions and recommendations

In   the   absence   of   a   comprehensive   study   of   the   costs   of   supply   to   different   customer  


categories,   it   is   difficult   to   determine   whether   existing   tariffs   are   cost-­‐reflective.   Our  
                                                                                                               
27 World Bank, Commodities Price Data, 3 April 2015. The heat content is assumed to be 6,000
kcal/kg. (http://siteresources.worldbank.org/INTPROSPECTS/Resources/334934-
1111002388669/829392-1420582283771/Pnk_0415.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  71  of  89  
March  2015  
 
 
 
Tariffs  
   

expectation   would   generally   be   that   industrial   customers   would   have   lower   tariffs   than  
domestic   customers   given   their   greater   level   of   sales   and   flatter   load   or   demand  
profiles.   However,   we   also   recognise   the   validity   of   EAC’s   argument   that   industrial  
customers  consume  more  at  times  of  system  peak  and  so  should  pay  a  higher  share  of  
the  system’s  fixed  costs  and  that  Cambodia’s  current  tariff  structure  is  in  line  with  that  
of  its  neighbours  in  Thailand  and  Vietnam.    

We  do  recommend  that  EAC  commission  a  study  of  the  costs  of  supply  to  different  
customer   categories   and   that   the   results   are   made   publicly   available.   This   would  
provide  a  basis  for  the  proper  assessment  of  the  cost-­‐reflectivity  of  tariffs  and  whether  
the  current  structure  should  be  adjusted.  

We   also   note   that   the   current   TOU   tariff   does   not   appear   adequate   to   encourage  
switching   of   consumption   times   and   that   the   differences   between   peak   and   off-­‐peak  
periods   is   lower   than   that   in   Thailand   and   Vietnam.   We   recommend   that   the  
difference  between  TOU  tariffs  for  peak  and  off-­‐peak  periods  is  increased  to  better  
reflect  cost  differences  between  periods  and  to  make  switching  cost-­‐effective.  This  can  
benefit  industrial  customers  in  the  short-­‐term  by  reducing  their  costs  and  in  the  longer-­‐
term  by  helping  address  the  problem  of  excess  capacity  in  night-­‐time  hours.  However,  
its   effectiveness   for   labour-­‐intensive   industries   will   remain   limited   without  
increased  flexibility  under  Cambodian  labour  law  as  regards  night-­‐time  working.  
Currently,  the  savings  in  electricity  costs  are  unlikely,  in  our  estimation,  to  outweigh  the  
increased  labour  costs  in  most  cases.    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  72  of  89  
March  2015  
 
 
 
Consumption  
   

6. Consumption

In  this  final  analytical  section,  we  look  at  how  industrial  customers  can  themselves  act  
to  reduce  their  electricity  costs.  There  are  two  main  routes  by  which  they  can  do  so.  The  
first   is   improving   the   energy   efficiency   of   their   operations,   reducing   electricity  
consumption.  The  second  is  to  substitute  for  grid  electricity  supplies  by  self-­‐generation.  

6.1 Energy efficiency

Energy efficiency potential and practice in industry

There  have  been  numerous  assessments  of  the  potential  for  improving  energy  efficiency  
in   Cambodian   industry.   However,   the   impacts   to   date   seem   to   have   been   limited.   This  
seems   to   be   due   to   a   combination   of   lack   of   awareness   of   the   opportunities   (only   one   of  
our   interviewees,   for   example,   had   had   an   energy   audit   conducted   and   was   not   familiar  
with   the   results)   and   reluctance   to   invest   in   energy-­‐saving   measures.   This   reluctance  
has   been   attributed   to   constraints   on   total   borrowing   by   enterprises   and   an  
unwillingness  to  use  up  scarce  credit  from  commercial  institutions  on  investments  with  
lengthy   and   uncertain   pay-­‐backs   compared   to   investments   to,   for   example,   increase  
capacity.  

UNIDO   in   collaboration   with   MME   and   the   National   Cleaner   Production   Office   –  
Cambodia,   has   been   implementing   the   Industrial   Energy   Efficiency   Cambodia   project  
since  2011.  This  has  conducted  a  number  of  rapid  energy  audits  which  have  been  used  
to   identify   and   support   demonstration   energy   efficiency   projects   within   industrial  
enterprises 28 .   While   the   audits   generally   focused   on   smaller   enterprises,   they   did  
include   two   garment   factories   (Sky   High   (Cambodia)   Co   Ltd   and   Dignity   Knitter   Ltd)  
which  provide  an  example  of  the  savings  offered  by  improved  energy  efficiency.    

For  Sky  High,  the  energy  audit  estimated  that  electricity  costs  could  be  reduced  by:  the  
substitution  of  grid  supplies  and  on-­‐site  diesel  generation  by  self-­‐generation  using  a  mix  
of   biogas   and   diesel   oil;   the   replacement   of   fluorescent   lamps   with   LEDs;   and   the  
installation   of   solar   panels   to   generate   electricity   for   lighting.   However,   only   the  
replacement   of   fluorescent   lamps   has   been   implemented   at   an   investment   cost   of   US$  
74,000  with  annual  savings  estimated  at  US$  50,000  (representing  around  6%  of  total  
electricity  costs).    

