Está en la página 1de 151

PROGRES PEKERJAAN MINGGUAN

PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR


SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 50.00% 0.11% 50.00% 0.11% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 50.00% 0.06% 30.00% 0.03% 80.00% 0.09%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 95.00% 0.11% 5.00% 0.01% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 90.00% 0.02% 10.00% 0.00% 100.00% 0.02%
7 Listrik, air kerja dan telpon Is 1.00 0.17% 35.00% 0.06% 35.00% 0.06% 70.00% 0.12%
8 Keamanan proyek Is 1.00 0.11% 0.03% 0.00% 0.03% 0.00% 0.05% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.04% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 75.00% 0.02% 25.00% 0.01% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.04% 0.00%

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 90.00% 0.20% 10.00% 0.02% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 50.00% 0.47% 25.00% 0.23% 75.00% 0.70%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 40.00% 0.04% 35.00% 0.03% 75.00% 0.07%

2 Pekerjaan Galian

409984289.xls Page 1
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 0.00% 0.00% 0.00% 0.00%
2 . Galian pondasi setempat m3 205.70 0.30% 75.00% 0.22% 20.00% 0.06% 95.00% 0.28%
3 . Galian beam m3 112.50 0.16% 75.00% 0.12% 20.00% 0.03% 95.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 0.00% 0.00% 10.00% 0.00% 10.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 40.00% 0.19% 40.00% 0.19% 80.00% 0.38%

SUB TOTAL III.b

409984289.xls Page 2
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 0.00% 0.00% 0.00% 0.00%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 0.00% 0.00% 0.00% 0.00%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 50.00% 0.02% 50.00% 0.02% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 50.00% 1.56% 35.00% 1.09% 85.00% 2.65%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 50.00% 0.12% 40.00% 0.09% 90.00% 0.21%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 0.00% 0.00% 40.00% 1.20% 40.00% 1.20%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 20.00% 0.75% 25.00% 0.94% 45.00% 1.69%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 3
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 4
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 5
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 6
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 7
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 8
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 9
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 10
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 11
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 12
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 13
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 14
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 0.00% 0.00% 10.00% 0.01% 10.00% 0.01%
2 Instalasi air kotor ls 1.00 0.25% 0.00% 0.00% 5.00% 0.01% 5.00% 0.01%
3 Instalasi drain AC ls 27.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Instalasi Air hujan ls 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Resapan ls 1.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 15
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 16
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 17
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 60.00% 1.98% 40.00% 1.32% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 65.00% 3.21% 35.00% 1.73% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 18
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SATUAN VOL. KET
MINGGU LALU MUNGGU INI TOTAL
SUB TOTAL XIII 100% 12.60% 9.33% 5.95% 0.07 18.55 0.17

409984289.xls Page 19
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 80.00% 0.09% 3.00% 0.00% 83.00% 0.09%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 70.00% 0.12% 10.00% 0.02% 80.00% 0.13%
8 Keamanan proyek Is 1.00 0.11% 0.05% 0.00% 0.05% 0.00% 0.10% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.04% 0.00% 0.02% 0.00% 0.06% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.00% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 75.00% 0.70% 15.00% 0.14% 90.00% 0.84%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 75.00% 0.07% 15.00% 0.01% 90.00% 0.08%

2 Pekerjaan Galian

409984289.xls Page 20
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
2 . Galian pondasi setempat m3 205.70 0.30% 95.00% 0.28% 5.00% 0.01% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 95.00% 0.16% 5.00% 0.01% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 10.00% 0.00% 5.00% 0.00% 15.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi

3 Pekerjaan Anti Rayap m2 707.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi

SUB TOTAL III.b

409984289.xls Page 21
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 85.00% 2.65% 10.00% 0.31% 95.00% 2.97%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 90.00% 0.21% 10.00% 0.02% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 15.00% 0.45% 0.00% 0.00% 15.00% 0.45% Revisi
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 45.00% 1.69% 25.00% 0.94% 70.00% 2.62%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 22
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 23
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 24
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 25
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 26
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 27
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 28
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 29
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 30
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 31
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 32
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 33
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 0.00% 0.00% 10.00% 0.01%
2 Instalasi air kotor ls 1.00 0.25% 5.00% 0.01% 5.00% 0.01% 10.00% 0.02%
3 Instalasi drain AC ls 27.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Instalasi Air hujan ls 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 0.00% 0.00% 30.00% 0.06% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 0.00% 0.00% 30.00% 0.02% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 34
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 35
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 36
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 0.00% 0.00% 15.00% 0.00% 15.00% 0.00%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 37
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
SUB TOTAL XIII 100% 14.50% 15.32% 1.83% 2% 16.33 17%

409984289.xls Page 38
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 83.00% 0.09% 3.00% 0.00% 86.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 80.00% 0.13% 2.50% 0.00% 82.50% 0.14%
8 Keamanan proyek Is 1.00 0.11% 0.10% 0.00% 0.02% 0.00% 0.12% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.06% 0.00% 0.15% 0.00% 0.21% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.00% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 90.00% 0.84% 10.00% 0.09% 100.00% 0.93%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 90.00% 0.08% 10.00% 0.01% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 39
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 0.00% 0.00% 100.00% 0.01% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 0.00% 0.00% 70.00% 0.33% 70.00% 0.33%

SUB TOTAL III.b

409984289.xls Page 40
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 0.00% 0.00% 100.00% 0.02% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 0.00% 0.00% 100.00% 0.06% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 0.00% 0.00% 100.00% 0.04% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 95.00% 2.97% 5.00% 0.16% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 15.00% 0.45% 65.00% 1.94% 80.00% 2.39%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 0.00% 0.00% 5.00% 0.03% 5.00% 0.03%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 0.00% 0.00% 20.00% 0.84% 20.00% 0.84%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 70.00% 2.62% 5.00% 0.19% 75.00% 2.81%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 41
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 42
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 43
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 0.00% 0.00% 80.00% 1.52% 80.00% 1.52%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 44
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 45
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 46
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 47
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 48
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 49
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 50
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 51
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 52
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 0.00% 0.00% 10.00% 0.01%
2 Instalasi air kotor ls 1.00 0.25% 10.00% 0.02% 2.50% 0.01% 12.50% 0.03%
3 Instalasi drain AC ls 27.00 0.15% 0.00% 0.00% 5.00% 0.01% 5.00% 0.01%
4 Instalasi Air hujan ls 1.00 0.28% 0.00% 0.00% 5.00% 0.01% 5.00% 0.01%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 53
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 54
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 55
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 56
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
SUB TOTAL XIII 100% 16.33% 16.89% 6.88% 5% 23.21 22%

409984289.xls Page 57
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 86.00% 0.10% 0.00% 0.00% 86.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 82.50% 0.14% 0.00% 0.00% 82.50% 0.14%
8 Keamanan proyek Is 1.00 0.11% 0.12% 0.00% 0.02% 0.00% 0.14% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.21% 0.00% 0.10% 0.00% 0.31% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 100.00% 0.93% 0.00% 0.00% 100.00% 0.93%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 58
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 70.00% 0.33% 15.00% 0.07% 85.00% 0.40%

SUB TOTAL III.b

409984289.xls Page 59
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 100.00% 3.12% 0.00% 0.00% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 80.00% 2.39% 5.00% 0.15% 85.00% 2.54%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 5.00% 0.03% 5.00% 0.03% 10.00% 0.06%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 20.00% 0.84% 40.00% 1.67% 60.00% 2.51%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 75.00% 2.81% 5.00% 0.19% 80.00% 3.00%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 0.00% 0.00% 65.00% 3.26% 65.00% 3.26%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 0.00% 0.00% 10.00% 0.38% 10.00% 0.38%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 60
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 61
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 62
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 80.00% 1.52% 10.00% 0.19% 90.00% 1.71%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 63
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 64
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 65
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 66
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 67
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 68
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 69
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 70
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 71
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 0.00% 0.00% 10.00% 0.01%
2 Instalasi air kotor ls 1.00 0.25% 12.50% 0.03% 2.50% 0.01% 15.00% 0.04%
3 Instalasi drain AC ls 27.00 0.15% 0.00% 0.00% 5.00% 0.01% 5.00% 0.01%
4 Instalasi Air hujan ls 1.00 0.28% 5.00% 0.01% 5.00% 0.01% 10.00% 0.03%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 72
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 73
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 74
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 15.00% 0.00% 5.00% 0.00% 20.00% 0.01%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 0.00% 0.00% 10.00% 0.02% 10.00% 0.02%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 75
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MUNGGU INI TOTAL
SUB TOTAL XIII 100% 23.16% 22.15% 1.83% 6% 24.99 28%

