Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Kampala
e-mail: Solomon.balemezi@gmail.com
NOVEMBER 2018
Table of contents
1 Introduction ...................................................................................................................... 3
1 Introduction
This report entails a storm water management plan for the already constructed mixed
use building along Plot 146 Block 9 along Apollo Kagwa Road in Old Kampala. The
report was a result of the neigbour along plot 147 staging a complaint to KCCA. The
purpose of the report is to deduce the hydrological parameters that will be used to
carry out hydraulic checks and check the current drainage system and propose any
changes if any. This will provide a technical justification of any drainage decision
taken in relation with drainage
SITE
The plot therefore acts a conduit of these attenuated flows from the upstream
catchment areas to the low lying sections of the catchment.
This therefore implies that the plot is a critical drain outlet for upstream. This analysis
will therefore take this consideration and all the critical parameters for both the sub
basin and basin as a whole
In the southern part of the plot, there is road side channel that conveys water from
the upstream sections of the section .through a terrain culvert which is
downstream to Nsalo road . However the velocity in the channel is so high that is
causing scouring the channel base and causing deterioration of the channel as
whole. This is shown in the figure 3 and 4 below
Figure 3 and 4: Deterioration of channel side walls and base due to high flows
Within the Project premises, there exists a reinforced concrete U- channel which is
approximately 0.8m wide 0.5m deep. The channel runs along the entire perimeter
wall in the southern western part of the plot a s shown in the figure 5. In addition,
the channel is aimed at draining the offsite runoff generated from Plot 147 and
beyond through the entry point shown in the figure 6.
Finally the channel shown above, discharges into a stone pitched tributary channel
shown in the figure 7 below which in turn discharges into the road side channel
shown in the figures 3 and 4 shown above
Figure 7: Tributary that discharges runoff from the site to the Public
Channel
The hydraulic component routes the storm water that results from the hydrologic
component through the conveyance system. The hydraulic component evaluates the
conveyance system’s capacity to route the design storm and is used to identify areas
that may be prone to flooding. The hydraulic analysis depends on geometry (size,
shape and slope) and other characteristic data of the pipe and channel system to
estimate capacity.
2 Hydrologic Analysis
The rational formula will be used to deduce the discharge values for onsite
catchment as per the table below.
𝑸 = 𝑪𝑰𝑨
This software provided the geospatial analysis environment where all the spatial
analysis and mapping of the channel catchment was carried out.
ARCSWAT 2012
This was embedded in ARCGIS and it was used in drainage area delineation as
described in detail in the proceeding section.
Figures 8 and 9 show the delineation map assuming an outlet at the main basin
Table 2
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average
Rainfall
(mm) 735 702 1307 1609 1109 576 540 1042 1296 1570 1686 1216 1116
1800
1600
1400
1200
Rainfall(mm)
1000
800
600
400
200
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month
From the table and graph above we deduce that the two precipitation components
needed for a hydrologic analysis are:
The total depth of precipitation for the design storm event
The rainfall distribution over the duration of the storm event
The storm hyetograph (rainfall intensity versus time) is needed. The largest rainstorm
recorded by the digital rainfall station at (90.4mm occurred in November 2012.) To
obtain a 120mm a scaling factor of 1.13 has been considered for extreme events as
while maintaining its basic temporal characteristics (see figure below). The modeling
event shows a peak intensity of more than 120 mm/hr and a shorter duration.
Table 3
Kampala Drainage Master Plan 2016-Under drainage guidelines extracted as per table
1 below.
𝑸 = 𝟎. 𝟕𝟓 ∗ 𝟑. 𝟔
=2.745m3/s
Note from the table above , the critical values have made bold in the output section
. Therefore if this option is to be implemented, the top width must be made at least
1.2m assuming a side slope of 10% side slope
Given that the average velocity is above the critical velocity , concrete of C30 and
scour checks (steps ) should be constructed every 30m along the channels to
gradually reduce the average velocity below the critical velocity
and the side slope and velocity parameters as in option one are followed since even
in this case the average slope is above the critical velocity