In  Dignity  Knitter,  total  potential  savings  in  energy  costs  were  estimated  at  US$  468,000  
(including  US$  355,000  in  electricity  costs  or  25%  of  existing  electricity  costs)  but  only  
US$   126,500   has   been   realised   (US$   113,000   in   electricity   costs   or   8%),   requiring  
investments  of  US$  115,000.  The  greatest  savings  would  come  from  the  installation  of  
co-­‐generation  facilities  replacing  grid  electricity  supplies  but  the  up-­‐front  costs  of  this  
appear  to  have  been  a  deterrent.  
                                                                                                               
28 Summaries of the audits and demonstration projects are available at: http://www.cambodian-
cpc.org/ccpp/index.php/en/publication/2013-04-18-08-58-51
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  73  of  89  
March  2015  
 
 
 
Consumption  
   

Although,   in   both   these   case   studies,   only   a   part   of   the   identified   energy   efficiency  
measures   were   implemented,   the   impacts   are   still   very   significant.   The   savings   in  
electricity   costs   achieved   of   6-­‐8%   with   relatively   low   up-­‐front   investments   are  
equivalent  to  reducing  electricity  tariffs  by  around  1-­‐1.5  USc/kWh..  

While   only   two   examples,   these   case   studies   also   support   the   views   expressed   that  
enterprises   are   reluctant   to   invest   in   energy   efficiency   measures   that   have   a   large   up-­‐
front   cost   due   to   difficulties   in   obtaining   credit.   Therefore,   many   opportunities   to  
reduce  electricity  costs  may  not  be  realised.    

National Energy Efficiency Strategy

A   draft   National   Policy,   Strategy   and   Action   Plan   on   Energy   Efficiency   in   Cambodia  
(CNEE)   was   issued   in   May   201329.   The   preparation   of   the   CNEE   was   supported   by  
consultants  under  European  Union  funding.  It  sets  an  overall  goal  of  reducing  national  
energy   demand   by   20%   by   2035   compared   to   business   as   usual   projections.   Of   this,  
around   25%   of   the   savings   would   come   from   reduced   electricity   consumption   (the  
majority  would  come  from  reduced  biomass  consumption).    

Among  key  industrial  sub-­‐sectors,  the  CNEE  estimates  that  energy  consumption  by  rice  
mills  can  be  reduced  by  35%  on  average  through  the  substitution  of  fossil  fuels  by  rice  
husk  gasifiers  (RHGs)  and  by  20%  to  35%  in  the  garment  industry  through  the  use  of  
more  efficient  wood  boilers,  sewing  machines  and  thermal  insulation.  The  CNEE’s  action  
plan  for  promoting  energy  efficiency  in  industry  includes  the  following:  

❏ Institution   of   a   system   of   mandatory   collection   of   data   on   energy  


consumption   from   major   industrial   users   by   MME,   which   can   be   used   to  
establish  benchmarks  and  targets.  

❏ Raising   awareness   of   good   energy   management   practices   in   industrial  


enterprises  (following  the  ISO  50001  standard).  

❏ Substituting   biomass   gasifiers   and   bio   digesters   for   thermal   and   electrical  
energy  use.  

❏ Establishing   standards   on   energy   efficiency   and   management   in   industrial  


enterprises   and   encouraging   voluntary   compliance   with   these   and,  
potentially,  mandatory  compliance  for  larger  users.  

❏ Creating   tax   and   other   incentives   for   import   and   domestic   manufacture   of  
energy  efficient  equipment.  

❏ Funding   energy   audits   for   small   and   medium   enterprises,   training   of  


technicians   and   energy   auditors   and,   in   the   longer-­‐term,   creating   a  

                                                                                                               
29 EUEI PDF and Integration, 24 May 2013, National Policy, Strategy and Action Plan on Energy Efficiency
in Cambodia: Draft (http://www.euei-
pdf.org/sites/default/files/files/field_pblctn_file/EUEI%20PDF_Cambodia_Energy%20Efficiency_
May2013_EN.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  74  of  89  
March  2015  
 
 
 
Consumption  
   

favourable   framework   for   the   development   of   Energy   Service   Companies  


(ESCOs)30.  

❏ Providing  loans  for  energy  efficiency-­‐improving  investments  as  a  catalyst  for  


the  development  of  a  supporting  financial  sector.  

We  understand  from  MME  that  the  draft  CNEE  is  still  under  review  and  revision  prior  to  
being   submitted   to   the   Council   of   Ministers   for   approval.   In   the   meantime,   MME   is  
undertaking   limited   initiatives   to   promote   industrial   energy   efficiency,   including   in  
some  of  these  areas,  but  these  efforts  should  be  strengthened  and  enhanced.  

A   general   comment   is   that   the   draft   CNEE   is   much   more   specific   about   short-­‐term  
actions   such   as   improving   data   collection   than   longer-­‐term   but   more   wide-­‐reaching  
actions  such  as  developing  a  supporting  financial  sector  willing  to  lend  money  to  finance  
energy  efficiency  investments  with  repayment  linked  to  the  resulting  savings.  It  is  not  
clear,  therefore,  to  what  extent  it  will  address  the  barriers  that  experience  to  date  has  
identified,  which  appear  to  be  related  to  financing  constraints,  even  if  implemented  in  
full.  

