Está en la página 1de 4

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

A A
UF
UF-80-PE-18-50 FROM 223000-PE-PE-400-0018.DWG

UF-80-PE-18-50

TI
4701

B B
TIT
4701

50

50
UF-50-PE-47-01

XV4701 HV4701

C C
Lube Oil Skid
P1804
(See Drawing 223000-PE-PE-400-0048)

UF-50-PE-47-04

D D
TI

UF-80-PE-18-50
4702

TIT
4702

E E

RED4702

80x50
50

50
UF-50-PE-47-02

XV4702 HV4702

F TI
F
4703

Lube Oil Skid


P1805
(See Drawing 223000-PE-PE-400-0049) TIT
4703

UF-50-PE-47-05

G G

UF-80-PE-18-50
UF-80-PE-47-01

H H

RED4701

80x50
50

50
UF-50-PE-47-03

XV4703 HV4703
I I
TI
4704

Lube Oil Skid


P1806
(See Drawing 223000-PE-PE-400-0050) TIT - - - - - - - -
4704 - - - - - - - -
11 26/05/14 First Issue MEX - JS JIL ACGP
J UF-50-PE-47-06
Rev. Date Description Drn.
Str. Mech. Elec. Inst. J
Approved by
Owner:
REPUBLIC OF GHANA
Befesa Desalination
Project:
60 MLD Sea Water Developments Ghana LTD
Desalination Plant Nungua
UF Contractor:
80 Date Name Signature
UF-80-PE-47-01 UF-80-PE-47-01 Drawn 26/05/2014 MEX
K TO 223000-PE-PE-000-0035.DWG Designed 26/05/2014 FPV
K
HV4704
Checked 26/05/2014 MEB
ABEIMA TEYMA GHANA
Dept.Head 26/05/2014 APA
Proj.Mgr. 26/05/2014 PRH
Title: Off-Taker:
P&ID
Process Diagram
Cooling Lube Oil System
Ghana Water Company LTD.
L Dwg.No. 223000-PE-PE-400-0047 Dept. - - Job No. - Sheet : 1 of 1 Rev. L
Scale. N.T.S. Original Format : A1 11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

LEGEND
A A
Gate Valve TI Temperature Indicator

Plug TW Thermowell
I

Breather Filter & Filter Strainer


Change-Over Inline Filter
UF UF

TO 223000-PE-PE-400-0047.DWG UF-50-PE-47-01 I
B UF-50-PE-47-04 FROM 223000-PE-PE-400-0047.DWG
B
Level Gauge
Manifold 1/2

LG Level Gauge

UF-50-PE-47-01
UF-50-PE-47-04
PI (PG) Pressure Indicator (Gauge)
Electric Heater
PSLL Pressure Switch Low-Low
TS Temperature Swicth
PSL Pressure Switch Low
Foot Valve

C Pump C
R4 R3 Junction Box
M Electric Motor

Check Valve
DPIS Diff. Pressure Indicator Switch
Relief Valve

Heating Exchanger Manifold 2/5


TS TI PI (PG) PSLL PSL
DPIS
4801 4801 4801 4801 4801
D 4801 13
Excess Pressure Valve TSH Temperature Switch High
D

CONNECTIONS

TP1 DESCRIPTION SIZE RATING

TP1 Oil Injection 40 ASME B 16.5 CL. 150 R.F.


E E
TP2 Oil Suction Main Pump 40 ASME B 16.5 CL. 150 R.F.

TP3 Oil Injection Main Pump 32 ASME B 16.5 CL. 150 R.F.

TP4 Oil Return 50 ASME B 16.5 CL. 150 R.F.

TP5 Oil Return 50 ASME B 16.5 CL. 150 R.F.

LOD Lube Oil Drain 20 ASME B 16.5 CL. 150 R.F.


