1 1 0 2 6 B - 3 . 1 - 0 0 - M - 0 2 - S A - 0 0 0 6 - 0 1 - 2

TITLE :

CALCULATION FOR AC BUILDING


PURPOSE :

FOR TRAINING
REV Description Prepared Checked Approved Date

CONTRACTOR Doc No. :

CONSULTANT
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 2 of 25

TABLE OF CONTENT

1. GENERAL ............................................................................................................................ 3
1.1 Scope................................................................................................................................ 3
2. DEFINITIONS ...................................................................................................................... 3
3. REFERENCE ........................................................................................................................ 3
3.1 Standards and Codes ........................................................................................................ 3
3.2 Reference documents: ...................................................................................................... 3
3.3 Abbreviations ................................................................................................................... 4
4. AIR CONDITIONING CALCULATION ............................................................................ 5
4.1 Design Input ..................................................................................................................... 5
4.2 Outdoor Design Condition ............................................................................................... 6
4.3 Indoor Design Condition ................................................................................................. 7
4.4 People and Occupancy ..................................................................................................... 7
4.5 Electrical Equipment Heat Dissipation ............................................................................ 8
5. VENTILATION REQUIREMENT CALCULATION ......................................................... 8
5.1 Fresh Air for People ......................................................................................................... 8
5.2 Air Pressure Calculation .................................................................................................. 9
5.3 Fresh Air Requirement................................................................................................... 10
6. SUMMARY OF AIR CONDITIONING SYSTEM ........................................................... 11
7. HVAC EQUIPMENT SELECTION .................................................................................. 12
8. PRESSURIZE FAN ............................................................................................................ 12
9. APPENDIX ......................................................................................................................... 13
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 3 of 25

1. GENERAL

1.1 Scope

This calculation covers of Buildings by PT. PUSTEK E&T and located at Depok, Jawa Barat,
Indonesia.

2. DEFINITIONS

PROJECT Head Office PT. PUSTEK E&T

CLIENT PT. PUSTEK E&T

CONSULTANT PT. PUSTEK E&T

CONTRACTOR PT. PUSTEK E&T

VENDOR/ Refers to the company selected by CLIENT or CONTRACTOR, which


MANUFACTURER is responsible for the purchase agreement specification.

3. REFERENCE

3.1 Standards and Codes

 ASHRAE Standard 62.1-2007 Ventilation for Acceptable Indoor Air Quality


 ASHRAE Handbook Fundamental 2013 (SI)
 ASHRAE Handbook HVAC Application

3.2 Reference documents:

o Head Office Building Layout


PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 4 of 25

3.3 Abbreviations

Term Definition
American Society of Heating, Refrigerating and Air Conditioning
ASHRAE
Engineers
°C degrees Celsius
CMH Cubic meters per hour
H Enthalpy
hr hour
kg kilogram
kW kilowatt
L/s Liters per second
MAX Maximum
m meters
2
m Square meters
m3 Cubic meters
N/C Not Conditioned
Pa Pascal
RH Relative Humidity
TEMP Temperature
W watt
NE North East
NW North West
SE South East
SW South West
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 5 of 25

4. AIR CONDITIONING CALCULATION

4.1 Design Input

The components that contribute to room heat gains and losses consist of external load (solar
transmissions, radiations, wall transmissions, floor transmissions, ceiling transmissions,
ventilations load and infiltration loads) and internal load (equipment heat dissipation, people
and lighting heat gain).

 General Info

Floor Room Wall Area (m2)


No Room Area Height Facing to the sun

m2 m NE NW SE SW
1 Head Office Building
1.1 LT1 CEO ROOM 30 3.5 - - 17.5 -
LTG WORKSPACE
1.2 87.5 4.2 21 73.5 42 -
ROOM
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10

People and Lighting Heat Gain

Lighting
People 2)
Power 1)
No Room
Sensible Latent
Watt Degrees of Activity
(W/person) (W/person)

1 Head Office Building


Moderately active
1.1 LT1 CEO ROOM 2166 75 55
office work
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 6 of 25

LTG WORKSPACE Moderately active


1.2 648 75 55
ROOM office work
1.3 75 55

1.4 75 55

1.5 75 55

1.6 70 45

1.7 75 55

1.8 75 70

1.9 75 70

1.10 75 70

1)
Refer to Lighting Layout
2)
Refer to ASHRAE Handbook Fundamental 2013 (SI) page 18.4 Table 1.