6.2 Self-generation

Competitiveness of self-generation using renewable sources

The  other  means  for  industrial  electricity  users  to  reduce  their  costs  is  to  substitute  self-­‐
generation   for   grid   electricity   supply.   Many   industrial   customers   already   have   oil   and  
diesel-­‐fired  generators  although  these  often  seem  to  be  for  security  of  supply  in  the  case  
of  interruptions  rather  than  for  reducing  costs.    

The  most  promising  self-­‐generation  options  would  appear  to  be  the  use  of  agricultural  
residues   (such   as   rice   husks)   in   gasifiers   or   in   co-­‐generation   (combined   heat   and  
power)  boilers  which  offer  much  higher  efficiency  than  conventional  boilers.    

Other   self-­‐generation   options   seem   unlikely   to   offer   reductions   in   costs   for   larger  
industrial  customers.  The  decline  in  grid  generation  costs  and  electricity  tariffs  means  
that  self-­‐generation  with  diesel  or  fuel  oil  is  now  more  expensive  than  grid  supply31.  The  
use   of   solar   panels   by   industrial   customers   is   more   costly   than   grid   supply   (on   a  
levelised   cost   or   USc/kWh   basis),   requires   very   sizeable   up-­‐front   investments   and  
raises   problems   with   intermittency   of   supply   due   to   cloud   cover   and   at   night.   However,  
solar   power   remains   an   attractive   option   for   many   smaller   users,   particularly   for   off-­‐
grid   consumers,   where   the   alternative   supply   source   is   diesel   generation   or   car  
                                                                                                               
30 ESCOs are companies which will identify energy efficiency-improving investments, arrange
financing for these and be repaid from the savings achieved from the investments relative to a pre-
determined baseline level of energy consumption.
31 A 500 kW diesel generator operating at full load consumes around 135 litres per hour. Assuming a

diesel price of 1 US$/litre, this would give a cost of electricity of 27 USc/kWh before taking account
of capital and non-fuel operating costs. Lower load factors and smaller capacities would use
proportionally more fuel with higher generation costs.
(http://www.dieselserviceandsupply.com/Diesel_Fuel_Consumption.aspx)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  75  of  89  
March  2015  
 
 
 
Consumption  
   

batteries  with  very  high  costs  and  where  issues  of  intermittency  of  supply  and  limited  
supply  in  night-­‐time  hours  matter  far  less.  

This   is   likely   to   limit   self-­‐generation   as   an   option   for   reducing   electricity   costs   to  


agricultural   processing   industries   such   as   rice   mills   which   have   ready   access   to  
agricultural  residues.  In  future,  there  may  be  potential  for  the  development  of  biomass  
grown  as  a  cash  crop  for  use  in  self-­‐generation.  

A   major   challenge   for   any   enterprise   generating   its   own   electricity   is   how   to   manage  
mismatches   between   output   and   their   own   consumption.   Doing   so   generally   requires  
the  ability  to  sell  surplus  generation  to  the  electricity  grid.  EDC  already  purchases  from  
three  such  generators  with  installed  capacities  from  10  MW  to  20  MW  (one  using  rice  
husks  and  two  bagasse).  However,  the  tariff  paid  is  only  7  USc/kWh  and  a  PPA  has  to  be  
individually   negotiated   in   each   case.   The   basis   for   this   tariff   and   how   it   relates   to   the  
cost  savings  to  EDC  of  purchasing  from  industrial  enterprises  is  not  clear.

As   with   energy   efficiency,   there   have   been   a   large   number   of   projects   promoting   self-­‐
generation   by   industrial   enterprises.   In   particular,   the   use   of   RHGs   has   been  
encouraged.  A  2012  survey  recorded  around  30%  of  rice  mills  as  using  RHGs,  although  
these   appear   to   be   smaller   mills   substituting   for   diesel   self-­‐generation   rather   than   for  
grid  electricity  supplies32.  The  estimated  savings  from  use  of  RHGs  with  duel  fuel  (diesel  
and  gas)  generators  were  equivalent  to  around  US$  5  per  tonne  of  milled  rice  relative  to  
diesel  generation  alone.  The  average  RHG  capacity  was  410  kW  and  the  average  output  
of  mills  included  in  the  survey  was  3,925  tonnes  of  milled  rice  annually33.  

The   survey   also   identified   the   main   barrier   to   installation   of   RHGs   as   being   a   lack   of  
investment   capital   (as   loans   are   generally   not   available   specifically   to   fund   RHGs)   but  
also   noted   problems   in   their   operation   including   gas   leakages   and   managing   the   tar  
residues.   One   of   our   interviewees,   who   owns   a   larger   rice   mill,   confirmed   these  
concerns.  They  have  installed  a  RHG  but  do  not  use  it  due  to  the  environmental  impacts.  
A   recent   field   survey   identified   the   same   environmental   concerns   and   noted   that  
gasification   is   becoming   less   economically   attractive   and   may   not   be   competitive   with  
grid   electricity34.   This   is   supported   by   available   evidence   on   costs   of   supply   from  
gasification—for  example,  a  2009  study  estimated  the  average  costs  of  supply  from  a  50  
kW   system   operating   for   2,190   hours   annually   at   37   USc/kWh   excluding   fuel   costs.   The  
average  costs  will  be  lower  for  larger  systems  and  with  higher  load  factors  but  are  still  
unlikely  to  compete  with  grid  supply  available  at  prices  of  less  than  20  USc/kWh35.    

