Está en la página 1de 1

CONTRATISTA: MOTA ENGIL PERU SA

CONTRATO: MCP-P-025OBR LINEA BASE 03

# Activity ID Activity Name Budgeted Labor Original Start Finish 2017 2018 2019
Units Duration
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1 PRESA DE RELAVES ETAPA 3 870557 629 01-May-17 19-Jan-19

2 HITOS 0 629 01-May-17 19-Jan-19


3 HITOS 0 629 01-May-17 19-Jan-19
4 HITOS 0 629 01-May-17 19-Jan-19
5 HITOS 0 629 01-May-17 19-Jan-19
6 CONSTRUCCION 870557 629 01-May-17 19-Jan-19
7 GENERALES 50509 586 01-May-17 07-Dec-18 07-Dec-18, GENERALES
8 GENERALES 50509 586 01-May-17 07-Dec-18 07-Dec-18, GENERALES
9 GENERALES 50509 586 01-May-17 07-Dec-18 07-Dec-18, GENERALES
10 ETAPA DE 2B - NIVELACION 8676 82 01-Mar-18 21-May-18 21-May-18, ETAPA DE 2B - NIVELACION
11 ETAPA DE 2B - NIVELACION 8676 82 01-Mar-18 21-May-18 21-May-18, ETAPA DE 2B - NIVELACION
12 ETAPA DE 2B - NIVELACION 8676 82 01-Mar-18 21-May-18 21-May-18, ETAPA DE 2B - NIVELACION
13 LIMPIEZA DE FUNDACON Y ESTRIBOS 71136 548 01-Jun-17 30-Nov-18 30-Nov-18, LIMPIEZA DE FUN
14 FUNDACION 29603 82 01-Jun-17 22-Aug-17 22-Aug-17, FUNDACION
15 FUNDACION 29603 82 01-Jun-17 22-Aug-17 22-Aug-17, FUNDACION
16 ESTRIBOS 41533 466 22-Aug-17 30-Nov-18 30-Nov-18, ESTRIBOS
17 ESTRIBOS 41533 466 22-Aug-17 30-Nov-18 30-Nov-18, ESTRIBOS
18 ETAPA 3A 320724 452 06-Jul-17 30-Sep-18 30-Sep-18, ETAPA 3A
19 CUERPO 3A 253398 319 06-Jul-17 21-May-18 21-May-18, CUERPO 3A
20 TRAMO 00: DESDE 4,479 A4500 10685 29 06-Jul-17 03-Aug-17 03-Aug-17, TRAMO 00: DESDE 4,479 A 4500
21 TRAMO 01: DESDE 4,500 A4,515 12632 40 04-Aug-17 12-Sep-17 12-Sep-17, TRAMO 01: DESDE 4,500 A 4,515
22 TRAMO 02: DESDE 4,515 A4,530 15816 20 13-Sep-17 02-Oct-17 02-Oct-17, TRAMO 02: DESDE 4,515 A 4,530
23 TRAMO 03: DESDE 4,530 A4,545 20102 28 03-Oct-17 30-Oct-17 30-Oct-17, TRAMO 03: DESDE 4,530 A 4,545
24 TRAMO 04: DESDE 4,545 A4,560 25778 27 31-Oct-17 26-Nov-17 26-Nov-17, TRAMO 04: DESDE 4,545 A 4,560
25 TRAMO 05: DESDE 4,560 A4,575 28676 35 26-Nov-17 31-Dec-17 31-Dec-17, TRAMO 05: DESDE 4,560 A 4,575
26 TRAMO 06: DESDE 4,575 A4,590 30573 31 31-Dec-17 31-Jan-18 31-Jan-18, TRAMO 06: DESDE 4,575 A 4,590
27 TRAMO 07: DESDE 4,590 A4,605 32392 28 31-Jan-18 28-Feb-18 28-Feb-18, TRAMO 07: DESDE 4,590 A 4,605
28 TRAMO 08: DESDE 4,605 A4,620 35693 34 28-Feb-18 03-Apr-18 03-Apr-18, TRAMO 08: DESDE 4,605 A 4,620
29 TRAMO 09: DESDE 4,620 A4,635 36347 40 03-Apr-18 13-May-18 13-May-18, TRAMO 09: DESDE 4,620 A 4,635
