Está en la página 1de 25

CRONOGRAMA DE ADICIONAL POR PARTIDAS NUEVAS

OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 115.47 3,271.27 100.00% 0.00
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 417.8 5,757.28 100.00% 0.00
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 188.01 10,167.58 100.00% 0.00
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 265.7 3,661.35 100.00% 0.00
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 132.85 10,398.17 100.00% 0.00
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 26.5 1,345.14 100.00% 0.00
01.03.16 ELIMIN. MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,240.30 28,935.88 100.00% 0.00
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,346.75 6,168.12 100.00% 0.00
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 43.03 771.96 100.00% 0.00
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 30.12 8,372.46 100.00% 0.00
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.55 12.91
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 28.37 820.74
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35.46 779.77
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 198.06 907.11
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17.1 288.31
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.21 1,213.53
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21.2 1,767.66
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10.35 757.52
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1 67.78
COSTO DIRECTO 85,464.54 0.00 0.00 0.00 0.00 78,849.20 6,615.34
% DE AVANCE FISICO 0.00% 0.00% 0.00% 0.00% 92.26% 7.74%
GASTOS GENERALES (14.95%) 6,739.47 0.00 0.00 0.00 0.00 6,217.81 521.66
GASTOS DE SUPERVISION (5.10%) 2,845.35 0.00 0.00 0.00 0.00 2,625.11 220.24
PRESUPUESTO TOTAL 95,049.36 0.00 0.00 0.00 0.00 87,692.12 7,357.24

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 0.00% 0.00% 0.00% 0.00% 10.90% 0.91%
DICIEMBRE
%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.00%
0.00%
0.00%

100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
VALORIZACION DE ADICIONAL POR PARTIDAS NUEVAS FINAL (COSTO INICIAL)
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 115.47 3,271.27 100.00% 0.00 0.00% 115.47 3,271.27 100.00% 0.00 0.00 0.00%
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 279.8 3,855.64 66.97% 0.00 0.00% 279.80 3,855.64 66.97% 138.00 1,901.64 33.03%
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 125.91 6,809.21 66.97% 0.00 0.00% 125.91 6,809.21 66.97% 62.10 3,358.37 33.03%
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 265.7 3,661.35 100.00% 0.00 0.00% 265.70 3,661.35 100.00% 0.00 0.00 0.00%
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 132.85 10,398.17 100.00% 0.00 0.00% 132.85 10,398.17 100.00% 0.00 0.00 0.00%
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 26.5 1,345.14 100.00% 0.00 0.00% 26.50 1,345.14 100.00% 0.00 0.00 0.00%
01.03.16 ELIMINACION DE MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 3,240.30 28,935.88 100.00% 0.00 0.00% 3,240.30 28,935.88 100.00% 0.00 0.00 0.00%
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 1,346.75 6,168.12 100.00% 0.00 0.00% 1,346.75 6,168.12 100.00% 0.00 0.00 0.00%
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 43.03 771.96 100.00% 0.00 0.00% 43.03 771.96 100.00% 0.00 0.00 0.00%
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 30.12 8,372.46 100.00% 0.00 0.00% 30.12 8,372.46 100.00% 0.00 0.00 0.00%
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.55 12.91 100.00%
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.37 820.74 100.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 35.46 779.77 100.00%
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 198.06 907.11 100.00%
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.10 288.31 100.00%
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.21 1,213.53 100.00%
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 21.20 1,767.66 100.00%
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.35 757.52 100.00%
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 67.78 100.00%
COSTO DIRECTO 85,464.54 73,589.19 0.00 73,589.19 11,875.34
% DE AVANCE FISICO 86.10% 0.00% 86.10% 13.90%
GASTOS GENERALES (14.95%) 6,739.47 5,803.02 0.00 5,803.02 936.45
GASTOS DE SUPERVISION (5.10%) 2,845.35 2,449.99 0.00 2,449.99 395.36
PRESUPUESTO TOTAL 95,049.36 81,842.19 0.00 81,842.19 13,207.16

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 10.17% 0.00% 10.17%
VALORIZACION DE ADICIONAL DE OBRA POR MAYORES METRADOS FINAL (COSTO INICIAL)
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 562.75 2,228.49 100.00% 0.00 0.00% 562.75 2,228.49 100.00% 0.00 0.00 0.00%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 381.31 3,141.99 100.00% 0.00 0.00% 381.31 3,141.99 100.00% 0.00 0.00 0.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 381.31 8,385.01 100.00% 0.00 0.00% 381.31 8,385.01 100.00% 0.00 0.00 0.00%
01.04 CONCRETO SIMPLE 0.00
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 11.84 1,959.16 100.00% 0.00 0.00% 11.84 1,959.16 100.00% 0.00 0.00 0.00%
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 165.47 757.85 100.00% 0.00 0.00% 165.47 757.85 100.00% 0.00 0.00 0.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 62.59 1,055.27 100.00% 0.00 0.00% 62.59 1,055.27 100.00% 0.00 0.00 0.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 6.22 1,792.92 100.00% 0.00 0.00% 6.22 1,792.92 100.00% 0.00 0.00 0.00%
COSTO DIRECTO 19,320.69 19,320.69 0.00 19,320.69 0.00
% DE AVANCE FISICO 100.00% 0.00% 100.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 1,523.57 0.00 1,523.57 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 643.24 0.00 643.24 0.00
PRESUPUESTO TOTAL 21,487.50 21,487.50 0.00 21,487.50 0.00

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 2.67% 0.00% 2.67%

RESUMEN DE VALORIZACION
COSTO DIRECTO OBRA PRINCIPAL COSTO INICIAL 1,916,180.00 405,527.27 0.00 405,527.27 1,510,652.75
COSTO DIRECTO OBRA PRINCIPAL COSTO ACTUALIZADO 1,595,318.87 249,690.32 0.00 249,690.32 1,345,628.56
COSTO DIRECTO PARTIDAS NUEVAS COSTO INICIAL 85,464.54 73,589.19 0.00 73,589.19 11,875.34
COSTO DIRECTO MAYORES METRADOS COSTO INICIAL 19,320.69 19,320.69 0.00 19,320.69 0.00

COSTO DIRECTO TOTAL 748,127.47 0.00 748,127.47

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 103.40% 0.00% 103.40%
CRONOGRAMA DE EJECUCION DE ADICIONAL DE OBRA POR MAYORES METRADOS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 562.75 2,228.49 100.00% 0.00
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 381.31 3,141.99 100.00% 0.00
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 381.31 8,385.01 100.00% 0.00
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11.84 1,959.16 100.00% 0.00
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 165.47 757.85 100.00% 0.00
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62.59 1,055.27 100.00% 0.00
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6.22 1,792.92 100.00% 0.00
COSTO DIRECTO 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00
% DE AVANCE FISICO 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 0.00 0.00 0.00 0.00 1,523.57 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 0.00 0.00 0.00 0.00 643.24 0.00
PRESUPUESTO TOTAL 21,487.50 0.00 0.00 0.00 0.00 21,487.50 0.00

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 0.00% 0.00% 0.00% 0.00% 2.67% 0.00%
DICIEMBRE
%