I FOC Fill Oil Connection 50 -----

F 80
TW
R3 Cooling Water Inlet 50 ASME B 16.5 CL. 150 R.F. F
TP1 R4 Cooling Water Outlet 50 ASME B 16.5 CL. 150 R.F.
Oil Injection

TP3
G Oil Injection Main Pump G
6 BAR

1,5 BARG

Delivery Flow: ~65 lts/min TP5


TP2
Oil Suction Main Pump n: 1420 rpm Oil Return
N: 1,5 kW
400V(Y)-50Hz TP4
H M FOC
Oil Return
H

LG

I 4801
I

Oil Tank
Level LOD
- - - - - - - -
- - - - - - - -
11 26/05/14 First Issue MEX - JS JIL ACGP
TSH
J 4801 Rev. Date Description Drn.
Str. Mech. Elec. Inst. J
1,5 Kw Approved by
230V-50Hz Owner:
REPUBLIC OF GHANA
Befesa Desalination
Project:
60 MLD Sea Water Developments Ghana LTD
Desalination Plant Nungua
Contractor:
Date Name Signature
Drawn 26/05/2014 MEX
K Designed 26/05/2014 FPV
K
Checked 26/05/2014 MEB
ABEIMA TEYMA GHANA
Dept.Head 26/05/2014 APA
Proj.Mgr. 26/05/2014 PRH
Title: Off-Taker:
P&ID
Process Diagram
Lube Oil System Pump P1804
Ghana Water Company LTD.
L Dwg.No. 223000-PE-PE-400-0048 Dept. - - Job No. - Sheet : 1 of 1 Rev. L
Scale. N.T.S. Original Format : A1 11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

LEGEND
A A
Gate Valve TI Temperature Indicator

Plug TW Thermowell
I

Breather Filter & Filter Strainer


Change-Over Inline Filter
UF UF

TO 223000-PE-PE-400-0047.DWG UF-50-PE-47-02 I
B UF-50-PE-47-05 FROM 223000-PE-PE-400-0047.DWG
B
Level Gauge
Manifold 1/2

LG Level Gauge

UF-50-PE-47-05

UF-50-PE-47-02
PI (PG) Pressure Indicator (Gauge)
Electric Heater
PSLL Pressure Switch Low-Low
TS Temperature Swicth
PSL Pressure Switch Low
Foot Valve

C Pump C
R4 R3 Junction Box
M Electric Motor

Check Valve
DPIS Diff. Pressure Indicator Switch
Relief Valve

Heating Exchanger Manifold 2/5


TS TI PI (PG) PSLL PSL
DPIS
4901 4901 4901 4901 4901
D 4901 14
Excess Pressure Valve TSH Temperature Switch High
D

CONNECTIONS

TP1 DESCRIPTION SIZE RATING

TP1 Oil Injection 40 ASME B 16.5 CL. 150 R.F.


E E
TP2 Oil Suction Main Pump 40 ASME B 16.5 CL. 150 R.F.

TP3 Oil Injection Main Pump 32 ASME B 16.5 CL. 150 R.F.

TP4 Oil Return 50 ASME B 16.5 CL. 150 R.F.

TP5 Oil Return 50 ASME B 16.5 CL. 150 R.F.

LOD Lube Oil Drain 20 ASME B 16.5 CL. 150 R.F.


I FOC Fill Oil Connection 50 -----

F 80
TW
R3 Cooling Water Inlet 50 ASME B 16.5 CL. 150 R.F. F
TP1 R4 Cooling Water Outlet 50 ASME B 16.5 CL. 150 R.F.
Oil Injection

TP3
G Oil Injection Main Pump G
6 BAR

1,5 BARG

Delivery Flow: ~65 lts/min TP5


TP2
Oil Suction Main Pump n: 1420 rpm Oil Return
N: 1,5 kW
400V(Y)-50Hz TP4
H M FOC
Oil Return
H

