Está en la página 1de 8

Strengthening of the cable-stayed bridge over Danube at Agigea

I.R.Răcănel
Technical University of Civil Engineering of Bucharest, Romania
C.S.Mutu
Bridges Department, Design Institute for Road, Water and Air Transport, Romania

ABSTRACT: In the design of a bridge structure the optimization process plays an important role. This pro-
cess includes economic aspects, strength and safety conditions and maintenance, retrofitting and strengthen-
ing possibilities during service life. Sometime, a good solution from strength, safety and esthetics point of
view can lead at major difficulties for maintenance and strengthening. In the design stage of a cable-stayed
bridge, several parameters are to be considered. From these, the number and position of stays plays a very
important role from strengthening point of view, a large number of stays making easier such a process. In this
paper, the strengthening of an old cable-stayed bridge over Danube at Agigea is presented. The bridge was
built in 1984 and the lack in maintenance and the climatic conditions on the site have led to severe corrosion
of the wires in the stays and the strengthening of the bridge should be performed quickly.

1 INTRODUCTION through this, the corrosion of the strands was not en-
sured anymore.
Cable-stayed bridges are modern solutions offering The lack in maintenance and the climatic condi-
important advantages: the possibility to cover large tions on the site have led to severe corrosion of the
spans and through this reducing the number of sub- strands and a large number of them failed by rup-
structure elements, a relative small construction ture. Because the number a broken wires increases
depth together with a good esthetic. with time, the strengthening of the bridge should be
In the design stage of such type of bridge, several performed quickly. The bridge closure is not possi-
parameters concerning the bridge geometry are to be ble because it is the shortest link with the Constanţa
considered: span length, height of the pylons, the harbor and with the Romanian coast of the Black
number and distribution of stays along the bridge Sea, which is visited each year by a large number of
deck. From these, the number and position of stays tourists.
plays a very important role from possible further The geometry of the bridge and the small number
strengthening point of view. A large number of stays of stays made very difficult the strengthening pro-
together with an optimized distribution can lead to cess. Several solutions for the strengthening were
major advantages, if stays damages occur or if the discussed taking into account the advantages and
strengthening of bridge is necessary in order to ful- disadvantages of each one, especially from econom-
fill the new traffic requirements. ic point of view, but considering also the technical
In this paper, the strengthening of an old cable- aspects related to the efficiency of the applied meth-
stayed bridge over Danube at Agigea is presented. od and its impact on the bridge safety during the fu-
The bridge was built in 1984 as a cable-stayed of ture service period.
asymmetrical type, having one pylon placed on the The goal of the paper is to describe the chosen
left bank of the Danube-Black Sea Canal. The erec- strengthening method together with the calculations
tion of the bridge superstructure was done by the aid performed for the design of temporary supplemen-
of a temporary scaffolding system. During the de- tary structural elements used during the entire pro-
sign stage, the different elongation capabilities of cess.
stay cables and protection steel tubes was not ac-
counted for. Thus, after dismounting the scaffolding
system in order to transfer the loads to the cable 2 DESCRIPTION OF THE BRIDGE
stays, under the self-weight of the superstructure,
some of the steel tubes were broken at their ends and The bridge is placed on the national road DN39
Constanţa-Mangalia at km 8+988 in Agigea city,
near to the confluence between Danube-Black Sea 40.50+40.50+162.00+23.00m. A general layout of
Canal and Black Sea. The total bridge length is the bridge is shown in Figure 1.
307.70m and is covered by four spans:

