EHS RISK ASSESSMENT

Ref : HMRP - 08 B Rev 00


Project : Hyderabad Metro Rail
Client : Hyderabad Metro Rail limited
Independent Engineer : Louis Berger Consulting Pvt. Ltd
Concessionaire : L&T Metro Rail Hyderabad Limited
Contractor : L&T Construction PT&D IC (POWER SUPPLY & SCADA PROJECT)

Activity considered : DG UNLOADING / ERECTION Date: 08.11.13

Severity rating
Hazard / Environment Aspect

Probability
Risk / Residual

rating
Sl.no Activity Existing control measures Imapct Additional Control measures Risk / Action by
Source / Situation
Possible outcome People at risk level Impact
/ Act

1) Making the access clear without


1) Making the access road
any undulations
sufficient enough width at
2) Making the access rigid enough
culverts etc Site Incharge
(compacted) to withstand the load
Transportation Electrocution, 2) Taking LC, if in presence of / Engineer /
Access / Workmen in 3) Making the access clear without
1 (Trailor / crane Topple & fall 4 5 High overhead power lines Low Time keeper
undulations etc the trailor any powerlines existence
entering into site) hazards 3) Abiding the site safety rules / EHSO
4) Vehicle having all statutory
of speed limitations etc supervisor
documents & all safety
4) Driver is medically fit w.r.t to
requirements as per format HMRP-
eye & physique (eye test)
15A Rev 00
5) All the workmen should be
screened & trained etc

1) Ensure to have good


Trailor into the Access / Workmen in 1) Making the access clear without
communication while reversing Site Incharge
position (before undulations / the trailor & any undulations 2) Making
2 Topple & fall etc 4 5 High of the vehicle Low / Engineer &
the Transformer turning or surrounding the access rigid enough
2) Ensure to have chock blocks supervisor
foundation) reversing etc workmen etc (compacted) to withstand the load
to arrest the freeflow
1) The working area to be
made well compacted
2) The crane out riggers should
1) The area should be without rest on the ground
undulations 3) Outriggers should be placed
2) The working area to be clear on rigid base plates to avoid
Injury to workmen workmen in from overhead power lines 3) point load Site Incharge
Positining of crane topple,
3 & damage of surrounding The crane having all statutory 4 5 High 4) Do not lift beyond the Low / Engineer &
/ cranes electrocution etc
property area documents & safety requirements limitations (angle as per load supervisor
4) To know the capacity of load chart)
being lift & engaging of crane as 5) Prepare lifting plan & obtain
per the load lifting permit
6) Establishing good
communication between 2
cranes & fellow workmen

1) All tools to be inspected


prior to use & follow color
code
2) While lifting the DG /
enclosure; no workmen shall
stand beneath the load
3) While lifting & positioning of
DG swing alarm to be made
active
4) The load to be controlled
1) All the lifting tools using should
against swing by using tag lines
workmen in have 3rd party test certificates &
Injury to workmen on both the ends Site Incharge
Lifting of the DG the should be sufficient capacity
4 Fall, topple etc & damage of 4 5 High 5) Do not lift beyond the Low / Engineer &
& placing surrounding 2) Should have good
property limitations (angle as per load supervisor
area communication between operator
chart)
& the working fellows
6) Demarcate the work area &
do not allow trespassers
7) Follow the signals given by
the identified signalman
8) STOP signal from any of the
person to be considered
9) Consider inclement weather
conditions & act (no to
work if bad weather, wind
persists etc)
PM / CM EHSO