OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 115.47 3,271.27 100.00% 0.00
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 417.8 5,757.28 100.00% 0.00
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 188.01 10,167.58 100.00% 0.00
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 265.7 3,661.35 100.00% 0.00
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 132.85 10,398.17 100.00% 0.00
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 26.5 1,345.14 100.00% 0.00
01.03.16 ELIMIN. MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,240.30 28,935.88 100.00% 0.00
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,346.75 6,168.12 100.00% 0.00
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 43.03 771.96 100.00% 0.00
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 30.12 8,372.46 100.00% 0.00
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 8.55 12.91
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 28.37 820.74
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 35.46 779.77
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 198.06 907.11
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 17.1 288.31
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4.21 1,213.53
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 21.2 1,767.66
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10.35 757.52
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1 67.78
COSTO DIRECTO 85,464.54 0.00 0.00 0.00 0.00 78,849.20 6,615.34
% DE AVANCE FISICO 0.00% 0.00% 0.00% 0.00% 92.26% 7.74%
GASTOS GENERALES (14.95%) 6,739.47 0.00 0.00 0.00 0.00 6,217.81 521.66
GASTOS DE SUPERVISION (5.10%) 2,845.35 0.00 0.00 0.00 0.00 2,625.11 220.24
PRESUPUESTO TOTAL 95,049.36 0.00 0.00 0.00 0.00 87,692.12 7,357.24
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 0.00% 0.00% 0.00% 0.00% 10.90% 0.91%
DICIEMBRE
%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
VALORIZACION DE ADICIONAL POR PARTIDAS NUEVAS FINAL (COSTO INICIAL)
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 115.47 3,271.27 100.00% 0.00 0.00% 115.47 3,271.27 100.00% 0.00 0.00 0.00%
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 279.8 3,855.64 66.97% 0.00 0.00% 279.80 3,855.64 66.97% 138.00 1,901.64 33.03%
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 125.91 6,809.21 66.97% 0.00 0.00% 125.91 6,809.21 66.97% 62.10 3,358.37 33.03%
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 265.7 3,661.35 100.00% 0.00 0.00% 265.70 3,661.35 100.00% 0.00 0.00 0.00%
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 132.85 10,398.17 100.00% 0.00 0.00% 132.85 10,398.17 100.00% 0.00 0.00 0.00%
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 26.5 1,345.14 100.00% 0.00 0.00% 26.50 1,345.14 100.00% 0.00 0.00 0.00%
01.03.16 ELIMINACION DE MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 3,240.30 28,935.88 100.00% 0.00 0.00% 3,240.30 28,935.88 100.00% 0.00 0.00 0.00%
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO DE REFUERZO FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 1,346.75 6,168.12 100.00% 0.00 0.00% 1,346.75 6,168.12 100.00% 0.00 0.00 0.00%
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 43.03 771.96 100.00% 0.00 0.00% 43.03 771.96 100.00% 0.00 0.00 0.00%