409984289.xls Page 76
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 86.00% 0.10% 0.00% 0.00% 86.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 82.50% 0.14% 0.00% 0.00% 82.50% 0.14%
8 Keamanan proyek Is 1.00 0.11% 0.14% 0.00% 0.02% 0.00% 0.16% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.31% 0.00% 0.10% 0.00% 0.41% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 100.00% 0.93% 0.00% 0.00% 100.00% 0.93%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 77
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 85.00% 0.40% 15.00% 0.07% 100.00% 0.48%

SUB TOTAL III.b

409984289.xls Page 78
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 100.00% 3.12% 0.00% 0.00% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 85.00% 2.54% 5.00% 0.15% 90.00% 2.69%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 10.00% 0.06% 40.00% 0.24% 50.00% 0.29%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 60.00% 2.51% 30.00% 1.25% 90.00% 3.76%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 80.00% 3.00% 5.00% 0.19% 85.00% 3.19%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 65.00% 3.26% 35.00% 1.76% 100.00% 5.02%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 10.00% 0.38% 40.00% 1.53% 50.00% 1.91%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 79
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 0.00% 0.00% 10.00% 0.02% 10.00% 0.02%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 80
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 81
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 90.00% 1.71% 0.00% 0.00% 90.00% 1.71%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 82
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 83
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 84
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 85
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 86
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 87
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 88
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 89
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 90
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 0.00% 0.00% 100.00% 0.25% 100.00% 0.25%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 0.00% 0.00% 10.00% 0.01%
2 Instalasi air kotor ls 1.00 0.25% 15.00% 0.04% 0.00% 0.00% 15.00% 0.04%
3 Instalasi drain AC ls 27.00 0.15% 5.00% 0.01% 5.00% 0.01% 10.00% 0.02%
4 Instalasi Air hujan ls 1.00 0.28% 10.00% 0.03% 5.00% 0.01% 15.00% 0.04%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 91
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 92
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 93
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 20.00% 0.01% 0.00% 0.00% 20.00% 0.01%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 10.00% 0.02% 0.00% 0.00% 10.00% 0.02%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 94
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
SUB TOTAL XIII 100% 24.99% 28.14% 2.90% 5% 27.89 34%

409984289.xls Page 95
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 86.00% 0.10% 0.00% 0.00% 86.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 82.50% 0.14% 0.00% 0.00% 82.50% 0.14%
8 Keamanan proyek Is 1.00 0.11% 0.14% 0.00% 0.02% 0.00% 0.16% 0.00%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.31% 0.00% 0.10% 0.00% 0.41% 0.00%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua


hal yang diperlukan untuk mendapat hasil yang baik dari beton
jadi
a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai m3 278.00 0.93% 100.00% 0.93% 0.00% 0.00% 100.00% 0.93%
mencapai level, ukuran luas dan kepadatan sesuai yg telah
ditentukan
2 . Urugan kembali bekas galian m3 124.50 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 96
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%
5 . Galian septick tank & resapan m3 25.80 0.04% 0.00% 0.00% 10.00% 0.00% 10.00% 0.00%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 100.00% 0.48% 0.00% 0.00% 100.00% 0.48%

SUB TOTAL III.b

409984289.xls Page 97
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 100.00% 3.12% 0.00% 0.00% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 90.00% 2.69% 5.00% 0.15% 95.00% 2.84%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 50.00% 0.29% 30.00% 0.18% 80.00% 0.47%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 90.00% 3.76% 5.00% 0.21% 95.00% 3.97%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 85.00% 3.19% 5.00% 0.19% 90.00% 3.37%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 100.00% 5.02% 0.00% 0.00% 100.00% 5.02%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 0.00% 0.00% 25.00% 0.11% 25.00% 0.11%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 50.00% 1.91% 50.00% 1.91% 100.00% 3.82%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 0.00% 0.00% 75.00% 0.00% 75.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 98
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 0.00% 0.00% 20.00% 0.05% 20.00% 0.05%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 10.00% 0.02% 55.00% 0.11% 65.00% 0.13%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 0.00% 0.00% 60.00% 2.17% 60.00% 2.17%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 0.00% 0.00% 30.00% 0.86% 30.00% 0.86%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 99
PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Pertemuan Dengan Dinding)

409984289.xls Page 100


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 90.00% 1.71% 0.00% 0.00% 90.00% 1.71%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 101


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 102


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 103


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 104


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00%


(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 105


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)

409984289.xls Page 106


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 107


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 10.00% 0.12% 10.00% 0.12%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 10.00% 0.06% 10.00% 0.06%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 108


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 10.00% 0.02% 10.00% 0.02%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 10.00% 0.00% 10.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 109


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 100.00% 0.25% 0.00% 0.00% 100.00% 0.25%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 10.00% 0.01% 20.00% 0.02%
2 Instalasi air kotor ls 1.00 0.25% 15.00% 0.04% 2.50% 0.01% 17.50% 0.04%
3 Instalasi drain AC ls 27.00 0.15% 10.00% 0.02% 2.50% 0.00% 12.50% 0.02%
4 Instalasi Air hujan ls 1.00 0.28% 15.00% 0.04% 10.00% 0.03% 25.00% 0.07%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 110


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 111


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 112


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

XII. ITEM KOMPENSASI

Item - item pekerjaan yang belum/tidak tercantum dalam bill


of item tetapi menurut kontraktor dianggap perlu untuk
dicantumkan (ada dalam gambar atau tidak ada
tetapimerupakan basic dari konstruksi) bisa dimasukkan
dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 20.00% 0.01% 0.00% 0.00% 20.00% 0.01%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 m2 43.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 10.00% 0.02% 0.00% 0.00% 10.00% 0.02%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.

409984289.xls Page 113


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
SUB TOTAL XIII 100% 27.89% 33.61% 4.35% 6% 32.24 40%

409984289.xls Page 114


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 90.00% 0.10% 2.00% 0.00% 92.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 82.50% 0.14% 0.00% 0.00% 82.50% 0.14%
8 Keamanan proyek Is 1.00 0.11% 0.16% 0.00% 39.84% 0.04% 40.00% 0.04%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 0.41% 0.00% 39.59% 0.04% 40.00% 0.04%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.02% 0.00% 0.02% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua hal yang
diperlukan untuk mendapat hasil yang baik dari beton jadi

a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai mencapai m3 278.00 0.93% 100.00% 0.93% 0.00% 0.00% 100.00% 0.93%
level, ukuran luas dan kepadatan sesuai yg telah ditentukan

2 . Urugan kembali bekas galian m3 124.50 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 115


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 15.00% 0.00% 45.00% 0.01% 60.00% 0.02%
5 . Galian septick tank & resapan m3 25.80 0.04% 10.00% 0.00% 10.00% 0.00% 20.00% 0.01%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 100.00% 0.48% 0.00% 0.00% 100.00% 0.48%

SUB TOTAL III.b

409984289.xls Page 116


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 100.00% 3.12% 0.00% 0.00% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 95.00% 2.84% 5.00% 0.15% 100.00% 2.99%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 80.00% 0.47% 20.00% 0.12% 100.00% 0.59%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 95.00% 3.97% 5.00% 0.21% 100.00% 4.18%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 90.00% 3.37% 10.00% 0.37% 100.00% 3.75%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 100.00% 5.02% 0.00% 0.00% 100.00% 5.02%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 25.00% 0.11% 75.00% 0.33% 100.00% 0.44%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 0.00% 0.00% 70.00% 0.04% 70.00% 0.04%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 100.00% 3.82% 0.00% 0.00% 100.00% 3.82%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 75.00% 0.00% 15.00% 0.00% 90.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 117


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 20.00% 0.05% 65.00% 0.18% 85.00% 0.23%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

8 Pekerjaan talang baja m' 26.00 0.20% 55.00% 0.11% 45.00% 0.09% 100.00% 0.20%

9 Pekerjaan waterproofing m' 103.00 0.06% 0.00% 0.00% 80.00% 0.05% 80.00% 0.05%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 60.00% 2.17% 25.00% 0.90% 85.00% 3.07%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 30.00% 0.86% 50.00% 1.44% 80.00% 2.31%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 0.00% 0.00% 45.00% 0.16% 45.00% 0.16%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 0.00% 0.00% 60.00% 0.01% 60.00% 0.01%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 0.00% 0.00% 50.00% 0.01% 50.00% 0.01%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 0.00% 0.00% 60.00% 1.45% 60.00% 1.45%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 118


