DEVELOPMENT OF DHA CITY KARACHI.

Dec-08-16 20:14

# Activity ID Activity Name Original Start Finish Budgeted Total Cost


Duration

1 DHA DEVELOPMENT OF DHA CITY KARACHI. 400 Mar-01-16 Mar-01-17 Rs116,446,878.00

2 DHA.1 MOBILIZATION 36 Mar-01-16 Apr-02-16 Rs0.00

3 A1000 PROJECT START 0 Mar-01-16 Rs0.00


4 A1010 JOINT SURVEY 10 Mar-12-16 Mar-21-16 Rs0.00
5 A1020 PREPARATION OF DRAWINGS 19 Mar-16-16 Apr-02-16 Rs0.00
6 DHA.2 ROADS & STREETS 154 Apr-07-16 Aug-25-16 Rs102,708,155.00

7 DHA.2.1 FORMATION OF ROAD 30 Apr-07-16 May-04-16 Rs50,796,604.00


8 DHA.2.1.1 Clearing & Grubbing 10 Apr-07-16 Apr-16-16 Rs922,146.00
9 A1030 Down Town Street 21 10 Apr-07-16 Apr-16-16 Rs27,150.00
10 A1040 Down Town Avenue 4 10 Apr-07-16 Apr-16-16 Rs839,066.00
11 A1050 Down Town Lane A 3 Apr-07-16 Apr-10-16 Rs27,150.00
12 A1060 Down Town Lane B 3 Apr-07-16 Apr-10-16 Rs28,780.00
13 DHA.2.1.2 NATURAL GROUND COMPACTION 24 Apr-12-16 May-04-16 Rs49,874,458.00
14 A1070 Down Town Street 21 15 Apr-20-16 May-04-16 Rs10,666,765.00
15 A1080 Down Town Avenue 4 12 Apr-20-16 May-01-16 Rs36,757,519.00
16 A1090 Down Town Lane A 4 Apr-12-16 Apr-16-16 Rs1,189,391.00
17 A1100 Down Town Lane B 4 Apr-12-16 Apr-16-16 Rs1,260,783.00
18 DHA.2.2 PREPARATION OF ROAD STRUCTURE 102 Apr-18-16 Jul-20-16 Rs8,319,386.00
19 DHA.2.2.1 Subgrade Prepration 50 Apr-18-16 Jun-01-16 Rs341,395.00
20 A1110 Down Town Street 21 25 May-10-16 Jun-01-16 Rs73,015.00
21 A1120 Down Town Avenue 4 28 May-05-16 May-30-16 Rs251,609.00
22 A1130 Down Town Lane A 5 Apr-18-16 Apr-22-16 Rs8,141.00

Page 1 of 4 TASK filter: All Activities

© Oracle Corporation
DEVELOPMENT OF DHA CITY KARACHI. Dec-08-16 20:14

# Activity ID Activity Name Original Start Finish Budgeted Total Cost


Duration

23 A1140 Down Town Lane B 5 Apr-18-16 Apr-22-16 Rs8,630.00


24 DHA.2.2.2 Granuar Sub Base 60 Apr-28-16 Jun-21-16 Rs3,716,386.00
25 A1150 Down Town Street 21 30 May-25-16 Jun-21-16 Rs794,832.00
26 A1160 Down Town Avenue 4 30 May-20-16 Jun-15-16 Rs2,738,980.00
27 A1170 Down Town Lane A 10 Apr-28-16 May-07-16 Rs88,627.00
28 A1180 Down Town Lane B 10 Apr-28-16 May-07-16 Rs93,947.00
29 DHA.2.2.3 Aggregate Base Coarse 72 May-14-16 Jul-20-16 Rs4,261,605.00
30 A1190 Down Town Street 21 30 Jun-21-16 Jul-20-16 Rs911,439.00
31 A1200 Down Town Avenue 4 30 Jun-15-16 Jul-15-16 Rs3,140,807.00
32 A1210 Down Town Lane A 10 May-14-16 May-23-16 Rs101,629.00
33 A1220 Down Town Lane B 10 May-14-16 May-23-16 Rs107,730.00
34 DHA.2.3 ASPHALT & KERB BLOCK 24 Jul-20-16 Aug-11-16 Rs38,618,243.00
35 DHA.2.3.1 Prime Coat 12 Jul-20-16 Jul-31-16 Rs2,105,210.00
36 A1230 Down Town Street 21 2 Jul-25-16 Jul-26-16 Rs450,246.00
37 A1240 Down Town Avenue 4 2 Jul-20-16 Jul-22-16 Rs1,551,542.00
38 A1250 Down Town Lane A 1 Jul-26-16 Jul-26-16 Rs50,204.00
39 A1260 Down Town Lane B 1 Jul-30-16 Jul-31-16 Rs53,218.00
40 DHA.2.3.2 Asphaltic Wearing Coarse 15 Jul-28-16 Aug-11-16 Rs19,142,747.00
41 A1270 Down Town Street 21 2 Aug-09-16 Aug-11-16 Rs4,094,103.00
42 A1280 Down Town Avenue 4 2 Aug-05-16 Aug-07-16 Rs14,108,222.00
43 A1290 Down Town Lane A 1 Jul-28-16 Jul-29-16 Rs456,510.00
44 A1300 Down Town Lane B 1 Aug-03-16 Aug-03-16 Rs483,912.00
45 DHA.2.3.3 Tack Coat 6 Aug-03-16 Aug-08-16 Rs583,870.00
46 A1310 Down Town Street 21 2 Aug-06-16 Aug-08-16 Rs131,325.00
Page 2 of 4 TASK filter: All Activities