4.2 Outdoor Design Condition

Relative Humidity (2018)


https://www.worldweatheronline.com/depok-weather-averages/west-java/id.aspx

Relative Humidity %

Min. 53
Max. 76
Temperature

Temperature Dry Bulb °C

Min. 25
Max. 38

 Plant Located : Depok, Jawa Barat-Indonesia


 Latitude : -6,39 deg
 Longitude : 106, 83 deg
 Elevation : 83 Meters
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 7 of 25

4.3 Indoor Design Condition

Min.
Temperature Humidity
Pressurized
No Room
Min. Max. Min. % Max. %
(Pa)
(°C) (°C)
1 Head Office Building
1.1 LT1 CEO ROOM 23.00 25.00 45 55 15
LTG WORKSPACE
1.2 23.00 25.00 45 55 15
ROOM
1.3 23.00 25.00 45 55 15
1.4 23.00 25.00 45 55 15

1.5 23.00 25.00 45 55 15

1.6 23.00 25.00 45 55 15

1.7 23.00 25.00 45 55 15


1.8 23.00 25.00 45 55 15
1.9 23.00 25.00 45 55 15
1.10 23.00 25.00 45 55 15

4.4 People and Occupancy

No Room Occupant Density (Persons)

1 Head Office Building


1.1 LT1 CEO ROOM 2
1.2 LTG WORKSPACE ROOM 8
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 8 of 25

4.5 Electrical Equipment Heat Dissipation

Average Power
Consumption
Room Equipment
NO
Total (W)

1 Head Office Building


Computer, Monitor, 690+360+508+383
1.1 LT1 CEO ROOM
Printer, TV =19412100
1.2 LTG WORKSPACE Laptop 130x4=520x1.1=600

1.3

1.4

1.5

1.6

1.7

1.8

1.9

1.10

5. VENTILATION REQUIREMENT CALCULATION

5.1 Fresh Air for People

Fresh air required for People tabulated as below:

Occupant Density Requirement Total FA


No Room
(Persons) L/(s-person) L/s

1 Head Office Building


1.1
1.2
1.3
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 9 of 25

1.4
1.5
1.6
1.7
1.8
1.9
1.10

5.2 Air Pressure Calculation

Fresh air required for room pressure

Q  CD * A 2P ........ refer to ASHRAE Handbook Fundamental 2013 (SI) page 16.13

Where

Q  air flow rate, m


3

s
C D  discharge coefficient for opening, dimensionless, ( C D  0.40  0.0045 Ti  To )

A  cross-sectional area of opening, m


2

  air density, kg
m3
P  pressure difference across opening, Pa
X X

Y
Y Y Y

Single Door (2X x a) + ( 2Y x a ) Double Door (2X x a) + (3Y x a)

Where:
A = (2X x a) + (2Y x a) or (2X x a) + (3Y x a)
a = Gaps, m
Fresh Air for Pressurized tabulated as below:
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 10 of 25

A ∆P ρ Q
NO Room Door CD
(m2) (Pa) (kg/m3) (m3/s) L/s
1 Head Office Building
LT1 CEO ROOM SD 0.463 0.038 15 1.14 0.09 90.33
LTG WORKSPACE
DD 0.463 0.046 15 1.14 0.11 109.35
ROOM

Note:
SD : Single Door
DD: Double Door

5.3 Fresh Air Requirement

FA FA for OA 10%
FA for FA
for make air of
No Room Pressurized selected
person (Exhaust) Supply
(L/s) (L/s) (L/s) Air (L/s) (L/s)
1 Head Office Building
LT1 CEO ROOM 17 90.33 30.5 90.33
LTG WORKSPACE ROOM 68 109.35 85.4 109.35
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 11 of 25

6. SUMMARY OF AIR CONDITIONING SYSTEM

Accordance to result of E-20 calculation, cooling load capacity tabulated as below:

Sensible Supply Duct Heater


Total Heat Fresh Air
No Service Heat Air Capacity
(kW) (kW) (L/s) (L/s) (kW)
1 Head Office Building
LT1 CEO ROOM 4.6 3.5 305.4 - -
LTG WORKSPACE
15.4 11.0 854.3 - -
ROOM
- -
- -
- -
- -
- -
- -
- -
- -
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 12 of 25

7. HVAC EQUIPMENT SELECTION

External
Cooling Air Flow
Qty. Static AC
No Building AC Type Capacity Capacity Remark
(unit) Pressure (PK)
(kW) (L/s)
(Pa)
Head Office
1
Building
Wall Mounted 1 4.6 305.4 N/A 2 1 x 100%
LTG Wall Mounted N/A 2
WORKSPACE 3 15.4 854.3 1 x 100%
ROOM
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%
Wall Mounted N/A 1 x 100%

Note :
N/A : Not Applicable

8. PRESSURIZE FAN

Cap.
FA selected Qty
No Room Fan*
(L/s) (m3/h) (m3/h)
1 Head Office Building
PT. PUSTEK E&T

ENGINEERING DOCUMENT
PUSTEK HEAD
OFFICE
CALCULATION FOR AC BUILDING 13 of 25

* To be finalized data from vendor.

9. APPENDIX
9.1. Appendix A – Weather Input Data
9.2. Appendix B – System Design AC Building
9.3. Appendix C – ASHRAE Standard 62.1. 2007
9.4. Appendix D– ASHRAE Handbook Fundamental 2009 (SI)
9.5. Appendix E – Heat Dissipation Panel Room