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 0.00% 0.00% 40.00% 0.11% 40.00% 0.11%
(Pertemuan Dengan Dinding)

409984289.xls Page 119


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 90.00% 1.71% 10.00% 0.19% 100.00% 1.90%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 0.00% 0.00% 70.00% 0.02% 70.00% 0.02%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 0.00% 0.00% 50.00% 0.07% 50.00% 0.07%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 0.00% 0.00% 65.00% 3.86% 65.00% 3.86%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 0.00% 0.00% 75.00% 0.96% 75.00% 0.96%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 0.00% 0.00% 50.00% 0.08% 50.00% 0.08%

409984289.xls Page 120


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 0.00% 0.00% 45.00% 0.14% 45.00% 0.14%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 121


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 0.00% 0.00% 70.00% 0.20% 70.00% 0.20%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 0.00% 0.00% 70.00% 0.10% 70.00% 0.10%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 0.00% 0.00% 20.00% 0.05% 20.00% 0.05%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 0.00% 0.00% 20.00% 0.10% 20.00% 0.10%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 122


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 0.00% 0.00% 20.00% 0.04% 20.00% 0.04%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 0.00% 0.00% 70.00% 0.11% 70.00% 0.11%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 0.00% 0.00% 70.00% 0.19% 70.00% 0.19%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 0.00% 0.00% 70.00% 0.08% 70.00% 0.08%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 0.00% 0.00% 70.00% 0.11% 70.00% 0.11%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 0.00% 0.00% 70.00% 0.73% 70.00% 0.73%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 123


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 0.00% 0.00% 70.00% 0.39% 70.00% 0.39%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 0.00% 0.00% 70.00% 0.44% 70.00% 0.44%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 124


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 0.00% 0.00% 70.00% 0.08% 70.00% 0.08%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 0.00% 0.00% 70.00% 0.91% 70.00% 0.91%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 0.00% 0.00% 70.00% 0.10% 70.00% 0.10%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 0.00% 0.00% 70.00% 0.03% 70.00% 0.03%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 0.00% 0.00% 70.00% 0.07% 70.00% 0.07%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 0.00% 0.00% 70.00% 0.14% 70.00% 0.14%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 0.00% 0.00% 70.00% 0.06% 70.00% 0.06%
(Kusen solid wood ex.Merbau)

409984289.xls Page 125


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 0.00% 0.00% 70.00% 0.32% 70.00% 0.32%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 126


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 0.00% 0.00% 70.00% 0.01% 70.00% 0.01%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 0.00% 0.00% 70.00% 0.14% 70.00% 0.14%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 0.00% 0.00% 70.00% 0.03% 70.00% 0.03%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 0.00% 0.00% 70.00% 0.09% 70.00% 0.09%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 0.00% 0.00% 70.00% 0.08% 70.00% 0.08%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 0.00% 0.00% 60.00% 0.04% 60.00% 0.04%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 0.00% 0.00% 60.00% 0.00% 60.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 0.00% 0.00% 60.00% 0.01% 60.00% 0.01%
10 Instalasi Titik lampu titik 290.00 1.16% 0.00% 0.00% 60.00% 0.69% 60.00% 0.69%
11 Instalasi Power outlet titik 139.00 0.59% 0.00% 0.00% 60.00% 0.36% 60.00% 0.36%
12 Instalasi Outlet Data titik 67.00 0.56% 0.00% 0.00% 60.00% 0.34% 60.00% 0.34%

409984289.xls Page 127


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 0.00% 0.00% 60.00% 0.14% 60.00% 0.14%
14 Instalasi Power AC titik 27.00 0.22% 0.00% 0.00% 60.00% 0.13% 60.00% 0.13%
15 Instalasi RCA titik 16.00 0.08% 0.00% 0.00% 45.00% 0.04% 45.00% 0.04%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 0.00% 0.00% 45.00% 0.03% 45.00% 0.03%
17 Instalasi Pompa air titik 1.00 0.01% 0.00% 0.00% 60.00% 0.00% 60.00% 0.00%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 0.00% 0.00% 20.00% 0.00% 20.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 0.00% 0.00% 20.00% 0.00% 20.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 0.00% 0.00% 20.00% 0.00% 20.00% 0.00%

409984289.xls Page 128


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 0.00% 0.00% 20.00% 0.00% 20.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 0.00% 0.00% 45.00% 0.05% 45.00% 0.05%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 0.00% 0.00% 45.00% 0.07% 45.00% 0.07%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 0.00% 0.00% 15.00% 0.01% 15.00% 0.01%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 0.00% 0.00% 25.00% 0.00% 25.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 0.00% 0.00% 15.00% 0.01% 15.00% 0.01%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 0.00% 0.00% 15.00% 0.00% 15.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 0.00% 0.00% 15.00% 0.01% 15.00% 0.01%
29 AC 0.5 PK unit 2.00 0.17% 0.00% 0.00% 15.00% 0.02% 15.00% 0.02%
30 AC 1 PK unit 2.00 0.19% 0.00% 0.00% 15.00% 0.03% 15.00% 0.03%
31 AC 1,5 PK unit 3.00 0.38% 0.00% 0.00% 15.00% 0.06% 15.00% 0.06%
32 AC 2 PK unit 18.00 3.26% 0.00% 0.00% 15.00% 0.49% 15.00% 0.49%
33 AC 2.5 PK unit 2.00 0.49% 0.00% 0.00% 15.00% 0.07% 15.00% 0.07%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 0.00% 0.00% 20.00% 0.07% 20.00% 0.07%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 0.00% 0.00% 20.00% 0.08% 20.00% 0.08%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 100.00% 0.25% 0.00% 0.00% 100.00% 0.25%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 10.00% 0.01% 40.00% 0.04% 50.00% 0.06%
2 Instalasi air kotor ls 1.00 0.25% 15.00% 0.04% 55.00% 0.14% 70.00% 0.17%
3 Instalasi drain AC ls 27.00 0.15% 10.00% 0.02% 40.00% 0.06% 50.00% 0.08%
4 Instalasi Air hujan ls 1.00 0.28% 15.00% 0.04% 55.00% 0.15% 70.00% 0.20%
5 Instalasi Exhaus fan ls 1.00 0.15% 0.00% 0.00% 60.00% 0.09% 60.00% 0.09%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 0.00% 0.00% 50.00% 0.01% 50.00% 0.01%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 0.00% 0.00% 80.00% 0.03% 80.00% 0.03%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 0.00% 0.00% 20.00% 0.01% 20.00% 0.01%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 129


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 130


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 0.00% 0.00% 90.00% 0.40% 90.00% 0.40%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 0.00% 0.00% 90.00% 0.21% 90.00% 0.21%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 0.00% 0.00% 100.00% 0.14% 100.00% 0.14%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

409984289.xls Page 131


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

XII. ITEM KOMPENSASI


Item - item pekerjaan yang belum/tidak tercantum dalam bill of item
tetapi menurut kontraktor dianggap perlu untuk dicantumkan (ada
dalam gambar atau tidak ada tetapimerupakan basic dari konstruksi)
bisa dimasukkan dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 20.00% 0.01% 80.00% 0.02% 100.00% 0.03%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 cm) m2 43.00 0.09% 0.00% 0.00% 80.00% 0.07% 80.00% 0.07%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 0.00% 0.00% 40.00% 0.02% 40.00% 0.02%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 0.00% 0.00% 15.00% 0.03% 15.00% 0.03%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 10.00% 0.02% 90.00% 0.14% 100.00% 0.16%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.
SUB TOTAL XIII 100% 31.53% 39.54% 48.06% 20% 79.60 60%

409984289.xls Page 132


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
% VALUE % VALUE % VALUE
0% 0.00% 0.00%

I. PEKERJAAN PRELIMINARY

1 Mobilisasi dan Demobilisasi Is 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%
2 Pembersihan lokasi Is 1.00 0.11% 92.00% 0.10% 0.00% 0.00% 92.00% 0.10%
3 Bangunan penunjang sementara (direksi keet) Is 1.00 0.11% 100.00% 0.11% 0.00% 0.00% 100.00% 0.11%
4 Uitzet & bouwplank Is 1.00 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
5 Gambar2 kerja (shop drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
6 Gambar2 kenyataan (as built drawing) Is 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi
7 Listrik, air kerja dan telpon Is 1.00 0.17% 82.50% 0.14% 7.50% 0.01% 90.00% 0.15%
8 Keamanan proyek Is 1.00 0.11% 40.00% 0.04% 40.00% 0.04% 80.00% 0.09%
9 Pengelolaan kebersihan lapangan Is 1.00 0.11% 40.00% 0.04% 40.00% 0.04% 80.00% 0.09%
10 Pengukuran (setting out) Is 1.00 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
11 Masa pemeliharaan Is 1.00 0.11% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Revisi