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 30.12 8,372.46 100.00% 0.00 0.00% 30.12 8,372.46 100.00% 0.00 0.00 0.00%
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.55 12.91 100.00%
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 28.37 820.74 100.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 35.46 779.77 100.00%
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 198.06 907.11 100.00%
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.10 288.31 100.00%
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.21 1,213.53 100.00%
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 21.20 1,767.66 100.00%
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 10.35 757.52 100.00%
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 67.78 100.00%
COSTO DIRECTO 85,464.54 73,589.19 0.00 73,589.19 11,875.34
% DE AVANCE FISICO 86.10% 0.00% 86.10% 13.90%
GASTOS GENERALES (14.95%) 6,739.47 5,803.02 0.00 5,803.02 936.45
GASTOS DE SUPERVISION (5.10%) 2,845.35 2,449.99 0.00 2,449.99 395.36
PRESUPUESTO TOTAL 95,049.36 81,842.19 0.00 81,842.19 13,207.16
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 10.17% 0.00% 10.17%
VALORIZACION DE ADICIONAL DE OBRA POR MAYORES METRADOS FINAL (COSTO INICIAL)
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO" DEL 01/04/2015 AL 22/04/2015
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
AVANCE ANTERIOR AVANCE MENSUAL AVANCE ACUMULADO SALDOS
Item Descripción Und. Metrado Precio s/. Parcial s/. CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL % CANTIDAD PARCIAL %
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 562.75 2,228.49 100.00% 0.00 0.00% 562.75 2,228.49 100.00% 0.00 0.00 0.00%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 381.31 3,141.99 100.00% 0.00 0.00% 381.31 3,141.99 100.00% 0.00 0.00 0.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 381.31 8,385.01 100.00% 0.00 0.00% 381.31 8,385.01 100.00% 0.00 0.00 0.00%
01.04 CONCRETO SIMPLE 0.00
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 11.84 1,959.16 100.00% 0.00 0.00% 11.84 1,959.16 100.00% 0.00 0.00 0.00%
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 165.47 757.85 100.00% 0.00 0.00% 165.47 757.85 100.00% 0.00 0.00 0.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 62.59 1,055.27 100.00% 0.00 0.00% 62.59 1,055.27 100.00% 0.00 0.00 0.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 6.22 1,792.92 100.00% 0.00 0.00% 6.22 1,792.92 100.00% 0.00 0.00 0.00%
COSTO DIRECTO 19,320.69 19,320.69 0.00 19,320.69 0.00
% DE AVANCE FISICO 100.00% 0.00% 100.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 1,523.57 0.00 1,523.57 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 643.24 0.00 643.24 0.00
PRESUPUESTO TOTAL 21,487.50 21,487.50 0.00 21,487.50 0.00
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 2.67% 0.00% 2.67%
RESUMEN DE VALORIZACION
COSTO DIRECTO OBRA PRINCIPAL COSTO INICIAL 1,916,180.00 405,527.27 0.00 405,527.27 1,510,652.75
COSTO DIRECTO OBRA PRINCIPAL COSTO ACTUALIZADO 1,595,318.87 249,690.32 0.00 249,690.32 1,345,628.56
COSTO DIRECTO PARTIDAS NUEVAS COSTO INICIAL 85,464.54 73,589.19 0.00 73,589.19 11,875.34
COSTO DIRECTO MAYORES METRADOS COSTO INICIAL 19,320.69 19,320.69 0.00 19,320.69 0.00