Figure 1. General layout of the bridge

The bridge superstructure is a composite structure transversally. The total height of the pylon above the
consisting in a steel deck connected at the upper part upper part of the foundation mat is 78.70m. All sub-
with a reinforced concrete slab. In cross section structure elements have deep foundations on con-
there are two groups of two steel plate girders which crete piles of 1.08 (abutments and pier P1) and of
are forming the main girders of the superstructure. 1.50m (pylon and pier P2) and variable length.
The distance between these two groups of girders is The bearing of the superstructure on the substruc-
14.00m and between the girders in a group is 2.00m. ture elements is made through steel bearing devices.
The girders webs are 3000mm deep. In order to re- The superstructure extremity towards Constanţa was
duce the span of the concrete slab, three rows of anchored in the abutment by means of two L-shaped
welded I-shaped longitudinal stringers are foreseen. steel structures, welded at the upper part on the deck
Transversally, the main girders and the stringers are girders and resting at the bottom part on bearings
connected using cross beams. The cross beams on placed upside-down in order to take the tensile forc-
the abutments, piers and pylon, together with those es caused by the presence of the loads on the unbal-
where the anchorages for the stays are disposed, anced spans of the bridge.
have welded steel box cross sections. The current The superstructure is supported by stay cables
cross beams have I-welded cross sections and they which are anchored at the top of the pylon. For each
are placed at 7.84m along the bridge. All cross stay cable 48Ø5mm SBP I wires were used. The
beams have the total depth of 2050mm. The steel strands were introduced in steel tubes in order to en-
deck is connected with the reinforced concrete slab sure the protection against corrosion.
disposed above it using steel studs.
The substructure of the bridge consists in two
massive abutments, two piers having a lamellar ele-
vation and an A-shaped pylon. The pylon comprises
two inclined concrete legs with variable dimensions.
At the bottom part, the cross section of the pylon
legs is a full concrete rectangular section having the
5.50m in bridge longitudinal direction and 3.25m in
transverse direction. Starting at 12.50m above the
foundation, the cross sections of the pylon legs be-
came concrete boxes with variable dimensions: from Figure 2 Cross section of the bridge superstructure
5.05m to 3.15m in longitudinal direction and 3.25m
A cross section of the bridge superstructure is pre- and supplementary, several pairs of stays are added
sented in Figure 2. in order to support the deck. The anchorages of the
existing stays A3-A8, A4-A7, A5-A6 are kept at the
deck level, but those placed at the top of the pylon
3 STRENGTHENING SOLUTIONS are disaffected. In order to allow the connection of
the stays on the pylon, at its top, a special composite
The large number of wires broken in a short time pe- (steel-concrete) structure was foreseen. This solution
riod lead to the conclusion that the bridge should be has a major advantage: the larger number of stays
strengthened as soon as possible. Several solutions will ensure a better behavior of the bridge under ser-
were proposed for strengthening and they will be vice loads and will allow an easier change process if
briefly presented in the following. The choosing of further strengthening are necessary. Moreover, it is a
the appropriate solution was based on the simplicity significant improvement from esthetical point of
in execution, efficiency in use during strengthening view. The disadvantage of the solution is related
time period and in the future in service and on nec- with the high consumption of steel because of the
essary costs. larger number of stays and the steel special struc-
In the first solution (Fig. 3), a temporary bearing tures necessary to fix the stays at the deck and pylon
steel structure should be placed in the largest span, respectively. Also, especially at the deck level, the
under the stays A4 and A7 (Fig. 1). The foundation construction of the anchorages for the new stays will
of this structure should be placed on the bottom of be complicated implying other supplementary sys-
the Canal Danube-Black Sea, on a special existing tems on the deck. It was concluded that the solution
concrete block that was foreseen during the execu- will have an important impact on the total costs fore-
tion of the Canal. This structure should allow the seen for the bridge strengthening and it was also re-
bearing of the superstructure ensuring it’s stability jected.
during strengthening process, by reducing the span
value and through this the value of the vertical de-
formations, which could be caused by the collapse of
one or more stays. This solution had a major disad-
vantage: it’s strongly reduces the clearance, increas-
ing the risk of collision of the temporary tower and
the ships and loaded barges traveling on the Canal.

Figure 4. Second strengthening solution

Figure 3. First strengthening solution

The second solution (Fig. 4) consists in building


of a new pylon on the right bank of the Canal to-
Figure 5. Third strengthening solution
gether with a concrete anchorage block for the back-
stays. Both, the pylon and the anchorage block had
The last proposed solution, which is also the
deep foundations on large diameter concrete piles.
adopted one, is presented in Figure 6. In this solution
Three pairs of stays should ensure the suspension of
five pairs of supplementary temporary stays should
the bridge in the larger span being connected to the
be added in order to support the deck during the
superstructure near to the existing cable-stays A3-
strengthening process. The solution implies the exe-
A8, A4-A7, A5-A6. The disadvantages of this solu-
cution of new steel structures placed below the deck
tion are linked with the difficulty in execution of
and at the top of the pylon to anchor the stays at both
foundations and elevation of the new pylon and with
ends. Adapting the cross section of the new tempo-
the lack of space behind the abutment Mangalia.
rary stays to the stress level required by the breaking
Moreover, the new anchorages needed for the tem-
of the wires in old stays and optimizing the dimen-
porary stays could lead to difficulties during the
sions of the supplementary steel structures recom-
changing process of the damaged stays. For these
mend this solution as the most effective from costs
reasons this solution was also rejected.
and time required to execute it. This solution was
The third solution is presented in Figure 5. In this
accepted and detailed in the project for the bridge
solution, the pylon and the existing stays are kept
strengthening. In the figure below, in plan view, the
temporary cables are denoted with C1…C10 and be- ate cable is sketched.
low each notation, the cross section of the appropri-