II. PEKERJAAN BONGKARAN

a. Pekerjaan Bongkaran ls 1.00


1 Bongkar bangunan existing ls 1.00
2 Bongkar pagar depan ls 1.00
3 Bongkar paving ls 1.00
4 Bongkar planter box ls 1.00

III. PEKERJAAN STRUKTUR

Harga satuan termasuk pengujian, proteksi, coring dan semua hal yang
diperlukan untuk mendapat hasil yang baik dari beton jadi

a. Pekerjaan Perhitungan Struktur

1 Pekerjaan Perhitungan Struktur ls 1.00 0.22% 100.00% 0.22% 0.00% 0.00% 100.00% 0.22%

SUB TOTAL III.a


b. Pekerjaan Galian dan Urugan
1 Pekerjaan Urugan
1 . Pegurugan dan pemadatan "sirtu" atau pasir urug sampai mencapai m3 278.00 0.93% 100.00% 0.93% 0.00% 0.00% 100.00% 0.93%
level, ukuran luas dan kepadatan sesuai yg telah ditentukan

2 . Urugan kembali bekas galian m3 124.50 0.09% 100.00% 0.09% 0.00% 0.00% 100.00% 0.09%

2 Pekerjaan Galian

409984289.xls Page 133


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
1 . Galian pondasi batu kali m3 7.10 0.01% 100.00% 0.01% 0.00% 0.00% 100.00% 0.01%
2 . Galian pondasi setempat m3 205.70 0.30% 100.00% 0.30% 0.00% 0.00% 100.00% 0.30%
3 . Galian beam m3 112.50 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
4 . Galian drainase m3 21.60 0.03% 60.00% 0.02% 30.00% 0.01% 90.00% 0.03%
5 . Galian septick tank & resapan m3 25.80 0.04% 20.00% 0.01% 0.00% 0.00% 20.00% 0.01%

3 Pekerjaan Anti Rayap m2 707.00 0.48% 100.00% 0.48% 0.00% 0.00% 100.00% 0.48%

SUB TOTAL III.b

409984289.xls Page 134


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
c. Pekerjaan Pondasi
1 Pekerjaan pondasi batu kali
1 . Annstamping m3 2.35 0.02% 100.00% 0.02% 0.00% 0.00% 100.00% 0.02%
2 . Pondasi batu kali (1PC : 4PS) m3 4.60 0.06% 100.00% 0.06% 0.00% 0.00% 100.00% 0.06%
3 . Urugan pasir bawah pondasi t.5 cm m3 12.30 0.04% 100.00% 0.04% 0.00% 0.00% 100.00% 0.04%

2 Pekerjaan pondasi plat setempat m3 55.75 3.12% 100.00% 3.12% 0.00% 0.00% 100.00% 3.12%

3 Pekerjaan lantai kerja dibawah pondasi m3 11.70 0.24% 100.00% 0.24% 0.00% 0.00% 100.00% 0.24%

SUB TOTAL III.c


d. Pekerjaan Kolom dan Balok Struktur
1 Pekerjaan kolom struktur
1 . Kolom struktur beton m3 24.70 2.99% 100.00% 2.99% 0.00% 0.00% 100.00% 2.99%
2 . Kolom struktur baja kg -
3 . Kolom praktis m3 7.63 0.59% 100.00% 0.59% 0.00% 0.00% 100.00% 0.59%

2 Pekerjaan balok struktur


1 . Balok struktur beton m3 49.70 4.18% 100.00% 4.18% 0.00% 0.00% 100.00% 4.18%
2 . Balok struktur baja kg -
3 . Sloof dan ring balok m3 43.80 3.75% 100.00% 3.75% 0.00% 0.00% 100.00% 3.75%

SUB TOTAL III.d


e. Pekerjaan Lantai & Atap

1 Pekerjaan Lantai m2 596.00 5.02% 100.00% 5.02% 0.00% 0.00% 100.00% 5.02%
(Plat bondeck)
(beton K-275 t=12cm)
(wiremesh M-7 double layer)

2 Pekerjaan atap deck beton m2 38.50 0.44% 100.00% 0.44% 0.00% 0.00% 100.00% 0.44%
(Plat bondeck)
(beton K-275 t=12cm + waterproofing)
(wiremesh M-7 double layer)

3 Pekerjaan screed pelindung waterproofing m2 48.00 0.06% 70.00% 0.04% 30.00% 0.02% 100.00% 0.06%
(Include kawat ayam)

4 Pekerjaan kuda-kuda dan rangka atap baja m2 786.00 3.82% 100.00% 3.82% 0.00% 0.00% 100.00% 3.82%
(Zyncromate finish)

5 Pekerjaan penutup atap galvalum m2 786.00 2.13% 90.00% 0.00% 10.00% 0.00% 100.00% 0.00%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area office

409984289.xls Page 135


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
. Area parkir motor & genset

6 Pekerjaan listplank beton m3 4.40 0.27% 85.00% 0.23% 15.00% 0.04% 100.00% 0.27%

7 Pekerjaan listplank kayu m' 61.00 0.24% 0.00% 0.00% 100.00% 0.24% 100.00% 0.24%

8 Pekerjaan talang baja m' 26.00 0.20% 100.00% 0.20% 0.00% 0.00% 100.00% 0.20%

9 Pekerjaan waterproofing m' 103.00 0.06% 80.00% 0.05% 20.00% 0.01% 100.00% 0.06%
(ex.Sika)

IV. PEKERJAAN DINDING & PLAFOND

a. Pekerjaan Dinding
1 Pekerjaan pasangan dinding m2 1,467.00 3.62% 85.00% 3.07% 15.00% 0.54% 100.00% 3.62%
(Bata ringan ex.Citicon)

2 Pekerjaan plester & aci dinding m2 2,572.00 2.88% 80.00% 2.31% 20.00% 0.58% 100.00% 2.88%

3 Pekerjaan Pas.Granite tile dinding m2 74.00 0.53% 0.00% 0.00% 98.00% 0.52% 98.00% 0.52%
(ex.Granito 30x60cm)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Keramik dinding t.150 cm m2 109.00 0.35% 45.00% 0.16% 55.00% 0.19% 100.00% 0.35%
(ex.Roman 20x25cm)
. Toilet 2
. Toliet 3
. Area Pantry LT 1
. Area Pantry LT 2
. Area wudhu

5 Pekerjaan Pas.Keramik dinding t.60 cm m2 5.00 0.02% 60.00% 0.01% 40.00% 0.01% 100.00% 0.02%
(ex.Roman 20x20cm)
. Area janitor

6 Pekerjaan Tali Air m' 102.00 0.03% 50.00% 0.01% 50.00% 0.01% 100.00% 0.03%

SUB TOTAL IV.a


b. Pekerjaan Plafond
1 Pekerjaan Plafond Gypsum m2 1,150.00 2.42% 60.00% 1.45% 30.00% 0.73% 90.00% 2.18%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

2 Pekerjaan Plafond Kalsiboard bagian luar m2 244.00 0.50% 0.00% 0.00% 100.00% 0.50% 100.00% 0.50%

409984289.xls Page 136


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Plasterboard 4mm ex.Jaya Board)
(Steel hollow frame)

3 Pekerjaan Drop Ceilling m' 45.00 0.10% 0.00% 0.00% 70.00% 0.07% 70.00% 0.07%
(Plasterboard 9mm ex.Jaya Board)
(Steel hollow frame)

4 Pekerjaan Tali Air Plafond Gypsum m' 802.00 0.27% 40.00% 0.11% 55.00% 0.15% 95.00% 0.26%
(Pertemuan Dengan Dinding)

409984289.xls Page 137


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

V. PEKERJAAN LANTAI

1 Pekerjaan Rabatan Lantai 1 m2 707.00 1.90% 100.00% 1.90% 0.00% 0.00% 100.00% 1.90%
(beton K-250 t=8cm)
(wiremesh M-5 single layer)