0.00%
0.00%
0.00%

0.00%

0.00%
0.00%
0.00%
METRADOS EJECUTADOS DURANTE EL MES

ITEM PARTIDAS DEL EXPEDIENTE APROBADO UNID. METRADO

01.03 MOVIMIENTO DE TIERRAS


01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 42.90
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.03 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 2.05
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 141.05
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 48.15
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 5.15
01.05.03 VIGAS DE CONFINAMIENTO
01.05.03.01 VIGAS DE CONFINAMIENTO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 286.46
01.05.03.02 VIGAS DE CONFINAMIENTO, ENCOFRADO Y DESENCOFRADO m2 14.40
01.05.03.03 VIGAS DE CONFINAMIENTO, CONCRETO F'C=210 KG/CM2 m3 1.80
01.05.04 COLUMNAS
01.05.04.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 165.62
01.05.04.03 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 18.84
01.05.05 VIGAS
01.05.05.01 VIGAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,640.86
01.05.05.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 110.75
01.05.05.03 VIGAS, CONCRETO F'C=210 KG/CM2 - PRIMER PISO m3 16.93
01.05.06 LOSAS ALIGERADAS
01.05.06.01 LOSA ALIGERADAS, ENCOFRADO Y DESENCOFRADO m2 213.05
01.05.06.02 LOSA ALIGERADAS, LADRILLO HUECO TECHO 0.30 X 0.30 X 0.15M und 1,774.66
01.05.06.03 LOSA ALIGERADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,084.66
01.05.06.04 LOSA ALIGERADAS, CONCRETO F'C=210 KG/CM2 m3 18.63
01.06 MUROS Y TABIQUES DE ALBAÑILERIA
01.06.01 MUROS DE LADRILLO KK TIPO IV CABEZA M: 1:4, J:1.5CM m2 24.98
01.06.02 MUROS DE LADRILLO KK TIPO IV SOGA M: 1:4, J:1.5CM m2 21.45
01.06.03 ALAMBRE REFUERZO HORIZONTAL EN ALBAÑILERIA #8 kg 87.93
04 INSTALACIONES ELECTRICAS
04.01 SALIDA PARA ALUMBRADO
04.01.01 SALIDA PARA CENTRO DE LUZ EN TECHO pto 18.00
04.01.02 SALIDA PARA CENTRO DE LUZ EN PARED pto 2.00
VALORIZACION DE OBRA PRINCIPAL Nº 08 FINAL (COSTO INICIAL)
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01 ESTRUCTURAS
01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40M pza 1.00 1,162.69 1,162.69 1.00 1,162.69 100.00% 0.00 0.00% 1.00 1,162.69 100.00% 0.00 0.00 0.00%
01.01.02 CERCO PROVISIONAL DE SEGURIDAD C/ARPILLERA H=2.0M C/ROLLIZOS m 179.82 18.79 3,378.82 179.82 3,378.82 100.00% 0.00 0.00% 179.82 3,378.82 100.00% 0.00 0.00 0.00%
01.01.03 ALMACEN, OFICINA Y CASETA DE GUARDIANIA m2 84.00 141.01 11,844.84 84.00 11,844.84 100.00% 0.00 0.00% 84.00 11,844.84 100.00% 0.00 0.00 0.00%
01.01.04 SERVICIOS HIGIENICOS PROVISIONALES m2 9.00 323.01 2,907.09 9.00 2,907.09 100.00% 0.00 0.00% 9.00 2,907.09 100.00% 0.00 0.00 0.00%
01.01.05 AGUA PARA CONSTRUCCION glb 1.00 1,327.84 1,327.84 1.00 1,327.84 100.00% 0.00 0.00% 1.00 1,327.84 100.00% 0.00 0.00 0.00%
01.01.06 PLAN DE CONTINGENCIA P/INTERRUPCION DE CLASES glb 1.00 9,600.00 9,600.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 9,600.00 100.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO NORMAL m2 1,763.21 0.62 1,093.19 1,068.10 662.22 60.58% 0.00 0.00% 1,068.10 662.22 60.58% 695.11 430.97 39.42%
01.02.02 DEMOLICIONES Y DESMONTAJES DE CONSTRUCCION EXISTENTE
01.02.02.01 DESMONTAJE DE PUERTAS m2 23.72 1.85 43.88 23.72 43.88 100.00% 0.00 0.00% 23.72 43.88 100.00% 0.00 0.00 0.00%
01.02.02.02 DESMONTAJE DE VENTANAS m2 12.32 1.39 17.12 12.32 17.12 100.03% 0.00 0.00% 12.32 17.12 100.03% 0.00 0.00 0.00%
01.02.02.03 DESMONTAJE DE COBERTURAS m2 677.51 1.05 711.39 677.51 711.39 100.00% 0.00 0.00% 677.51 711.39 100.00% 0.00 0.00 0.00%
01.02.02.04 DEMOLICION DE PISOS DE CONCRETO INC. FALSO PISO m2 583.63 5.04 2,941.50 583.63 2,941.50 100.00% 0.00 0.00% 583.63 2,941.50 100.00% 0.00 0.00 0.00%
01.02.02.05 DEMOLICION DE MUROS DE ADOBE m3 49.73 1.98 98.47 49.73 98.47 100.00% 0.00 0.00% 49.73 98.47 100.00% 0.00 0.00 0.00%
01.02.02.06 DEMOLICION CIMIENTOS ADOBE Y PIEDRA m3 357.62 4.20 1,502.00 357.62 1,502.00 100.00% 0.00 0.00% 357.62 1,502.00 100.00% 0.00 0.00 0.00%
01.02.02.07 DEMOLICION DE VEREDAS m2 32.00 6.30 201.60 32.00 201.60 100.00% 0.00 0.00% 32.00 201.60 100.00% 0.00 0.00 0.00%
01.02.02.08 DEMOLICION DE ELEMENTOS DE CONCRETO Y ALBAÑILERIA m3 107.24 8.40 900.82 107.24 900.82 100.00% 0.00 0.00% 107.24 900.82 100.00% 0.00 0.00 0.00%
01.02.02.09 TRAZO Y REPLANTEO DURANTE EJECUCION m2 1,763.21 3.18 5,607.01 1,068.10 3,396.56 60.58% 0.00 0.00% 1,068.10 3,396.56 60.58% 695.11 2,210.45 39.42%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE TERRENO CON MAQUINARIA m3 2,810.47 6.04 16,975.24 2,700.25 16,309.51 96.08% 0.00 0.00% 2,700.25 16,309.51 96.08% 110.22 665.73 3.92%
01.03.02 EXCAVACION PARA ZAPATAS HASTA 2.3 m. m3 1,394.91 28.93 40,354.75 324.47 9,386.92 23.26% 0.00 0.00% 324.47 9,386.92 23.26% 1,070.44 30,967.83 76.74%
01.03.03 EXCAVACION DE ZANJAS PARA CIMIENTO CORRIDO HASTA 1.40 M. m3 611.73 23.15 14,161.55 95.78 2,217.31 15.66% 0.00 0.00% 95.78 2,217.31 15.66% 515.95 11,944.24 84.34%
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 1,721.56 3.96 6,817.38 70.19 277.95 4.08% 0.00 0.00% 70.19 277.95 4.08% 1,651.37 6,539.43 95.92%
01.03.05 RELLENO Y COMPACT. MANUAL C/MAT. AFIRMADO m3 166.38 59.63 9,921.24 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 166.38 9,921.24 100.00%
01.03.06 RELLENO Y COMPACT. MANUAL C/MAT. DE FILTRO m3 45.09 88.67 3,998.13 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 45.09 3,998.13 100.00%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 1,363.49 8.24 11,235.16 1,040.10 8,570.42 76.28% 0.00 0.00% 1,040.10 8,570.42 76.28% 323.39 2,664.73 23.72%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1,363.49 21.99 29,983.15 410.42 9,025.14 30.10% 0.00 0.00% 410.42 9,025.14 30.10% 953.07 20,958.01 69.90%
01.03.09 NIVELACION Y COMPACATADO DE SUB-BASE m2 1,907.20 1.04 1,983.49 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,907.20 1,983.49 100.00%
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 82.44 165.47 13,641.35 43.06 7,125.14 52.23% 0.00 0.00% 43.06 7,125.14 52.23% 39.38 6,516.21 47.77%
01.04.02 SOLADO e=4" MEZCLA 1:12 CEMENTO-HORMIGON m2 280.77 20.94 5,879.32 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 280.77 5,879.32 100.00%
01.04.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30%PG m3 74.62 137.55 10,263.98 11.35 1,561.19 15.21% 0.00 0.00% 11.35 1,561.19 15.21% 63.27 8,702.79 84.79%
01.04.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 164.29 27.80 4,567.26 4.52 125.66 2.75% 0.00 0.00% 4.52 125.66 2.75% 159.77 4,441.61 97.25%
01.04.05 SOBRECIMIENTOS CORRIDOS MEZCLA 1:8 CEMENTO-HORMIGON 25%PM m3 12.34 171.37 2,114.71 0.34 58.27 2.76% 0.00 0.00% 0.34 58.27 2.76% 12.00 2,056.44 97.24%
01.04.06 FALSO PISO DE H=4" MEZCLA 1:8 m2 402.07 20.92 8,411.30 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 402.07 8,411.30 100.00%
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 ZAPATAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 2,754.16 4.58 12,614.05 2,502.00 11,459.16 90.84% 0.00 0.00% 2,502.00 11,459.16 90.84% 252.16 1,154.89 9.16%
01.05.01.02 ZAPATAS, ENCOFRADO Y DESENCOFRADO m2 39.60 17.94 710.42 33.84 607.09 85.46% 0.00 0.00% 33.84 607.09 85.46% 5.76 103.33 14.54%
01.05.01.03 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 95.77 277.97 26,621.19 51.78 14,393.29 54.07% 0.00 0.00% 51.78 14,393.29 54.07% 43.99 12,227.90 45.93%
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 947.77 4.58 4,340.79 629.69 2,883.98 66.44% 0.00 0.00% 629.69 2,883.98 66.44% 318.08 1,456.81 33.56%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 334.71 16.86 5,643.21 180.57 3,044.41 53.95% 0.00 0.00% 180.57 3,044.41 53.95% 154.14 2,598.80 46.05%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 38.14 288.25 10,993.86 18.01 5,191.38 47.22% 0.00 0.00% 18.01 5,191.38 47.22% 20.13 5,802.47 52.78%
01.05.03 VIGAS DE CONFINAMIENTO
01.05.03.01 VIGAS DE CONFINAMIENTO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 3,045.03 4.58 13,946.24 2,475.93 11,339.76 81.31% 0.00 0.00% 2,475.93 11,339.76 81.31% 569.10 2,606.48 18.69%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.05.03.02 VIGAS DE CONFINAMIENTO, ENCOFRADO Y DESENCOFRADO m2 184.75 17.94 3,314.42 74.75 1,341.02 40.46% 0.00 0.00% 74.75 1,341.02 40.46% 110.00 1,973.40 59.54%
01.05.03.03 VIGAS DE CONFINAMIENTO, CONCRETO F'C=210 KG/CM2 m3 26.42 285.31 7,537.89 9.34 2,664.80 35.35% 0.00 0.00% 9.34 2,664.80 35.35% 17.08 4,873.09 64.65%
01.05.04 COLUMNAS
01.05.04.01 COLUMNAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 20,024.11 4.58 91,710.42 12,650.09 57,937.41 63.17% 0.00 0.00% 12,650.09 57,937.41 63.17% 7,374.02 33,773.01 36.83%
01.05.04.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 1,002.20 22.14 22,188.71 449.80 9,958.57 44.88% 0.00 0.00% 449.80 9,958.57 44.88% 552.40 12,230.14 55.12%
01.05.04.03 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 102.01 336.75 34,351.87 45.08 15,180.69 44.19% 0.00 0.00% 45.08 15,180.69 44.19% 56.93 19,171.18 55.81%
01.05.05 VIGAS
01.05.05.01 VIGAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 16,751.22 4.58 76,720.59 6,279.20 28,758.74 37.49% 0.00 0.00% 6,279.20 28,758.74 37.49% 10,472.02 47,961.85 62.51%
01.05.05.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 784.37 28.50 22,354.55 308.60 8,795.10 39.34% 0.00 0.00% 308.60 8,795.10 39.34% 475.77 13,559.45 60.66%
01.05.05.03 VIGAS, CONCRETO F'C=210 KG/CM2 - PRIMER PISO m3 53.13 292.72 15,552.21 19.40 5,678.77 36.51% 0.00 0.00% 19.40 5,678.77 36.51% 33.73 9,873.45 63.49%
01.05.05.04 VIGAS, CONCRETO F'C=210 KG/CM2 - SEGUNDO PISO m3 47.13 308.73 14,550.44 24.57 7,585.50 52.13% 0.00 0.00% 24.57 7,585.50 52.13% 22.56 6,964.95 47.87%
01.05.06 LOSAS ALIGERADAS
01.05.06.01 LOSA ALIGERADAS, ENCOFRADO Y DESENCOFRADO m2 1,067.27 18.25 19,477.68 468.56 8,551.22 43.90% 0.00 0.00% 468.56 8,551.22 43.90% 598.71 10,926.46 56.10%
01.05.06.02 LOSA ALIGERADAS, LADRILLO HUECO TECHO 0.30 X 0.30 X 0.15M und 4,570.60 3.55 16,225.63 1,896.90 6,734.00 41.50% 0.00 0.00% 1,896.90 6,734.00 41.50% 2,673.70 9,491.64 58.50%
01.05.06.03 LOSA, LADRILLO P/TECHO 0.30 X 0.30 X 0.15MT SEGUNDO PISO und 4,227.30 3.55 15,006.92 2,006.21 7,122.05 47.46% 0.00 0.00% 2,006.21 7,122.05 47.46% 2,221.09 7,884.87 52.54%
01.05.06.04 LOSA ALIGERADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 6,237.72 4.58 28,568.76 2,199.31 10,072.84 35.26% 0.00 0.00% 2,199.31 10,072.84 35.26% 4,038.41 18,495.92 64.74%
01.05.06.05 LOSA ALIGERADAS, CONCRETO F'C=210 KG/CM2 m3 89.28 296.36 26,459.02 41.06 12,168.54 45.99% 0.00 0.00% 41.06 12,168.54 45.99% 48.22 14,290.48 54.01%
01.05.07 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.05.07.01 COLUMNETAS, VIGUETAS DE AMARRE, ACERO DE REFUERZO FY=4200 kg 3,145.10 4.58 14,404.56 343.35 1,572.54 10.92% 0.00 0.00% 343.35 1,572.54 10.92% 2,801.75 12,832.02 89.08%
01.05.07.02 COLUMNETAS,VIGUETAS DE AMARRE, ENCOFRADO Y DESENCOFRADO m2 320.55 22.14 7,096.98 45.23 1,001.39 14.11% 0.00 0.00% 45.23 1,001.39 14.11% 275.32 6,095.58 85.89%
01.05.07.03 COLUMNETAS, VIGUETAS DE AMARRE, CONCRETO F'C=175 KG/CM2 m3 32.04 293.24 9,395.41 2.66 780.02 8.30% 0.00 0.00% 2.66 780.02 8.30% 29.38 8,615.39 91.70%
01.05.08 ESCALERAS
01.05.08.01 ESCALERA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 698.14 4.58 3,197.48 698.14 3,197.48 100.00% 0.00 0.00% 698.14 3,197.48 100.00% 0.00 0.00 0.00%
01.05.08.02 ESCALERA, ENCOFRADO Y DESENCOFRADO m2 41.56 17.07 709.43 41.56 709.43 100.00% 0.00 0.00% 41.56 709.43 100.00% 0.00 0.00 0.00%
01.05.08.03 ESCALERA, CONCRETO F'C=210 KG/CM2 m3 7.67 339.57 2,604.50 7.67 2,604.50 100.00% 0.00 0.00% 7.67 2,604.50 100.00% 0.00 0.00 0.00%
01.05.09 LOSAS MACIZAS
01.05.09.01 LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,918.39 4.58 8,786.23 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,918.39 8,786.23 100.00%
01.05.09.02 LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 57.89 26.57 1,538.14 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 57.89 1,538.14 100.00%
01.05.09.03 LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 8.68 305.81 2,654.43 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.68 2,654.43 100.00%
01.05.10 CANALETA DE DRENAJE PLUVIAL EN TECHO
01.05.10.01 CANALETA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 950.41 4.58 4,352.88 803.29 3,679.07 84.52% 0.00 0.00% 803.29 3,679.07 84.52% 147.12 673.81 15.48%
01.05.10.02 CANALETA, ENCOFRADO Y DESENCOFRADO m2 56.87 17.07 970.77 46.08 786.59 81.03% 0.00 0.00% 46.08 786.59 81.03% 10.79 184.19 18.97%
01.05.10.03 CANALETA, CONCRETO F'C=210 KG/CM2 m3 3.68 338.75 1,246.60 3.28 1,111.10 89.13% 0.00 0.00% 3.28 1,111.10 89.13% 0.40 135.50 10.87%
01.05.11 PARASOLES
01.05.11.01 PARASOLES, ACERO DE REFUERZO FY=4200 KG/CM2 kg 503.08 4.58 2,304.11 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 503.08 2,304.11 100.00%
01.05.11.02 PARASOLES, ENCOFRADO Y DESENCOFRADO m2 67.50 17.07 1,152.23 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 67.50 1,152.23 100.00%
01.05.11.03 PARASOLES, CONCRETO F'C=210 KG/CM2 m3 3.38 305.81 1,033.64 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.38 1,033.64 100.00%
01.05.12 MUROS DE CONTENCION
01.05.12.01 MUROS DE CONTENCION, ACERO DE REFUERZO FY=4200 KG/CM2 kg 13,203.56 4.58 60,472.30 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13,203.56 60,472.30 100.00%
01.05.12.02 MUROS DE CONTENCION, ENCOFRADO Y DESENCOFRADO m2 821.52 27.92 22,936.84 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 821.52 22,936.84 100.00%
01.05.12.03 MUROS DE CONTENCION, CONCRETO F'C=210 KG/CM2 m3 49.60 336.75 16,702.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.60 16,702.80 100.00%
01.05.12.04 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 m3 219.01 309.25 67,728.84 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 219.01 67,728.84 100.00%
01.05.12.05 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 + 30% PG m3 8.36 226.47 1,893.29 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.36 1,893.29 100.00%
01.05.13 CISTERNA SUBTERRANEA
01.05.13.01 TANQUE CISTERNA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 186.60 4.58 854.63 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 186.60 854.63 100.00%
01.05.13.02 TANQUE CISTERNA, ENCOFRADO Y DESENCOFRADO m2 60.86 19.32 1,175.82 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 60.86 1,175.82 100.00%
01.05.13.03 TANQUE CISTERNA, CONCRETO F'C=210 KG/CM2 m3 10.33 518.75 5,358.69 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.33 5,358.69 100.00%
01.05.14 PLACAS Y LOSAS MACIZAS
01.05.14.01 PLACA Y LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 268.73 4.58 1,230.78 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 268.73 1,230.78 100.00%
01.05.14.02 PLACA Y LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 149.96 26.57 3,984.44 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 149.96 3,984.44 100.00%
01.05.14.03 PLACA Y LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 5.81 305.81 1,776.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.81 1,776.76 100.00%
01.06 MUROS Y TABIQUES DE ALBAÑILERIA
01.06.01 MUROS DE LADRILLO KK TIPO IV CABEZA M: 1:4, J:1.5CM m2 530.97 87.80 46,619.17 239.71 21,046.54 45.15% 0.00 0.00% 239.71 21,046.54 45.15% 291.26 25,572.63 54.85%
01.06.02 MUROS DE LADRILLO KK TIPO IV SOGA M: 1:4, J:1.5CM m2 655.24 52.30 34,269.05 91.81 4,801.66 14.01% 0.00 0.00% 91.81 4,801.66 14.01% 563.43 29,467.39 85.99%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.06.03 ALAMBRE REFUERZO HORIZONTAL EN ALBAÑILERIA #8 kg 221.54 4.97 1,101.05 87.93 437.01 39.69% 0.00 0.00% 87.93 437.01 39.69% 133.61 664.04 60.31%
01.06.04 MURO DE LADRILLO KK SOGA M:1:5 E=1.4 CM CARA VISTA UNA CARA m2 337.82 53.54 18,086.88 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 337.82 18,086.88 100.00%
02 ARQUITECTURA
02.01 REVOQUES ENLUCIDOS Y MOLDURAS
02.01.01 TARRAJEO PRIMARIO, MORTERO 1:5 C:A m2 277.27 11.51 3,191.38 21.10 242.86 7.61% 0.00 0.00% 21.10 242.86 7.61% 256.17 2,948.52 92.39%
02.01.02 TARRAJEO EN MUROS INTERIOR, MORTERO 1:5 C:A m2 1,096.38 18.41 20,184.36 538.15 9,907.34 49.08% 0.00 0.00% 538.15 9,907.34 49.08% 558.23 10,277.01 50.92%
02.01.03 TARRAJEO EN MUROS EXTERIOR, MORTERO 1:5 C:A m2 802.89 20.89 16,772.37 199.38 4,165.05 24.83% 0.00 0.00% 199.38 4,165.05 24.83% 603.51 12,607.32 75.17%
02.01.04 TARRAJEO EN COLUMNAS, MORTERO 1:5 C:A m2 771.80 16.55 12,773.29 298.39 4,938.35 38.66% 0.00 0.00% 298.39 4,938.35 38.66% 473.41 7,834.94 61.34%
02.01.05 TARRAJEO EN VIGAS, MORTERO 1:5 C:A m2 578.21 27.07 15,652.14 223.61 6,053.12 38.67% 0.00 0.00% 223.61 6,053.12 38.67% 354.60 9,599.02 61.33%
02.01.06 TARRAJEO EN MUROS DE SOSTENIMIENTO, MORTERO 1:5 C:A m2 155.22 23.25 3,608.87 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 155.22 3,608.87 100.00%
02.01.07 TARRAJEO CON IMPERMEABILIZANTE m2 199.32 33.88 6,752.96 89.73 3,040.05 45.02% 0.00 0.00% 89.73 3,040.05 45.02% 109.59 3,712.91 54.98%
02.01.08 VESTIDURA DE DERRAMES 1:5 C:A m 619.43 5.42 3,357.31 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 619.43 3,357.31 100.00%
02.01.09 BRUÑAS SEGUN DETALLE 1 X 1CM m 2,306.69 3.12 7,196.87 85.65 267.23 3.71% 0.00 0.00% 85.65 267.23 3.71% 2,221.04 6,929.64 96.29%
02.02 CIELO RASOS
02.02.01 CIELO RASO CON MEZCLA C:A 1:5 m2 1,282.25 27.94 35,826.07 454.37 12,695.10 35.44% 0.00 0.00% 454.37 12,695.10 35.44% 827.88 23,130.97 64.56%
02.03 PISOS Y PAVIMENTOS
02.03.01 CONTRAPISO DE 40MM m2 788.95 20.55 16,212.92 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 788.95 16,212.92 100.00%
02.03.02 PISO PORCELANATO ANTIDESLIZANTE 0.60X0.60 m2 780.85 66.26 51,739.12 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 780.85 51,739.12 100.00%
