Documentos de Académico
Documentos de Profesional
Documentos de Cultura
com
14. CONTRACT COSTING
SOLUTIONS TO ASSIGNNT PROBLEMS
Problem No.1
Contract A/c
Particulars Amount Particulars Amount
To Materials A/c 5,000 By Work - in - Progress
Work Certified 10,000
Work Uncertified 3,800 13,800
To Direct labour A/c 4,600 By closing stock of raw Materials 950
To indirect labour A/c 640
To overhead expenses 1,950
To Depreciation on plant 125
To Notional Profit 2435
14,750 14,750
To P & L A/c 1,623 By Notional Profit 2,435
To Reserve A/c 812
2,435 2,435
Balance Sheet
Particulars Amount Particulars Amount
Plant 12,000
Less: Depreciation 125 11,875
Net Profit 1,623 Closing Stock of raw Materials 950
Work - in - Progress 13,800
(-) Reserve 812 12,988
Problem No.2
st
1. Contract Account for the year ended 31 March
Notes:
Work Certified Rs. 79,90,000
a. Percentage of Completion = = = 87.80%
Contract Pr ice Rs. 91,00,000
2 Cash Re ceived
b. So, Profit trfd to P&L A/c = x Notional Pr ofit x
3 Work Certified
2 Rs. 71,91,800
= x Rs. 4,19,510 x = Rs. 2,51,708
3 Rs. 79,90,000
st
2. Balance Sheet as on 31 March (Abstract)
Liabilities Rs. Assets Rs.
Profit and Loss A/c 2,51,706 Fixed Assets:
Current Assets:
Contract Work-in-Progress
Work Certified 79,90,000
Work Uncertified 3,17,000
Plant (WDV) at Site (See Note a) 6,16,000
Materials at Site 85,400
Sub-Total 90,08,400
Current Liabilities: Less: Reserve Profit (or Profit-in- (1,67,804)
Reserve)
Wages Accrued 78,120 Net – Total 88,40,596
Direct Expenses Accured 9,310 Less: Contractee’s Account balance (71,91,000)
Net Value of Contract WIP 16,49,596
Note:
a. WDV ofPlant at site can also be shown under the heading “Fixed Assets”.
b. The above is only an extract of the Balance Sheet. Hence, Totals are not drawn up.
Problem No.3
Note: Profit of Rs.21,000 is to be entirely taken to P & L Account, since contract is fully complete and all
cash is received.
Problem No. 4
In the books of contractor
Dr. Contract A/c for the year ended 31.12.1988 Cr.
House House House House
Particulars Particulars
A B A B
To Opening Work in Progress 14,000 - By Materials at site 400 540
To Materials 23,000 16,600 By Work in
To Wages 20,000 14,000 progress:
To Electrical Fittings 1,400 300 - Work certified - 36,000
To Road making charges 8,000 - (24,000 x 2/3)
To Establishment charges 7,200 5,040 - Work uncertified - 2,500
(12,240-20:14)
To depreciation on plant 1,000 400 By Contractee A/c 60,000 -
(12,000×10 (6,000 ×
% ×10/12) 10%×8/12) By P& L A/c (Loss) 14,200 -
To National Profit - 2,700
39,040 39,040
To P & L A/c (Profit) (W.N-1) - 1,200 By National Profit 2,700
To Work in Progress reserve - 1,500
74,600 2,700 74,600 2,700
Problem No.5
Brock Construction Ltd. Contract A/c
(November 1, 2003 to Oct. 31, 2004)
Brock Construction Ltd. Contract A/c (November 1, 2003 to March 31, 2005)
(For computing estimated profit)
Amount Amount
Particulars Particulars
(Rs.) (Rs.)
To Material issued 19,12,500 By Material at site 37,500
(6,75,000+12,37,500)
To Labour (paid & 10,15,000 By Plant returned to 64,583
outstanding) stores on 31/3/04
(4,25,000+5,87,500+2,500)
To Plant purchased 3,75,000 By Plant returned to 1,72,222
stores on 31/3/05
Problem No.6
In the books of Rex Ltd.
Dr. Contract A/c for the year ended 31-12-1988 Cr.
Particulars Amount Particulars Amount
To Materials 75,000 By Materials at site 5,000
W.N-1: Statement showing calculation of cost to date, estimated cost to be incurred, total cost
Particulars Amount
Contract Price 4,50,000
Less: Cost incurred to date (W.N-1) 1,49,000
Less: Estimated cost to be incurred (W.N-1) 2,35,000
Estimated Profit 66,000
Profit to be taken to Profit & Loss A/c: 26,400
cash received 1,80,000
Estimated Profit × = 66,000 ×
contract price 4,50,000
Working notes:
Cost of work certified 100 lacs
1. Percentage of contract completion = x100 = x100 = 92.59%
Value of the Contract 108 lacs
2. Since the percentage of Contract completion is more than 90% therefore the profit to be
taken to Profit and Loss Account can be computed by using the following formula.
Cash received Work certified
Profit to be taken to P & L A/c = Budged/Estimated Profit x x
Work certified Contract price
7,200 10,000 7,200
= 1,800 x x = 1,800 x = Rs. 1,200
10,000 10,800 10,800
Problem No.8
Problem No. 9
Calculation of claim under escalation clause
Standard Deviation in Escalation
Material Contract Price Actual Price
Quantity price claim
A 500 50 45 (5.00) (2500)
B 1000 30 35 5.00 5,000
C 20 1000 1010 10.00 200
Claim for Materials 2,700
Standard Deviation in Escalation
Labour Contract Rate Actual Rate
hours price claim
X 4,800 2.00 2.25 0.25 1,200
Y 2,400 1.00 1.50 0.50 1,200
Z 9,600 1.50 1.50 0 -
Claim for Labour 2,400
Total claim under Escalation clause = 2,700 + 2,400 5,100
Note: Actual Quantity and Actual Hours need not be considered.
THE END