2 Pekerjaan Pas.Lantai Keramik 20x20cm m2 9.00 0.02% 70.00% 0.02% 30.00% 0.01% 100.00% 0.02%
(ex.Roman)
. Toilet 2
. Toliet 3
. Area wudhu

3 Pekerjaan Pas.Lantai Granite tile 30x30cm m2 29.00 0.14% 50.00% 0.07% 50.00% 0.07% 100.00% 0.14%
(ex.Granito)
. Toilet 1
. Toilet 4

4 Pekerjaan Pas.Lantai Granite tile 60x60cm m2 736.00 5.94% 65.00% 3.86% 33.00% 1.96% 98.00% 5.82%
(ex.Granito)
. Area coridoor
. Area tangga
. Area reception
. Area Meeting room
. Area Personalia
. Area Multifunction room
. Area Coridoor
. Area Manager
. Area Director
. Area Office
. Dll

5 Pekerjaan Pas.Lantai Keramik 40x40cm m2 326.00 1.28% 75.00% 0.96% 25.00% 0.32% 100.00% 1.28%
(ex.Roman)
. Area Storage
. Area File storage
. Area Dining room
. Area Pantry
. Area Musholla
. Area Coridoor
. Area Mechanic
. Area Janitor
. Area Security
. Dll

6 Pekerjaan Plint Lantai Keramik t. 8cm m1 246.00 0.15% 50.00% 0.08% 50.00% 0.08% 100.00% 0.15%

409984289.xls Page 138


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

7 Pekerjaan Plint Lantai Granite t. 8cm m1 310.00 0.32% 45.00% 0.14% 55.00% 0.18% 100.00% 0.32%

8 Pekerjaan Pas.Lantai Parquette (Stage) m2 60.00 0.94% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(solid wood ex.Merbau t.18mm)
(UPL Finish)
(under layer multiplex)
(wooden frame ex.Kamper)
. Waitting area Lt.1
. Waitting area Lt.2

409984289.xls Page 139


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

VI. PEKERJAAN FINISHING CAT

1 Pekerjaan Cat Dinding Exterior m2 1,276.00 1.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

2 Pekerjaan Cat Dinding Interior m2 1,302.00 0.82% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

4 Pekerjaan Cat Plafond Gypsum m2 1,150.00 0.72% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Pentalite)

5 Pekerjaan Cat Plafond Kalsiboard m2 244.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Ex.ICI - Dulux Wheathershield)

6 Pekerjaan Cat Dinding Interior m2 108.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Epoxy paint Ex.Propan)
. Area Dining room

VII. PEKERJAAN PINTU DAN JENDELA

a. Pekerjaan Pintu Jendela


1 Pintu jendela DW.01 unit 1.00 0.28% 70.00% 0.20% 20.00% 0.06% 90.00% 0.25%
(Kusen solid wood ex.Merbau)
(Solid slimar door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Pintu jendela DW.02 unit 1.00 0.14% 70.00% 0.10% 20.00% 0.03% 90.00% 0.13%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Pintu jendela DW.03 unit 1.00 0.26% 20.00% 0.05% 0.00% 0.00% 20.00% 0.05%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

4 Pintu jendela DW.04 unit 1.00 0.48% 20.00% 0.10% 0.00% 0.00% 20.00% 0.10%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

409984289.xls Page 140


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

5 Pintu jendela DW.05 unit 1.00 0.20% 20.00% 0.04% 0.00% 0.00% 20.00% 0.04%
(Framless Door - Tempered glass 12mm)
(Framless Windoow - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu jendela DW.06 unit 1.00 0.15% 70.00% 0.11% 20.00% 0.03% 90.00% 0.14%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Pintu jendela DW.07 unit 2.00 0.27% 70.00% 0.19% 20.00% 0.05% 90.00% 0.25%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

8 Pintu jendela DW.08 unit 1.00 0.12% 70.00% 0.08% 20.00% 0.02% 90.00% 0.11%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

9 Pintu jendela DW.09 unit 1.00 0.15% 70.00% 0.11% 20.00% 0.03% 90.00% 0.14%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

SUB TOTAL VII.a


b. Pekerjaan Pintu
1 Pintu D.01 unit 1.00 0.14% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

2 Pintu D.02 unit 11.00 1.04% 70.00% 0.73% 20.00% 0.21% 90.00% 0.94%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

409984289.xls Page 141


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
3 Pintu D.03 unit 6.00 0.55% 70.00% 0.39% 20.00% 0.11% 90.00% 0.50%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

4 Pintu D.04 unit 4.00 0.63% 70.00% 0.44% 20.00% 0.13% 90.00% 0.56%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(PU natural finish ex.Propan)
(Hardware ex.Kend)

5 Pintu D.05 unit 1.00 0.29% 0.00% 0.00% 20.00% 0.06% 20.00% 0.06%
(Framless Door - Tempered glass 12mm)
(Hardware ex.Kend)

6 Pintu D.06 unit 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
(Steel hollow frame + wiremesh M-7)
(Duco finish ex.Nippe)

7 Pintu D.07 unit 1.00 0.18% 0.00% 0.00% 90.00% 0.16% 90.00% 0.16%
(Steel hollow frame + plat besi)
(Duco finish ex.Nippe)

409984289.xls Page 142


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Pintu D.08 unit 2.00 0.11% 70.00% 0.08% 20.00% 0.02% 90.00% 0.10%
(Kusen solid wood ex.Merbau)
(Solid panel door ex.Merbau)
(Duco finish ex.Nippe)
(Hardware ex.Kend)

SUB TOTAL VII.b


c. Pekerjaan Jendela
1 Jendela W.01 unit 6.00 1.30% 70.00% 0.91% 20.00% 0.26% 90.00% 1.17%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

2 Jendela W.02 unit 2.00 0.15% 70.00% 0.10% 20.00% 0.03% 90.00% 0.13%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

3 Jendela W.03 unit 1.00 0.04% 70.00% 0.03% 20.00% 0.01% 90.00% 0.04%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

4 Jendela W.04 unit 1.00 0.09% 70.00% 0.07% 20.00% 0.02% 90.00% 0.08%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

5 Jendela W.05 unit 2.00 0.20% 70.00% 0.14% 20.00% 0.04% 90.00% 0.18%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

6 Jendela W.06 unit 1.00 0.08% 70.00% 0.06% 20.00% 0.02% 90.00% 0.07%
(Kusen solid wood ex.Merbau)

409984289.xls Page 143


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

7 Jendela W.07 unit 3.00 0.45% 70.00% 0.32% 20.00% 0.09% 90.00% 0.41%
(Kusen solid wood ex.Merbau)
(Solid windoow frame ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

409984289.xls Page 144


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

8 Jendela W.08 unit 1.00 0.01% 70.00% 0.01% 20.00% 0.00% 90.00% 0.01%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

9 Jendela W.09 unit 1.00 0.19% 70.00% 0.14% 20.00% 0.04% 90.00% 0.18%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 10mm)
(Hardware ex.Kend)

10 Jendela W.10 unit 1.00 0.05% 70.00% 0.03% 20.00% 0.01% 90.00% 0.04%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

11 Jendela W.11 unit 1.00 0.13% 70.00% 0.09% 20.00% 0.03% 90.00% 0.12%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

12 Jendela W.12 unit 1.00 0.11% 70.00% 0.08% 20.00% 0.02% 90.00% 0.10%
(Kusen solid wood ex.Merbau)
(PU natural finish ex.Propan)
(Clear glass 8mm)
(Hardware ex.Kend)

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT

1 Down light 4" ex.Artolite unit 126.00 0.48% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Down light halogen unit 38.00 0.34% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Surface Mounted Balk TL 1x36 Watt ex.Artolite unit 53.00 0.22% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Surface Mounted Balk TL 2x36 Watt ex.Artolite unit 73.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Mercury unit 4.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
6 LED (hidden light drop ceilling area) m' 45.00 0.18% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Instalasi Exhaust Fan Ceilling unit 15.00 0.06% 60.00% 0.04% 40.00% 0.02% 100.00% 0.06%
8 Instalasi Wall Exhaust Fan unit 1.00 0.00% 60.00% 0.00% 40.00% 0.00% 100.00% 0.00%
9 Instalasi Wall Fan unit 5.00 0.02% 60.00% 0.01% 40.00% 0.01% 100.00% 0.02%
10 Instalasi Titik lampu titik 290.00 1.16% 60.00% 0.69% 30.00% 0.35% 90.00% 1.04%
11 Instalasi Power outlet titik 139.00 0.59% 60.00% 0.36% 40.00% 0.24% 100.00% 0.59%
12 Instalasi Outlet Data titik 67.00 0.56% 60.00% 0.34% 40.00% 0.23% 100.00% 0.56%

