Documentos de Académico
Documentos de Profesional
Documentos de Cultura
N
ASA at its Marshall Space Flight Center in Huntsville, Ala., contracted an energy consulting
company to evaluate the operation of the central chilled water plant (CCWP) built in 1999 to
ascertain if any improvements could be made to reduce operating cost with no expenditure of capital
funds. Only no-cost changes were considered. This was a decision made by the owner to ensure
existing systems were operating at peak performance before extensive capital expenditure projects
were evaluated. The consultant’s study showed that the chilled water system was not producing the
ΔT that matched the chillers’ design during off-peak conditions. This condition is often called low ΔT
syndrome and has been written about in many articles.1,2,3,4
36 ASHRAE Journal ashrae.org July 2007
Secondary Loops A – E
#6
#9 #5 #4 #3 #2 #1
#5
#4
Primary Pumps Typ.(9) Decoupler
75 hp (56 kW) at 2,750 gpm
(168.6 L/s) #3
Secondary ΔT
not at peak. As the OA and load 8
7
decreases, the secondary ΔT 6
reduces to approximately 7°F 5
(3.9°C) at its minimum. This 4
is a graphical representation of 3
Mixing 48°F
(8.9°C) Secondary Pumps
44°F
(6.7°C)
Decoupler Loop
0 gpm
Building Load
1,536 gpm
1,250 ton (4396 kW) Chiller 2,750 gpm (94.2 L/s)
(168.6 L/s)
Primary Pump
51°F (10.6°C) 51°F (10.6°C) 2,750 gpm (168.6 L/s)
Tons Loop= 2,750 gpm × 7°F / 24 = 802 tons Tons Loop= 4,286 gpm × 7°F / 24 = 1,250 tons
Chiller Tons = 2,750 gpm × 7°F / 24 = 802 tons Chiller Tons = 2,750 gpm × 11°F / 24 = 1,250 tons
Number of Chillers On
secondary loop. To deal with this 6
44°F
Mixing (6.7°C)
T
Chiller Discharge
44°F Secondary Pumps
Temperature Reset
(6.7°C)
40°F
(4.4°C)
Building Load
Decoupler Loop
0 gpm
1,250 ton (4396 kW) Chiller
1,536 gpm
2,750 gpm (94.2 L/s)
(168.6 L/s)
Primary Pump
2,750 gpm (168.6 L/s)
New Start Sequence: If CHWS Sec. >1°F (0.6°C) above reset setpoint for five minutes, then start next chiller.
(1759 kW). Yet Figure 4 shows that on all but two one-hour decoupler, for loads above 802 tons (2821 kW) as seen by the
events, there was always a minimum of two chillers running. arrows in Figure 5, the temperature in the secondary supply
As previously noted, the next chiller for this site was started starts to increase. With the new code in control on the actual
when the secondary flow exceeded the primary. system, the existing temperature sensors on the secondary loops
detect this increase and the UCS system modulates the chiller
UCS Code Logic Change discharge temperature setpoint to maintain the desired mixed
Is there a controls logic change that could be implemented at water temperature in the secondary. As the load increases, and
the CCWP that would enable the chillers to control the secondary more mixing occurs at the supply side of the decoupler, the
temperature setpoint and load to 100% despite the impact of low chiller(s) discharge temperature is lowered through a typical
ΔT syndrome? The CCWP’s product is chilled water that is distrib- control loop from the UCS to maintain the secondary sup-
uted to users around the site, which specifically is the secondary ply setpoint. This means that during some part of the day the
chilled water system. Logically speaking, shouldn’t the secondary chiller discharge temperature could be lower than the secondary
temperature be directly monitored
and controlled to the desired
setpoint? This, in simple terms, 12/1/05 - 5/31/06 Peak OA
Start 6th chiller 96°F (35.6°C)
is exactly what the new logic (No 7th chiller)
>85°F (29.4°C)
code does. The new logic for the
8
CCWP is to directly maintain and Start 5th chiller
control the secondary setpoint 7 >72°F (22.2°C)
Number of Chillers On
the change in operation in this way removes the impact of the • The previous code operated the sixth chiller for six hours
weather and load. during the day versus only one hour for the new code;
Several methods were used to verify this improvement in • The new code dropped back to only two chillers running
efficiency of the new logic code. One method that proved to versus four at the end of the day for the previous code;
be interesting was a side-by-side 24-hour-by-hour comparison. and
A 24-hour day from the previous operational trend data (May • In the previous code, the flow in the primary was con-
16, 2003) and one from after the change (May 23, 2006) were trolled to always be more than the secondary and was
selected that was as close as possible to the same in OA dry- always “positive” in the decoupler. The flow in the
bulb temperature and is shown in Table 1. decoupler was “negative (or opposite)” in the after logic
A reset chilled water schedule up to 44°F (6.7°C) was also change, representing a greater flow in the secondary
implemented during this change that enabled the lowering of the than the primary for most hours of the day.
chiller discharge temperatures. The following can be observed This side-by-side comparison shows that fewer chillers were
from this side-by-side comparison in Table 1: operated between the data before the code change (2003–04) and
• The day started with one less chiller operating with the the data after (2006). As previously stated, the site added a Loop B
new code; to the CCWP in the summer of 2005, which means that even with
• The new code did start the fifth chiller sooner in the day an increased load, the new code operated with fewer chillers.
than the previous code, but the OA temperature was 3.6°F
(2°C) higher; Energy Savings
• The sixth chiller was started by the new code two hours Where are the savings coming from for this new logic change?
later than the previous code; The majority of savings is coming from the equipment that is