Id Modo de Nombre de tarea Costo Trabajo Duración Comienzo Fin 18 dic '17 25 dic '17 01 ene '18 08 ene

18 dic '17 25 dic '17 01 ene '18 08 ene '18 15 ene '18 22 ene '18 29 ene '18 05 feb '18 12 feb '18 19 feb '18 26 feb '18 05 mar '18 12 mar '18
tarea Detalles L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L M X J V S D L
1 PROYECTO VIVIENDA S/ 47,298.00 1,872 horas50 días lun 18/12/17 vie 23/02/18 Trab. 32h 32h 32h 32h 32h 40h 40h 40h 40h 40h 40h 40h 40h 48h 48h 48h 48h 48h 48h 48h 32h 32h 32h 32h 32h 32h 32h 32h 32h 32h 48h 48h 48h 48h 40h 40h 40h 40h 40h 32h 32h 32h 32h 32h 32h 40h 40h 40h 16h 16h
2 modulo 1 S/ 31,164.00 1,136 horas30 días lun 18/12/17 vie 26/01/18 Trab. 32h 32h 32h 32h 32h 40h 40h 40h 40h 40h 40h 40h 40h 48h 48h 48h 48h 48h 48h 48h 32h 32h 32h 32h 32h 32h 32h 32h 32h 32h
3 limpieza de terreno S/ 3,004.00 160 horas 5 días lun 18/12/17 vie 22/12/17 Trab. 32h 32h 32h 32h 32h
CARLOS S/ 800.00 40 horas lun 18/12/17 vie 22/12/17 Trab. 8h 8h 8h 8h 8h
VICTOR S/ 800.00 40 horas lun 18/12/17 vie 22/12/17 Trab. 8h 8h 8h 8h 8h
CAPATAZ S/ 750.00 40 horas lun 18/12/17 vie 22/12/17 Trab. 8h 8h 8h 8h 8h
VIGILANTE S/ 300.00 40 horas lun 18/12/17 vie 22/12/17 Trab. 8h 8h 8h 8h 8h
AGUA S/ 24.00 3 M³ lun 18/12/17 vie 22/12/17 Trab. (M³) 0.6 0.6 0.6 0.6 0.6
ALMUERZO S/ 150.00 lun 18/12/17 vie 22/12/17 Trab.
CENA S/ 180.00 lun 18/12/17 vie 22/12/17 Trab.
4 cimientos S/ 8,452.00 320 horas 8 días lun 25/12/17 mié 03/01/18 Trab. 40h 40h 40h 40h 40h 40h 40h 40h
CARLOS S/ 1,280.00 64 horas lun 25/12/17 mié 03/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h
VICTOR S/ 1,280.00 64 horas lun 25/12/17 mié 03/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h
SUPERVISOR S/ 2,200.00 64 horas lun 25/12/17 mié 03/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h
CAPATAZ S/ 1,200.00 64 horas lun 25/12/17 mié 03/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h
VIGILANTE S/ 480.00 64 horas lun 25/12/17 mié 03/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h
CEMENTO S/ 1,210.00 55 Bolsas lun 25/12/17 mié 03/01/18 Trab. (Bolsas) 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88
AGUA S/ 32.00 4 M³ lun 25/12/17 mié 03/01/18 Trab. (M³) 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5
CLAVOS S/ 10.00 2 KG lun 25/12/17 mié 03/01/18 Trab. (KG) 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
FIERRO S/ 330.00 22 UNID lun 25/12/17 mié 03/01/18 Trab. (UNID) 2.75 2.75 2.75 2.75 2.75 2.75 2.75 2.75
ALMUERZO S/ 250.00 lun 25/12/17 mié 03/01/18 Trab.
CENA S/ 180.00 lun 25/12/17 mié 03/01/18 Trab.
