BUILDING COST CALCULATIONS

TOTAL AREA: 26’-8” X 24’-7” = 651.7 SQFT

DOOR 1 = 3’-6”X 8’

DOOR 2 = 2’-6” X 7’

WINDOWS 1 & 2 = 4’X 5’; SILL LEVEL= 2’

WASHROOM WINDOW = 3’ X 2’; SILL LEVEL = 6’

VOLUME OF SOUTH-EAST WALL = 209.475 CFT

VOLUME OF DOOR = 21 CFT

TOTAL VOLUME SUBTRACTING THAT OF DOOR = 188.475 CFT

VOLUME OF NORTH-EAST WALL = 192.93 CFT

VOLUME OF TWO WINDOWS = 30 CFT

VOLUME SUBTRACTING THAT OF WINDOWS = 162.93 CFT

VOLUME OF NORTH-WEST WALL = 209.475 CFT

VOLUME OF SOUTH-WEST WALL = 192.93 CFT

VOLUME OF WINDOW = 4.5 CFT

VOLUME SUBTRACTING WINDOW = 188.43 CFT

TOTAL VOLUME OF 9” BRICK WALLS = 749.31 CFT

TOTAL NO. OF BRICKS = 10,116 ( FORMULA: 1 CFT = 13.5 BRICKS )

WASHROOM WALLS:

VOLUME = 74.325 CFT

NO. OF BRICKS = 1003

4.5“THICK PARTITION WALL:

VOLUME = 90.5 CFT

NO. OF BRICKS = 1222.5

4.5” THICK PARAPET, 2’ HIGH:

VOLUME = 57.5 CFT


NO. OF BRICKS = 777

TOTAL VOLUME OF BRICK WALLS = 971.7 CFT

TOTAL NO. OF BRICKS USED = 13,119

TOTAL COST OF BRICKS = RS. 104,952

MORTAR
MORTER USED (30% OF TOTAL VOLUME) = 3,935

CONVERTING TO DRY MATERIAL = 3935 X 1.2

=4722.6 CFT / 7 = 675 CFT

CEMENT : SAND

1 : 6

CEMENT USED = 675 / 1.25 = 540 BAGS ( FORMULA: 1 BAG = 1.25 CFT )

SAND USED = 675 X 6 = 4050 CFT

PLASTER
TOTAL VOLUME = 971.63CFT

CONVERTING INTO DRY MATERIAL =971.63 X 1.2 = 1,166 CFT / 5 = 233.2 CFT

CEMENT : SAND

1 : 4

CEMENT USED = 233.2 / 1.25 = 186.56 BAGS

SAND USED = 233.2 X 4 = 932.8 CFT

PCC (PLAIN CEMENT CONCRETE)


TOTAL AREA = 651.7 SQFT

VOLUME = 651.7 X 0.33 = 215CFT

CONVERTING INTO DRY MATERIAL = 215 CFT X 1.54 = 331.1 CFT/7 = 47.3 CFT

CEMENT : SAND : AGGREGATE

1 : 2 : 4

CEMENT USED = 47.3/1.25 = 38 BAGS

SAND USED = 94.6 CFT

AGGREGATE USED= 189.2CFT


COST AGGREGATE = RS. 14,757

RCC (RE-INFORCED CEMENT CONCRETE)


CEMENT USED= 38 BAGS

SAND USED = 94.6 CFT

AGGREGATE = 189.2 CFT

COST= 189.2 X 78 = RS. 14,757

STEEL
1KG/SQFT

STEEL USED = 651.7 KG

COST = RS. 48,878

OUTER WALLS PLASTER


TOTAL VOLUME = 806.81 X 1.2 = 968.172/ 5 = 193.6 CFT

CEMENT USED= 242 BAGS

SAND USED = 774.5 CFT

SAND USED IN FLOOR = 215.061 CFT

TOTAL QUANTITIES:

TOTAL CEMENT USED= 540 + 186.56 + 38 +38 + 242 = 1044 BAGS

COST = RS. 542,880


TOTAL SAND USED = 4050 CFT + 932.8CFT+ 189.2 CFT + 189.2CFT + 774.5 + 215.061 = 2301 CFT

COST =2301 CFT X 30 = RS. 69,030

BRICK BALLAST 4 “
VOLUME = 215.061 CFT

COST = 215.061 X 30 = RS. 6451.83

BRICK TILES ON ROOF


3.5 TILES / SQFT

TOTAL TILES = 2280.95


COST = 2280.95 X 8 = RS. 18,248

WASHROOM AREA = 74.3 SQFT; IN METERS = 6.90 SQM


TOTAL CERAMIC TILE COST = RS. 4,830
BEDROOM AND LIVING FLOOR AREA = 391 SQFT; IN METERS= 36.3 SQM

TOTAL FLOORING TILE (CHINA) COST = RS. 107,992


KITCHENETTE AREA = 94 SQFT; IN METERS = 8.7 SQM

TOTAL COST WOODEN TILE = RS. 23,500

BITUMEN
AREA= 651.7 SQFT

COST = 651.7 X 10 = RS. 6,517

PAINT EXTERIOR & INTERIOR


TOTAL AREA TO BE PAINTED = 2019 SQFT

COST =1000/ 100SQFT

COST OF PAINT = RS. 20,190

CABINET
RS.650 /SQFT

AREA = 18 SQFT

COST = RS. 11,700


TOTAL COST OF BUILDING =RS. 994,683

COST OF WASHROOM FIXTURES:


W.C= RS. 17,000

VANITY = RS. 8,000

SHOWER = RS. 9500

WATER TAP =RS. 4285

TOTAL = RS. 38,785


LABOUR COST = 651.7 SQFT X 400 = RS. 260,680
5% WASTAGE = RS. 13,034

ADDING ALL VALUES

TOTAL COST OF BUILDING = RS. 1,307,182


COST CHART

MATERIAL RATE (RS.)


CERAMIC TILE 700 /SQM
CABINET 650/SQFT
BRICK 8/ BRICK
CEMENT 520 PER BAG
SAND 60/CFT
AGGREGATE 78/CFT
BRICK TILE 8/TILE
WOOD TILE 250/SQFT
STEEL 60 GRADE 7500/ 100 KG
BRICK BALLAST 30/CFT
SAND (CHENAB) 30/CFT
BITUMEN 10/CFT
FLOORING TILE (CHINA) 2975 SQM