                                                                                                               
32 SNV, 20 August 2012, Waste to Energy for the Rice Milling Sector in Cambodia: Baseline Study, Report
for the EU (http://www.snvworld.org/download/publications/baseline_report-
in_line_indicators_v2_final_with_snv_template.pdf).
33 Averages of 2.27 tonnes per hour, 8.28 hours of operation per day, 21.6 days per month and 9.67

months per year.


34 Minh Ha-uong and Hong Nam Nguyen, 21 January 2015, Rice Husk Gasification for Electricity

Generation in Cambodia in December 2014: Research Report (https://hal-enpc.archives-ouvertes.fr/hal-


01107615/document)
35 FACT Foundation, 2009, Biomass Gasification for Village Electrification: Case Study (http://fact-

foundation.com/sites/default/files/library/documents/21._biomass_gasification_for_village_electri
fication.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  76  of  89  
March  2015  
 
 
 
Consumption  
   

For  larger  mills,  the  use  of  cogeneration  using  rice  husks  becomes  feasible.  Cambodia’s  
rice   mills   are   relatively   small   by   global   standards   but   larger   mills   are   now   being  
established.  The  14  largest  mills  in  Cambodia  have  an  average  milling  capacity  of  14.25  
tonnes  of  paddy  rice  per  hour,  or  approximately  20,000  tonnes  of  milled  rice  annually36.    

We   provide   below   an   estimate   of   the   costs   of   co-­‐generation   of   electricity   using   data  


from   Thailand.   To   illustrate   the   benefits   of   the   sale   of   surplus   energy   to   the   grid,   we  
show  the  levelised  cost  with  and  without  sales  of  surplus  energy  using  the  current  tariff  
offered   by   EDC.   These   estimates   assume   no   value   is   attached   to   rice   husks—in   practice,  
growing   demand   for   their   use   in   electricity   generation   means   that   they   are   now  
acquiring  a  market  value.  What  these  estimates  suggest  is  that  self-­‐generation  without  
the   option   for   selling   excess   energy   to   the   grid   is   either   not   viable   or   only   marginally  
viable  for  most  rice  mills  given  their  limited  hours  of  operation.  However,  with  sales  of  
surplus   energy   to   the   grid,   the   effective   cost   is   very   attractive   in   comparison   to   grid  
electricity  supply.  

Table  10  Estimated  costs  of  co-­‐generation  from  rice  husks  


  Unit   Value  
Costs      
Investment  cost   US$/kW   2,457  
Annualised  investment  cost  (10%  discount  rate,  15-­‐year  life)   US$/kW/year   323  
O&M  costs   US$/kW/year   61  
Total  cost   US$/kW/year   384  
     
Hours  utilised  for  rice  milling     1,760  
Average  cost  before  grid  electricity  sales   USc/kWh   21.85  
     
Revenues  from  grid  electricity  sales      
Grid  sales  price   USc/kWh   7.00  
Hours  utilised  for  grid  sales  (70%  load  factor)     4,372  
Annual  income  from  grid  sales   US$/kW/year   306  
     
Net  cost  after  grid  sales   US$/kW/year   78  
Average  cost  after  grid  sales   USc/kWh   4.46  
Source:  ECA  calculations.  Investment  cost  estimated  as  average  for  six  biomass-­‐based  co-­‐generation  plants  
in   Thailand   as   reported   by   Excellent   Energy   International   Co   Ltd37.   Operating   and   maintenance   cost   as  
                                                                                                               
36 Source: General Directorate of Agriculture (Department of Rice Crop), 18-22 March 2013, Overview:
Rice Production in Cambodia (http://www.agribenchmark.org/fileadmin/Dateiablage/B-Cash-
Crop/Projects/Rice-Initiative/Presentations-WS-130319/country_presentation_KH_130319.pdf).
Both existing (as at 2009) and new mills are included. Conversion to annual output assumes 1.5
tonnes of paddy rice converts to 1 tonne of milled rice, eight hours operating per day and 22 days per
month.
37 Excellent Energy International Co Ltd, 5 June 2013, “Making Energy Investment Projects Work by

Cogeneration Technology with ESCO”, Renewable Energy Asia 2013


(http://www.iei.or.th/media/www/file/165/19082071371352886.pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  77  of  89  
March  2015  
 
 
 
Consumption  
   

reported   in   a   study   for   a   proposed   rice   husk-­‐fired   co-­‐generation   plant   by   King   Mongkut’s   University   of  
Technology   Thonburi38.   Utilisation   for   rice   milling   assumes   8   hours   operation   per   day,   22   days   per   month  
and  10  months  per  year.  