409984289.xls Page 145


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
13 Instalasi Outlet TLP. titik 45.00 0.23% 60.00% 0.14% 40.00% 0.09% 100.00% 0.23%
14 Instalasi Power AC titik 27.00 0.22% 60.00% 0.13% 40.00% 0.09% 100.00% 0.22%
15 Instalasi RCA titik 16.00 0.08% 45.00% 0.04% 0.00% 0.00% 45.00% 0.04%
16 Instalasi CCTV Cabel Quarsial RG. 6 titik 12.00 0.07% 45.00% 0.03% 55.00% 0.04% 100.00% 0.07%
17 Instalasi Pompa air titik 1.00 0.01% 60.00% 0.00% 40.00% 0.00% 100.00% 0.01%
18 Instalasi TV Coaksial 5C titik 1.00 0.00% 20.00% 0.00% 0.00% 0.00% 20.00% 0.00%
19 Saklar single ex.Clipsal E 30 series unit 12.00 0.01% 20.00% 0.00% 0.00% 0.00% 20.00% 0.00%
20 Saklar double ex.Clipsal E 30 series unit 30.00 0.02% 20.00% 0.00% 0.00% 0.00% 20.00% 0.00%

409984289.xls Page 146


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
21 Saklar double hotel ex.Clipsal E 30 series unit 1.00 0.00% 20.00% 0.00% 0.00% 0.00% 20.00% 0.00%
22 Outlet power/stop kontak ex.Clipsal E30 series unit 139.00 0.11% 45.00% 0.05% 0.00% 0.00% 45.00% 0.05%
23 Outlet data ex.Clipsal E30 series unit 67.00 0.16% 45.00% 0.07% 0.00% 0.00% 45.00% 0.07%
24 Outlet Tlp. ex.Clipsal E30 series unit 45.00 0.08% 15.00% 0.01% 0.00% 0.00% 15.00% 0.01%
25 Outlet TV. ex.Clipsal E30 series unit 1.00 0.00% 25.00% 0.00% 0.00% 0.00% 25.00% 0.00%
26 Exhaust Fan ex.KDK - 25TGQ1 unit 15.00 0.10% 15.00% 0.01% 0.00% 0.00% 15.00% 0.01%
27 Exhaust Fan ex.KDK unit 1.00 0.01% 15.00% 0.00% 0.00% 0.00% 15.00% 0.00%
28 Wall Fan ex. KDK unit 5.00 0.05% 15.00% 0.01% 0.00% 0.00% 15.00% 0.01%
29 AC 0.5 PK unit 2.00 0.17% 15.00% 0.02% 0.00% 0.00% 15.00% 0.02%
30 AC 1 PK unit 2.00 0.19% 15.00% 0.03% 0.00% 0.00% 15.00% 0.03%
31 AC 1,5 PK unit 3.00 0.38% 15.00% 0.06% 85.00% 0.33% 100.00% 0.38%
32 AC 2 PK unit 18.00 3.26% 15.00% 0.49% 85.00% 2.77% 100.00% 3.26%
33 AC 2.5 PK unit 2.00 0.49% 15.00% 0.07% 85.00% 0.42% 100.00% 0.49%
34 Outdoor CCTV camera - infra red ex. Samsung unit 4.00 0.34% 20.00% 0.07% 0.00% 0.00% 20.00% 0.07%
35 Indoor CCTV camera - infra red ex. Samsung unit 8.00 0.42% 20.00% 0.08% 0.00% 0.00% 20.00% 0.08%
36 DVR ex. Samsung unit 1.00 0.24% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
37 Box panel MDP (metal) + MCB, MCCB, ex.MG ls 1.00 0.61% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
38 Box panel LT 2 (metal) + MCB, MCCB, ex.MG ls 1.00 0.40% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
39 Box panel Pompa (metal) + MCB, MCCB, ex.MG ls 1.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
40 COS unit 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
41 Box panel INF ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
42 PABX ex panasonic ls 1.00 0.25% 100.00% 0.25% 0.00% 0.00% 100.00% 0.25%
43 Lan ex D-link ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
44 Genset 200 KVA Silent Type ex Perkins ls 1.00 7.84% 0.00% 0.00% 20.00% 1.57% 20.00% 1.57%
45 Penangkal petir radius ±60m ex.Prevecton ls 1.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

IX. PEKERJAAN PLUMBING

1 Instalasi air bersih ls 1.00 0.11% 50.00% 0.06% 50.00% 0.06% 100.00% 0.11%
2 Instalasi air kotor ls 1.00 0.25% 70.00% 0.17% 20.00% 0.05% 90.00% 0.22%
3 Instalasi drain AC ls 27.00 0.15% 50.00% 0.08% 50.00% 0.08% 100.00% 0.15%
4 Instalasi Air hujan ls 1.00 0.28% 70.00% 0.20% 30.00% 0.08% 100.00% 0.28%
5 Instalasi Exhaus fan ls 1.00 0.15% 60.00% 0.09% 40.00% 0.06% 100.00% 0.15%
6 Guter dengan penutup beton + buis beton ls 1.00 0.38% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
7 Tower tank stainless steel 2500Lt. unit 2.00 0.27% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
8 Pompa air unit 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
9 Valve unit 6.00 0.03% 50.00% 0.01% 50.00% 0.01% 100.00% 0.03%
10 Septictank ls 1.00 0.19% 30.00% 0.06% 0.00% 0.00% 30.00% 0.06%
11 Resapan ls 1.00 0.06% 30.00% 0.02% 0.00% 0.00% 30.00% 0.02%
12 Bak Control + Gril besi ls 6.00 0.04% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
13 Roof Drain unit 8.00 0.03% 80.00% 0.03% 20.00% 0.01% 100.00% 0.03%
14 Floor drain ex.Toto - TX 1 BN unit 9.00 0.07% 20.00% 0.01% 0.00% 0.00% 20.00% 0.01%
15 Closet ex.Toto - CW 660 PJ unit 7.00 0.31% 0.00% 0.00% 20.00% 0.06% 20.00% 0.06%
16 Jet spray ex.Toto - THX 20 NBPIV unit 7.00 0.05% 0.00% 0.00% 20.00% 0.01% 20.00% 0.01%
17 Wastafel ex.Toto - LW 526 J unit 5.00 0.29% 0.00% 0.00% 20.00% 0.06% 20.00% 0.06%

409984289.xls Page 147


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL
18 Wastafel ex.Toto - LW 220 J unit 2.00 0.06% 0.00% 0.00% 20.00% 0.01% 20.00% 0.01%
19 Urinal ex.Toto - U 57 M unit 2.00 0.09% 0.00% 0.00% 20.00% 0.02% 20.00% 0.02%
20 Kran air ex.Toto - T 23 B13V7NB unit 3.00 0.01% 0.00% 0.00% 20.00% 0.00% 20.00% 0.00%
21 Paper holder ex.Toto TX 703 AESV1 unit 7.00 0.06% 0.00% 0.00% 20.00% 0.01% 20.00% 0.01%

409984289.xls Page 148


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

X. PEKERJAAN LANDSCAPE

1 Pekerjaan kanstin ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
2 Pekerjaan paving 20x20cm (include urugan pasir) m2 480.00 1.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
3 Tanah subur (tanaman) m3 9.50 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
4 Tanaman ls 1.00 0.15% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
5 Pekerjaan kuda-kuda dan rangka atap baja m2 91.00 0.44% 90.00% 0.40% 10.00% 0.04% 100.00% 0.44%
(Zyncromate finish) area parkir motor & Genset

6 Pekerjaan penutup atap galvalum m2 91.00 0.23% 90.00% 0.21% 10.00% 0.02% 100.00% 0.23%
(Galvalum ex.Jaindo)
(Aluminium foil 5mm)
. Area parkir motor & genset

XI. PEKERJAAN LAIN - LAIN

1 Pas. Meja Kitchen ls 1.00 0.14% 100.00% 0.14% 0.00% 0.00% 100.00% 0.14%
(Beton finishing keramik 20x20cm ex.Roman)

2 Pas. Meja Washtafel


(Beton finishing topping marble ex.Gold Black)
. Toilet-1 ls 1.00 0.07% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.13% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Decorative Mirror (Toilet)


(Wooden frame + multiplex backing))
(Fancy ex.Jati)
(Natural finish ex.Propan)
(5mm mirror)
(Hidden lamp TL)
. Toilet-1 ls 1.00 0.03% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

3 Pas. Partisi Kaca Toilet


(12mm tempered glass frameles)
(Sandblast finish)
. Toilet-1 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
. Toilet-4 ls 1.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

4 Peninggian Kenalpot Genset ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

5 Pekerjaan Pagar keliling bangunan t = 3m m' 29.00 1.11% 0.00% 0.00% 60.00% 0.67% 60.00% 0.67%

409984289.xls Page 149


PROGRES PEKERJAAN MINGGUAN
PROYEK PEMBANGUNAN GUDANG PRODUKSI & KANTOR
SEDURI,TUMAPEL DLANGGU Periode ; .............. 2016
MOJOKERTO
Bobot PROGRESS REPORT
No. PEKERJAAN SAT. VOL. KET
MINGGU LALU MINGGU INI TOTAL

XII. ITEM KOMPENSASI


Item - item pekerjaan yang belum/tidak tercantum dalam bill of item
tetapi menurut kontraktor dianggap perlu untuk dicantumkan (ada
dalam gambar atau tidak ada tetapimerupakan basic dari konstruksi)
bisa dimasukkan dalam item kompensasi.