02.03.03 PISO CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR m2 281.77 22.08 6,221.48 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 281.77 6,221.48 100.00%
02.03.04 REVESTIMIENTO DE MURO, TIPO LAJA m2 83.68 47.79 3,999.07 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 83.68 3,999.07 100.00%
02.03.05 VEREDA CONCRETO F'C=175 KG/CM2 FROT. Y BRUÑADO m2 526.73 39.35 20,726.83 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 526.73 20,726.83 100.00%
02.03.06 CONCRETO EN LOSA DEPORTIVA F'C=175 KG/CM2 m3 81.42 344.35 28,036.98 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 81.42 28,036.98 100.00%
02.03.07 CONCRETO EN DADOS DE ANCLAJE F'C=175 KG/CM2 m3 0.17 283.86 48.26 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.17 48.26 100.00%
02.03.08 PISO ADOQUINADO m2 110.80 71.46 7,917.77 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 110.80 7,917.77 100.00%
02.03.09 ENCOFRADO DE LOSAS DEPORTIVAS m2 86.49 32.25 2,789.30 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 86.49 2,789.30 100.00%
02.04 CONTRAZOCALOS
02.04.01 CONTRAZOCALO DE LOSETA VENECIANA COLOR CLARO 10X30CM m 19.10 24.06 459.55 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.10 459.55 100.00%
02.04.02 CONTRAZOCALO S/COLOREAR H=30CM MEZCLA 1:2 E=1.5CM m 676.38 5.94 4,017.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 676.38 4,017.70 100.00%
02.05 ZOCALOS
02.05.01 ZOCALO DE MAYOLICA BLANCA 20X30 1RA m2 277.27 49.55 13,738.73 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 277.27 13,738.73 100.00%
02.06 CUBIERTAS
02.06.01 COBERTURA C/PLANCHA TIPO TEJA ANDINA m2 706.68 76.94 54,371.96 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 706.68 54,371.96 100.00%
02.06.02 CUMBRERA C/PLANCHA TIPO TEJA ANDINA m 60.40 72.66 4,388.66 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 60.40 4,388.66 100.00%
02.07 CARPINTERIA DE MADERA
02.07.01 PUERTA CEDRO MACHIMBRADA m2 63.91 539.53 34,481.36 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 63.91 34,481.36 100.00%
02.07.02 PUERTA CON TRIPLAY 9MM P/SSHH m2 12.04 270.32 3,254.65 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.04 3,254.65 100.00%
02.08 CARPINTERIA METALICA
02.08.01 VENTANA DE ALUMINIO m2 176.97 25.00 4,424.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 176.97 4,424.25 100.00%
02.08.02 PASAMANO DE TUBO F°G° DE 2" m 15.70 54.72 859.10 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 15.70 859.10 100.00%
02.08.03 CANTONERA DE FIERRO EN ESCALERA m 77.60 21.10 1,637.36 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 77.60 1,637.36 100.00%
02.08.04 ESCALERA DE GATO, TUBO F°G° 1 1/2" Y 1" TQE ELEVADO m 3.40 97.53 331.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.40 331.60 100.00%
02.08.05 TAPA DE FIERRO EN CISTERNA und 1.00 323.43 323.43 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 323.43 100.00%
02.08.06 PUERTA DE INGRESO PRINCIPAL C/PERFILES SEGUN DISEÑO und 1.00 13,879.33 13,879.33 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 13,879.33 100.00%
02.08.07 BARANDA DE TUBO F°G° DE 2" m 233.80 98.98 23,141.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 233.80 23,141.52 100.00%
02.09 CERRAJERIA
02.09.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 4" PESADA EN PUERTA pza 187.00 12.49 2,335.63 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 187.00 2,335.63 100.00%
02.09.02 CERRADURA DOS GOLPES EN PUERTA pza 29.00 70.04 2,031.16 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.00 2,031.16 100.00%
02.09.03 MANIJA DE BRONCE 4" P/PUERTAS pza 29.00 11.12 322.48 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 29.00 322.48 100.00%
02.09.04 CANDADO TIPO FORTE 60MM pza 3.00 54.56 163.68 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 163.68 100.00%
02.09.05 CERROJO DE 3" ALUMINIZADO P/PUERTA pza 14.00 7.94 111.16 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 111.16 100.00%
02.10 VIDRIOS CRISTALES Y SIMILARES
02.10.01 VIDRIO SEMIDOBLE INCOLORO CRUDO p2 2,299.47 13.65 31,387.77 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,299.47 31,387.77 100.00%
02.11 PINTURAS
02.11.01 PINTURA LATEX 02 MANOS EN CIELO RASO m2 1,180.70 7.52 8,878.86 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,180.70 8,878.86 100.00%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
02.11.02 PINTURA OLEO 2 MANOS EN VIGAS m2 578.21 5.66 3,272.67 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 578.21 3,272.67 100.00%
02.11.03 PINTURA OLEO 2 MANOS EN MUROS Y COLUMNAS m2 1,589.40 7.00 11,125.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,589.40 11,125.80 100.00%
02.11.04 PINTURA OLEO 2 MANOS EN DERRAMES m 619.43 3.87 2,397.19 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 619.43 2,397.19 100.00%
02.11.05 PINTURA BARNIZ 2 MANOS EN CARP. MADERA m2 75.95 10.82 821.78 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 75.95 821.78 100.00%
02.11.06 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=30CM m 663.88 2.13 1,414.06 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 663.88 1,414.06 100.00%
02.11.07 PINTURA ESMALTE ENLOSA DEPORTIVA m 360.00 3.85 1,386.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 360.00 1,386.00 100.00%
02.12 DRYWALL
02.12.01 PROVISION Y COLOCACION DE RIELES DE 90X25X0.90 m 10.23 37.71 385.77 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.23 385.77 100.00%
02.12.02 PROVISION Y COLOCACION DE PARANTES 89X38X0.90 m 74.13 46.31 3,432.96 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 74.13 3,432.96 100.00%
02.12.03 PROVISION Y COLOCACION DE PLACA GYPLAC DE 1/2" R.H. m2 49.90 50.34 2,511.97 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.90 2,511.97 100.00%
02.13 VARIOS
02.13.01 PIZARRA ACRILICA und 16.00 250.00 4,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.00 4,000.00 100.00%
02.13.02 TAPAJUNTA METALICA EN PISOS m 9.55 49.83 475.88 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.55 475.88 100.00%
02.13.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) m 30.00 19.82 594.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 594.60 100.00%
02.13.04 JUNTA DILATACION RELLENO CON MORTERO ASFALTICO E=1" m 69.30 6.18 428.27 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 69.30 428.27 100.00%
02.13.05 JUNTA DE CONSTRUCCION CON TECNOPORT m2 49.55 6.64 329.01 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.55 329.01 100.00%
02.13.06 ARCO Y TABLERO FULBITO-BASKET S/DISEÑO und 2.00 2,514.52 5,029.04 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 5,029.04 100.00%
02.13.07 NET CON SOPORTE F°G° D=3" + ACCESORIOS SUMINISTRO Y COLOCACI und 1.00 763.73 763.73 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 763.73 100.00%
02.13.08 TANQUE DE POLIETILENO und 2.00 1,310.04 2,620.08 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,620.08 100.00%
02.13.09 LETRERO METALICO DE IDENTIFICACION glb 1.00 1,500.00 1,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,500.00 100.00%
03 INSTALACIONES SANITARIAS
03.01 APARATOS SANITARIOS Y ACCESORIOS
03.01.01 INODORO TANQUE BAJO DE LOSA 1RA CALIDAD ADULTO pza 14.00 312.70 4,377.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 4,377.80 100.00%
03.01.02 LAVATORIO DE PARED BLANCO INC. ACCESORIOS pza 4.00 331.26 1,325.04 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 1,325.04 100.00%
03.01.03 URINARIO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 3.00 427.45 1,282.35 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 1,282.35 100.00%
03.01.04 BEBEDERO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 7.40 491.15 3,634.51 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.40 3,634.51 100.00%
03.01.05 DUCHA CROMADA DE CABEZA GIRATORIA und 4.00 52.96 211.84 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 211.84 100.00%
03.02 INSTALACIONES SANITARIAS
03.02.01 SALIDA DESAGUE DE PVC SAL 2" pto 30.00 34.69 1,040.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 1,040.70 100.00%
03.02.02 SALIDA DESAGUE DE PVC SAL 4" pto 14.00 44.54 623.56 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 623.56 100.00%
03.02.03 SALIDA PARA VENTILACION pto 9.00 42.88 385.92 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.00 385.92 100.00%
03.02.04 TUBERIA DE PVC SAL 2" m 84.60 9.86 834.16 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 84.60 834.16 100.00%
03.02.05 TUBERIA DE PVC SAL 4" m 94.00 14.13 1,328.22 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 94.00 1,328.22 100.00%
03.02.06 REGISTRO DE BRONCE 4" und 14.00 22.29 312.06 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 312.06 100.00%
03.02.07 SUMIDERO DE BRONCE ROSCADO 3" und 30.00 57.10 1,713.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 1,713.00 100.00%
03.02.08 CAJA SUMIDERO CON REJILLA DE FIERRO und 8.00 178.96 1,431.68 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 1,431.68 100.00%
03.02.09 CAJA DE REGISTRO DESAGUE 12"X24" C/TAPA CONCRETO und 7.00 585.67 4,099.69 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 4,099.69 100.00%
03.03 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.03.01 SALIDA DE AGUA FRIA TUBERIA PVC 1/2" pto 30.00 99.15 2,974.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 2,974.50 100.00%
03.03.02 TUBERIA PVC CLASE 10 - 1/2" m 60.50 8.49 513.65 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 60.50 513.65 100.00%
03.03.03 TUBERIA PVC CLASE 10 - 3/4" m 156.20 9.15 1,429.23 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 156.20 1,429.23 100.00%
03.03.04 VALVULA COMPUERTA DE BRONCE 1/2" und 7.00 136.69 956.83 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 956.83 100.00%
03.03.05 VALVULA COMPUERTA DE BRONCE 3/4" und 5.00 184.69 923.45 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 923.45 100.00%
03.03.06 VALVULA GLOBO DE 1/2" und 2.00 152.29 304.58 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 304.58 100.00%
03.03.07 REDUCCION PVC SAP 3/4" A 1/2" und 5.00 12.17 60.85 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 60.85 100.00%
03.03.08 CAJA DE MADERA PARA VALVULA und 1.00 43.91 43.91 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 43.91 100.00%
03.03.09 CAJA EN NICHO DE MAYOLICA PARA VALVULA und 7.00 18.97 132.79 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 132.79 100.00%
03.03.10 SUCCION E IMPULSION INCLUYE INSTALACION Y ACCESORIOS glb 1.00 4,363.32 4,363.32 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 4,363.32 100.00%
03.03.11 REBOSE Y LIMPIA INCLUYE INSTALACION Y ACCESORIOS glb 1.00 1,365.36 1,365.36 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,365.36 100.00%
03.04 SISTEMA DE AGUA DE LLUVIA Y SUBDREN
03.04.01 TUBERIA DE PVC SAP 3" P/LLUVIAS m 73.00 28.43 2,075.39 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 73.00 2,075.39 100.00%
03.04.02 FALSA COLUMNA/PROTECCION TUBERIA MONTANTE, CONCRETO F'C=17 m3 0.65 1,536.36 998.63 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.65 998.63 100.00%
03.04.03 CANALETA DE EVACUACION PLUVIAL, CONCRETO F'C=210 KG/CM2 m3 16.65 1,274.00 21,212.10 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.65 21,212.10 100.00%
03.04.04 ENCOFRADO Y DESENCOFRADO, CANALETA DE EVACUACION PLUVIAL m2 111.03 42.04 4,667.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 111.03 4,667.70 100.00%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
03.04.05 TUBERIA DE PVC SAL 4" (PERFORADA) m 99.33 14.13 1,403.53 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 99.33 1,403.53 100.00%
03.04.06 TUBERIA DE PVC SAL 6" (PERFORADA) m 65.05 19.23 1,250.91 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.05 1,250.91 100.00%
04 INSTALACIONES ELECTRICAS
04.01 SALIDA PARA ALUMBRADO
04.01.01 SALIDA PARA CENTRO DE LUZ EN TECHO pto 81.00 74.68 6,049.08 39.00 2,912.52 48.15% 0.00 0.00% 39.00 2,912.52 48.15% 42.00 3,136.56 51.85%
04.01.02 SALIDA PARA CENTRO DE LUZ EN PARED pto 42.00 74.68 3,136.56 2.00 149.36 4.76% 0.00 0.00% 2.00 149.36 4.76% 40.00 2,987.20 95.24%
04.01.03 SALIDA PARA INTERRUPTOR SIMPLE pto 33.00 79.63 2,627.79 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 33.00 2,627.79 100.00%
04.01.04 SALIDA PARA INTERRUPTOR DE CONMUTACION pto 6.00 115.22 691.32 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 6.00 691.32 100.00%
04.02 SALIDA PARA TOMACORRIENTES
04.02.01 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 0 pto 125.00 95.89 11,986.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 125.00 11,986.25 100.00%
04.02.02 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 1 pto 4.00 110.40 441.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 441.60 100.00%
04.02.03 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION E pto 30.00 87.59 2,627.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 2,627.70 100.00%
04.03 CAJAS Y TABLEROS
04.03.01 CAJA DE PASE 102X102X100 MM und 8.00 21.26 170.08 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 170.08 100.00%
04.03.02 CAJA DE PASE 200X200X100 MM und 4.00 26.11 104.44 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 104.44 100.00%
04.03.03 TABLERO DE 3X40A, 20 POLOS und 2.00 489.50 979.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 979.00 100.00%
04.03.04 TABLERO DE 3X35A, 20 POLOS und 2.00 489.50 979.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 979.00 100.00%
04.03.05 TABLERO DE 2X30A, 24 POLOS und 1.00 468.81 468.81 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 468.81 100.00%
04.03.06 TABLERO DE 2X10A, 8 POLOS und 1.00 259.61 259.61 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 259.61 100.00%
04.04 ARTEFACTOS
04.04.01 ARTEFACTO TIPO BRAQUETE CON 3 LAMPARAS FLUORECENTES DE 36W und 56.00 120.72 6,760.32 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 56.00 6,760.32 100.00%
04.04.02 ARTEFACTO CON LAMPARA FLUORECENTE CIRCULAR DE 32W und 24.00 114.30 2,743.20 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 24.00 2,743.20 100.00%
04.04.03 ARTEFACTO TIPO BRAQUETE CON 2 LAMPARAS AHORRADORAS DE 18W und 42.00 94.12 3,953.04 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 42.00 3,953.04 100.00%
04.05 TABLEROS
04.05.01 TABLERO GENERAL TG 3X100A 28 POLOS und 1.00 915.01 915.01 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 915.01 100.00%
04.06 ALIMENTADORES
04.06.01 N2XH(3-1X50X1X50(N)X1X25(T))MM2 m 38.00 183.38 6,968.44 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 38.00 6,968.44 100.00%
04.06.02 N2XH(3-1X16X1X16(N)X1X10(T))MM2 m 116.00 65.86 7,639.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 116.00 7,639.76 100.00%
04.06.03 N2XH(1X16X1X16(N)X1X10(T))MM2 m 37.00 37.38 1,383.06 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 37.00 1,383.06 100.00%
04.06.04 N2XH(1X6X1X6(N)X1X6(T))MM2 m 12.00 38.70 464.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 464.40 100.00%
04.07 CIRCUITO DE TIMBRES
04.07.01 SALIDA PARA TIMBRES pto 2.00 142.72 285.44 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 285.44 100.00%
04.08 SISTEMA DE PUESTA A TIERRA
04.08.01 PUESTA A TIERRA TIPO P-1 (R<15 OHMIOS) und 1.00 937.95 937.95 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 937.95 100.00%
04.08.02 PUESTA A TIERRA TIPO P-2 (R<5 OHMIOS) und 4.00 1,114.95 4,459.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 4,459.80 100.00%
04.08.03 CONDUCTOR DE COBRE DESNUDO DE 1X16MM2 und 62.00 9.56 592.72 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.00 592.72 100.00%
04.08.04 PARARRAYO CON DISPOSITIVO DE CEBADO, C/03 P/TIERRA und 1.00 2,501.15 2,501.15 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2,501.15 100.00%
04.09 SISTEMA DE ALUMBRADO EXTERIOR
04.09.01 ILUMINACION DE LOZA DEPORTIVA und 4.00 1,886.43 7,545.72 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 7,545.72 100.00%
04.10 OTROS EQUIPOS
04.10.01 ELECTROBOMBA PARA TANQUE ELEVADO und 2.00 958.22 1,916.44 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 1,916.44 100.00%
04.10.02 INSTALACION DEMEDIDOR ELECTRICO und 1.00 794.40 794.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 794.40 100.00%
05 EQUIPAMIENTO, MOBILIARIO Y MATERIAL EDUCATIVO
05.01 EQUIPOS glb 1.00 63,192.00 63,192.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 63,192.00 100.00%
05.02 MOBILIARIO glb 1.00 64,806.01 64,806.01 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 64,806.01 100.00%
05.03 MATERIAL EDUCATIVO glb 1.00 54,185.00 54,185.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 54,185.00 100.00%
06 CAPACITACION
06.01 CAPACITACION glb 1.00 13,500.00 13,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 13,500.00 100.00%
07 PLAN MANEJO AMBIENTAL
07.01 SEMBRADO DE GRASS m2 413.00 18.80 7,764.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 413.00 7,764.40 100.00%
07.02 LIMPIEZA PERMANENTE DE OBRA glb 1.00 1,412.57 1,412.57 0.50 706.29 50.00% 0.00 0.00% 0.50 706.29 50.00% 0.50 706.29 50.00%
07.03 CAPACITACION EN TEMA AMBIENTAL A PERSONAL OBRERO glb 1.00 10,000.00 10,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 10,000.00 100.00%
07.04 SEÑALIZACION AMBIENTAL EN OBRA glb 1.00 1,500.00 1,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,500.00 100.00%
07.05 EQUIPAMIENTO PARA MITIGACION AMBIENTAL EN OBRA glb 1.00 950.70 950.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 950.70 100.00%
07.06 TRATAMIENTO DE BOTADEROS glb 1.00 3,000.00 3,000.00 0.50 1,500.00 50.00% 0.00 0.00% 0.50 1,500.00 50.00% 0.50 1,500.00 50.00%
COSTO DIRECTO 1,916,180.00 405,527.27 0.00 405,527.27 1,510,652.75
% DE AVANCE FISICO 21.16% 0.00% 21.16% 78.84%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
GASTOS GENERALES (6.2424981%) 119,617.50 25,315.03 0.00 25,315.03 94,302.47
GASTOS DE SUPERVISION (2.648342%) 50,747.00 10,739.75 0.00 10,739.75 40,007.25
PRESUPUESTO TOTAL 2,086,544.50 441,582.05 0.00 441,582.05 1,644,962.47