Sale of surplus electricity

EDC   has   an   existing   programme   of   encouraging   purchases   of   surplus   electricity  


generated   by   industrial   customers   and   has   signed   a   number   of   contracts.   However,  
these  are  individually  negotiated  on  a  case-­‐by-­‐case  basis  which  increases  the  time  taken  
and  creates  uncertainty  for  industrial  customers  over  what  prices  they  will  receive.    

Requiring  utilities  to  purchase  surplus  electricity  from  enterprises  generating  their  own  
supply  does,  of  course,  impose  costs  and  risks  on  the  utility.  These  must  be  recognised  
and   provision   made   to   ensure   that   either   the   utility’s   total   costs   do   not   increase   or   that,  
where  they  do,  it  is  able  to  recover  these  additional  costs.  

For  these  reasons,  we  consider  the  adoption  of  a  standard  Power  Purchase  Agreement,  
including   a   standard   price   for   electricity   purchases,   is   desirable.   This   will   make   the  
process   of   agreeing   a   contract   more   rapid,   transparent   and   certain.   The   price   should  
reflect  the  benefits  to  EDC  so  that  it  is  ‘fair’  to  both  parties.  

There   are   three   main   approaches   to   setting   the   price   for   purchases   of   surplus  
electricity:  

❏ Avoided   cost   tariff.   The   price   is   set   equal   to   the   cost   savings   (the   ‘avoided  
costs’)   of   the   purchasing   utility.   This   will   be   the   savings   in   fuel   costs   and  
system  losses  plus  an  allowance  for  savings  from  reduced  need  to  invest  in  
expanding  generation  and  network  capacity.  More  sophisticated  systems  will  
offer  different  prices  depending  on  the  season  and  time  period  and  whether  
the  supply  of  energy  is  ‘firm’(guaranteed)  or  not.  Under  current  conditions,  
the   avoided   costs   of   EDC   are   likely   to   be   low,   except   in   peak   hours   in   the   dry  
season  when  oil-­‐fired  generation  might  be  required  to  meet  demand,  due  to  
the   current   excess   supply   in   many   hours   which   means   little   saving   to   EDC  
from  purchasing  more  power.  An  avoided  cost  tariff  has  been  introduced  in  
Vietnam  for  purchases  from  small  hydro  power  plants  but  has  been  criticised  
as   leading   to   tariffs   that   are   too   low   for   many   generators   to   be   financially  
viable.  

❏ Adder  payment.  An  adder  represents  a  mark-­‐up  on  the  cost  of  bulk  power  to  
the  purchasing  utility.  Depending  on  how  the  cost  of  bulk  power  is  defined,  
this   can   be   seen   as   a   variant   on   an   avoided   cost   tariff   under   which   an  
additional   premium   is   paid   to   the   supplier   as   an   incentive.   This   model   can  
support   higher-­‐cost   generators   while   sharing   the   risk   between   generators  
and  the  purchasing  utility  that  the  prices  paid  move  away  from  the  costs  of  
alternative   supplies.   An   adder   of   this   type   was   the   pricing   arrangement   used  
for  Thailand’s  highly  successful  programme  to  promote  the  development  of  

                                                                                                               
38 Prachuab Peerapong and Bundit Limmeechokchai, July 2009, “Thermodynamic and Economic
Analysis of 1.4 MWe Rice-Husk Fired Cogeneration in Thailand”, Journal of Renewable Energy, Vol 4,
No. 2 (http://www.sert.nu.ac.th/IIRE/V4N2(4).pdf)
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  78  of  89  
March  2015  
 
 
 
Consumption  
   

small   and   very   small   power   producers   selling   to   the   state   utility   among  
industrial  enterprises.    

❏ Feed-­‐in-­‐tariff   (FIT).   A   fixed   price   is   paid   based   on   the   costs   of   the   generator  
rather   than   the   costs   saved   by   the   purchasing   utility.   This   provides   strong  
incentives   to   generators   (provided   prices   are   high   enough)   but   places  
significant  risk  on  the  purchasing  utility  that  prices  paid  will  exceed  its  cost  
savings   from   the   displacement   of   alternative   supplies.   Vietnam   has  
introduced  this  pricing  arrangement  for  purchases  from  wind  generators  but  
the   price   offered   appears   to   have   been   set   too   low   to   allow   generators   to  
recover   their   costs   and,   therefore,   has   not   succeeded   in   promoting  
investment.   Thailand   is   moving   to   a   FIT   for   purchases   from   renewable  
energy  sources  in  response  to  concerns  that  the  incentives  under  the  current  
adder   arrangement   are   too   high   and   promoting   excessive   and   financially  
unsustainable  expansion  of  renewables  capacity.  

The   costs   of   purchases   at   prices   above   avoided   costs   (which   should   be   self-­‐financing  
from   the   resulting   cost   savings)   can   either   be   recovered   by   ‘bundling’   them   into   the  
costs   of   power   purchases   recovered   from   customers   or   through   an   explicit   levy.   The  
former   approach   is   adopted   in   Thailand   and   Vietnam   while   the   latter   is   used   in   the  
Philippines  (where  the  renewable  energy  levy  represents  around  3-­‐5%  of  tariffs).    