5 levantar estructura S/ 14,828.00 336 horas 7 días jue 04/01/18 vie 12/01/18 Trab. 48h 48h 48h 48h 48h 48h 48h
CARLOS S/ 1,120.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
VICTOR S/ 1,120.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
SUPERVISOR S/ 1,925.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
CAPATAZ S/ 1,050.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
ARQUITECTO S/ 1,575.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
MEZCLADORA DE S/ 3,740.00 56 horas jue 04/01/18 vie 12/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h
CEMENTO
CEMENTO S/ 2,970.00 135 Bolsas jue 04/01/18 vie 12/01/18 Trab. (Bolsas) 19.29 19.29 19.29 19.29 19.29 19.29 19.29
AGUA S/ 12.00 1.5 M³ jue 04/01/18 vie 12/01/18 Trab. (M³) 0.21 0.21 0.21 0.21 0.21 0.21 0.21
CLAVOS S/ 15.00 3 KG jue 04/01/18 vie 12/01/18 Trab. (KG) 0.43 0.43 0.43 0.43 0.43 0.43 0.43
FIERRO S/ 825.00 55 UNID jue 04/01/18 vie 12/01/18 Trab. (UNID) 7.86 7.86 7.86 7.86 7.86 7.86 7.86
PETRÓLEO S/ 96.00 8 GLN jue 04/01/18 vie 12/01/18 Trab. (GLN) 1.14 1.14 1.14 1.14 1.14 1.14 1.14
ALMUERZO S/ 200.00 jue 04/01/18 vie 12/01/18 Trab.
CENA S/ 180.00 jue 04/01/18 vie 12/01/18 Trab.
6 secado S/ 4,880.00 320 horas 10 días lun 15/01/18 vie 26/01/18 Trab. 32h 32h 32h 32h 32h 32h 32h 32h 32h 32h
CAPATAZ S/ 1,500.00 80 horas lun 15/01/18 vie 26/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h 8h 8h
VIGILANTE S/ 600.00 80 horas lun 15/01/18 vie 26/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h 8h 8h
PEDRO S/ 1,200.00 80 horas lun 15/01/18 vie 26/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h 8h 8h
OMAR S/ 1,200.00 80 horas lun 15/01/18 vie 26/01/18 Trab. 8h 8h 8h 8h 8h 8h 8h 8h 8h 8h
ALMUERZO S/ 200.00 lun 15/01/18 vie 26/01/18 Trab.
CENA S/ 180.00 lun 15/01/18 vie 26/01/18 Trab.
7 modulo 2 S/ 12,755.00 584 horas 15 días lun 29/01/18 vie 16/02/18 Trab. 48h 48h 48h 48h 40h 40h 40h 40h 40h 32h 32h 32h 32h 32h 32h
8 acabado de exteriores S/ 3,840.00 192 horas 4 días lun 29/01/18 jue 01/02/18 Trab. 48h 48h 48h 48h
CARLOS S/ 640.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
VICTOR S/ 640.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
CAPATAZ S/ 600.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
VIGILANTE S/ 240.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
ARQUITECTO S/ 900.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
DISEÑADOR DE S/ 440.00 32 horas lun 29/01/18 jue 01/02/18 Trab. 8h 8h 8h 8h
INTERIORES
ALMUERZO S/ 200.00 lun 29/01/18 jue 01/02/18 Trab.
CENA S/ 180.00 lun 29/01/18 jue 01/02/18 Trab.
9 instalaciones S/ 4,905.00 200 horas 5 días vie 02/02/18 jue 08/02/18 Trab. 40h 40h 40h 40h 40h
CARLOS S/ 800.00 40 horas vie 02/02/18 jue 08/02/18 Trab. 8h 8h 8h 8h 8h
SUPERVISOR S/ 1,375.00 40 horas vie 02/02/18 jue 08/02/18 Trab. 8h 8h 8h 8h 8h
OMAR S/ 600.00 40 horas vie 02/02/18 jue 08/02/18 Trab. 8h 8h 8h 8h 8h
ARQUITECTO S/ 1,125.00 40 horas vie 02/02/18 jue 08/02/18 Trab. 8h 8h 8h 8h 8h
ELECTRICISTA S/ 625.00 40 horas vie 02/02/18 jue 08/02/18 Trab. 8h 8h 8h 8h 8h
ALMUERZO S/ 200.00 vie 02/02/18 jue 08/02/18 Trab.
