Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Task 01:
1.1 (a) Explain in detail what are the factors and usage considered when proposing the earthmoving equipment needed for this
project.
According to the given details this project is exploited within the city limits of Colombo, (adjacent to main Colombo – Galle
road) and one boundary facing private properties with multi-storied buildings which is :
Highly populated
Has a large traffic
Therefore when selecting equipment’s for earthmoving equipment’s we must consider factors like:
Size of machine
Possibility of transportation with the traffic in Galle road.
Check whether equipment can be transported to site.
Consider whether the roads are able to bear the load of machines.
Consider whether equipment’s can be moved around the plot without damaging the existing buildings.
Considering all these factors we cannot recommend very large earthmoving equipment’s which is difficult to
transport and handle.
Consider the soil conditions, (sandy soil – non-cohesive , sandy clay – partially cohesive)
Natural Ground
Sandy Clay
(1.2m)
1
Sandy
(30.0m)
Rock
(b) Select and recommend the most suitable combination of equipment for this project from the given list.
Selected equipment’s :
Back-hoe excavator and front-end loader (Back-actor)
Bulldozer ( if backhoe is not sufficient )
Dump trucks
Skimmers
Dragline
* Back-hoe excavator:
Can be used as multi-purpose equipment with It digs earth backward rather than
other attachments (tilt rotator, breaker, grapple, For digging earth lifting it with forward motion like a
or with a frontend loader etc.) bulldozer.
2
Can also be used as a crane and also like a Easy to use as it can perform many
bulldozer. activities rather than having to select
many equipment’s separately.
* Bulldozer:
* Dump trucks:
Why dump truck is selected For what purpose we use it Properties
* Easy to use To transport soil from one place to Brand -TATA LPK 3118 TC
* Because its designed for large- another.
capacity loads Dump capacity: 18m3
* Can carry for a large distance. Normal capacity- 5 to 15m3
* Skimmers:
3
For what purpose we use it
* For surface excavation and for
leveling upto300mm depth.
* Can also use for loading.
* Dragline:
1.2. Discuss appropriate techniques used to ensure safe and productive activities during excavation of basement for multi-storied
building.
Shoring:
For deep excavations in basements and cut and cover structures require :
Secure earth & Groundwater retention.
For a bottom up excavation where the excavation is temporary support, this support is not a part of the final structure.
Methods:
Permanent or temp retaining walls
4
Steel sheet pilling with temp propping
Retaining walls using ground anchors
Etc.
For this excavation we select sheet piles as the shoring method.
Dewatering system:
Dewatering is the removal of water from solid material or soil by different industrial processes.
For the purpose of dewatering we can select either sump ditches, or diaphragm walls, but for this project we select sump because diaphragm
walls are very expensive. Sump pumping is the simplest dewatering system we can use for this project. It allows groundwater to seep into
excavation and then it is collected in sumps and pumped away for disposal. Sump is equipped with a robust pump therefore it gets the needed
capacity to handle a considerable amount of solids. Sump pumps are very effective to use in this project of dewatering it is economic as well
compared to diaphragm walls. Sump system is best for well graded coarse soils such as sands, sandy gravels and coarse gravels, therefore this can
be considered as the best dewatering system for the given project as the soil condition given is sandy clay and sandy.
But if seepage of water in to the excavation occurs it creates a risk of instability and other construction problems to overcome this problem we
must lower the groundwater level before starting excavation known as pre-drainaging.
5
2.1. (a) Explain in detail (where, how and why) with annotated sketches the types given below:
* Sheet piling:
It’s a soil/earth retention and excavation support technique that retains soil. It’s made up of wood, concrete or steel.
Where sheet piling is used? How sheet pilling is used? Why sheet pilling is used?
* Used in soft/water logged soils * It’s installed in order of designed * Interlocked sheet piles form a wall
and tight spaces and for depth along the planned excavation for permanent or temporary lateral
complicated shoring. perimeter or seawall alignment. earth support with reduced
groundwater inflow.
* Used to support excavations for * They can also be hydraulically
below grade basements, parking pushed into the ground. * As its designed to provide a long
lots, foundations etc. service. (durability)
* It’s driven side by side into the
* Used as permanent steel sheet ground. * It’s sustainable as recycled steel is
piles are designed to provide a used.
long service. (durability)
* Piles can also be reused.