Figure 6. The approved strengthening solution

bridge) and having the upper flange extended in two


sections, in order to allow the connection with the
4 PRESENTATION OF THE APROVED bottom flanges of girders.
SOLUTION

In this approved solution, five pairs of temporary


cables are used to sustain the bridge deck during the
time period necessary to change the damaged stays.
The necessary cross section of each temporary cable
was established through calculation, assuming that
in the first stage when these cables are placed on the
structure, each one should take the axial force corre-
sponding to the appropriate area of the broken wires
of existing stays plus a safety percentage. Because Figure 7. The steel elements used for fixing the temporary
for the most damaged stay the percentage of the bro- stays at the deck level
ken wires was assumed to be around 20% from the
initial cross section and according to the distribution In Figure 7 the elements are shown upside-down. In
low of the phenomenon, a safety percentage of 10% order to ensure the resistance capacity and the stabil-
ity of these elements, diaphragms and stiffeners are
was added, so that each stay must take an axial force
foreseen and fixed through welding seams inside and
corresponding to 30% of the initial cross section. outside of the box cross section. Each girder has at
Some supplementary steel components were de- the end placed on the exterior side of the bridge
signed and manufactured in order to allow the fixing cross section a circular hole to allow the passing of
of the temporary stays in the composite deck and in the temporary stays. These manufactured steel ele-
the concrete pylon respectively. At the deck level, ments were connected to the flanges of the plate
under each group of plate girders near to the anchor- girders forming the bridge cross section using high
ages sections of existing stays, a special steel ele- strength bolts. For this purpose, the surfaces in con-
ment was placed (Fig. 7). This element is a steel tact were treated by sandblast cleaning and alumi-
girder with a welded box cross section, placed across num coating, allowing to reach the desired value of
each group of two plate girders (each side of the the friction coefficient.
The connection of the temporary cables on the According to the climate on the site and for man-
concrete pylon was made through a steel structure ufacturing purposes all steel elements were made in
which form a steel ring around the top of the pylon steel S355J2W+N.
(Fig. 8). In order to respect the clearance gauge on
the roads from the factory to the site, this structure is
composed from two subassemblies which were con-
nected using high strength bolts with a diameter of
36mm. In bridge longitudinal direction, the ring
cross section is a welded steel box with three webs
having a depth of 2350mm. The exterior webs have
the same inclination with respect to the horizontal as
the lateral inclined legs of the pylon. In bridge trans-
verse direction, on the side of Mangalia city, the ring
cross section is a box with two webs having the
same depth as for the parts disposed in bridge longi-
tudinal direction. On the side of Constanţa city, two
Figure 9. Bottom view of the steel ring with visiting holes
webs were also used for the ring cross section, but
their depth is only 1450mm. Inside of all girders di-
aphragms were placed in order to avoid the local
buckling of the webs and flanges in compression. In
the steel plates forming the bottom flanges of the
box steel girders placed along the bridge as well as
in the interior diaphragms, visiting holes were fore-
seen in order to allow the welding (Fig. 9). Also,
steel tubes of appropriate diameters were welded in-
side the box sections allowing the passing through of
temporary cables (Fig. 9).