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 103.40% 0.00% 103.40%
CRONOGRAMA DE EJECUCION DE ADICIONAL DE OBRA POR MAYORES METRADOS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 562.75 2,228.49 100.00% 0.00
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 381.31 3,141.99 100.00% 0.00
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 381.31 8,385.01 100.00% 0.00
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11.84 1,959.16 100.00% 0.00
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 165.47 757.85 100.00% 0.00
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 62.59 1,055.27 100.00% 0.00
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6.22 1,792.92 100.00% 0.00
COSTO DIRECTO 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00
% DE AVANCE FISICO 0.00% 0.00% 0.00% 0.00% 100.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 0.00 0.00 0.00 0.00 1,523.57 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 0.00 0.00 0.00 0.00 643.24 0.00
PRESUPUESTO TOTAL 21,487.50 0.00 0.00 0.00 0.00 21,487.50 0.00
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 0.00% 0.00% 0.00% 0.00% 2.67% 0.00%
DICIEMBRE
%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
METRADOS EJECUTADOS DURANTE EL MES
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 56.05% 0.00% 56.05% 43.95%
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 12.16% 7.44% 6.30% 7.92% 13.55% 8.67% 32.00%
CRONOGRAMA DE EJECUCION DE ADICIONALES POR PARTIDAS NUEVAS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 MES DE AGOSTO MES DE SETIEMBRE MES DE OCTUBRE MES DE NOVIEMBRE MES DE DICIEMBRE DEL 09/03 AL 22/04 del 2015
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL %
01 ESTRUCTURAS
1.03 MOVIMIENTO DE TIERRAS
01.03.10 EXCAVACION PARA ZAPATAS CORRIDAS ARMADAS HASTA 2.3 m. m3 115.47 28.33 3,271.27 115.47 3,271.27 100.00% 0.00 0.00%
01.03.11 EXCAVACION C/MAQUINARIA DE ZANJAS P/DRENAJE TIPO OVER m3 417.8 13.78 5,757.28 279.8 3,855.64 66.97% 138.00 1,901.64 33.03%
01.03.12 DRENAJE TIPO OVER m3 188.01 54.08 10,167.58 125.91 6,809.21 66.97% 62.10 3,358.37 33.03%
01.03.13 EXCAV. C/MAQUINARIA DE ZANJAS P/DRENAJE C/TUB. PVC PERF. 8" m3 265.7 13.78 3,661.35 265.7 3,661.35 100.00% 0.00 0.00%
01.03.14 DRENAJE CON TUB. PVC PERFORADA Ø=8" m 132.85 78.27 10,398.17 132.85 10,398.17 100.00% 0.00 0.00%
01.03.15 PERFORACION Y VOLADURA EN ROCA FIJA m3 26.5 50.76 1,345.14 26.5 1,345.14 100.00% 0.00 0.00%
01.03.16 ELIMIN. DE MATERIAL PROCEDENTE EXCAV. MASICA C/MAQUINARIA m3 3,240.30 8.93 28,935.88 3,240.30 28,935.88 100.00% 0.00 0.00%
1.05 CONCRETO ARMADO
01.05.15 ZAPATAS CORRIDAS ARMADAS
01.05.15.01 ZAPATAS CORRIDAS ARMADAS, ACERO DE FY=4200 KG/CM2 kg 1,346.75 4.58 6,168.12 1,346.75 6,168.12 100.00% 0.00 0.00%
01.05.15.02 ZAPATAS CORRIDAS ARMADAS, ENCOFRADO Y DESENCOFRADO m2 43.03 17.94 771.96 43.03 771.96 100.00% 0.00 0.00%
01.05.15.03 ZAPATAS CORRIDAS ARMADAS, CONCRETO F'C=210 KG/CM2 m3 30.12 277.97 8,372.46 30.12 8,372.46 100.00% 0.00 0.00%
1.07 POZO DE PERCOLACIÓN
01.07.01 TRAZO Y REPLANTEO PRELIMINAR m2 8.55 1.51 12.91 0.00 0.00% 0.00 0.00%
01.07.02 EXCAVACIÓN MANUAL PARA ESTRUCTURAS m3 28.37 28.93 820.74 0.00 0.00% 0.00 0.00%
01.07.03 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 35.46 21.99 779.77 0.00 0.00% 0.00 0.00%