30 TRAMO 10: DESDE 4,635 A4,638 4704 8 13-May-18 21-May-18 21-May-18, TRAMO 10: DESDE 4,635 A 4,638
31 CRESTA 3A 67326 393 03-Sep-17 30-Sep-18 30-Sep-18, CRESTA 3A
32 CONCRETO DENTAL 9350 357 03-Sep-17 25-Aug-18 25-Aug-18, CONCRETO DENTAL
33 TRAMO 1: DESDE 4,638 A4,639.5 13377 21 22-May-18 11-Jun-18 11-Jun-18, TRAMO 1: DESDE 4,638 A 4,639.5
34 TRAMO 2: DESDE 4,639.5 A4,641 7688 23 03-Jun-18 25-Jun-18 25-Jun-18, TRAMO 2: DESDE 4,639.5 A 4,641
35 TRAMO 3: DESDE 4,641 A4,642.5 9011 34 13-Jun-18 16-Jul-18 16-Jul-18, TRAMO 3: DESDE 4,641 A 4,642.5
36 TRAMO 4: DESDE 4,642.5 A4,644 6093 40 21-Jun-18 30-Jul-18 30-Jul-18, TRAMO 4: DESDE 4,642.5 A 4,644
37 TRAMO 5: DESDE 4,644 A4,645.5 4959 50 01-Jul-18 19-Aug-18 19-Aug-18, TRAMO 5: DESDE 4,644 A 4,645.5
38 TRAMO 6: DESDE 4,645.5 A4,647 7638 58 11-Jul-18 06-Sep-18 06-Sep-18, TRAMO 6: DESDE 4,645.5 A 4,647
39 TRAMO 7: DESDE 4,647 A4,648.5 9210 70 23-Jul-18 30-Sep-18 30-Sep-18, TRAMO 7: DESDE 4,647 A 4,648.5
40 ETAPA 3B 272190 504 28-Aug-17 13-Jan-19
41 CUERPO 3B 189025 396 28-Aug-17 27-Sep-18 27-Sep-18, CUERPO 3B
42 TRAMO 01: DESDE 4,500 A4,515 9926 50 28-Aug-17 16-Oct-17 16-Oct-17, TRAMO 01: DESDE 4,500 A 4,515
43 TRAMO 02: DESDE 4,515 A4,530 12559 50 17-Oct-17 05-Dec-17 05-Dec-17, TRAMO 02: DESDE 4,515 A 4,530
44 TRAMO 03: DESDE 4,530 A4,545 17091 50 06-Dec-17 24-Jan-18 24-Jan-18, TRAMO 03: DESDE 4,530 A 4,545
45 TRAMO 04: DESDE 4,545 A4,560 19663 40 25-Jan-18 05-Mar-18 05-Mar-18, TRAMO 04: DESDE 4,545 A 4,560
46 TRAMO 05: DESDE 4,560 A4,575 22102 40 06-Mar-18 14-Apr-18 14-Apr-18, TRAMO 05: DESDE 4,560 A 4,575
47 TRAMO 06: DESDE 4,575 A4,590 24897 43 15-Apr-18 27-May-18 27-May-18, TRAMO 06: DESDE 4,575 A 4,590
48 TRAMO 07: DESDE 4,590 A4,605 28276 30 27-May-18 26-Jun-18 26-Jun-18, TRAMO 07: DESDE 4,590 A 4,605
49 TRAMO 08: DESDE 4,605 A4,620 31067 30 26-Jun-18 26-Jul-18 26-Jul-18, TRAMO 08: DESDE 4,605 A 4,620
50 TRAMO 09: DESDE 4,620 A4,635 7045 36 26-Jul-18 31-Aug-18 31-Aug-18, TRAMO 09: DESDE 4,620 A 4,635
51 TRAMO 10: DESDE 4,635 A4,648.5 16399 27 31-Aug-18 27-Sep-18 27-Sep-18, TRAMO 10: DESDE 4,635 A 4,648.5
52 CRESTA 3B 83165 498 03-Sep-17 13-Jan-19
53 CONCRETO DENTAL 9350 452 03-Sep-17 28-Nov-18 28-Nov-18, CONCRETO DENTA
54 TRAMO 1: DESDE 4,648.5 A4,650 12579 6 01-Oct-18 06-Oct-18 06-Oct-18, TRAMO 1: DESDE 4,648.5 A 4,650
55 TRAMO 2: DESDE 4,650 A4,651.5 12491 19 06-Oct-18 24-Oct-18 24-Oct-18, TRAMO 2: DESDE 4,650 A 4,651.5