LG

I 4901
I

Oil Tank
Level LOD
- - - - - - - -
- - - - - - - -
11 26/05/14 First Issue MEX - JS JIL ACGP
TSH
J 4901 Rev. Date Description Drn.
Str. Mech. Elec. Inst. J
1,5 Kw Approved by
230V-50Hz Owner:
REPUBLIC OF GHANA
Befesa Desalination
Project:
60 MLD Sea Water Developments Ghana LTD
Desalination Plant Nungua
Contractor:
Date Name Signature
Drawn 26/05/2014 MEX
K Designed 26/05/2014 FPV
K
Checked 26/05/2014 MEB
ABEIMA TEYMA GHANA
Dept.Head 26/05/2014 APA
Proj.Mgr. 26/05/2014 PRH
Title: Off-Taker:
P&ID
Process Diagram
Lube Oil System Pump P1805
Ghana Water Company LTD.
L Dwg.No. 223000-PE-PE-400-0049 Dept. - - Job No. - Sheet : 1 of 1 Rev. L
Scale. N.T.S. Original Format : A1 11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

LEGEND
A A
Gate Valve TI Temperature Indicator

Plug TW Thermowell
I

Breather Filter & Filter Strainer


Change-Over Inline Filter
UF UF

TO 223000-PE-PE-400-0047.DWG UF-50-PE-47-03 I
B UF-50-PE-47-06 FROM 223000-PE-PE-400-0047.DWG
B
Level Gauge
Manifold 1/2

LG Level Gauge

UF-50-PE-47-06

UF-50-PE-47-03
PI (PG) Pressure Indicator (Gauge)
Electric Heater
PSLL Pressure Switch Low-Low
TS Temperature Swicth
PSL Pressure Switch Low
Foot Valve

C Pump C
R4 R3 Junction Box
M Electric Motor

Check Valve
DPIS Diff. Pressure Indicator Switch
Relief Valve

Heating Exchanger Manifold 2/5


TS TI PI (PG) PSLL PSL
DPIS
5001 5001 5001 5001 5001
D 5001 15
Excess Pressure Valve TSH Temperature Switch High
D

CONNECTIONS

TP1 DESCRIPTION SIZE RATING

TP1 Oil Injection 40 ASME B 16.5 CL. 150 R.F.


E E
TP2 Oil Suction Main Pump 40 ASME B 16.5 CL. 150 R.F.

TP3 Oil Injection Main Pump 32 ASME B 16.5 CL. 150 R.F.

TP4 Oil Return 50 ASME B 16.5 CL. 150 R.F.

TP5 Oil Return 50 ASME B 16.5 CL. 150 R.F.

LOD Lube Oil Drain 20 ASME B 16.5 CL. 150 R.F.


I FOC Fill Oil Connection 50 -----

F 80
TW
R3 Cooling Water Inlet 50 ASME B 16.5 CL. 150 R.F. F
TP1 R4 Cooling Water Outlet 50 ASME B 16.5 CL. 150 R.F.
Oil Injection

TP3
G Oil Injection Main Pump G
6 BAR

1,5 BARG

Delivery Flow: ~65 lts/min TP5


TP2
Oil Suction Main Pump n: 1420 rpm Oil Return
N: 1,5 kW
400V(Y)-50Hz TP4
H M FOC
Oil Return
H

LG

I 5001
I

Oil Tank
Level LOD
- - - - - - - -
- - - - - - - -
11 26/05/14 First Issue MEX - JS JIL ACGP
TSH
J 5001 Rev. Date Description Drn.
Str. Mech. Elec. Inst. J
1,5 Kw Approved by
230V-50Hz Owner:
REPUBLIC OF GHANA
Befesa Desalination
Project:
60 MLD Sea Water Developments Ghana LTD
Desalination Plant Nungua
Contractor:
Date Name Signature
Drawn 26/05/2014 MEX
K Designed 26/05/2014 FPV
K
Checked 26/05/2014 MEB
ABEIMA TEYMA GHANA
Dept.Head 26/05/2014 APA
Proj.Mgr. 26/05/2014 PRH
Title: Off-Taker:
P&ID
Process Diagram
Lube Oil System Pump P1806
Ghana Water Company LTD.
L Dwg.No. 223000-PE-PE-400-0050 Dept. - - Job No. - Sheet : 1 of 1 Rev. L
Scale. N.T.S. Original Format : A1 11

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

También podría gustarte