Figure 10. One of two subassemblies equipped with truss canti-


levers prepared for lifting

After placing on the bridge superstructure and on the


pylon these additional steel elements, the first stage
of tensioning of the temporary cables was per-
formed. During this operation, only for short time
periods, the traffic on the bridge was restricted. Af-
ter the first stage of tensioning, the level of axial
forces in the temporary cables, as well of the vertical
and horizontal displacements of the deck and pylon
Zone for the anchorage of respectively were measured and compared with the
temporary cables calculated values. The values were in very good ac-
cordance and will be briefly presented in a table in
Final plates for the bolted con- the next paragraph of the paper. In order to achieve
nections of two subassemblies the desired deformed shape of the deck needed for
Figure 8. One subassembly of the ring changing the damaged stays, a second stage of ten-
sioning was performed. The level of the axial forces
For both subassemblies on one side, two truss canti- in the temporary cables for this stage were also cal-
levers with special baskets were foreseen. Adding culated and delivered on the site to the builder. The
calculated counterweights in the basket, the equilib- new values of the vertical superstructures displace-
rium of the subassembly could be kept during the as- ments corresponding to the new axial forces in the
sembling on the site made with the aid of two cranes temporary stays measured on the site were in good
(Fig. 10). accordance with the calculated values.
Using the cranes, after bolting the joints between For the changing of the damaged stays, three sce-
the two subassemblies, the ring was lowered down narios were considered and they will be described in
on the pylon until it stops. In order to avoid the the following.
damage of the concrete in the pylon because of high In the first solution (Fig. 11) the existing stays are
pressures produced by the ring, special mortars were changed one by one, symmetrically with respect to
injected between the parts in contact. the longitudinal axis of the bridge. The new stays
will have circular cross sections. The area of each third solution. The disadvantage in both solutions is
cross section was established through numerical cal- related with the higher values of the axial forces in
culation, so that after all tensioning stages and re- temporary cables and remaining stays during the
moving of the temporary cables, the deformed shape changing process. One major advantage of the third
of the bridge is identical with those at the time when solution is that the both, at the deck level and at the
the bridge was putted in service. To limit the dis- top of the pylon, the existing anchorage zones can be
placement of the pylon during the change of final kept unchanged or will suffer only minor changes.
stays on Constanţa side, temporary back-stays were Analyzing these aspects the third solution was pre-
added on the structure (Fig. 11). ferred, even the time necessary for changing all
damaged cables increases significantly.

Figure 11. First solution for the change of existing stays


Figure 13. The third solution for the change of existing stays
In the second solution (Fig. 12), the existing stays
are changed also one by one, symmetrically on two
sides of the bridge, but the existing strands are taken 5 FINITE ELEMENT MODELS, PERFORMED
out progressively and replaced with new stays of ANALYSES AND RESULTS
circular form. This time, the existing stays C1-C10
and C5-C6 were replaced each by three equivalent In order to establish the stress state in the structural
stays and stays C4-C7 by two equivalent stays. The elements and the displacements level of the bridge
diameters of these new stays are smaller with respect components before, during and after strengthening
to those used in the first solution. process, several finite elements were built. Using
these finite elements, linear and nonlinear static
analyses were performed and based on these, the de-
sign of the new introduced steel components, tempo-
rary cables and new stays could be performed.
For establishing the stress state in the existing,
temporary and new cables of the bridge a full 3D fi-
nite element model was used (Fig. 14).

Figure 12. The second solution for the change of existing stays

The third solution consists in changing the strands


forming the cross section of each existing stay, one
by one and replacing them by new undamaged
strands (Fig. 13). This operation will be done also
symmetrically with respect to the bridge longitudinal
axis. Figure 14. The used global finite element model
The first and the second solution have the ad-
vantage that the new stays will have a compact cir- For the piers and pylon two joint straight frame fi-
cular shape of the cross section, reducing the unfa- nite elements were used. The stay-cables were mod-
vorable effect of wind and improving the bridge eled using cable finite elements with nonlinear be-
behavior. Also, the time required for the changing havior, which can take into account the changing in
process is significantly smaller comparing with the stiffness due to the axial force level and the de-
formed shape of the cable. For the deck, four nodes cables, placed on the pylon and under the bridge
finite elements with combined membrane and shell deck could be performed. Thus, other finite element
behavior were used (Fig. 15). model were built and analyzed.
In Figure 16 a detailed deformed view of the fi-
nite element model of the steel ring are presented.
For the model, isoparametric thin shell finite ele-
ments were used. Special supports conditions were
imposed into the model in order to simulate the con-
tact existing between the two lateral faces of the
steel ring and the pylon legs. The loads acting on the
model were considered the axial forces in the tempo-
rary cables calculated using the global finite ele-
ments model and the staged nonlinear analysis. For
safety reasons, the axial forces were increased up to
the values corresponding the ultimate resistance of
Figure 15. Detailed view of the finite element model at the the steel in the strands used for the temporary cables.
deck level Based on this, the considered dimensions for the
cross section of the girders forming the ring as well
The values of the axial forces in the damaged cables the position and the thickness of steel plates could be
at the moment of introduction in the structure of checked. Under these extreme loading conditions,
temporary cables was established based on a nonlin- the displacements of some parts of the ring with the
ear staged analysis, considering all the execution values of 2-3mm were below the allowable limits
stages performed until the opening of the bridge in and equivalent von Mises stress distribution indi-
1984. Based on the observations on the site per- cates that only punctually, the values are over-
formed and summarized each week, the area of the passing the yield strength of the steel with the max-
remaining cross section of each cable was estimated imum values of 703N/mm2.
and starting from this parameter, the necessary cross
section of each temporary cable and the correspond-
ing value of the axial forces needed for tensioning
could be calculated.