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 56.05% 0.00% 56.05% 43.95%

VALORIZACION DE OBRA PRINCIPAL Nº 08 FINAL(COSTO ACTUALIZADO)


OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Saldo Metr CU. Actualiz Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01 ESTRUCTURAS
01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40M pza 0.00 1,168.80 0.00
01.01.02 CERCO PROVISIONAL DE SEGURIDAD C/ARPILLERA H=2.0M C/ROLLIZOS m 0.00 19.49 0.00
01.01.03 ALMACEN, OFICINA Y CASETA DE GUARDIANIA m2 0.00 143.66 0.00
01.01.04 SERVICIOS HIGIENICOS PROVISIONALES m2 0.00 334.75 0.00
01.01.05 AGUA PARA CONSTRUCCION glb 0.00 1,388.81 0.00
01.01.06 PLAN DE CONTINGENCIA P/INTERRUPCION DE CLASES glb 1.00 9,600.00 9,600.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 9,600.00 100.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO NORMAL m2 695.11 0.76 528.28 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 695.11 528.28 100.00%
01.02.02 DEMOLICIONES Y DESMONTAJES DE CONSTRUCCION EXISTENTE
01.02.02.01 DESMONTAJE DE PUERTAS m2 0.00 2.36 0.00
01.02.02.02 DESMONTAJE DE VENTANAS m2 0.00 1.77 0.00
01.02.02.03 DESMONTAJE DE COBERTURAS m2 0.00 1.32 0.00
01.02.02.04 DEMOLICION DE PISOS DE CONCRETO INC. FALSO PISO m2 0.00 6.23 0.00
01.02.02.05 DEMOLICION DE MUROS DE ADOBE m3 0.00 2.44 0.00
01.02.02.06 DEMOLICION CIMIENTOS ADOBE Y PIEDRA m3 0.00 5.19 0.00
01.02.02.07 DEMOLICION DE VEREDAS m2 0.00 7.78 0.00
01.02.02.08 DEMOLICION DE ELEMENTOS DE CONCRETO Y ALBAÑILERIA m3 0.00 10.37 0.00
01.02.02.09 TRAZO Y REPLANTEO DURANTE EJECUCION m2 695.11 3.39 2,356.42 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 695.11 2,356.42 100.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE TERRENO CON MAQUINARIA m3 110.22 6.13 675.65 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 110.22 675.65 100.00%
01.03.02 EXCAVACION PARA ZAPATAS HASTA 2.3 m. m3 1,070.44 33.77 36,148.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,070.44 36,148.76 100.00%
01.03.03 EXCAVACION DE ZANJAS PARA CIMIENTO CORRIDO HASTA 1.40 M. m3 515.95 27.02 13,940.97 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 515.95 13,940.97 100.00%
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 1,651.37 4.88 8,058.69 101.72 496.39 6.16% 0.00 0.00% 101.72 496.39 6.16% 1,549.65 7,562.29 93.84%
01.03.05 RELLENO Y COMPACT. MANUAL C/MAT. AFIRMADO m3 166.38 62.68 10,428.70 30.14 1,889.18 18.12% 0.00 0.00% 30.14 1,889.18 18.12% 136.24 8,539.52 81.88%
01.03.06 RELLENO Y COMPACT. MANUAL C/MAT. DE FILTRO m3 45.09 91.72 4,135.65 8.40 770.45 18.63% 0.00 0.00% 8.40 770.45 18.63% 36.69 3,365.21 81.37%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 323.39 10.18 3,292.11 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 323.39 3,292.11 100.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 953.07 22.20 21,158.15 617.50 13,708.50 64.79% 0.00 0.00% 617.50 13,708.50 64.79% 335.57 7,449.65 35.21%
01.03.09 NIVELACION Y COMPACATADO DE SUB-BASE m2 1,907.20 1.28 2,441.22 301.36 385.74 15.80% 0.00 0.00% 301.36 385.74 15.80% 1,605.84 2,055.48 84.20%
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 39.38 171.09 6,737.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 39.38 6,737.52 100.00%
01.04.02 SOLADO e=4" MEZCLA 1:12 CEMENTO-HORMIGON m2 280.77 22.48 6,311.71 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 280.77 6,311.71 100.00%
01.04.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30%PG m3 63.27 143.17 9,058.37 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 63.27 9,058.37 100.00%
01.04.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 159.77 29.84 4,767.54 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 159.77 4,767.54 100.00%
01.04.05 SOBRECIMIENTOS CORRIDOS MEZCLA 1:8 CEMENTO-HORMIGON 25%PM m3 12.00 180.76 2,169.12 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 2,169.12 100.00%
01.04.06 FALSO PISO DE H=4" MEZCLA 1:8 m2 402.07 22.68 9,118.95 196.84 4,464.33 48.96% 0.00 0.00% 196.84 4,464.33 48.96% 205.23 4,654.62 51.04%
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 ZAPATAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 252.16 4.72 1,190.20 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 252.16 1,190.20 100.00%
01.05.01.02 ZAPATAS, ENCOFRADO Y DESENCOFRADO m2 5.76 20.30 116.93 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.76 116.93 100.00%
01.05.01.03 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 43.99 284.36 12,509.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 43.99 12,509.00 100.00%
01.05.02 SOBRECIMIENTO REFORZADO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 318.08 4.72 1,501.34 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 318.08 1,501.34 100.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 154.14 19.22 2,962.57 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 154.14 2,962.57 100.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 20.13 302.31 6,085.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 20.13 6,085.50 100.00%
01.05.03 VIGAS DE CONFINAMIENTO
01.05.03.01 VIGAS DE CONFINAMIENTO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 569.10 4.72 2,686.15 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 569.10 2,686.15 100.00%
01.05.03.02 VIGAS DE CONFINAMIENTO, ENCOFRADO Y DESENCOFRADO m2 110.00 20.30 2,233.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 110.00 2,233.00 100.00%
01.05.03.03 VIGAS DE CONFINAMIENTO, CONCRETO F'C=210 KG/CM2 m3 17.08 293.28 5,009.22 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.08 5,009.22 100.00%
01.05.04 COLUMNAS
01.05.04.01 COLUMNAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 7,374.02 4.72 34,805.37 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7,374.02 34,805.37 100.00%
01.05.04.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 552.40 25.69 14,191.16 32.16 826.19 5.82% 0.00 0.00% 32.16 826.19 5.82% 520.24 13,364.97 94.18%
01.05.04.03 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 56.93 356.20 20,278.47 2.90 1,032.98 5.09% 0.00 0.00% 2.90 1,032.98 5.09% 54.03 19,245.49 94.91%
01.05.05 VIGAS
01.05.05.01 VIGAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 10,472.02 4.72 49,427.93 866.67 4,090.68 8.28% 0.00 0.00% 866.67 4,090.68 8.28% 9,605.35 45,337.25 91.72%
01.05.05.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 475.77 33.24 15,814.59 34.92 1,160.74 7.34% 0.00 0.00% 34.92 1,160.74 7.34% 440.85 14,653.85 92.66%
01.05.05.03 VIGAS, CONCRETO F'C=210 KG/CM2 - PRIMER PISO m3 33.73 302.43 10,200.96 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 33.73 10,200.96 100.00%
01.05.05.04 VIGAS, CONCRETO F'C=210 KG/CM2 - SEGUNDO PISO m3 22.56 319.53 7,208.60 4.92 1,572.09 21.81% 0.00 0.00% 4.92 1,572.09 21.81% 17.64 5,636.51 78.19%
01.05.06 LOSAS ALIGERADAS
01.05.06.01 LOSA ALIGERADAS, ENCOFRADO Y DESENCOFRADO m2 598.71 21.09 12,626.79 53.20 1,121.99 8.89% 0.00 0.00% 53.20 1,121.99 8.89% 545.51 11,504.81 91.11%
01.05.06.02 LOSA ALIGERADAS, LADRILLO HUECO TECHO 0.30 X 0.30 X 0.15M und 2,673.70 3.63 9,705.53 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2,673.70 9,705.53 100.00%
01.05.06.03 LOSA, LADRILLO P/TECHO 0.30 X 0.30 X 0.15MT SEGUNDO PISO und 2,221.09 3.63 8,062.56 418.15 1,517.88 18.83% 0.00 0.00% 418.15 1,517.88 18.83% 1,802.94 6,544.67 81.17%
01.05.06.04 LOSA ALIGERADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 4,038.41 4.72 19,061.30 981.31 4,631.78 24.30% 0.00 0.00% 981.31 4,631.78 24.30% 3,057.10 14,429.51 75.70%
01.05.06.05 LOSA ALIGERADAS, CONCRETO F'C=210 KG/CM2 m3 48.22 305.36 14,724.46 4.51 1,377.17 9.35% 0.00 0.00% 4.51 1,377.17 9.35% 43.71 13,347.29 90.65%
01.05.07 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.05.07.01 COLUMNETAS, VIGUETAS DE AMARRE, ACERO DE REFUERZO FY=4200 kg 2,801.75 4.72 13,224.26 269.77 1,273.31 9.63% 0.00 0.00% 269.77 1,273.31 9.63% 2,531.98 11,950.95 90.37%
01.05.07.02 COLUMNETAS,VIGUETAS DE AMARRE, ENCOFRADO Y DESENCOFRADO m2 275.32 25.69 7,072.97 55.19 1,417.83 20.05% 0.00 0.00% 55.19 1,417.83 20.05% 220.13 5,655.14 79.95%
01.05.07.03 COLUMNETAS, VIGUETAS DE AMARRE, CONCRETO F'C=175 KG/CM2 m3 29.38 306.20 8,996.16 3.57 1,093.13 12.15% 0.00 0.00% 3.57 1,093.13 12.15% 25.81 7,903.02 87.85%
01.05.08 ESCALERAS
01.05.08.01 ESCALERA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 0.00 4.72 0.00
01.05.08.02 ESCALERA, ENCOFRADO Y DESENCOFRADO m2 0.00 19.43 0.00
01.05.08.03 ESCALERA, CONCRETO F'C=210 KG/CM2 m3 0.00 353.23 0.00
01.05.09 LOSAS MACIZAS
01.05.09.01 LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,918.39 4.72 9,054.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,918.39 9,054.80 100.00%
01.05.09.02 LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 57.89 31.31 1,812.54 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 57.89 1,812.54 100.00%
01.05.09.03 LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 8.68 316.47 2,746.96 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.68 2,746.96 100.00%
01.05.10 CANALETA DE DRENAJE PLUVIAL EN TECHO
01.05.10.01 CANALETA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 147.12 4.72 694.41 103.82 490.03 70.57% 0.00 0.00% 103.82 490.03 70.57% 43.30 204.38 29.43%
01.05.10.02 CANALETA, ENCOFRADO Y DESENCOFRADO m2 10.79 19.43 209.65 4.94 95.98 45.78% 0.00 0.00% 4.94 95.98 45.78% 5.85 113.67 54.22%
01.05.10.03 CANALETA, CONCRETO F'C=210 KG/CM2 m3 0.40 354.95 141.98 0.40 141.98 100.00% 0.00 0.00% 0.40 141.98 100.00% 0.00 0.00 0.00%
01.05.11 PARASOLES
01.05.11.01 PARASOLES, ACERO DE REFUERZO FY=4200 KG/CM2 kg 503.08 4.72 2,374.54 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 503.08 2,374.54 100.00%
01.05.11.02 PARASOLES, ENCOFRADO Y DESENCOFRADO m2 67.50 19.43 1,311.53 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 67.50 1,311.53 100.00%
01.05.11.03 PARASOLES, CONCRETO F'C=210 KG/CM2 m3 3.38 316.47 1,069.67 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.38 1,069.67 100.00%
01.05.12 MUROS DE CONTENCION
01.05.12.01 MUROS DE CONTENCION, ACERO DE REFUERZO FY=4200 KG/CM2 kg 13,203.56 4.72 62,320.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13,203.56 62,320.80 100.00%
01.05.12.02 MUROS DE CONTENCION, ENCOFRADO Y DESENCOFRADO m2 821.52 32.66 26,830.84 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 821.52 26,830.84 100.00%
01.05.12.03 MUROS DE CONTENCION, CONCRETO F'C=210 KG/CM2 m3 49.60 356.20 17,667.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.60 17,667.52 100.00%
01.05.12.04 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 m3 219.01 328.70 71,988.59 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 219.01 71,988.59 100.00%
01.05.12.05 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 + 30% PG m3 8.36 240.08 2,007.07 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.36 2,007.07 100.00%
01.05.13 CISTERNA SUBTERRANEA
01.05.13.01 TANQUE CISTERNA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 186.60 4.72 880.75 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 186.60 880.75 100.00%
01.05.13.02 TANQUE CISTERNA, ENCOFRADO Y DESENCOFRADO m2 60.86 22.87 1,391.87 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 60.86 1,391.87 100.00%
01.05.13.03 TANQUE CISTERNA, CONCRETO F'C=210 KG/CM2 m3 10.33 538.20 5,559.61 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.33 5,559.61 100.00%
01.05.14 PLACAS Y LOSAS MACIZAS
01.05.14.01 PLACA Y LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 268.73 4.72 1,268.41 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 268.73 1,268.41 100.00%
01.05.14.02 PLACA Y LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 149.96 31.31 4,695.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 149.96 4,695.25 100.00%
01.05.14.03 PLACA Y LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 5.81 316.47 1,838.69 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.81 1,838.69 100.00%
01.06 MUROS Y TABIQUES DE ALBAÑILERIA
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.06.01 MUROS DE LADRILLO KK TIPO IV CABEZA M: 1:4, J:1.5CM m2 291.26 92.98 27,081.35 40.61 3,775.92 13.94% 0.00 0.00% 40.61 3,775.92 13.94% 250.65 23,305.44 86.06%
01.06.02 MUROS DE LADRILLO KK TIPO IV SOGA M: 1:4, J:1.5CM m2 563.43 55.35 31,185.85 97.67 5,406.03 17.33% 0.00 0.00% 97.67 5,406.03 17.33% 465.76 25,779.82 82.67%
01.06.03 ALAMBRE REFUERZO HORIZONTAL EN ALBAÑILERIA #8 kg 133.61 5.03 672.06 24.33 122.38 18.21% 0.00 0.00% 24.33 122.38 18.21% 109.28 549.68 81.79%
01.06.04 MURO DE LADRILLO KK SOGA M:1:5 E=1.4 CM CARA VISTA UNA CARA m2 337.82 56.93 19,232.09 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 337.82 19,232.09 100.00%
02 ARQUITECTURA
02.01 REVOQUES ENLUCIDOS Y MOLDURAS
02.01.01 TARRAJEO PRIMARIO, MORTERO 1:5 C:A m2 256.17 13.17 3,373.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 256.17 3,373.76 100.00%
02.01.02 TARRAJEO EN MUROS INTERIOR, MORTERO 1:5 C:A m2 558.23 21.64 12,080.10 192.77 4,171.54 34.53% 0.00 0.00% 192.77 4,171.54 34.53% 365.46 7,908.55 65.47%
02.01.03 TARRAJEO EN MUROS EXTERIOR, MORTERO 1:5 C:A m2 603.51 24.84 14,991.19 110.12 2,735.38 18.25% 0.00 0.00% 110.12 2,735.38 18.25% 493.39 12,255.81 81.75%
02.01.04 TARRAJEO EN COLUMNAS, MORTERO 1:5 C:A m2 473.41 19.64 9,297.77 61.21 1,202.16 12.93% 0.00 0.00% 61.21 1,202.16 12.93% 412.20 8,095.61 87.07%
02.01.05 TARRAJEO EN VIGAS, MORTERO 1:5 C:A m2 354.60 30.87 10,946.50 35.90 1,108.23 10.12% 0.00 0.00% 35.90 1,108.23 10.12% 318.70 9,838.27 89.88%
02.01.06 TARRAJEO EN MUROS DE SOSTENIMIENTO, MORTERO 1:5 C:A m2 155.22 27.84 4,321.32 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 155.22 4,321.32 100.00%
02.01.07 TARRAJEO CON IMPERMEABILIZANTE m2 109.59 39.40 4,317.85 19.78 779.33 18.05% 0.00 0.00% 19.78 779.33 18.05% 89.81 3,538.51 81.95%
02.01.08 VESTIDURA DE DERRAMES 1:5 C:A m 619.43 6.68 4,137.79 303.43 2,026.91 48.99% 0.00 0.00% 303.43 2,026.91 48.99% 316.00 2,110.88 51.01%
02.01.09 BRUÑAS SEGUN DETALLE 1 X 1CM m 2,221.04 4.03 8,950.79 996.92 4,017.59 44.89% 0.00 0.00% 996.92 4,017.59 44.89% 1,224.12 4,933.20 55.11%
02.02 CIELO RASOS
02.02.01 CIELO RASO CON MEZCLA C:A 1:5 m2 827.88 31.46 26,045.10 165.95 5,220.79 20.05% 0.00 0.00% 165.95 5,220.79 20.05% 661.93 20,824.32 79.95%
02.03 PISOS Y PAVIMENTOS
02.03.01 CONTRAPISO DE 40MM m2 788.95 22.31 17,601.47 366.58 8,178.40 46.46% 0.00 0.00% 366.58 8,178.40 46.46% 422.37 9,423.07 53.54%
02.03.02 PISO PORCELANATO ANTIDESLIZANTE 0.60X0.60 m2 780.85 68.32 53,347.67 366.58 25,044.75 46.95% 0.00 0.00% 366.58 25,044.75 46.95% 414.27 28,302.93 53.05%
02.03.03 PISO CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR m2 281.77 23.91 6,737.12 103.28 2,469.42 36.65% 0.00 0.00% 103.28 2,469.42 36.65% 178.49 4,267.70 63.35%
02.03.04 REVESTIMIENTO DE MURO, TIPO LAJA m2 83.68 50.25 4,204.92 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 83.68 4,204.92 100.00%
02.03.05 VEREDA CONCRETO F'C=175 KG/CM2 FROT. Y BRUÑADO m2 526.73 41.64 21,933.04 104.52 4,352.21 19.84% 0.00 0.00% 104.52 4,352.21 19.84% 422.21 17,580.82 80.16%
02.03.06 CONCRETO EN LOSA DEPORTIVA F'C=175 KG/CM2 m3 81.42 356.54 29,029.49 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 81.42 29,029.49 100.00%
02.03.07 CONCRETO EN DADOS DE ANCLAJE F'C=175 KG/CM2 m3 0.17 290.25 49.34 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.17 49.34 100.00%
02.03.08 PISO ADOQUINADO m2 110.80 75.57 8,373.16 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 110.80 8,373.16 100.00%
02.03.09 ENCOFRADO DE LOSAS DEPORTIVAS m2 86.49 34.29 2,965.74 7.68 263.35 8.88% 0.00 0.00% 7.68 263.35 8.88% 78.81 2,702.39 91.12%
02.04 CONTRAZOCALOS
02.04.01 CONTRAZOCALO DE LOSETA VENECIANA COLOR CLARO 10X30CM m 19.10 25.32 483.61 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 19.10 483.61 100.00%
02.04.02 CONTRAZOCALO S/COLOREAR H=30CM MEZCLA 1:2 E=1.5CM m 676.38 7.28 4,924.05 370.27 2,695.57 54.74% 0.00 0.00% 370.27 2,695.57 54.74% 306.11 2,228.48 45.26%
02.05 ZOCALOS
02.05.01 ZOCALO DE MAYOLICA BLANCA 20X30 1RA m2 277.27 54.10 15,000.31 23.09 1,249.17 8.33% 0.00 0.00% 23.09 1,249.17 8.33% 254.18 13,751.14 91.67%
02.06 CUBIERTAS
02.06.01 COBERTURA C/PLANCHA TIPO TEJA ANDINA m2 706.68 77.88 55,036.24 365.91 28,497.07 51.78% 0.00 0.00% 365.91 28,497.07 51.78% 340.77 26,539.17 48.22%