6
Cast–in–place Piling:
Cast-in-place piles are those which are cast in position inside the ground. The concrete pile is made by pouring concrete
into a tapered hole or cylindrical form which is previously driven into the ground. The left-in-place form may be a steel
shell which is heavy enough to be driven without a mandrel, or it may be a steel form designed for driving with a
mandrel that is removed after the driving is completed.
They are used when conditions are favorable. First method is with steel cores. To eliminate the need of pile driving
machine.
Can also be used in marine structures with Using precast sections for core of the pile.
bored piles. Not necessary to reinforce the pile in
Used after pouring concrete into a metal ordinary cases or in places where the
Used in places where light loads are to be shell or tube. pile is completely submerged in the
carried. soil.
Where precast concrete piles are used? How it’s used? Why precast concrete piles are used?
Used in marine and river structures. * Cast and cured in a casting * Used as they resist the stresses produced
Used in places where the use of cast in place yard.
piles is not practical or uneconomical. * They are driven in with
help of pile drivers.
Caissons:
It is a water-tight box like structure or chamber which is made of steel, wood or concrete.
Where caissons are used? How it’s used? Why caissons are used?
7
* In foundations which are to be laid * Sunk by excavating within it * They adopt when the depth
under water. and gaining access to bed of water is great.
stream and the placing the
* Used bridges in rivers and other foundations. * It’s used as rivers are used
water bodies. for navigation purpose and if
* Its built in the shore and more peers are used it will
* Used when piles or piers are not launched in to the river. obstruct the path way.
suitable.
* Then it’s sunk in proper * Use of cylindrical caissons
position. has more advantage than
using large board piles.
(b) What will you propose as the most suitable foundation for the proposed 6-storied building with basement car park?
As the soil condition is sandy clay and sandy and beneath its rock and the project is to build a 6-storied building with basement car park we select
a deep foundation considering the transferring of load and the differential settlement. Sand can hold together reasonably well when damp,
compacted and uniform, but if we use trenches it might collapse therefore we can use sheet pilling. Sheet piling can be used in this project to
support excavation of basement car park. To get a long service life we can recommend permanent steel sheet piles.
To install sheet piles we can use a vibratory hammer or we can either use a hydraulically push method. Sheet piling is cost effective as it can also
be reused.
2.2 (a) Explain why large span bridges (constructed on major highways) need complex or deep foundations such as Piling and Caissons.
* The functions of a foundation are:
Transferring of load from super structure safely to soil strata
Ensure minimum differential settlement.
* When transferring of loads is considered, bridges carry a very large weight of dead loads, live loads and wind loads and break
loads, foundation of bridge should ensure that the bridge will have an adequate structural capacity to support heaviest vehicles
or posted for load limits and weight of the bridge, impact of loads and breaking load due to lateral load. Weight of the bridge
and force bearing down on the soil (bearing pressure) should also be considered. Bridges must be able to bare the load of
vehicles, containers, trucks etc. passing over it. It should resist forces applied on it. It should also have the strength to resist
high winds or earthquakes. Load should be distributed evenly else it would break or crack. It should be durable while carrying
all these loads.
* When differential settlement is considered, as bridge is in water the differential settlement is high therefore we need a strong
deep foundation. Differential settlement occurs when soil beneath the bridge cannot bear the weights imposed. Bridges can
also collapse, sink or go under soil erosion due to differential settlement. Most bridges failure occurs due to either because of
inadequate hydraulic capacity (too small) or because of scour and undermining of foundation placed upon sine soil. Bridges
must also be able to handle the vibrations and pressures occurred by vehicles. It should be able to resist floods, overflowing of
water and high rains. Bridges must be able to resist the soil/earth movements. Differential settlement occurs when foundation
settle unevenly.
8
Therefore considering all these factors we suggest to use pilling or caissons (deep foundation) for large span bridges.
(b) Describe in detail (with sketches showing all stages) the method of construction of a caisson supported bridge peer.
* Step 01: Mark center line and set out then find the diameter. Get working space. (Refer figure 01 )
* Step 02: Assume the cylinder is placed at point A (Figure 02) of timber frame as shown in Figures.