Table 1. Measured on the site and calculated values of the axial


forces in temporary cables in the first tensioning stage
__________________________________________________
Cable Measured axial force ___________________
________________ Calculated axial force
kN
__________________________________________________ kN
C1 2216.90 2173.10
C10 2215.50 2174.00
C2 592.70 734.40
C9 500.20 734.50
C3 1016.00 948.60
C8 966.70 956.30 Figure 16. Detailed view of the deformed shape of the ring un-
C4 879.30 816.70 der considered loads
C7 846.60 818.90
C5 1175.70 1027.80 In Figure 17 the contours of equivalent von Mises
C6 1151.30 1029.60 stresses are shown.
In Table 1 the calculated and measured on the site
values of the tensioning forces for the first stage of
strengthening are given. It can be seen that is a good
accordance between measured and calculated values
with one exception for the cables C2 and C9. These
temporary cables are near to the pier P1 so they are
not so efficient in reality. In the finite element model
the real bearing of the structure on the pier could not
be exactly modeled.
In order to change the existing damaged stay-
cables, a desired calculated deformed shape of
bridge was obtained by re-tensioning the temporary
cables. Using these forces, the design of the steel
Figure 17. Contours of the von Mises stresses
structures, needed for the anchorage of temporary
A separate finite elements model (Fig. 18) was con- severe damage by corrosion. Several solutions for
sidered for the steel elements placed under the the strengthening were studied and finally, based on
bridge deck, where the anchorages for the temporary technical, economical and ease in execution aspects,
cables were placed. The gauge of these elements was one solution was chosen. This solution implies to
limited, because there should be placed near to the use of some temporary cables, appropriate ten-
anchorages of existing damaged cables. sioned, to sustaining the deck during the strengthen-
ing process. The complexity of the problem lead to
use of several complex finite elements models for
establishing the deformations and stress state in all
bridge elements and for the correct design of the
new steel structural elements needed for the
strengthening process.
At this time, the strengthening operation is going
on and the bridge will regain a safety coefficient
which allow the future use in very good conditions.

REFERENCES

Dumitrescu, N., Popa, N. and Popa, V., 1995. The new road
bridges over the Romanian navigable canals. Proceedings
of “The Second International Conference – Bridges over
the Danube”, 11-15 September 1995, Bucharest, 347-356.
Gimsing, N.J., 1983. Cable Supported Bridges-Concept and
Figure 18. Model used for the steel elements placed under the Design. John Wiley&Sons Ltd., London.
bridge deck Pododlny, W. and Scalzi, J.B., 1986. Construction and Design
of Cable Stayed Bridges–Second Edition. John
Wiley&Sons Ltd., London.
Troitsky, M.S., 1988. Cable Stayed Bridges: Theory and De-
sign-Second Edition. BSP Professional Books.
Walther, R., Houriet, B., Isler, W., Moïa, P. and Klein, J.F.,
1999. Cable Stayed Bridges-Second Edition. Thomas Tel-
ford Publishing, London.
Mehlhorn, G., 2010. Handbuch Brücken. Entwerfen, Kon-
struiren, Berechnen, Bauen und Erhalten. Springer Verlag
Berlin.

Figure 19. Contours of von Mises stresses under considered


loads

Using this model, these steel elements were checked


in order to avoid resistance and loss of stability
problems that can occur under the considered loads.
Moreover, the bolted connections between the flang-
es of the girders forming the bridge deck and the up-
per flanges of the steel pieces used for the anchorag-
es were also correct designed. The values of the
displacements and the peak values of the von Mises
stresses (Fig. 19) were below the allowable limits.

6 CONCLUSIONS

In this paper the strengthening solution of an old ca-


ble-stayed bridge over Danube is presented. Due to
the lack in maintenance and climatic conditions, the
wires which are forming the existing stays suffered

También podría gustarte