The   use   of   adders   and   FITs   which   pay   a   premium   above   the   utility’s   cost   savings   is  
common   as   a   means   of   encouraging   the   development   of   renewable   energy   sources—
whose   costs   are   generally   above   those   of   conventional   generation.   Cambodia   at   present  
has   a   commitment   to   support   the   collective   ASEAN   target   of   renewables   representing  
15%  of  installed  capacity  by  201539  and  is  also  promoting  the  use  of  renewable  energy  
for   off-­‐grid   rural   electrification   but,   otherwise,   has   no   specific   targets   or   policies   to  
develop  renewable  energy  sources.    

Without   such   policies   and   targets,   it   is   difficult   to   argue   for   premium   payments   for  
purchases   from   renewable   energy   sources.   Whether   Cambodia   should   be   actively  
promoting   the   expansion   of   grid-­‐connected   renewable   energy   generation   (other   than  
large  hydro  power  projects)  is  a  wider  question  and  one  that  is  outside  the  scope  of  this  
study.  

6.3 Conclusions and recommendations

Improving   energy   efficiency   has   significant   potential   to   reduce   the   costs   of   electricity  
supplies  for  industrial  customers  in  Cambodia.  In  the  case  studies  reviewed,  even  with  
only   a   small   part   of   identified   efficiency   investments   being   undertaken,   savings   in   costs  
of  6%  to  8%  were  readily  achieved.  

Cambodia’s   draft   national   energy   efficiency   strategy   contains   a   set   of   measures   to  


further  promote  energy  efficiency  among  industrial  enterprises  (and  other  energy-­‐using  
                                                                                                               
39 The definition of ‘renewables’ follows that of the World Energy Council which includes modern
biomass, hydro power (of all sizes), geothermal, wind, solar and marine energy. Using this definition,
the share of renewables in Cambodia’s installed capacity is expected to reach 56% in 2015.
 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  79  of  89  
March  2015  
 
 
 
Consumption  
   

sectors).   The   draft   action   plan   that   forms   part   of   the   strategy   has   a   number   of  
immediate   actions   such   as   instituting   a   process   of   data   collection   on   energy   use   by  
industry,  awareness-­‐raising  of  energy  efficiency  opportunities  and  the  development  of  
energy   management   standards   can   be   implemented   rapidly   and   at   low   cost.   We  
recommend   that   the   short-­‐term   low-­‐cost   actions   to   improve   data   and   raise  
awareness  of  industrial  energy  efficiency  identified  in  the  draft  national  strategy  
are  implemented  now,  without  waiting  for  the  approval  of  the  full  strategy.  

In  the  longer-­‐term,  it  will  be  critical  if  energy  efficiency  potential  is  to  be  fully  realised,  
to   address   the   difficulties   faced   by   enterprises   in   borrowing   to   fund   energy   efficiency  
investments.   The   draft   national   strategy   recognises   this   need   but   lacks   detailed   actions.  
We   recommend   that   Cambodia   investigate   the   potential   for   creating   a   revolving  
energy   efficiency   fund,   along   the   lines   of   Thailand’s   well-­‐established   and   successful  
model,  as  a  means  of  catalysing  commercial  lending  for  energy  efficiency.  However,  we  
recognise  that  steps  towards  introducing  such  a  fund,  given  the  associated  institutional  
and   financial   commitments,   must   wait   for   approval   of   the   national   energy   efficiency  
strategy.  Therefore,  we  also  recommend  that  the  draft  strategy  is  approved  as  soon  
as   possible   to   provide   a   basis   for   further   development   of   energy   efficiency  
opportunities.    

Self-­‐generation   using   rice   husks   and   other   agricultural   residues   is   attractive   for  
agricultural   processing   industries   when   compared   to   diesel   generation.   However,   it   is  
less  so  when  compared  to  current  grid  electricity  tariffs.  The  costs  of  self-­‐supply  from  
co-­‐generation   plants   using   rice   husks   for   fuel   is   closer   to   grid-­‐parity   costs   but   still  
unlikely   to   be   viable   if   output   is   only   used   for   internal   purposes.   Other   technologies  
appear   unlikely   to   be   competitive   with   grid   supplies   given   their   higher   costs   and,   in   the  
case  of  solar  panels,  intermittent  supply.  

Most processing industries operate at relatively low load factors, which means that the
average or unit costs of self-generation are high and may make otherwise promising
technologies uncompetitive with grid electricity supply. Higher load factors and additional
revenues can be achieved if surplus generation can be sold to the grid. However, in doing
so, a balance must be struck between the benefits to the selling enterprise and the additional
costs and risks that may be imposed on the purchasing utility.

We   recommend   that   EDC   introduce   a   standard   tariff,   based   on   its   avoided   costs,  
and   accompanying   PPA   for   purchases   of   surplus   energy   from   industrial  
enterprises   with   their   own   electricity   generation.   This   will   help   make   self-­‐
generation   more   attractive   and,   thereby,   allow   customers   to   reduce   their   costs.   By  
linking  the  price  paid  to  EDC’s  avoided  costs,  the  net  impact  on  EDC’s  costs  and  tariffs  
should   be   zero.   In   future,   if   the   government   adopts   a   policy   of   promoting   renewable  
energy  sources,  a  higher  price  in  excess  of  avoided  costs  might  be  offered.  