* Step 03: Dewater and see the bed. Then using the crane the cylinder is lowered as showed in step 01 figure 02 at point C.
Then the cylinder will sink inside, when it sinks halfway another ring is placed and again it’s excavated. (Figure 03)
Due to the large surface area sinking will face a friction.
* Step 04: Then place a cantilever and again excavate. Cantilever must be placed on the edge (Figure 04).
* Step 05: Again dewater and drain it. (Figure 05)
* Step 06: Then remove the soft rock, reduce it to anchor length which is given by designer known as the pile anchoring. (Figure 06)
The rocks are then drilled and dowels are put into it. The dowels will be stainless steel dowels. Then put an additional reinforcement mesh.
Dowels are used for anchorage or to give additional reinforcement. (Figure 6.1)
* Step 07: Then continuously dewater, after dewatering concrete it, do an underwater concreting also. ( figure 07)
* Step 08: Use a flip bucket to pour concrete. (Figure 08)
2.3(a) Explain why sewer pipeline needs to be constructed to a designed gradient or slope?
Sewer lines are based on gravity flow.
Particles flow in sewer pipe because of pressure and gravity this occurs due to the head difference (from higher elevation to lower
elevation) therefore sewer lines should have a proper gradient or slope.
Flow depends on friction.
A designed slope of gravity drainage and sewer pipes is important for the liquids to flow smoothly, a proper gradient helps transport of
solids without letting it to clog.
Large sewer lines require a proper calculated pitch.
Sewer pipes need a proper gradient as it passes both solids and liquids and also self-cleans it.
The Q angle depends on the type of pipe material and the gradient.
The pipe should also have a smooth surface to make the flow smooth.
Sewer mains should be designed to have a minimum flow rate of 2 feet-per-second.
There should be different gradients at different levels and distances, as the same distance cannot be maintained everywhere.
(Figure 2.3)
(b) Illustrate with sketches the detail steps of construction from setting out to laying of 500m long, 150mm diameter, UPVC sewer
pipeline with slope or gradient at 1:80, with sufficient cover with suitable backfilling materials.
Step 01:
Initial checkups:
Walk the planned line of the sewer and identify the problems that might cause a disturbance to the setting out.
Get a clear idea on the layout plan, sections, manhole schedule and specifications and set the positions of backdrop
manholes and junctions, the size and types of pipes and the required
bedding with the necessary concrete protection.
Then mark the positions and place pegs and set out.
9
Center line pegs of the sewer must be driven at a distance of every 7.5 m or 15m.
Center line of the sewer line should be properly maintained by providing an off-set line usually marked at a distance of
2m to 3m.
Levels can be checked by excavating trial holes.
Step 02:
Control of line:
Distance of center line must be sufficient if a dual trench is used to allow clearance between the outside of the manhole
wall (or surround) and the adjacent sewer.
Then do the offsetting of center line, this can be done a according to the depth of trench.
The excavation can be done manually or by using machines.
Sufficient amount of pegs must be provided for re-establishing the center of manholes.
To obtain the intersecting points either place pegs on line with sewer or off-set at right angles to the line of the sewer.
For both given ways we need two pegs, then record the distances from both pegs to manhole.
Manhole dimensions may vary when branches come to sewer line.
We find drop man holes where the levels change in a sewer.
Step 03:
Controlling the level:
Use sight rails to one side of the excavation; this can be calculated by adding traveler.
After the first manhole is excavated transfer a level peg to the trench
bottom.
Set the construction laser up in the manhole or trench bottom to the correct level and align by theodolite with the
required gradient set of 1:80.
After setting up the laser check out the gradient carefully.
Check the horizontal alignment of dial grade using theodolite when a short length trench is open.
Step 04:
After laying of the sewer pipe between two manholes excavate again to lay the sewer pipe between next consecutive
manholes.The process is continued form the outfall end of the sewer towards the starting end till the entire sewers is laid
out.
It is started after the sewer line is properly laid in position, aligned, jointed and test for leakage and alignment.