© Oracle Corporation
DEVELOPMENT OF DHA CITY KARACHI. Dec-08-16 20:14

# Activity ID Activity Name Original Start Finish Budgeted Total Cost


Duration

47 A1320 Down Town Avenue 4 2 Aug-03-16 Aug-04-16 Rs452,545.00


48 DHA.2.3.4 Asphaltic Base Coarse 5 Jul-27-16 Aug-01-16 Rs16,786,416.00
49 A1330 Down Town Street 21 2 Jul-30-16 Aug-01-16 Rs3,775,634.00
50 A1340 Down Town Avenue 4 2 Jul-27-16 Jul-29-16 Rs13,010,782.00
51 DHA.2.4 OTHER WORKS 18 Aug-09-16 Aug-25-16 Rs4,973,922.00
52 DHA.2.4.1 PAVEMENT MARKING 10 Aug-09-16 Aug-18-16 Rs0.00
53 A1350 Down Town Street 21 5 Aug-13-16 Aug-18-16 Rs0.00
54 A1360 Down Town Avenue 4 5 Aug-09-16 Aug-13-16 Rs0.00
55 A1370 Down Town Lane A 1 Aug-09-16 Aug-10-16 Rs0.00
56 A1380 Down Town Lane B 1 Aug-12-16 Aug-13-16 Rs0.00
57 DHA.2.4.2 PAVEMENT STUDS 10 Aug-16-16 Aug-25-16 Rs4,973,922.00
58 A1390 Down Town Street 21 3 Aug-22-16 Aug-25-16 Rs1,063,784.00
59 A1400 Down Town Avenue 4 3 Aug-17-16 Aug-19-16 Rs3,665,785.00
60 A1410 Down Town Lane A 1 Aug-16-16 Aug-17-16 Rs118,617.00
61 A1420 Down Town Lane B 1 Aug-19-16 Aug-19-16 Rs125,736.00
62 DHA.2.5 FOOTPATH, PIAZA & MEDIAN 101 Aug-02-16 Nov-02-16 Rs13,738,723.00

63 DHA.2.5.1 KERB BLOCK FIXING 46 Aug-02-16 Sep-13-16 Rs1,250,482.00


64 A1430 Down Town Street 21 30 Aug-16-16 Sep-13-16 Rs312,620.50
65 A1440 Down Town Avenue 4 30 Aug-12-16 Sep-07-16 Rs312,620.50
66 A1450 Down Town Lane A 15 Aug-02-16 Aug-15-16 Rs312,620.50
67 A1460 Down Town Lane B 15 Aug-06-16 Aug-19-16 Rs312,620.50
68 DHA.2.5.2 FOOTH PATH LEAN 46 Aug-19-16 Sep-29-16 Rs663,410.00
69 A1470 Down Town Street 21 10 Sep-21-16 Sep-29-16 Rs165,852.50

Page 3 of 4 TASK filter: All Activities

© Oracle Corporation
DEVELOPMENT OF DHA CITY KARACHI. Dec-08-16 20:14

# Activity ID Activity Name Original Start Finish Budgeted Total Cost


Duration

70 A1480 Down Town Avenue 4 10 Sep-16-16 Sep-25-16 Rs165,852.50


71 A1490 Down Town Lane A 5 Aug-19-16 Aug-23-16 Rs165,852.50
72 A1500 Down Town Lane B 5 Aug-25-16 Aug-29-16 Rs165,852.50
73 DHA.2.5.3 STONE TILE FIXING 51 Aug-30-16 Oct-17-16 Rs10,993,885.00
74 A1510 Down Town Street 21 10 Oct-07-16 Oct-17-16 Rs2,748,471.25
75 A1520 Down Town Avenue 4 10 Oct-04-16 Oct-15-16 Rs2,748,471.25
76 A1530 Down Town Lane A 5 Aug-30-16 Sep-04-16 Rs2,748,471.25
77 A1540 Down Town Lane B 5 Sep-03-16 Sep-07-16 Rs2,748,471.25
78 DHA.2.5.4 PAINT 21 Oct-15-16 Nov-02-16 Rs830,946.00
79 A1550 Down Town Street 21 5 Oct-29-16 Nov-02-16 Rs207,736.50
80 A1560 Down Town Avenue 4 5 Oct-29-16 Nov-02-16 Rs207,736.50
81 A1570 Down Town Lane A 2 Oct-15-16 Oct-17-16 Rs207,736.50
82 A1580 Down Town Lane B 2 Oct-20-16 Oct-22-16 Rs207,736.50
83 DHA.2.6 HANDING OVER 130 Nov-03-16 Mar-01-17 Rs0.00

84 A1590 AS BUILT 100 Nov-03-16 Feb-02-17 Rs0.00

85 A1600 SITE CLEARANCE 30 Feb-02-17 Mar-01-17 Rs0.00


86 A1610 HANDING TAKING CERTIFICATE 0 Mar-01-17 Rs0.00