02.06.02 CUMBRERA C/PLANCHA TIPO TEJA ANDINA m 60.40 73.44 4,435.78 30.75 2,258.28 50.91% 0.00 0.00% 30.75 2,258.28 50.91% 29.65 2,177.50 49.09%
02.07 CARPINTERIA DE MADERA
02.07.01 PUERTA CEDRO MACHIMBRADA m2 63.91 565.61 36,148.14 28.16 15,927.58 44.06% 0.00 0.00% 28.16 15,927.58 44.06% 35.75 20,220.56 55.94%
02.07.02 PUERTA CON TRIPLAY 9MM P/SSHH m2 12.04 278.64 3,354.83 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.04 3,354.83 100.00%
02.08 CARPINTERIA METALICA
02.08.01 VENTANA DE ALUMINIO m2 176.97 25.00 4,424.25 101.57 2,539.25 57.39% 0.00 0.00% 101.57 2,539.25 57.39% 75.40 1,885.00 42.61%
02.08.02 PASAMANO DE TUBO F°G° DE 2" m 15.70 60.27 946.24 11.10 669.00 70.70% 0.00 0.00% 11.10 669.00 70.70% 4.60 277.24 29.30%
02.08.03 CANTONERA DE FIERRO EN ESCALERA m 77.60 22.28 1,728.93 60.80 1,354.62 78.35% 0.00 0.00% 60.80 1,354.62 78.35% 16.80 374.30 21.65%
02.08.04 ESCALERA DE GATO, TUBO F°G° 1 1/2" Y 1" TQE ELEVADO m 3.40 102.48 348.43 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.40 348.43 100.00%
02.08.05 TAPA DE FIERRO EN CISTERNA und 1.00 328.15 328.15 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 328.15 100.00%
02.08.06 PUERTA DE INGRESO PRINCIPAL C/PERFILES SEGUN DISEÑO und 1.00 13,935.86 13,935.86 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 13,935.86 100.00%
02.08.07 BARANDA DE TUBO F°G° DE 2" m 233.80 104.60 24,455.48 46.10 4,822.06 19.72% 0.00 0.00% 46.10 4,822.06 19.72% 187.70 19,633.42 80.28%
02.09 CERRAJERIA
02.09.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 4" PESADA EN PUERTA pza 187.00 13.43 2,511.41 65.00 872.95 34.76% 0.00 0.00% 65.00 872.95 34.76% 122.00 1,638.46 65.24%
02.09.02 CERRADURA DOS GOLPES EN PUERTA pza 29.00 73.82 2,140.78 13.00 959.66 44.83% 0.00 0.00% 13.00 959.66 44.83% 16.00 1,181.12 55.17%
02.09.03 MANIJA DE BRONCE 4" P/PUERTAS pza 29.00 11.46 332.34 13.00 148.98 44.83% 0.00 0.00% 13.00 148.98 44.83% 16.00 183.36 55.17%
02.09.04 CANDADO TIPO FORTE 60MM pza 3.00 55.19 165.57 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 165.57 100.00%
02.09.05 CERROJO DE 3" ALUMINIZADO P/PUERTA pza 14.00 8.31 116.34 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.00 116.34 100.00%
02.10 VIDRIOS CRISTALES Y SIMILARES
02.10.01 VIDRIO SEMIDOBLE INCOLORO CRUDO p2 2,299.47 13.80 31,732.69 1,093.31 15,087.68 47.55% 0.00 0.00% 1,093.31 15,087.68 47.55% 1,206.16 16,645.01 52.45%
02.11 PINTURAS
02.11.01 PINTURA LATEX 02 MANOS EN CIELO RASO m2 1,180.70 8.74 10,319.32 620.31 5,421.51 52.54% 0.00 0.00% 620.31 5,421.51 52.54% 560.39 4,897.81 47.46%
02.11.02 PINTURA OLEO 2 MANOS EN VIGAS m2 578.21 6.42 3,712.11 259.51 1,666.05 44.88% 0.00 0.00% 259.51 1,666.05 44.88% 318.70 2,046.05 55.12%
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
02.11.03 PINTURA OLEO 2 MANOS EN MUROS Y COLUMNAS m2 1,589.40 8.02 12,746.99 1,400.01 11,228.08 88.08% 0.00 0.00% 1,400.01 11,228.08 88.08% 189.39 1,518.91 11.92%
02.11.04 PINTURA OLEO 2 MANOS EN DERRAMES m 619.43 4.63 2,867.96 303.43 1,404.88 48.99% 0.00 0.00% 303.43 1,404.88 48.99% 316.00 1,463.08 51.01%
02.11.05 PINTURA BARNIZ 2 MANOS EN CARP. MADERA m2 75.95 12.34 937.22 28.16 347.49 37.08% 0.00 0.00% 28.16 347.49 37.08% 47.79 589.73 62.92%
02.11.06 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=30CM m 663.88 2.37 1,573.40 370.27 877.54 55.77% 0.00 0.00% 370.27 877.54 55.77% 293.61 695.86 44.23%
02.11.07 PINTURA ESMALTE ENLOSA DEPORTIVA m 360.00 4.08 1,468.80 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 360.00 1,468.80 100.00%
02.12 DRYWALL
02.12.01 PROVISION Y COLOCACION DE RIELES DE 90X25X0.90 m 10.23 38.73 396.21 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.23 396.21 100.00%
02.12.02 PROVISION Y COLOCACION DE PARANTES 89X38X0.90 m 74.13 47.83 3,545.64 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 74.13 3,545.64 100.00%
02.12.03 PROVISION Y COLOCACION DE PLACA GYPLAC DE 1/2" R.H. m2 49.90 54.16 2,702.58 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 49.90 2,702.58 100.00%
02.13 VARIOS
02.13.01 PIZARRA ACRILICA und 16.00 250.00 4,000.00 4.00 1,000.00 25.00% 0.00 0.00% 4.00 1,000.00 25.00% 12.00 3,000.00 75.00%
02.13.02 TAPAJUNTA METALICA EN PISOS m 9.55 50.81 485.24 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 9.55 485.24 100.00%
02.13.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) m 30.00 20.77 623.10 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 30.00 623.10 100.00%
02.13.04 JUNTA DILATACION RELLENO CON MORTERO ASFALTICO E=1" m 69.30 6.44 446.29 35.40 227.98 51.08% 0.00 0.00% 35.40 227.98 51.08% 33.90 218.32 48.92%
02.13.05 JUNTA DE CONSTRUCCION CON TECNOPORT m2 49.55 7.06 349.82 12.29 86.77 24.80% 0.00 0.00% 12.29 86.77 24.80% 37.26 263.06 75.20%
02.13.06 ARCO Y TABLERO FULBITO-BASKET S/DISEÑO und 2.00 2,581.13 5,162.26 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 5,162.26 100.00%
02.13.07 NET CON SOPORTE F°G° D=3" + ACCESORIOS SUMINISTRO Y COLOCACI und 1.00 806.65 806.65 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 806.65 100.00%
02.13.08 TANQUE DE POLIETILENO und 2.00 1,363.76 2,727.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 2,727.52 100.00%
02.13.09 LETRERO METALICO DE IDENTIFICACION glb 1.00 1,500.00 1,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,500.00 100.00%
03 INSTALACIONES SANITARIAS
03.01 APARATOS SANITARIOS Y ACCESORIOS
03.01.01 INODORO TANQUE BAJO DE LOSA 1RA CALIDAD ADULTO pza 14.00 316.52 4,431.28 2.00 633.04 14.29% 0.00 0.00% 2.00 633.04 14.29% 12.00 3,798.24 85.71%
03.01.02 LAVATORIO DE PARED BLANCO INC. ACCESORIOS pza 4.00 341.43 1,365.72 2.00 682.86 50.00% 0.00 0.00% 2.00 682.86 50.00% 2.00 682.86 50.00%
03.01.03 URINARIO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 3.00 454.75 1,364.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 3.00 1,364.25 100.00%
03.01.04 BEBEDERO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 7.40 523.79 3,876.05 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.40 3,876.05 100.00%
03.01.05 DUCHA CROMADA DE CABEZA GIRATORIA und 4.00 55.32 221.28 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 221.28 100.00%
03.02 INSTALACIONES SANITARIAS
03.02.01 SALIDA DESAGUE DE PVC SAL 2" pto 30.00 42.09 1,262.70 4.00 168.36 13.33% 0.00 0.00% 4.00 168.36 13.33% 26.00 1,094.34 86.67%
03.02.02 SALIDA DESAGUE DE PVC SAL 4" pto 14.00 51.94 727.16 4.00 207.76 28.57% 0.00 0.00% 4.00 207.76 28.57% 10.00 519.40 71.43%
03.02.03 SALIDA PARA VENTILACION pto 9.00 50.28 452.52 1.00 50.28 11.11% 0.00 0.00% 1.00 50.28 11.11% 8.00 402.24 88.89%
03.02.04 TUBERIA DE PVC SAL 2" m 84.60 10.54 891.68 15.00 158.10 17.73% 0.00 0.00% 15.00 158.10 17.73% 69.60 733.58 82.27%
03.02.05 TUBERIA DE PVC SAL 4" m 94.00 14.81 1,392.14 15.00 222.15 15.96% 0.00 0.00% 15.00 222.15 15.96% 79.00 1,169.99 84.04%
03.02.06 REGISTRO DE BRONCE 4" und 14.00 25.43 356.02 2.00 50.86 14.29% 0.00 0.00% 2.00 50.86 14.29% 12.00 305.16 85.71%
03.02.07 SUMIDERO DE BRONCE ROSCADO 3" und 30.00 63.27 1,898.10 2.00 126.54 6.67% 0.00 0.00% 2.00 126.54 6.67% 28.00 1,771.56 93.33%
03.02.08 CAJA SUMIDERO CON REJILLA DE FIERRO und 8.00 186.58 1,492.64 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 1,492.64 100.00%
03.02.09 CAJA DE REGISTRO DESAGUE 12"X24" C/TAPA CONCRETO und 7.00 636.00 4,452.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 4,452.00 100.00%
03.03 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.03.01 SALIDA DE AGUA FRIA TUBERIA PVC 1/2" pto 30.00 106.77 3,203.10 2.00 213.54 6.67% 0.00 0.00% 2.00 213.54 6.67% 28.00 2,989.56 93.33%
03.03.02 TUBERIA PVC CLASE 10 - 1/2" m 60.50 9.48 573.54 24.00 227.52 39.67% 0.00 0.00% 24.00 227.52 39.67% 36.50 346.02 60.33%
03.03.03 TUBERIA PVC CLASE 10 - 3/4" m 156.20 10.14 1,583.87 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 156.20 1,583.87 100.00%
03.03.04 VALVULA COMPUERTA DE BRONCE 1/2" und 7.00 141.77 992.39 1.00 141.77 14.29% 0.00 0.00% 1.00 141.77 14.29% 6.00 850.62 85.71%
03.03.05 VALVULA COMPUERTA DE BRONCE 3/4" und 5.00 189.77 948.85 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 948.85 100.00%
03.03.06 VALVULA GLOBO DE 1/2" und 2.00 157.37 314.74 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 314.74 100.00%
03.03.07 REDUCCION PVC SAP 3/4" A 1/2" und 5.00 14.05 70.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 5.00 70.25 100.00%
03.03.08 CAJA DE MADERA PARA VALVULA und 1.00 48.02 48.02 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 48.02 100.00%
03.03.09 CAJA EN NICHO DE MAYOLICA PARA VALVULA und 7.00 23.08 161.56 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 7.00 161.56 100.00%
03.03.10 SUCCION E IMPULSION INCLUYE INSTALACION Y ACCESORIOS glb 1.00 4,424.29 4,424.29 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 4,424.29 100.00%
03.03.11 REBOSE Y LIMPIA INCLUYE INSTALACION Y ACCESORIOS glb 1.00 1,426.33 1,426.33 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 1,426.33 100.00%
03.04 SISTEMA DE AGUA DE LLUVIA Y SUBDREN
03.04.01 TUBERIA DE PVC SAP 3" P/LLUVIAS m 73.00 30.47 2,224.31 41.80 1,273.65 57.26% 0.00 0.00% 41.80 1,273.65 57.26% 31.20 950.66 42.74%
03.04.02 FALSA COLUMNA/PROTECCION TUBERIA MONTANTE, CONCRETO F'C=17 m3 0.65 1,662.60 1,080.69 0.32 532.03 49.23% 0.00 0.00% 0.32 532.03 49.23% 0.33 548.66 50.77%
03.04.03 CANALETA DE EVACUACION PLUVIAL, CONCRETO F'C=210 KG/CM2 m3 16.65 1,296.05 21,579.23 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 16.65 21,579.23 100.00%
03.04.04 ENCOFRADO Y DESENCOFRADO, CANALETA DE EVACUACION PLUVIAL m2 111.03 49.13 5,454.90 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 111.03 5,454.90 100.00%
03.04.05 TUBERIA DE PVC SAL 4" (PERFORADA) m 99.33 14.81 1,471.08 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 99.33 1,471.08 100.00%
03.04.06 TUBERIA DE PVC SAL 6" (PERFORADA) m 65.05 19.91 1,295.15 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 65.05 1,295.15 100.00%
04 INSTALACIONES ELECTRICAS
04.01 SALIDA PARA ALUMBRADO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
04.01.01 SALIDA PARA CENTRO DE LUZ EN TECHO pto 42.00 79.76 3,349.92 8.00 638.08 19.05% 0.00 0.00% 8.00 638.08 19.05% 34.00 2,711.84 80.95%
04.01.02 SALIDA PARA CENTRO DE LUZ EN PARED pto 40.00 79.76 3,190.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 40.00 3,190.40 100.00%
04.01.03 SALIDA PARA INTERRUPTOR SIMPLE pto 33.00 83.45 2,753.85 16.00 1,335.20 48.48% 0.00 0.00% 16.00 1,335.20 48.48% 17.00 1,418.65 51.52%
04.01.04 SALIDA PARA INTERRUPTOR DE CONMUTACION pto 6.00 120.30 721.80 2.00 240.60 33.33% 0.00 0.00% 2.00 240.60 33.33% 4.00 481.20 66.67%
04.02 SALIDA PARA TOMACORRIENTES
04.02.01 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 0 pto 125.00 99.28 12,410.00 53.00 5,261.84 42.40% 0.00 0.00% 53.00 5,261.84 42.40% 72.00 7,148.16 57.60%
04.02.02 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 1 pto 4.00 115.48 461.92 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 461.92 100.00%
04.02.03 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION E pto 30.00 90.64 2,719.20 30.00 2,719.20 100.00% 0.00 0.00% 30.00 2,719.20 100.00% 0.00 0.00 0.00%
04.03 CAJAS Y TABLEROS
04.03.01 CAJA DE PASE 102X102X100 MM und 8.00 23.80 190.40 2.00 47.60 25.00% 0.00 0.00% 2.00 47.60 25.00% 6.00 142.80 75.00%
04.03.02 CAJA DE PASE 200X200X100 MM und 4.00 29.16 116.64 1.00 29.16 25.00% 0.00 0.00% 1.00 29.16 25.00% 3.00 87.48 75.00%
04.03.03 TABLERO DE 3X40A, 20 POLOS und 2.00 495.67 991.34 2.00 991.34 100.00% 0.00 0.00% 2.00 991.34 100.00% 0.00 0.00 0.00%
04.03.04 TABLERO DE 3X35A, 20 POLOS und 2.00 495.67 991.34 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 991.34 100.00%
04.03.05 TABLERO DE 2X30A, 24 POLOS und 1.00 474.98 474.98 1.00 474.98 100.00% 0.00 0.00% 1.00 474.98 100.00% 0.00 0.00 0.00%
04.03.06 TABLERO DE 2X10A, 8 POLOS und 1.00 263.72 263.72 1.00 263.72 100.00% 0.00 0.00% 1.00 263.72 100.00% 0.00 0.00 0.00%
04.04 ARTEFACTOS
04.04.01 ARTEFACTO TIPO BRAQUETE CON 3 LAMPARAS FLUORECENTES DE 36W und 56.00 124.05 6,946.80 24.00 2,977.20 42.86% 0.00 0.00% 24.00 2,977.20 42.86% 32.00 3,969.60 57.14%
04.04.02 ARTEFACTO CON LAMPARA FLUORECENTE CIRCULAR DE 32W und 24.00 117.63 2,823.12 23.00 2,705.49 95.83% 0.00 0.00% 23.00 2,705.49 95.83% 1.00 117.63 4.17%
04.04.03 ARTEFACTO TIPO BRAQUETE CON 2 LAMPARAS AHORRADORAS DE 18W und 42.00 97.45 4,092.90 2.00 194.90 4.76% 0.00 0.00% 2.00 194.90 4.76% 40.00 3,898.00 95.24%
04.05 TABLEROS
04.05.01 TABLERO GENERAL TG 3X100A 28 POLOS und 1.00 928.05 928.05 1.00 928.05 100.00% 0.00 0.00% 1.00 928.05 100.00% 0.00 0.00 0.00%
04.06 ALIMENTADORES
04.06.01 N2XH(3-1X50X1X50(N)X1X25(T))MM2 m 38.00 184.02 6,992.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 38.00 6,992.76 100.00%
04.06.02 N2XH(3-1X16X1X16(N)X1X10(T))MM2 m 116.00 66.42 7,704.72 56.00 3,719.52 48.28% 0.00 0.00% 56.00 3,719.52 48.28% 60.00 3,985.20 51.72%
04.06.03 N2XH(1X16X1X16(N)X1X10(T))MM2 m 37.00 37.88 1,401.56 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 37.00 1,401.56 100.00%
04.06.04 N2XH(1X6X1X6(N)X1X6(T))MM2 m 12.00 39.13 469.56 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 469.56 100.00%
04.07 CIRCUITO DE TIMBRES
04.07.01 SALIDA PARA TIMBRES pto 2.00 143.99 287.98 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 287.98 100.00%
04.08 SISTEMA DE PUESTA A TIERRA
04.08.01 PUESTA A TIERRA TIPO P-1 (R<15 OHMIOS) und 1.00 974.69 974.69 1.00 974.69 100.00% 0.00 0.00% 1.00 974.69 100.00% 0.00 0.00 0.00%
04.08.02 PUESTA A TIERRA TIPO P-2 (R<5 OHMIOS) und 4.00 1,151.69 4,606.76 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 4,606.76 100.00%
04.08.03 CONDUCTOR DE COBRE DESNUDO DE 1X16MM2 und 62.00 10.06 623.72 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.00 623.72 100.00%
04.08.04 PARARRAYO CON DISPOSITIVO DE CEBADO, C/03 P/TIERRA und 1.00 2,540.25 2,540.25 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2,540.25 100.00%
04.09 SISTEMA DE ALUMBRADO EXTERIOR
04.09.01 ILUMINACION DE LOZA DEPORTIVA und 4.00 1,919.72 7,678.88 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 7,678.88 100.00%
04.10 OTROS EQUIPOS
04.10.01 ELECTROBOMBA PARA TANQUE ELEVADO und 2.00 974.86 1,949.72 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 1,949.72 100.00%
04.10.02 INSTALACION DEMEDIDOR ELECTRICO und 1.00 827.69 827.69 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 827.69 100.00%
05 EQUIPAMIENTO, MOBILIARIO Y MATERIAL EDUCATIVO
05.01 EQUIPOS glb 1.00 63,192.00 63,192.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 63,192.00 100.00%
05.02 MOBILIARIO glb 1.00 64,806.01 64,806.01 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 64,806.01 100.00%
05.03 MATERIAL EDUCATIVO glb 1.00 54,185.00 54,185.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 54,185.00 100.00%
06 CAPACITACION
06.01 CAPACITACION glb 1.00 13,500.00 13,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 13,500.00 100.00%
07 PLAN MANEJO AMBIENTAL
07.01 SEMBRADO DE GRASS m2 413.00 19.39 8,008.07 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 413.00 8,008.07 100.00%
07.02 LIMPIEZA PERMANENTE DE OBRA glb 0.50 1,744.52 872.26 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 0.50 872.26 100.00%
07.03 CAPACITACION EN TEMA AMBIENTAL A PERSONAL OBRERO glb 1.00 10,000.00 10,000.00 0.50 5,000.00 50.00% 0.00 0.00% 0.50 5,000.00 50.00% 0.50 5,000.00 50.00%
07.04 SEÑALIZACION AMBIENTAL EN OBRA glb 1.00 1,500.00 1,500.00 0.50 750.00 50.00% 0.00 0.00% 0.50 750.00 50.00% 0.50 750.00 50.00%
07.05 EQUIPAMIENTO PARA MITIGACION AMBIENTAL EN OBRA glb 1.00 950.70 950.70 0.50 475.35 50.00% 0.00 0.00% 0.50 475.35 50.00% 0.50 475.35 50.00%
07.06 TRATAMIENTO DE BOTADEROS glb 0.50 3,000.00 1,500.00 0.50 1,500.00 100.00% 0.00 0.00% 0.50 1,500.00 100.00% 0.00 0.00 0.00%
COSTO DIRECTO 1,595,318.87 249,690.32 0.00 249,690.32 1,345,628.56
% DE AVANCE FISICO 15.65% 0.00% 15.65% 84.35%
GASTOS GENERALES (14.95%) 99,587.75 15,586.91 0.00 15,586.91 84,000.84
GASTOS DE SUPERVISION (5.10%) 42,249.50 6,612.65 0.00 6,612.65 35,636.85
PRESUPUESTO TOTAL 1,737,156.12 271,889.89 0.00 271,889.89 1,465,266.24
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 34.51% 0.00% 34.51% 65.49%
CRONOGRAMA REPROGRAMADO DE EJECUCION DE OBRA