CENA S/ 180.00 vie 02/02/18 jue 08/02/18 Trab.
10 acabado de interiores S/ 4,010.00 192 horas 6 días vie 09/02/18 vie 16/02/18 Trab. 32h 32h 32h 32h 32h 32h
CAPATAZ S/ 900.00 48 horas vie 09/02/18 vie 16/02/18 Trab. 8h 8h 8h 8h 8h 8h
OMAR S/ 720.00 48 horas vie 09/02/18 vie 16/02/18 Trab. 8h 8h 8h 8h 8h 8h
ARQUITECTO S/ 1,350.00 48 horas vie 09/02/18 vie 16/02/18 Trab. 8h 8h 8h 8h 8h 8h
DISEÑADOR DE S/ 660.00 48 horas vie 09/02/18 vie 16/02/18 Trab. 8h 8h 8h 8h 8h 8h
INTERIORES
ALMUERZO S/ 200.00 vie 09/02/18 vie 16/02/18 Trab.
CENA S/ 180.00 vie 09/02/18 vie 16/02/18 Trab.
11 modulo 3 S/ 3,379.00 152 horas 5 días lun 19/02/18 vie 23/02/18 Trab. 40h 40h 40h 16h 16h
12 pintado S/ 3,131.00 120 horas 3 días lun 19/02/18 mié 21/02/18 Trab. 40h 40h 40h
VICTOR S/ 480.00 24 horas lun 19/02/18 mié 21/02/18 Trab. 8h 8h 8h
CAPATAZ S/ 450.00 24 horas lun 19/02/18 mié 21/02/18 Trab. 8h 8h 8h
VIGILANTE S/ 180.00 24 horas lun 19/02/18 mié 21/02/18 Trab. 8h 8h 8h
PEDRO S/ 360.00 24 horas lun 19/02/18 mié 21/02/18 Trab. 8h 8h 8h
OMAR S/ 360.00 24 horas lun 19/02/18 mié 21/02/18 Trab. 8h 8h 8h
AGUA S/ 4.00 0.5 M³ lun 19/02/18 mié 21/02/18 Trab. (M³) 0.17 0.17 0.17
PINTURA S/ 875.00 25 BALDE lun 19/02/18 mié 21/02/18 Trab. (BALDE) 8.33 8.33 8.33
RODILLO S/ 28.00 7 UNID lun 19/02/18 mié 21/02/18 Trab. (UNID) 2.33 2.33 2.33
LIJAS S/ 14.00 7 UNID lun 19/02/18 mié 21/02/18 Trab. (UNID) 2.33 2.33 2.33
ALMUERZO S/ 200.00 lun 19/02/18 mié 21/02/18 Trab.
CENA S/ 180.00 lun 19/02/18 mié 21/02/18 Trab.
13 jardineria S/ 248.00 32 horas2 días jue 22/02/18 vie 23/02/18 Trab. 16h 16h
VIGILANTE S/ 120.00 16 horas jue 22/02/18 vie 23/02/18 Trab. 8h 8h
JARDINERO S/ 80.00 16 horas jue 22/02/18 vie 23/02/18 Trab. 8h 8h
AGUA S/ 8.00 1 M³ jue 22/02/18 vie 23/02/18 Trab. (M³) 0.5 0.5
ALMUERZO S/ 20.00 jue 22/02/18 vie 23/02/18 Trab.
PASAJES S/ 20.00 jue 22/02/18 vie 23/02/18 Trab.