Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Revision 1
[CLIENT LOGO]
Applicability All
[Sub-contractor LOGO]
Document Type Inspection & Test Plan
ITP-TEL-0002 Page 1 of 5
Document Number Document Title Revision
References:
PEC-QU-ITP-X-10849 : ITP-Installation of Electrical Power & Control Cables
PEC-QU-ITP-X-10859 : ITP-Installation of Cable Tray/Ladder & Conduit System
PEC-QU-PRO-X-11620 : QCP-Installation of Fiber Optic Cables
PEC-QU-PRO-X-11690 : QCP-Installation and Inspection Requirements for Certified
Electrical Equipment
PEC-QU-PRO-X-11151 : QCP-Closed Loop RFI & Inspection Control Procedure
PEC-QU-PRO-X-11152 : QCP-Control of Inspection, Measuring and Test Equipment
PEC-CM-PRO-X-6969 : CMP-Instrumentation Installation
PEC-CM-PRO-X-6971 : CMP-Instrumentation Testing
PEC-CM-PRO-X-7011 : CMP-Cable Installation
PEC-CM-PRO-X-7017 : CMP-Construction Electrical Testing
PEC-CM-PRO-X-7007 : CMP-Material Receiving
Notes:
This document and referenced ITRs shall be applied to Construction/Inspection & Test activities
carried out on OEC Project Sites.
This document is based on widely used international codes, standards and good engineering practice
that is applied in Oil & Gas Projects and is intended to highlight the minimum tests and inspections
that ensure quality requirements are fulfilled within the scope of the document.
This document and referenced ITRs are generated to provide guidelines to Petrofac OEC Project
teams including their sub-contractors during preparation of project specific ITPs/ITRs and shall be
customized to meet specific requirements based on applicable project specifications and/or other
statutory and regulatory requirements. It may also be utilized at bidding/proposals stage.
In case of any conflict between project specification, drawings and applicable code, project
specifications shall take precedence over this ITP and applicable ITRs.
This ITP serves primarily as a plan and it shall NOT be used to obtain signatures. Acceptance
signatures shall be obtained on the referenced Inspection and Test Record, which shall form part of
generic records to be handed over to the Client.
The referenced Inspection and Test Records (ITRs) are controlled independently. Therefore, the
latest revision of these ITRs, at the time of initiation, shall be utilized.
ITR number suffixed with letter “X” are classified as in-process Site/Field Quality Records and will
not be part of the Turnover System Process where as ITR number suffixed with letter “A” are part of
the Turnover Process and Turnover Records.
When filling ITRs do not leave any blanks. If an item/activity is not applicable, denote as N/A.
ITP-TEL-0002 Page 2 of 5
Document Number Document Title Revision
Inspection Codes: SC: Subcontractor PEC: Petrofac C: Company/Client TP: Third Party
I: Inspection/ Test R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
Purchase Order
Material Inspection a.Visual inspection to ensure no No damage and Material Purchase
Delivery Note
(subject to provisions of physical damages, all materials are Controller Order
2.0 Data Sheet R R S
Project Material Receiving materials are in accordance correct as per Material Delivery Note
Project Material
Procedure) with project requirements requirement Inspector Data Sheet
Receiving Procedure
a.Review of applicable
List of latest Site Engineer
Drawings and Documents drawings/documents and Complies with AFC
3.0 revision of Telecom QC NIL R R R
status ensure that latest revision is document register
applicable drawings Inspector
available at site
ITP-TEL-0002 Page 3 of 5
Document Number Document Title Revision
Inspection Codes: SC: Subcontractor PEC: Petrofac C: Company/Client TP: Third Party
I: Inspection/ Test R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
ITP-TEL-0002 Page 4 of 5
Document Number Document Title Revision
Inspection Codes: SC: Subcontractor PEC: Petrofac C: Company/Client TP: Third Party
I: Inspection/ Test R: Document/Report Review S: Surveillance RR: Random Review
H: Hold Point (Notification Required & Presence is Mandatory) W: Witness Point (Notification Required but Presence is not Mandatory)
ITP-TEL-0002 Page 5 of 5