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE DEL 09/03 AL 22/04 del 2015
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL %
01 ESTRUCTURAS
01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40M pza 1.00 1,162.69 1,162.69 1.00 1,162.69 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.01.02 CERCO PROVISIONAL DE SEGURIDAD C/ARPILLERA H=2.0M C/ROLLIZOS m 179.82 18.79 3,378.82 179.82 3,378.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.01.03 ALMACEN, OFICINA Y CASETA DE GUARDIANIA m2 84.00 141.01 11,844.84 84.00 11,844.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.01.04 SERVICIOS HIGIENICOS PROVISIONALES m2 9.00 323.01 2,907.09 9.00 2,907.09 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.01.05 AGUA PARA CONSTRUCCION glb 1.00 1,327.84 1,327.84 1.00 1,327.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.01.06 PLAN DE CONTINGENCIA P/INTERRUPCION DE CLASES glb 1.00 9,600.00 9,600.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO NORMAL m2 1,763.21 0.62 1,093.19 1,068.10 662.22 60.58% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02 DEMOLICIONES Y DESMONTAJES DE CONSTRUCCION EXISTENTE
01.02.02.01 DESMONTAJE DE PUERTAS m2 23.72 1.85 43.88 23.72 43.88 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.02 DESMONTAJE DE VENTANAS m2 12.32 1.39 17.12 12.32 17.12 100.03% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.03 DESMONTAJE DE COBERTURAS m2 677.51 1.05 711.39 677.51 711.39 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.04 DEMOLICION DE PISOS DE CONCRETO INC. FALSO PISO m2 583.63 5.04 2,941.50 583.63 2,941.50 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.05 DEMOLICION DE MUROS DE ADOBE m3 49.73 1.98 98.47 49.73 98.47 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.06 DEMOLICION CIMIENTOS ADOBE Y PIEDRA m3 357.62 4.20 1,502.00 357.62 1,502.00 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.07 DEMOLICION DE VEREDAS m2 32.00 6.30 201.60 32.00 201.60 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.08 DEMOLICION DE ELEMENTOS DE CONCRETO Y ALBAÑILERIA m3 107.24 8.40 900.82 107.24 900.82 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.02.02.09 TRAZO Y REPLANTEO DURANTE EJECUCION m2 1,763.21 3.18 5,607.01 1,068.10 3,396.56 60.58% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE TERRENO CON MAQUINARIA m3 2,810.47 6.04 16,975.24 2,700.25 16,309.51 96.08% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03.02 EXCAVACION PARA ZAPATAS HASTA 2.3 m. m3 1,394.91 28.93 40,354.75 253.60 7,336.65 18.18% 23.51 680.14 1.69% 47.36 1,370.12 3.40% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03.03 EXCAVACION DE ZANJAS PARA CIMIENTO CORRIDO HASTA 1.40 M. m3 611.73 23.15 14,161.55 66.97 1,550.36 10.95% 28.81 666.95 4.71% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 1,721.56 3.96 6,817.38 0.00 0.00% 0.00 0.00% 27.29 108.07 1.59% 42.90 169.88 2.49% 0.00 0.00% 0.00 0.00% 101.72 402.81 5.91%
01.03.05 RELLENO Y COMPACT. MANUAL C/MAT. AFIRMADO m3 166.38 59.63 9,921.24 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 30.14 1,797.25 18.12%
01.03.06 RELLENO Y COMPACT. MANUAL C/MAT. DE FILTRO m3 45.09 88.67 3,998.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.40 744.83 18.63%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 1,363.49 8.24 11,235.16 939.57 7,742.06 68.91% 62.79 517.39 4.61% 37.74 310.98 2.77% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1,363.49 21.99 29,983.15 0.00 0.00% 410.42 9,025.14 30.10% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 617.50 13,578.83 45.29%
01.03.09 NIVELACION Y COMPACATADO DE SUB-BASE m2 1,907.20 1.04 1,983.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 301.36 313.41 15.80%
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 82.44 165.47 13,641.35 0.00 0.00% 0.00 0.00% 43.06 7,125.14 52.23% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04.02 SOLADO e=4" MEZCLA 1:12 CEMENTO-HORMIGON m2 280.77 20.94 5,879.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04.03 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30%PG m3 74.62 137.55 10,263.98 0.00 0.00% 0.00 0.00% 11.35 1,561.19 15.21% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04.04 SOBRECIMIENTO ENCOFRADO Y DESENCOFRADO m2 164.29 27.80 4,567.26 0.00 0.00% 0.00 0.00% 4.52 125.66 2.75% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04.05 SOBRECIMIENTOS CORRIDOS MEZCLA 1:8 CEMENTO-HORMIGON 25%PM m3 12.34 171.37 2,114.71 0.00 0.00% 0.00 0.00% 0.34 58.27 2.76% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.04.06 FALSO PISO DE H=4" MEZCLA 1:8 m2 402.07 20.92 8,411.30 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 196.84 4,117.89 48.96%
01.05 CONCRETO ARMADO
01.05.01 ZAPATAS
01.05.01.01 ZAPATAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 2,754.16 4.58 12,614.05 0.00 0.00% 2,322.24 10,635.86 84.32% 179.76 823.30 6.53% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.01.02 ZAPATAS, ENCOFRADO Y DESENCOFRADO m2 39.60 17.94 710.42 0.00 0.00% 0.00 0.00% 33.12 594.17 83.64% 0.00 0.00% 0.72 12.92 1.82% 0.00 0.00% 0.00 0.00%
01.05.01.03 ZAPATAS, CONCRETO F'C=210 KG/CM2 m3 95.77 277.97 26,621.19 0.00 0.00% 0.00 0.00% 48.15 13,384.26 50.28% 2.05 569.84 2.14% 1.58 439.19 1.65% 0.00 0.00% 0.00 0.00%
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 947.77 4.58 4,340.79 0.00 0.00% 0.00 0.00% 383.72 1,757.44 40.49% 141.05 646.01 14.88% 104.92 480.53 11.07% 0.00 0.00% 0.00 0.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 334.71 16.86 5,643.21 0.00 0.00% 0.00 0.00% 124.10 2,092.33 37.08% 48.15 811.81 14.39% 0.00 0.00% 8.32 140.28 2.49% 0.00 0.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 38.14 288.25 10,993.86 0.00 0.00% 0.00 0.00% 12.46 3,591.60 32.67% 5.15 1,484.49 13.50% 0.00 0.00% 0.40 115.30 1.05% 0.00 0.00%
01.05.03 VIGAS DE CONFINAMIENTO
01.05.03.01 VIGAS DE CONFINAMIENTO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 3,045.03 4.58 13,946.24 0.00 0.00% 1,051.68 4,816.69 34.54% 409.84 1,877.07 13.46% 286.46 1,311.99 9.41% 727.95 3,334.01 23.91% 0.00 0.00% 0.00 0.00%
01.05.03.02 VIGAS DE CONFINAMIENTO, ENCOFRADO Y DESENCOFRADO m2 184.75 17.94 3,314.42 0.00 0.00% 0.00 0.00% 28.53 511.83 15.44% 14.40 258.34 7.79% 0.00 0.00% 31.82 570.85 17.22% 0.00 0.00%
01.05.03.03 VIGAS DE CONFINAMIENTO, CONCRETO F'C=210 KG/CM2 m3 26.42 285.31 7,537.89 0.00 0.00% 0.00 0.00% 6.68 1,905.87 25.28% 1.80 513.56 6.81% 0.00 0.00% 0.86 245.37 3.26% 0.00 0.00%
01.05.04 COLUMNAS
01.05.04.01 COLUMNAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 20,024.11 4.58 91,710.42 5,223.81 23,925.05 26.09% 4,176.11 19,126.58 20.86% 0.00 0.00% 0.00 0.00% 3,250.17 14,885.78 16.23% 0.00 0.00% 0.00 0.00%
01.05.04.02 COLUMNAS, ENCOFRADO Y DESENCOFRADO m2 1,002.20 22.14 22,188.71 0.00 0.00% 0.00 0.00% 59.07 1,307.81 5.89% 165.62 3,666.83 16.53% 134.30 2,973.40 13.40% 90.81 2,010.53 9.06% 32.16 712.02 3.21%
01.05.04.03 COLUMNAS, CONCRETO F'C=210 KG/CM2 m3 102.01 336.75 34,351.87 0.00 0.00% 0.00 0.00% 6.09 2,050.81 5.97% 18.84 6,344.37 18.47% 15.10 5,084.93 14.80% 5.05 1,700.59 4.95% 2.90 976.58 2.84%
01.05.05 VIGAS
01.05.05.01 VIGAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 16,751.22 4.58 76,720.59 0.00 0.00% 1,488.14 6,815.68 8.88% 0.00 0.00% 1,640.86 7,515.14 9.80% 3,150.20 14,427.92 18.81% 0.00 0.00% 866.67 3,969.35 5.17%
01.05.05.02 VIGAS, ENCOFRADO Y DESENCOFRADO m2 784.37 28.50 22,354.55 0.00 0.00% 0.00 0.00% 0.00 0.00% 110.75 3,156.38 14.12% 197.85 5,638.73 25.22% 0.00 0.00% 34.92 995.22 4.45%
01.05.05.03 VIGAS, CONCRETO F'C=210 KG/CM2 - PRIMER PISO m3 53.13 292.72 15,552.21 0.00 0.00% 0.00 0.00% 0.00 0.00% 16.93 4,955.75 31.87% 0.00 0.00% 2.47 723.02 4.65% 0.00 0.00%
01.05.05.04 VIGAS, CONCRETO F'C=210 KG/CM2 - SEGUNDO PISO m3 47.13 308.73 14,550.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 24.57 7,585.50 52.13% 0.00 0.00% 4.92 1,518.95 10.44%
01.05.06 LOSAS ALIGERADAS
01.05.06.01 LOSA ALIGERADAS, ENCOFRADO Y DESENCOFRADO m2 1,067.27 18.25 19,477.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 213.05 3,888.16 19.96% 226.52 4,133.99 21.22% 28.99 529.07 2.72% 53.20 970.90 4.98%
01.05.06.02 LOSA ALIGERADAS, LADRILLO HUECO TECHO 0.30 X 0.30 X 0.15M und 4,570.60 3.55 16,225.63 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,774.66 6,300.04 38.83% 0.00 0.00% 122.24 433.95 2.67% 0.00 0.00%
01.05.06.03 LOSA ALIGERADAS, LADRILLO HUECO TECHO 0.30 X 0.30 X 0.15MT und 4,227.30 3.55 15,006.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,861.92 6,609.82 44.05% 144.29 512.23 3.41% 418.15 1,484.43 9.89%
01.05.06.04 LOSA ALIGERADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 6,237.72 4.58 28,568.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,084.66 4,967.74 17.39% 1,114.65 5,105.10 17.87% 0.00 0.00% 981.31 4,494.40 15.73%
01.05.06.05 LOSA ALIGERADAS, CONCRETO F'C=210 KG/CM2 m3 89.28 296.36 26,459.02 0.00 0.00% 0.00 0.00% 0.00 0.00% 18.63 5,521.19 20.87% 18.04 5,346.33 20.21% 4.39 1,301.02 4.92% 4.51 1,336.58 5.05%
01.05.07 COLUMNETAS Y VIGUETAS DE CONFINAMIENTO
01.05.07.01 COLUMNETAS, VIGUETAS DE AMARRE, ACERO DE REFUERZO FY=4200 kg 3,145.10 4.58 14,404.56 0.00 0.00% 343.35 1,572.54 10.92% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 269.77 1,235.55 8.58%
01.05.07.02 COLUMNETAS,VIGUETAS DE AMARRE, ENCOFRADO Y DESENCOFRADO m2 320.55 22.14 7,096.98 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 45.23 1,001.39 14.11% 55.19 1,221.91 17.22%
01.05.07.03 COLUMNETAS, VIGUETAS DE AMARRE, CONCRETO F'C=175 KG/CM2 m3 32.04 293.24 9,395.41 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.66 780.02 8.30% 3.57 1,046.87 11.14%
01.05.08 ESCALERAS
01.05.08.01 ESCALERA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 698.14 4.58 3,197.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 698.14 3,197.48 100.00% 0.00 0.00%
01.05.08.02 ESCALERA, ENCOFRADO Y DESENCOFRADO m2 41.56 17.07 709.43 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 41.56 709.43 100.00% 0.00 0.00%
01.05.08.03 ESCALERA, CONCRETO F'C=210 KG/CM2 m3 7.67 339.57 2,604.50 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.67 2,604.50 100.00% 0.00 0.00%
01.05.09 LOSAS MACIZAS
01.05.09.01 LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,918.39 4.58 8,786.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.09.02 LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 57.89 26.57 1,538.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.09.03 LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 8.68 305.81 2,654.43 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.10 CANALETA DE DRENAJE PLUVIAL EN TECHO
01.05.10.01 CANALETA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 950.41 4.58 4,352.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 803.29 3,679.07 84.52% 0.00 0.00% 103.82 475.50 10.92%
01.05.10.02 CANALETA, ENCOFRADO Y DESENCOFRADO m2 56.87 17.07 970.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 46.08 786.59 81.03% 0.00 0.00% 4.94 84.33 8.69%
01.05.10.03 CANALETA, CONCRETO F'C=210 KG/CM2 m3 3.68 338.75 1,246.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3.28 1,111.10 89.13% 0.00 0.00% 0.40 135.50 10.87%
01.05.11 PARASOLES
01.05.11.01 PARASOLES, ACERO DE REFUERZO FY=4200 KG/CM2 kg 503.08 4.58 2,304.11 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.11.02 PARASOLES, ENCOFRADO Y DESENCOFRADO m2 67.50 17.07 1,152.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.11.03 PARASOLES, CONCRETO F'C=210 KG/CM2 m3 3.38 305.81 1,033.64 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.12 MUROS DE CONTENCION
01.05.12.01 MUROS DE CONTENCION, ACERO DE REFUERZO FY=4200 KG/CM2 kg 13,203.56 4.58 60,472.30 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.12.02 MUROS DE CONTENCION, ENCOFRADO Y DESENCOFRADO m2 821.52 27.92 22,936.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.12.03 MUROS DE CONTENCION, CONCRETO F'C=210 KG/CM2 m3 49.60 336.75 16,702.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.12.04 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 m3 219.01 309.25 67,728.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.12.05 MUROS DE CONTENCION, CONCRETO F'C=175 KG/CM2 + 30% PG m3 8.36 226.47 1,893.29 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.13 CISTERNA SUBTERRANEA
01.05.13.01 TANQUE CISTERNA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 186.60 4.58 854.63 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.13.02 TANQUE CISTERNA, ENCOFRADO Y DESENCOFRADO m2 60.86 19.32 1,175.82 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.13.03 TANQUE CISTERNA, CONCRETO F'C=210 KG/CM2 m3 10.33 518.75 5,358.69 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.14 PLACAS Y LOSAS MACIZAS
01.05.14.01 PLACA Y LOSA MACIZA, ACERO DE REFUERZO FY=4200 KG/CM2 kg 268.73 4.58 1,230.78 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.14.02 PLACA Y LOSA MACIZA, ENCOFRADO Y DESENCOFRADO m2 149.96 26.57 3,984.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.05.14.03 PLACA Y LOSA MACIZA, CONCRETO F'C=210 KG/CM2 m3 5.81 305.81 1,776.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
01.06 MUROS Y TABIQUES DE ALBAÑILERIA
01.06.01 MUROS DE LADRILLO KK TIPO IV CABEZA M: 1:4, J:1.5CM m2 530.97 87.80 46,619.17 0.00 0.00% 0.00 0.00% 55.36 4,860.61 10.43% 24.98 2,193.24 4.70% 90.29 7,927.46 17.00% 69.08 6,065.22 13.01% 40.61 3,565.56 7.65%
01.06.02 MUROS DE LADRILLO KK TIPO IV SOGA M: 1:4, J:1.5CM m2 655.24 52.30 34,269.05 0.00 0.00% 0.00 0.00% 3.83 200.31 0.58% 21.45 1,121.84 3.27% 40.53 2,119.72 6.19% 26.00 1,359.80 3.97% 97.67 5,108.14 14.91%
01.06.03 ALAMBRE REFUERZO HORIZONTAL EN ALBAÑILERIA #8 kg 221.54 4.97 1,101.05 0.00 0.00% 0.00 0.00% 0.00 0.00% 87.93 437.01 39.69% 0.00 0.00% 0.00 0.00% 24.33 120.92 10.98%
01.06.04 MURO DE LADRILLO KK SOGA M:1:5 E=1.4 CM CARA VISTA UNA CARA m2 337.82 53.54 18,086.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02 ARQUITECTURA
02.01 REVOQUES ENLUCIDOS Y MOLDURAS
02.01.01 TARRAJEO PRIMARIO, MORTERO 1:5 C:A m2 277.27 11.51 3,191.38 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21.10 242.86 7.61% 0.00 0.00%
02.01.02 TARRAJEO EN MUROS INTERIOR, MORTERO 1:5 C:A m2 1,096.38 18.41 20,184.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 79.99 1,472.62 7.30% 458.16 8,434.73 41.79% 192.77 3,548.90 17.58%
02.01.03 TARRAJEO EN MUROS EXTERIOR, MORTERO 1:5 C:A m2 802.89 20.89 16,772.37 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 199.38 4,165.05 24.83% 110.12 2,300.41 13.72%
02.01.04 TARRAJEO EN COLUMNAS, MORTERO 1:5 C:A m2 771.80 16.55 12,773.29 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 298.39 4,938.35 38.66% 61.21 1,013.03 7.93%
02.01.05 TARRAJEO EN VIGAS, MORTERO 1:5 C:A m2 578.21 27.07 15,652.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 223.61 6,053.12 38.67% 35.90 971.81 6.21%
02.01.06 TARRAJEO EN MUROS DE SOSTENIMIENTO, MORTERO 1:5 C:A m2 155.22 23.25 3,608.87 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.01.07 TARRAJEO CON IMPERMEABILIZANTE m2 199.32 33.88 6,752.96 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 89.73 3,040.05 45.02% 19.78 670.15 9.92%
02.01.08 VESTIDURA DE DERRAMES 1:5 C:A m 619.43 5.42 3,357.31 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 287.63 1,558.95 46.43%
02.01.09 BRUÑAS SEGUN DETALLE 1 X 1CM m 2,306.69 3.12 7,196.87 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 85.65 267.23 3.71% 0.00 0.00% 996.92 3,110.39 43.22%
02.02 CIELO RASOS
02.02.01 CIELO RASO CON MEZCLA C:A 1:5 m2 1,282.25 27.94 35,826.07 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 108.04 3,018.64 8.43% 346.33 9,676.46 27.01% 93.11 2,601.49 7.26%
02.03 PISOS Y PAVIMENTOS
02.03.01 CONTRAPISO DE 40MM m2 788.95 20.55 16,212.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 366.58 7,533.22 46.46%
02.03.02 PISO PORCELANATO ANTIDESLIZANTE 0.60X0.60 m2 780.85 66.26 51,739.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 366.58 24,289.59 46.95%
02.03.03 PISO CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR m2 281.77 22.08 6,221.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 103.28 2,280.42 36.65%