III. PEKERJAAN STRUKTUR

b. Pekerjaan Galian dan Urugan


Pekerjaan Galian
6 Galian Bor pile dia. 40 cm m' 1,133.00 3.30% 100.00% 3.30% 0.00% 0.00% 100.00% 3.30%

c. Pekerjaan Pondasi
4 Pekerjaan Pondasi Tangga m3 0.55 0.03% 100.00% 0.03% 0.00% 0.00% 100.00% 0.03%

5 Pekerjaan Beton Bor Pile dia. 40 cm m3 147.00 4.94% 100.00% 4.94% 0.00% 0.00% 100.00% 4.94%

V. PEKERJAAN LANTAI
7 Pekerjaan Waterproofing Coating (termasuk dinding T=30 cm) m2 43.00 0.09% 80.00% 0.07% 20.00% 0.02% 100.00% 0.09%
. Toilet 4
. Area Pantry LT 2
. Area janitor

VIII. PEKERJAAN LIGHTING DAN OUTLET POINT


46 Instalasi Titik lampu taman NYY GBY 3x2.5mm titik 4.00 0.05% 40.00% 0.02% 60.00% 0.03% 100.00% 0.05%
47 Kabel tuvur NYY 4x25mm panel MDB m 35.00 0.17% 15.00% 0.03% 0.00% 0.00% 15.00% 0.03%
48 Grounding ls 1.00 0.09% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
49 Test comisioning ls 1.00 0.08% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

XI. PEKERJAAN LAIN - LAIN


6 Pas. Decorative Mirror (Toilet)
(Wooden frame + multiplex backing))
(5mm mirror)
. Toilet-3 ls 1.00 0.01% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

7 Pekerjaan Tangga
1 . Struktur tangga beton m3 2.60 0.16% 100.00% 0.16% 0.00% 0.00% 100.00% 0.16%
2 . Pekerjaan pasang keramik tangga granite tile 60x60 cm m2 22.00 0.19% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
- ex Granito + step nozing
3 . Pekerjaan railling tangga m' 17.00 0.44% 0.00% 0.00% 50.00% 0.22% 50.00% 0.22%
- Hollow stainless steel
- Tempered glass 12 mm
4 . Pekerjaan plester & aci bawah tangga m2 19.00 0.02% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
.
SUB TOTAL XIII 100% 79.60% 59.51% 29.09% 15% 108.68 75%

409984289.xls Page 150


TIME SCHEDULE
PROYEK = Back Office Show Room Kawasaki thp. 2
LOKASI = Jl. Jemursari 156 Surabaya

JULI ' 14 AGUSTUS ' 14 SEPTEMBER ' 14 OKTOBER ' 14 NOPEMBER ' 14 DESEMBER ' 14
NO. URAIAN PEKERJAAN BOBOT
27-04 05-10 11-17 18-24 25-31 1-4 05-10 11-17 18-24 25-31 1-6 7-13 14-20 21-27 28-30 1-7 8-14 15-21 22-28 29-4 5-11 12-18 19-25 26-4 5-11 12-18 19-25

I PEKERJAAN PRELIMINARY
Mobilisasi dan Demobilisasi 0.22% 0.11% 0.11%

Pembersihan lokasi 0.11% 0.06% 0.06%

Bangunan penunjang sementara (direksi keet) 0.11% 0.11%


Uitzet & bouwplank 0.06% 0.06%
Gambar2 kerja (shop drawing) 0.02% 0.02%

Gambar2 kenyataan (as built drawing) 0.02% 0.01% 0.01% 0.01%


Listrik, air kerja dan telpon 0.17% 0.08% 0.08%
Keamanan proyek 0.11% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

Pengelolaan kebersihan lapangan 0.11% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%
Pengukuran (setting out) 0.02% L L 0.02%
Masa pemeliharaan 0.11% I I 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01% 0.01%

II PEKERJAAN BONGKARAN B B
III PEKERJAAN STRUKTUR U U
Pekerjaan Perhitungan Struktur 0.22% 0.07% 0.07% 0.07% R R
Pekerjaan Urugan 1.02% 0.51% 0.51%
Pekerjaan Galian 0.54% 0.14% 0.14% 0.14% 0.14%
Pekerjaan Anti Rayap 0.48% 0.24% 0.24%

Pekerjaan pondasi plat setempat 3.24% 0.81% 0.81% 0.81% 0.81%


Pekerjaan lantai kerja dibawah pondasi 0.24% 0.06% 0.06% 0.06% 0.06%
IV PEKERJAAN KOLOM & BALOK STRUKTUR
Pekerjaan kolom struktur 3.58% 0.89% 0.89% 0.89% 0.89%
Pekerjaan balok struktur 7.93% 1.59% 1.59% 1.59% 1.59% 1.59%
V PEKERJAAN LANTAI & ATAP
Pekerjaan Lantai 5.02% 1.67% 1.67% 1.67%

Pekerjaan atap deck beton 0.44% 0.22% 0.22%


Pekerjaan screed pelindung waterproofing 0.06% 0.03% 0.03%
Pekerjaan kuda-kuda dan rangka atap baja 3.82% 1.27% 1.27% 1.27%

Pekerjaan penutup atap galvalum 2.13% 1.07% 1.07%


Pekerjaan listplank beton 0.27% 0.14% 0.14%
Pekerjaan listplank kayu 0.24% 0.12% 0.12%

Pekerjaan talang baja 0.20% 0.10% 0.10%


Pekerjaan waterproofing 0.06% 0.03% 0.03%
VI PEKERJAAN DINDING & PLAFOND
Pekerjaan pasangan dinding 3.62% 0.90% 0.90% 0.90% 0.90%
Pekerjaan plester & aci dinding 2.88% 0.96% 0.96% 0.96%
Pekerjaan Pas.Granite tile dinding 0.53% 0.26% 0.26%

Pekerjaan Pas.Keramik dinding t.150 cm 0.35% 0.12% 0.12% 0.12%


Pekerjaan Pas.Keramik dinding t.60 cm 0.02% 0.02%
Pekerjaan Tali Air 0.03% 0.01% 0.01%

Pekerjaan Plafond Gypsum 2.42% 0.81% 0.81% 0.81%


Pekerjaan Plafond Kalsiboard bagian luar 0.50% 0.25% 0.25%
Pekerjaan Drop Ceilling 0.10% 0.10%

Pekerjaan Tali Air Plafond Gypsum 0.27% 0.13% 0.13%


VII PEKERJAAN LANTAI
Pekerjaan Rabatan Lantai 1 1.90% 0.63% 0.63% 0.63%

Pekerjaan Pas.Lantai Keramik 20x20cm 0.02% 0.02%


Pekerjaan Pas.Lantai Granite tile 30x30cm 0.14% 0.07% 0.07%
Pekerjaan Pas.Lantai Granite tile 60x60cm 5.94% 0.74% 0.74% 0.74% 0.74% 0.74% 0.74% 0.74% 0.74%
Pekerjaan Pas.Lantai Keramik 40x40cm 1.28% I I 0.32% 0.32% 0.32% 0.32%
Pekerjaan Plint Lantai Keramik t. 8cm 0.15% D D 0.15%
Pekerjaan Plint Lantai Granite t. 8cm 0.32% U U 0.16% 0.16%
Pekerjaan Pas.Lantai Parquette (Stage) 0.94% L L 0.47% 0.47%