56 TRAMO 3: DESDE 4,651.5 A4,653 11578 20 23-Oct-18 11-Nov-18 11-Nov-18, TRAMO 3: DESDE 4,651.5 A 4,6
57 TRAMO 4: DESDE 4,653 A4,654.5 10733 20 10-Nov-18 29-Nov-18 29-Nov-18, TRAMO 4: DESDE
58 TRAMO 5: DESDE 4,654.5 A4,656 7839 12 28-Nov-18 09-Dec-18 09-Dec-18, TRAMO 5: D
59 TRAMO 6: DESDE 4,656 A4,657.5 8394 17 08-Dec-18 24-Dec-18 24-Dec-18, T
60 TRAMO 7: DESDE 4,657 A4,659 10201 21 24-Dec-18 13-Jan-19
61 TRANSPORTE MATERIA DE CANTERA 126050 572 06-May-17 28-Nov-18 28-Nov-18, TRANSPORTE MA
62 MATERIAL INADECUADO 103974 572 06-May-17 28-Nov-18 28-Nov-18, MATERIAL INADEC
63 MATERIAL INADECUADO 103974 572 06-May-17 28-Nov-18 28-Nov-18, MATERIAL INADEC
64 MATERIA PRIMA 22076 482 30-Jul-17 23-Nov-18 23-Nov-18, MATERIA PRIMA
65 MATERIA PRIMA 22076 482 30-Jul-17 23-Nov-18 23-Nov-18, MATERIA PRIMA
66 RAMPA 242 11 04-Aug-17 14-Aug-17 14-Aug-17, RAMPA
67 RAMPA 242 11 04-Aug-17 14-Aug-17 14-Aug-17, RAMPA
68 RAMPA 242 11 04-Aug-17 14-Aug-17 14-Aug-17, RAMPA
69 ACCESO OESTE 527 184 03-Jun-18 03-Dec-18 03-Dec-18,ACCESO OEST
70 CORTE 414 24 03-Jun-18 26-Jun-18 26-Jun-18, CORTE
71 CORTE 414 24 03-Jun-18 26-Jun-18 26-Jun-18, CORTE
72 RELLENO 113 130 27-Jul-18 03-Dec-18 03-Dec-18, RELLENO
73 RELLENO 113 130 27-Jul-18 03-Dec-18 03-Dec-18, RELLENO
74 ACCESO ESTE 1044 32 03-Jun-18 04-Jul-18 04-Jul-18,ACCESO ESTE
75 CORTE 838 24 03-Jun-18 26-Jun-18 26-Jun-18, CORTE
76 CORTE 838 24 03-Jun-18 26-Jun-18 26-Jun-18, CORTE
77 RELLENO 206 8 27-Jun-18 04-Jul-18 04-Jul-18, RELLENO
78 RELLENO 206 8 27-Jun-18 04-Jul-18 04-Jul-18, RELLENO
79 INSTRUMENTACION 17519 302 24-Mar-18 19-Jan-19
80 CRESTA 2B 3927 6 24-Mar-18 29-Mar-18 29-Mar-18, CRESTA 2B
81 CRESTA 2B 3927 6 24-Mar-18 29-Mar-18 29-Mar-18, CRESTA 2B
82 CUERPO Y CRESTA3B 9092 264 01-May-18 19-Jan-19
83 CUERPO 3B 4026 6 14-Jan-19 19-Jan-19
84 CRESTA 3B 5066 96 01-May-18 04-Aug-18 04-Aug-18, CRESTA 3B
85 TENDIDO DE CABLES 4500 260 24-Mar-18 08-Dec-18 08-Dec-18, TENDIDO DE
86 TENDIDO DE CABLES 4500 260 24-Mar-18 08-Dec-18 08-Dec-18, TENDIDO DE
87 SELLADO FISURAS Y GRIETAS 1940 140 21-Jun-18 07-Nov-18 07-Nov-18, SELLADO FISURAS Y GRIETAS
88 SELLADO FISURAS Y GRIETAS 1940 140 21-Jun-18 07-Nov-18 07-Nov-18, SELLADO FISURAS Y GRIETAS
89 SELLADO FISURAS Y GRIETAS 1940 140 21-Jun-18 07-Nov-18 07-Nov-18, SELLADO FISURAS Y GRIETAS

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 1 TASK filter: All Activities

Primary Baseline Remaining Work Milestone © Oracle Corporation