01.07.04 P. PERCOLADOR, ACERO DE REFUERZO FY=4200 KG/CM2 kg 198.06 4.58 907.11 0.00 0.00% 0.00 0.00%
01.07.05 P. PERCOLADOR, ENCOFRADO Y DESENCOFRADO m2 17.1 16.86 288.31 0.00 0.00% 0.00 0.00%
01.07.06 P. PERCOLADOR, CONCRETO F'C=175 KG/CM2 m3 4.21 288.25 1,213.53 0.00 0.00% 0.00 0.00%
01.07.07 MURO DE CABEZA LADRILLO CORRIENTE (9x 12 x 23) C / C:A 1:5 m2 21.2 83.38 1,767.66 0.00 0.00% 0.00 0.00%
01.07.08 MATERIAL FILTRANTE (FILTROS) P/POZO PERCOLADOR m3 10.35 73.19 757.52 0.00 0.00% 0.00 0.00%
01.07.09 TAPA DE C° A° DE 0.10x0.90x0.90 M und 1 67.78 67.78 0.00 0.00% 0.00 0.00%
COSTO DIRECTO 85,464.54 0.00 0.00 0.00 0.00 73,589.19 0.00 5,260.01
% DE AVANCE FISICO 100% 0.00% 0.00% 0.00% 0.00% 86.10% 0.00% 6.15%
GASTOS GENERALES (14.95%) 6,739.47 0.00 0.00 0.00 0.00 5,803.02 0.00 414.79
GASTOS DE SUPERVISION (5.10%) 2,845.35 0.00 0.00 0.00 0.00 2,449.99 0.00 175.12
PRESUPUESTO TOTAL 95,049.36 0.00 0.00 0.00 0.00 81,842.19 0.00 5,849.92
CRONOGRAMA DE EJECUCION DE ADICIONALES POR MAYORES METRADOS
OBRA: "MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA IE Nª 38262/MX-P CARMEN SOTO FLORES DEL CENTRO POBLADO DE UYUVIRCA, DISTRITO DE HUANTA, PROVINCIA DE HUANTA - AYACUCHO"
UBICACIÓN UYUVIRCA-HUANTA-HUANTA-AYACUCHO
SUPERVISON: ING. ABDEL QUISPE HUAMAN
RESIDENTE: ING. VLADIMIR SICHA PINO
DEL 23/06 AL 31/07 AGOST SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE DEL 09/03 AL 22/04 del 2015
Item Descripción Und. Metrado Precio s/. Parcial s/. CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL % CANT PARCIAL %
01.03 MOVIMIENTO DE TIERRAS
01.03.04 RELLENO Y COMPACT. MANUAL C/MAT. PROPIO m3 562.75 3.96 2,228.49 562.75 2,228.49 100.00%
01.03.07 ACARREO INTERNO DE MAT. PROCEDENTE DE EXC. m3 381.31 8.24 3,141.99 381.31 3,141.99 100.00%
01.03.08 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 381.31 21.99 8,385.01 381.31 8,385.01 100.00%
01.04 CONCRETO SIMPLE
01.04.01 CONCRETO FC´=140 KG/CM2 + 30%PG. EN FALSA ZAPATA m3 11.84 165.47 1,959.16 11.84 1,959.16 100.00%
01.05 CONCRETO ARMADO
01.05.02 SOBRECIMIENTO REFORZADO
01.05.02.01 SOBREC. REFORZADO, ACERO DE REFUERZO FY=4200 KG/CM2 kg 165.47 4.58 757.85 165.47 757.85 100.00%
01.05.02.02 SOBREC. REFORZADO, ENCOFRADO Y DESENCOFRADO m2 62.59 16.86 1,055.27 62.59 1,055.27 100.00%
01.05.02.03 SOBREC. REFORZADO, CONCRETO F'C=175 KG/CM2 m3 6.22 288.25 1,792.92 6.22 1,792.92 100.00%
COSTO DIRECTO 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00 0.00
% DE AVANCE FISICO 100% 0.00% 0.00% 0.00% 0.00% 100.00% 0.00% 0.00%
GASTOS GENERALES (14.95%) 1,523.57 0.00 0.00 0.00 0.00 1,523.57 0.00 0.00
GASTOS DE SUPERVISION (5.10%) 643.24 0.00 0.00 0.00 0.00 643.24 0.00 0.00
PRESUPUESTO TOTAL 21,487.50 0.00 0.00 0.00 0.00 21,487.50 0.00 0.00
COSTO DIRECTO OBRA PRINCIPAL 1,916,180.00 87,960.45 53,856.98 45,616.81 57,327.20 98,008.83 62,756.96 231,549.47
COSTO DIRECTO PARTIDAS NUEVAS 85,464.54 0.00 0.00 0.00 0.00 73,589.19 0.00 5,260.01
COSTO DIRECTO MAYORES METRADOS 19,320.69 0.00 0.00 0.00 0.00 19,320.69 0.00 0.00
COSTO DIRECTO TOTAL 87,960.45 53,856.98 45,616.81 57,327.20 190,918.71 62,756.96 236,809.48
% DE AVANCE FISICO EN COMPARACION A LA PRIMERA ETAPA COSTO DIRECTO 723,525.84 12.16% 7.44% 6.30% 7.92% 26.39% 8.67% 32.73%
16500
9625
6875
9625
6875