VIII PEKERJAAN FINISHING CAT


Pekerjaan Cat Dinding Exterior 1.00% 0.50% 0.50%
Pekerjaan Cat Dinding Interior 0.82% 0.41% 0.41%
Pekerjaan Cat Plafond Gypsum 0.72% 0.36% 0.36%
Pekerjaan Cat Plafond Kalsiboard 0.15% 0.08% 0.08%
Pekerjaan Cat Dinding Interior 0.38% 0.19% 0.19%

IX PEKERJAAN PINTU DAN JENDELA


Pintu Jendel DW-01 s/d DW-09 2.06% 0.34% 0.34% 0.34% 0.34% 0.34% 0.34%
Pintu D-01 s/d D-08 3.09% 0.51% 0.51% 0.51% 0.51% 0.51% 0.51%
Jendela W.01 s/d W.12 2.82% 0.56% 0.56% 0.56% 0.56% 0.56%

X PEKERJAAN LIGHTING DAN OUTLET POINT


Down light 4" ex.Artolite 0.48% 0.16% 0.16% 0.16%
Down light halogen 0.34% 0.17% 0.17%
Surface Mounted Balk TL 1x36 Watt ex.Artolite 0.22% 0.11% 0.11%
Surface Mounted Balk TL 2x36 Watt ex.Artolite 0.38% 0.19% 0.19%
Mercury 0.04% 0.02% 0.02%

LED (hidden light drop ceilling area) 0.18% 0.09% 0.09%


Instalasi Exhaust Fan Ceilling 0.06% 0.03% 0.03%
Instalasi Wall Exhaust Fan 0.00% 0.00%

Instalasi Wall Fan 0.02% 0.02%


Instalasi Titik lampu 1.16% 0.39% 0.39% 0.39%
Instalasi Power outlet 0.59% 0.30% 0.30%

Instalasi Outlet Data 0.56% 0.19% 0.19% 0.19%


Instalasi Outlet TLP. 0.23% 0.11% 0.11%
Instalasi Power AC 0.22% 0.11% 0.11%

Instalasi RCA 0.08% 0.04% 0.04%


Instalasi CCTV Cabel Quarsial RG. 6 0.07% 0.03% 0.03%
Instalasi Pompa air 0.01% 0.01%

Instalasi TV Coaksial 5C 0.00% 0.00%


Saklar single ex.Clipsal E 30 series 0.01% 0.01%
Saklar double ex.Clipsal E 30 series 0.02% 0.02%

Saklar double hotel ex.Clipsal E 30 series 0.00% 0.00%


Outlet power/stop kontak ex.Clipsal E30 series 0.11% 0.05% 0.05%
Outlet data ex.Clipsal E30 series 0.16% 0.08% 0.08%

Outlet Tlp. ex.Clipsal E30 series 0.08% 0.04% 0.04%


Outlet TV. ex.Clipsal E30 series 0.00% 0.00%
Exhaust Fan ex.KDK - 25TGQ1 0.10% 0.05% 0.05%

Exhaust Fan ex.KDK 0.01% 0.01%

Wall Fan ex. KDK 0.05% 0.05%


AC 0.5 PK 0.17% 0.08% 0.08%
AC 1 PK 0.19% 0.19%

AC 1,5 PK 0.38% 0.19% 0.19%


AC 2 PK 3.26% 0.65% 0.65% 0.65% 0.65% 0.65%
AC 2.5 PK 0.49% 0.25% 0.25%

Outdoor CCTV camera - infra red ex. Samsung 0.34% 0.17% 0.17%
Indoor CCTV camera - infra red ex. Samsung 0.42% 0.21% 0.21%
DVR ex. Samsung 0.24% 0.12% 0.12%

Box panel MDP (metal) + MCB, MCCB, ex.MG 0.61% 0.30% 0.30%
Box panel LT 2 (metal) + MCB, MCCB, ex.MG 0.40% 0.20% 0.20%
Box panel Pompa (metal) + MCB, MCCB, ex.MG 0.04% 0.02% 0.02%

COS 0.08% 0.04% 0.04%


Box panel INF 0.01% 0.01%
PABX ex panasonic 0.25% 0.12% 0.12%

Lan ex D-link 0.02% 0.02%


Genset 200 KVA Silent Type ex Perkins 7.84% 1.96% 1.96% 1.96% 1.96%
Penangkal petir radius ±60m ex.Prevecton 0.27% 0.13% 0.13%

XI PEKERJAAN PLUMBING
Instalasi air bersih 0.11% 0.06% 0.06%
Instalasi air kotor 0.25% 0.08% 0.08% 0.08%

Instalasi drain AC 0.15% 0.08% 0.08%

Instalasi Air hujan 0.28% 0.14% 0.14%


Instalasi Exhaus fan 0.15% 0.07% 0.07%
Guter dengan penutup beton + buis beton 0.38% 0.13% 0.13% 0.13%

Tower tank stainless steel 2500Lt. 0.27% 0.09% 0.09% 0.09%


Pompa air 0.09% 0.05% 0.05%
Valve 0.03% 0.01% 0.01%

Septictank 0.19% 0.10% 0.10%


Resapan 0.06% 0.03% 0.03%
Bak Control + Gril besi 0.04% 0.02% 0.02%

Roof Drain 0.03% 0.02% 0.02%


Floor drain ex.Toto - TX 1 BN 0.07% 0.07%
Closet ex.Toto - CW 660 PJ 0.31% 0.10% 0.10% 0.10%

Jet spray ex.Toto - THX 20 NBPIV 0.05% 0.02% 0.02%


Wastafel ex.Toto - LW 526 J 0.29% 0.10% 0.10% 0.10%
Wastafel ex.Toto - LW 220 J 0.06% - - 0.03% 0.03%

Urinal ex.Toto - U 57 M 0.09% F F 0.05% 0.05%


Kran air ex.Toto - T 23 B13V7NB 0.01% I I 0.01%
Paper holder ex.Toto TX 703 AESV1 0.06% T T 0.03% 0.03%

XII PEKERJAAN LANDSCAPE R R


Pekerjaan kanstin 0.09% I I 0.04% 0.04%
Pekerjaan paving 20x20cm (include urugan pasir) 1.67% 0.42% 0.42% 0.42% 0.42%
Tanah subur (tanaman) 0.03% 0.03%
Tanaman 0.15% 0.08% 0.08%
Pekerjaan kuda-kuda dan rangka atap baja 0.44% 0.22% 0.22%
Pekerjaan penutup atap galvalum 0.23% 0.12% 0.12%
XIII PEKERJAAN LAIN - LAIN
Pas. Meja Kitchen 0.14% 0.07% 0.07%
Pas. Meja Washtafel 0.20% 0.10% 0.10%
Pas. Decorative Mirror (Toilet) 0.11% 0.05% 0.05%
Pas. Partisi Kaca Toilet 0.04% 0.04%
Peninggian Kenalpot Genset 0.09% 0.05% 0.05%
Pekerjaan Pagar keliling bangunan t = 3m 1.11% 0.37% 0.37% 0.37%
XIV PEKERJAAN STRUKTUR
Galian Bor pile dia. 40 cm 3.30% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47% 0.47%
Pekerjaan Pondasi Tangga 0.03% 0.03%
Pekerjaan Beton Bor Pile dia. 40 cm 4.94% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62% 0.62%
XV PEKERJAAN LANTAI
Pekerjaan Waterproofing Coating (termasuk dinding T=30 cm) 0.09% 0.04% 0.04%
XVI PEKERJAAN LIGHTING DAN OUTLET POINT 0.38% 0.19% 0.19%
XVII PEKERJAAN LAIN - LAIN
Pas. Decorative Mirror (Toilet) 0.01% 0.01%
Pekerjaan Tangga 0.82% 0.41% 0.41%

TOTAL ### 0.00% 0.07% 0.07% 0.07% 0.00% 1.63% 1.56% 1.55% 2.35% 2.65% 5.09% 4.60% 3.58% 3.43% 8.44% 8.34% 9.71% 8.87% 7.33% 9.57% 8.65% 6.19% 3.61% 2.32% 0.33%
TOTAL KOMULATIF 0.00% 0.07% 0.15% 0.22% 0.22% 1.86% 3.42% 4.96% 7.31% 9.96% 15.05% 19.65% 23.23% 26.65% 35.09% 43.43% 53.14% 62.01% 69.34% 78.91% 87.56% 93.75% 97.35% 99.67% 100.00%