02.03.04 REVESTIMIENTO DE MURO, TIPO LAJA m2 83.68 47.79 3,999.07 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.03.05 VEREDA CONCRETO F'C=175 KG/CM2 FROT. Y BRUÑADO m2 526.73 39.35 20,726.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 104.52 4,112.86 19.84%
02.03.06 CONCRETO EN LOSA DEPORTIVA F'C=175 KG/CM2 m3 81.42 344.35 28,036.98 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.03.07 CONCRETO EN DADOS DE ANCLAJE F'C=175 KG/CM2 m3 0.17 283.86 48.26 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.03.08 PISO ADOQUINADO m2 110.80 71.46 7,917.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.03.09 ENCOFRADO DE LOSAS DEPORTIVAS m2 86.49 32.25 2,789.30 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 7.68 247.68 8.88%
02.04 CONTRAZOCALOS
02.04.01 CONTRAZOCALO DE LOSETA VENECIANA COLOR CLARO 10X30CM m 19.10 24.06 459.55 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.04.02 CONTRAZOCALO S/COLOREAR H=30CM MEZCLA 1:2 E=1.5CM m 676.38 5.94 4,017.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 370.27 2,199.40 54.74%
02.05 ZOCALOS
02.05.01 ZOCALO DE MAYOLICA BLANCA 20X30 1RA m2 277.27 49.55 13,738.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 23.09 1,144.11 8.33%
02.06 CUBIERTAS
02.06.01 COBERTURA C/PLANCHA TIPO TEJA ANDINA m2 706.68 76.94 54,371.96 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 365.91 28,153.12 51.78%
02.06.02 CUMBRERA C/PLANCHA TIPO TEJA ANDINA m 60.40 72.66 4,388.66 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 30.75 2,234.30 50.91%
02.07 CARPINTERIA DE MADERA
02.07.01 PUERTA CEDRO MACHIMBRADA m2 63.91 539.53 34,481.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 28.16 15,193.16 44.06%
02.07.02 PUERTA CON TRIPLAY 9MM P/SSHH m2 12.04 270.32 3,254.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.08 CARPINTERIA METALICA
02.08.01 VENTANA DE ALUMINIO m2 176.97 25.00 4,424.25 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 101.57 2,539.25 57.39%
02.08.02 PASAMANO DE TUBO F°G° DE 2" m 15.70 54.72 859.10 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11.10 607.39 70.70%
02.08.03 CANTONERA DE FIERRO EN ESCALERA m 77.60 21.10 1,637.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 60.80 1,282.88 78.35%
02.08.04 ESCALERA DE GATO, TUBO F°G° 1 1/2" Y 1" TQE ELEVADO m 3.40 97.53 331.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.08.05 TAPA DE FIERRO EN CISTERNA und 1.00 323.43 323.43 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.08.06 PUERTA DE INGRESO PRINCIPAL C/PERFILES SEGUN DISEÑO und 1.00 13,879.33 13,879.33 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.08.07 BARANDA DE TUBO F°G° DE 2" m 233.80 98.98 23,141.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 46.10 4,562.98 19.72%
02.09 CERRAJERIA
02.09.01 BISAGRAS CAPUCHINA ALUMINIZADA DE 4" PESADA EN PUERTA pza 187.00 12.49 2,335.63 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 65.00 811.85 34.76%
02.09.02 CERRADURA DOS GOLPES EN PUERTA pza 29.00 70.04 2,031.16 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13.00 910.52 44.83%
02.09.03 MANIJA DE BRONCE 4" P/PUERTAS pza 29.00 11.12 322.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 13.00 144.56 44.83%
02.09.04 CANDADO TIPO FORTE 60MM pza 3.00 54.56 163.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.09.05 CERROJO DE 3" ALUMINIZADO P/PUERTA pza 14.00 7.94 111.16 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.10 VIDRIOS CRISTALES Y SIMILARES
02.10.01 VIDRIO SEMIDOBLE INCOLORO CRUDO p2 2,299.47 13.65 31,387.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,093.31 14,923.68 47.55%
02.11 PINTURAS
02.11.01 PINTURA LATEX 02 MANOS EN CIELO RASO m2 1,180.70 7.52 8,878.86 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 620.04 4,662.70 52.51%
02.11.02 PINTURA OLEO 2 MANOS EN VIGAS m2 578.21 5.66 3,272.67 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 259.51 1,468.83 44.88%
02.11.03 PINTURA OLEO 2 MANOS EN MUROS Y COLUMNAS m2 1,589.40 7.00 11,125.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 574.91 4,024.37 36.17%
02.11.04 PINTURA OLEO 2 MANOS EN DERRAMES m 619.43 3.87 2,397.19 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 287.63 1,113.13 46.43%
02.11.05 PINTURA BARNIZ 2 MANOS EN CARP. MADERA m2 75.95 10.82 821.78 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 28.16 304.69 37.08%
02.11.06 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALO DE CEMENTO H=30CM m 663.88 2.13 1,414.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 370.27 788.68 55.77%
02.11.07 PINTURA ESMALTE ENLOSA DEPORTIVA m 360.00 3.85 1,386.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.12 DRYWALL
02.12.01 PROVISION Y COLOCACION DE RIELES DE 90X25X0.90 m 10.23 37.71 385.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.12.02 PROVISION Y COLOCACION DE PARANTES 89X38X0.90 m 74.13 46.31 3,432.96 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.12.03 PROVISION Y COLOCACION DE PLACA GYPLAC DE 1/2" R.H. m2 49.90 50.34 2,511.97 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13 VARIOS
02.13.01 PIZARRA ACRILICA und 16.00 250.00 4,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 1,000.00 25.00%
02.13.02 TAPAJUNTA METALICA EN PISOS m 9.55 49.83 475.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.03 TAPAJUNTA METALICA ENTRE MODULOS (VERTICAL) m 30.00 19.82 594.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.04 JUNTA DILATACION RELLENO CON MORTERO ASFALTICO E=1" m 69.30 6.18 428.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.05 JUNTA DE CONSTRUCCION CON TECNOPORT m2 49.55 6.64 329.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12.29 81.61 24.80%
02.13.06 ARCO Y TABLERO FULBITO-BASKET S/DISEÑO und 2.00 2,514.52 5,029.04 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.07 NET CON SOPORTE F°G° D=3" + ACCESORIOS SUMINISTRO Y COLOCACI und 1.00 763.73 763.73 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.08 TANQUE DE POLIETILENO und 2.00 1,310.04 2,620.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
02.13.09 LETRERO METALICO DE IDENTIFICACION glb 1.00 1,500.00 1,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03 INSTALACIONES SANITARIAS
03.01 APARATOS SANITARIOS Y ACCESORIOS
03.01.01 INODORO TANQUE BAJO DE LOSA 1RA CALIDAD ADULTO pza 14.00 312.70 4,377.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 625.40 14.29%
03.01.02 LAVATORIO DE PARED BLANCO INC. ACCESORIOS pza 4.00 331.26 1,325.04 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 662.52 50.00%
03.01.03 URINARIO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 3.00 427.45 1,282.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.01.04 BEBEDERO CORRIDO S/DISEÑO REVEST. C/MAYOLICA 20X30CM m 7.40 491.15 3,634.51 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.01.05 DUCHA CROMADA DE CABEZA GIRATORIA und 4.00 52.96 211.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.02 INSTALACIONES SANITARIAS
03.02.01 SALIDA DESAGUE DE PVC SAL 2" pto 30.00 34.69 1,040.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 138.76 13.33%
03.02.02 SALIDA DESAGUE DE PVC SAL 4" pto 14.00 44.54 623.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 89.08 14.29%
03.02.03 SALIDA PARA VENTILACION pto 9.00 42.88 385.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 42.88 11.11%
03.02.04 TUBERIA DE PVC SAL 2" m 84.60 9.86 834.16 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6.00 59.16 7.09%
03.02.05 TUBERIA DE PVC SAL 4" m 94.00 14.13 1,328.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 15.00 211.95 15.96%
03.02.06 REGISTRO DE BRONCE 4" und 14.00 22.29 312.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 44.58 14.29%
03.02.07 SUMIDERO DE BRONCE ROSCADO 3" und 30.00 57.10 1,713.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 114.20 6.67%
03.02.08 CAJA SUMIDERO CON REJILLA DE FIERRO und 8.00 178.96 1,431.68 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.02.09 CAJA DE REGISTRO DESAGUE 12"X24" C/TAPA CONCRETO und 7.00 585.67 4,099.69 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 585.67 14.29%
03.03 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO
03.03.01 SALIDA DE AGUA FRIA TUBERIA PVC 1/2" pto 30.00 99.15 2,974.50 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 396.60 13.33%
03.03.02 TUBERIA PVC CLASE 10 - 1/2" m 60.50 8.49 513.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 169.80 33.06%
03.03.03 TUBERIA PVC CLASE 10 - 3/4" m 156.20 9.15 1,429.23 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03.04 VALVULA COMPUERTA DE BRONCE 1/2" und 7.00 136.69 956.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 136.69 14.29%
03.03.05 VALVULA COMPUERTA DE BRONCE 3/4" und 5.00 184.69 923.45 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 184.69 20.00%
03.03.06 VALVULA GLOBO DE 1/2" und 2.00 152.29 304.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03.07 REDUCCION PVC SAP 3/4" A 1/2" und 5.00 12.17 60.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 12.17 20.00%
03.03.08 CAJA DE MADERA PARA VALVULA und 1.00 43.91 43.91 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03.09 CAJA EN NICHO DE MAYOLICA PARA VALVULA und 7.00 18.97 132.79 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03.10 SUCCION E IMPULSION INCLUYE INSTALACION Y ACCESORIOS glb 1.00 4,363.32 4,363.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.03.11 REBOSE Y LIMPIA INCLUYE INSTALACION Y ACCESORIOS glb 1.00 1,365.36 1,365.36 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.04 SISTEMA DE AGUA DE LLUVIA Y SUBDREN
03.04.01 TUBERIA DE PVC SAP 3" P/LLUVIAS m 73.00 28.43 2,075.39 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 40.00 1,137.20 54.79%
03.04.02 FALSA COLUMNA/PROTECCION TUBERIA MONTANTE, CONCRETO F'C=17 m3 0.65 1,536.36 998.63 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.30 460.91 46.15%
03.04.03 CANALETA DE EVACUACION PLUVIAL, CONCRETO F'C=210 KG/CM2 m3 16.65 1,274.00 21,212.10 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.04.04 ENCOFRADO Y DESENCOFRADO, CANALETA DE EVACUACION PLUVIAL m2 111.03 42.04 4,667.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.04.05 TUBERIA DE PVC SAL 4" (PERFORADA) m 99.33 14.13 1,403.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
03.04.06 TUBERIA DE PVC SAL 6" (PERFORADA) m 65.05 19.23 1,250.91 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04 INSTALACIONES ELECTRICAS
04.01 SALIDA PARA ALUMBRADO
04.01.01 SALIDA PARA CENTRO DE LUZ EN TECHO pto 81.00 74.68 6,049.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 18.00 1,344.24 22.22% 21.00 1,568.28 25.93% 0.00 0.00% 40.00 2,987.20 49.38%
04.01.02 SALIDA PARA CENTRO DE LUZ EN PARED pto 42.00 74.68 3,136.56 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 149.36 4.76% 0.00 0.00% 0.00 0.00% 3.00 224.04 7.14%
04.01.03 SALIDA PARA INTERRUPTOR SIMPLE pto 33.00 79.63 2,627.79 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.00 1,592.60 60.61%
04.01.04 SALIDA PARA INTERRUPTOR DE CONMUTACION pto 6.00 115.22 691.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.02 SALIDA PARA TOMACORRIENTES
04.02.01 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 0 pto 125.00 95.89 11,986.25 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 68.00 6,520.52 54.40%
04.02.02 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION 1 pto 4.00 110.40 441.60 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.02.03 SALIDA PARA TOMACORRIENTE MONOFASICO, 15A, 220V, INSTALACION pto 30.00 87.59 2,627.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 30.00 2,627.70 100.00%
04.03 CAJAS Y TABLEROS
04.03.01 CAJA DE PASE 102X102X100 MM und 8.00 21.26 170.08 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.03.02 CAJA DE PASE 200X200X100 MM und 4.00 26.11 104.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.03.03 TABLERO DE 3X40A, 20 POLOS und 2.00 489.50 979.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.03.04 TABLERO DE 3X35A, 20 POLOS und 2.00 489.50 979.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2.00 979.00 100.00%
04.03.05 TABLERO DE 2X30A, 24 POLOS und 1.00 468.81 468.81 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 468.81 100.00%
04.03.06 TABLERO DE 2X10A, 8 POLOS und 1.00 259.61 259.61 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 259.61 100.00%
04.04 ARTEFACTOS
04.04.01 ARTEFACTO TIPO BRAQUETE CON 3 LAMPARAS FLUORECENTES DE 36W und 56.00 120.72 6,760.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 24.00 2,897.28 42.86%
04.04.02 ARTEFACTO CON LAMPARA FLUORECENTE CIRCULAR DE 32W und 24.00 114.30 2,743.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21.00 2,400.30 87.50%
04.04.03 ARTEFACTO TIPO BRAQUETE CON 2 LAMPARAS AHORRADORAS DE 18W und 42.00 94.12 3,953.04 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.00 376.48 9.52%
04.05 TABLEROS
04.05.01 TABLERO GENERAL TG 3X100A 28 POLOS und 1.00 915.01 915.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 915.01 100.00%
04.06 ALIMENTADORES
04.06.01 N2XH(3-1X50X1X50(N)X1X25(T))MM2 m 38.00 183.38 6,968.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 38.00 6,968.44 100.00%
04.06.02 N2XH(3-1X16X1X16(N)X1X10(T))MM2 m 116.00 65.86 7,639.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.06.03 N2XH(1X16X1X16(N)X1X10(T))MM2 m 37.00 37.38 1,383.06 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 37.00 1,383.06 100.00%
04.06.04 N2XH(1X6X1X6(N)X1X6(T))MM2 m 12.00 38.70 464.40 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12.00 464.40 100.00%
04.07 CIRCUITO DE TIMBRES
04.07.01 SALIDA PARA TIMBRES pto 2.00 142.72 285.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.08 SISTEMA DE PUESTA A TIERRA
04.08.01 PUESTA A TIERRA TIPO P-1 (R<15 OHMIOS) und 1.00 937.95 937.95 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.08.02 PUESTA A TIERRA TIPO P-2 (R<5 OHMIOS) und 4.00 1,114.95 4,459.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1.00 1,114.95 25.00%
04.08.03 CONDUCTOR DE COBRE DESNUDO DE 1X16MM2 und 62.00 9.56 592.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.08.04 PARARRAYO CON DISPOSITIVO DE CEBADO, C/03 P/TIERRA und 1.00 2,501.15 2,501.15 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.09 SISTEMA DE ALUMBRADO EXTERIOR
04.09.01 ILUMINACION DE LOZA DEPORTIVA und 4.00 1,886.43 7,545.72 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.10 OTROS EQUIPOS
04.10.01 ELECTROBOMBA PARA TANQUE ELEVADO und 2.00 958.22 1,916.44 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
04.10.02 INSTALACION DEMEDIDOR ELECTRICO und 1.00 794.40 794.40 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
05 EQUIPAMIENTO, MOBILIARIO Y MATERIAL EDUCATIVO
05.01 EQUIPOS glb 1.00 63,192.00 63,192.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
05.02 MOBILIARIO glb 1.00 64,806.01 64,806.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
05.03 MATERIAL EDUCATIVO glb 1.00 54,185.00 54,185.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
06 CAPACITACION
06.01 CAPACITACION glb 1.00 13,500.00 13,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
07 PLAN MANEJO AMBIENTAL
07.01 SEMBRADO DE GRASS m2 413.00 18.80 7,764.40 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
07.02 LIMPIEZA PERMANENTE DE OBRA glb 1.00 1,412.57 1,412.57 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.50 706.29 50.00% 0.00 0.00%
07.03 CAPACITACION EN TEMA AMBIENTAL A PERSONAL OBRERO glb 1.00 10,000.00 10,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
07.04 SEÑALIZACION AMBIENTAL EN OBRA glb 1.00 1,500.00 1,500.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
07.05 EQUIPAMIENTO PARA MITIGACION AMBIENTAL EN OBRA glb 1.00 950.70 950.70 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%
07.06 TRATAMIENTO DE BOTADEROS glb 1.00 3,000.00 3,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.50 1,500.00 50.00% 0.50 1,500.00 50.00%
COSTO DIRECTO 1,916,180.00 87,960.45 53,856.98 45,616.81 57,327.20 98,008.83 62,756.96 231,549.47
% DE AVANCE FISICO 4.59% 2.81% 2.38% 2.99% 5.11% 3.28% 12.08%
GASTOS GENERALES (14.95%) 119,617.50 5,490.93 3,362.02 2,847.63 3,578.65 6,118.20 3,917.60 14,454.47
GASTOS DE SUPERVISION (5.10%) 50,747.00 2,329.49 1,426.32 1,208.09 1,518.22 2,595.61 1,662.02 6,132.22
PRESUPUESTO TOTAL 2,086,544.50 95,780.87 58,645.32 49,672.53 62,424.06 106,722.64 68,336.58 252,136.16