Box  4  Thailand's  Energy  Efficiency  Revolving  Fund  

Objectives:    
To   facilitate   investment   in   energy   efficiency   (EE)   by   helping   commercial   banks   to   develop  
appraisal  procedures  and  provide  low  interest  rate  loans  for  EE  projects.    
Energy  Efficiency  Goals:    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  80  of  89  
March  2015  
 
 
 
Consumption  
   

No   minimum   level   of   energy   saving   is   required.   The   Royal   Government   of   Thailand   has   a   stated  
objective  to  reduce  energy  intensity  by  25%  between  2005  and  2025.    
Sectors  Targeted:    
For   industrial   projects,   criteria   include   improvement   of   combustion   efficiency   of   fuels,  
prevention  of  energy  loss,  recycling  of  energy  wastes,  reduction  of  power  peak  demand,  use  of  
EE  equipment,  etc.    
For  buildings,  criteria  include  reduction  of  heat  from  sunlight,  room  temperature  at  appropriate  
level,  use  of  quality  material,  effi  cient  use  of  lighting,  use  of  control  systems,  etc.    
Barriers  Addressed:    
Access  to  funding  at  competitive  rates  for  upfront  costs  of  EE  projects.  
Capacity-­‐building   for   commercial   banks   as   they   are   incentivized   to   finance   EE   projects   at  
attractive   financing   rates   and   are   encouraged   to   develop   EE   business   lines   to   gain   access   to  
ENCON  funding.    
Financing  Mechanism:    
Funds   from   the   ENCON   Fund   are   provided   as   programme   loans   to   commercial   banks   through  
EERF  at  zero  interest  for  amounts  of  THB  100–400  million  (US$  3.2  million-­‐  12.7  million).  Banks  
on-­‐lend  this  financing  and  are  allowed  to  charge  interest  up  to  4%  to  cover  their  costs  and  risks.  
Once  a  project  is  identifi  ed  (by  the  owner,  an  ESCO  or  other  service  provider),  it  is  submitted  to  
EERF   through   a   bank   which   conducts   an   appraisal   /   financial   analysis   prior   to   submission.   If  
successful,  the  project  is  then  submitted  to  the  Department  of  Alternative  Energy  Development  
and   Efficiency   (DEDE)   by   the   bank   with   a   repayment   plan.   Once   implemented,   the   borrower  
repays   the   loan   principal   and   interest   to   the   bank,   which   repays   the   principal   to   the   ENCON  
Fund.  The  owner  provides  regular  reports  to  DEDE  on  energy  saving  achievement.  EERF  loans  
may  be  used  to  cover  costs  of  purchase  and  installation  of  equipment,  design,  import  taxes  and  
duty,  etc.  as  defi  ned  in  the  ENCON  Act.  
(The   ENCON   Fund   was   established   under   the   Energy   Conservation   Promotion   Act   1992  
(ENCON)   and   is   financed   from   a   tax   on   all   petroleum   products   sold   in   Thailand.   It   is   used   to  
support  energy  conservation  and  renewable  energy  policies)  

Source:  Adapted  from  Institute  for  Industrial  Productivity  Fact  Sheet  (http://www.iipnetwork.org/IIP-­‐
FinanceFactsheet-­‐3-­‐EERF.pdf)    

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  81  of  89  
March  2015  
 
 
 
Part  III  -­‐  Recommendations  
   

Part III - Recommendations

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  82  of  89  
March  2015  
 
 
 
Recommended  policy  actions  
   

7. Recommended policy actions

In   this   concluding   section,   we   summarise   the   recommendations   from   the   preceding  


part.  We  have  organised  these  by  timing  and  the  responsible  lead  entity.    

7.1 Short-term (within one year)

Ministry  of  Economy  and  Finance  

❏ Consider  exempting  electricity  imports  from  duties  and  VAT  

Ministry  of  Mines  and  Energy  

❏ Approve  the  National  Energy  Efficiency  Strategy  

❏ Speed-­‐up   implementation   of   the   identified   short-­‐term   actions   in   the   strategy  


to  improve  data  and  raise  awareness  of  industrial  energy  efficiency    

Electricity  Authority  of  Cambodia  

❏ Publish  the  assessment  of  EDC’s  costs  used  to  determine  approved  tariffs  

❏ Increase   the   difference   between   TOU   tariffs   for   peak   and   off-­‐peak   periods   to  
better  reflect  cost  differences  and  practice  elsewhere  in  the  region  (however,  
this  may  need  to  be  accompanied  by  changes  to  labour  legislation  regarding  
night-­‐time  working  if  it  is  to  be  effective  in  changing  consumption  patterns)  

7.2 Medium-term (one to three years)

Ministry  of  Mines  and  Energy    

❏ Investigate   the   potential   for   creating   a   revolving   energy   efficiency   fund   to  


help  industry  fund  investments  

Electricity  Authority  of  Cambodia  

❏ Undertake   a   full   analysis   of   EDC’s   transmission   and   distribution   costs  


relative  to  the  current  allowances    

❏ Conduct  a  study  of  the  costs  of  supply  to  different  customer  categories  

Electricitè  du  Cambodge  

❏ Move   to   a   greater   reliance   on   debt   financing   of   new   investments   making   use  


of   the   concessional   rates   available   from   multilateral   and   bilateral   financing  
institutions  and  EXIM  banks  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  83  of  89  
March  2015  
 
 
 
Recommended  policy  actions  
   

❏ Introduce   a   standard   tariff,   based   on   its   avoided   costs,   and   accompanying  


PPA   for   purchases   of   surplus   energy   from   industrial   enterprises   with   their  
own  electricity  generation.  