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 12.16% 7.44% 6.30% 7.92% 13.55% 8.67% 32.00%
CRONOGRAMA DE EJECUCION DE ADICIONALES POR PARTIDAS NUEVAS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE DEL 09/03 AL 22/04 del 2015
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL %
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 115.47 3,271.27 100.00% 0.00 0.00%
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 279.8 3,855.64 66.97% 138.00 1,901.64 33.03%
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 125.91 6,809.21 66.97% 62.10 3,358.37 33.03%
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 265.7 3,661.35 100.00% 0.00 0.00%
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 132.85 10,398.17 100.00% 0.00 0.00%
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 26.5 1,345.14 100.00% 0.00 0.00%
01.03.16 ELIMIN. DE MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 3,240.30 28,935.88 100.00% 0.00 0.00%
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO DE FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 1,346.75 6,168.12 100.00% 0.00 0.00%
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 43.03 771.96 100.00% 0.00 0.00%
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 30.12 8,372.46 100.00% 0.00 0.00%
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00%
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00%
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00%
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00%
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00%
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00%
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00%
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00%
COSTO DIRECTO 85,464.54 0.00 0.00 0.00 0.00 73,589.19 0.00 5,260.01
% DE AVANCE FISICO 100% 0.00% 0.00% 0.00% 0.00% 86.10% 0.00% 6.15%
GASTOS GENERALES (14.95%) 6,739.47 0.00 0.00 0.00 0.00 5,803.02 0.00 414.79
GASTOS DE SUPERVISION (5.10%) 2,845.35 0.00 0.00 0.00 0.00 2,449.99 0.00 175.12
PRESUPUESTO TOTAL 95,049.36 0.00 0.00 0.00 0.00 81,842.19 0.00 5,849.92
CRONOGRAMA DE EJECUCION DE ADICIONALES POR MAYORES METRADOS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 AGOST SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE DEL 09/03 AL 22/04 del 2015
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL %
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 562.75 2,228.49 100.00%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 381.31 3,141.99 100.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 381.31 8,385.01 100.00%
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 11.84 1,959.16 100.00%
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 165.47 757.85 100.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 62.59 1,055.27 100.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 6.22 1,792.92 100.00%
COSTO DIRECTO 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00 0.00
% DE AVANCE FISICO 100% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 0.00 0.00 0.00 0.00 1,523.57 0.00 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 0.00 0.00 0.00 0.00 643.24 0.00 0.00
PRESUPUESTO TOTAL 21,487.50 0.00 0.00 0.00 0.00 21,487.50 0.00 0.00

COSTO DIRECTO OBRA PRINCIPAL 1,916,180.00 87,960.45 53,856.98 45,616.81 57,327.20 98,008.83 62,756.96 231,549.47
COSTO DIRECTO PARTIDAS NUEVAS 85,464.54 0.00 0.00 0.00 0.00 73,589.19 0.00 5,260.01
COSTO DIRECTO MAYORES METRADOS 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00 0.00

COSTO DIRECTO TOTAL 87,960.45 53,856.98 45,616.81 57,327.20 190,918.71 62,756.96 236,809.48

% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 12.16% 7.44% 6.30% 7.92% 26.39% 8.67% 32.73%
16500
9625
6875

9625
6875

También podría gustarte