7.3 Long-term (over three years)

Ministry  of  Mines  and  Energy  

❏ Actively   encourage   the   expansion   of   cross-­‐border   power   trading   in   the  


Greater   Mekong   Sub-­‐Region   and,   in   particular,   the   development   of   shorter-­‐
term  trading  arrangements  

❏ Implement  an  energy  efficiency  revolving  fund,  if  prior  assessment  considers  
this  feasible  

Electricity  Authority  of  Cambodia  

❏ Revise   tariff   structures   to   match   the   costs   of   supply   for   different   customer  
categories,  as  necessary  

❏ Consider   providing   incentives   for   EDC   to   improve   efficiency   and   reduce  


system  losses  through  the  application  of  performance-­‐based  regulation.  

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  84  of  89  
March  2015  
 
 
 
ANNEXES  
   

ANNEXES

 
Cambodia  –  In  Depth  Study  on  Electricity  Cost  and  Supplies     Page  85  of  89  
March  2015  
 
 
 
ANNEXES  
   

A1 List of persons met

Cambodia Chamber of Commerce

Setha  Hong  
Lead  Consultant,  Support  to  G-­‐PSF  Project  
(hsetha@gmail.com  /  012  819  367)  

Yun  Sovanna  
Development  and  Cooperation  
(ysovanna@gmail.com  /  012  667  222  /  086  557  777)  

Sotha  Sothan  
Information  Executive,  CCC  
(sothan.ccc@gmail.com  /  +855  81  30  32  33)  

Ministry of Mines and Energy

HE  Ith  Praing  
Secretary  of  State  
(ipraing@gmail.com  /  023  219  574)  

HE  Tun  Lean  
Undersecretary  of  State  (Energy)  
(tunlean@gmail.com  /  011  82  51  35)  

Victor  Jona  
Director-­‐General,  General  Department  of  Energy  
(jvictor.mime@gmail.com  /  012  918  401)  

Electricity Authority of Cambodia

Teng  Sokhomal  
Director  Tariffs  and  Licensee  Monitoring  

Badri  Rekhani  
International  Advisor  
(bprekhani@yahoo.com)    

Cambodia  In-­‐Depth  Study  on  Electricity  Cost  and  Supplies                                                                                                            Page  86  of  89  
FINAL  Report  -­‐  March  2015    
 
 
 
 
 
ANNEXES  
   

Electricite du Cambodge

Chun  Piseth  
Executive  Director,  Corporate  Planning  and  Projects  
(chun.piseth@gmail.com  /  012  92  92  17)  

Siky  Ra  
Deputy  Director,  Corporate  Planning  and  Projects  
(rs_kiry@hotmail.com)    

Lida  Van  
Deputy  Director,  Finance  
(lida_vann@yahoo.com)    

World Bank

Bun  Veasna  
Energy  Expert  
(vbun@worldbank.org)  

UNIDO

Sok  Narin  
Head  of  UNIDO  Operations,  Cambodia  
(n.sok@unido.org  /  012  757  327)  

Chheng  Ngov-­‐Veng  
National  Project  Coordinator,  Access  to  Clean  Energy  for  Productive  Uses  in  
Cambodia  
(n.chheng@unido.org  /  096  496  0206)  

Garment Manufacturers’ Association of Cambodia

Mr  Robert  Hwang  
GMAC  Exco  Member  /  CEO,  In  Kyung  Cambodia  Co  Ltd    
(roberthwang32310@gmail.com  /  +855  12  900  323)  

Cambodia  In-­‐Depth  Study  on  Electricity  Cost  and  Supplies                                                                                                            Page  87  of  89  
FINAL  Report  -­‐  March  2015    
 
 
 
 
 
ANNEXES  
   

Loran Group PLC

Oknha  Lim  Buheng  


President  and  CEO  
(info@lorangroup.com  /  012  790  168)  

Lim  Kim  Khung  


QA  Manager  
(qamanager@lorangroup.com  /  078  990  999)  

Ti-E Steel Corporation

Oknha  Loch  Sareth  


Chairman  
(lochsareth55@gmail.com  /  012  768  666)  

Chai  Wei  Thong  


Vice-­‐General  Manager  
(ti-­‐esteel_corp@yahoo.com,  tigaroda_cam@hotmail.com  /  016  833  933)  

Cambodia  In-­‐Depth  Study  on  Electricity  Cost  and  Supplies                                                                                                            Page  88  of  89  
FINAL  Report  -­‐  March  2015    
 
 

También podría gustarte