10
DATE OF SUBMISSION: 04/04/2016
3.1. As a Civil Engineer / Design Engineer, it is essential to provide the most cost effective and practical building solution for the client. A
client needs a factory building in shortest time (less than 6-months) so that he could produce apparel to meet the prospective client’s
urgent orders. You have the following building options:
Reinforced concrete (RCC) building
Pre-fabricated or Pre-engineered Metal building
Pre-cast concrete building
(a) Considering the above building solutions available for you, what will you propose (out of these three options) for the client to
meet his immediate need?
Pre-fabricated/ pre-engineered metal Low cost materials Handling & transportation may
building. Need less time and manpower cause breakage.
Shuttering and scaffolding is not If damaged during transportation
needed company will not recover the loss.
Installation of building service and Difficult to connect units.
finishing can be done immediately Takes time to connect the units.
Components are produced with They are to be exactly placed in
close supervision position or the loads coming on
Good quality them are likely to get changed.
Clean and dry work at site Corrosions.
Easy to transport. High transport cost
Can move from place to place Need of an erection equipment
Possibility of alteration and reuse Need skilled labor and supervision.
Correct shapes, dimensions and Difficult to maintain.
sharp edges are maintained Expensive
11
Very thin section can be entirely Gain heat
precast with precision Fire explosions
Fast construction
Latest designed building structure
can be obtained.
Architectural flexibility
(b) Discuss with sketches the suitable construction method that you propose for the building solution which you have selected.
As the expected building is a factory which is supposed to be built within a short time period so that the spent amount can be
gained as profit. We can select a pre-fabricated or pre-engineered metal building.
The construction is very fast can be finished within the expected time.
Easy to construct or erect with trained labors.
The spent cost can be gained soon.
It needs a low maintenance cost.
3.2(a) What is the difference between false work and form work?
False work Form work
Consist of temporary structures or temporary supports. Temporary or permanent molds into which concrete or similar
Used to support precast girders, steel girders, etc. material is poured.
Used to support structure erections until it become self-supporting. Sometimes might also take the support of false work.
It’s a part of form work which supports forms.
Types: tube and fittings Types: foundation formworks,
Prefabricated systems Column formworks,
Special designed false work Slab formworks
Beam formworks
False work is separate from formwork. Formwork includes false work.
Can be stripped to expose the finished concrete.
12
Can be plastic, steel etc. Types:
Timber formworks
Pre-engineered formworks
Plastic formworks
Precast formworks etc.
Two forms:
Vertical =walls, piers, columns etc.
Horizontal= metal bridge decks.
(b) Explain the use of false work and formwork (using sketches or illustrations) in construction of:
13
Reinforced concrete beam and slab
arrangement at double height slab
14
REPORT
4.1. Group Assignment: (BCAS Offices) to carryout health and safety inspection. Access the hazards and degree of risks associated with
the assigned site:
Introduction: This is the report of the group assignment/Presentation which was conducted to identify the health and safety issues in the BCAS
Mount Campus.
Identifying hazards.
Deciding who might be harmed and how?
Evaluate risks and decide the needed precautions.
Recording the findings and implementing them
Reviewing the assessment
Risk assessment:
Identify hazard Who might get Precautions Risk level Repairing method
harmed?
Tripping and falling. Aluminum strips of Students, lectures, Nailing the broken High Replace the broken
stair case is removed minor staffs, other strips until it’s aluminum /steels strips
Fig 01 walkers. replaced.
Explosions *Keeping gas All those who come Having fire Medium Removing the
No fire extinguishers cylinders in the to BCAS. extinguisher. unwanted gas cylinders
library. and placing in proper
*Throwing areas.
cigarettes.
Fig 02, 03
15
Falling Falling into depths Students, minor staff, Putting up a danger Low Preventing students
Fig 04 lectures etc. notice from going to that area.
Cuttings Broken glasses Students, minor staff Covering the broken Medium Replacing the broken
Fig 05 area glasses.
Cracked or broken All If too much damage Medium Repair the cracked ares.
slab has occurred prevent
Fig 06 people from going to
that area.
Electric shocks Improper fixing of All Avoid touching it. Medium Fix proper coverings.
wiring covers
Fig 07
Electric shocks Improper fixing of All Avoid touching it. Medium Fix proper coverings.
plugs and plug
coverings. Avoid hanging on it. Fix the wires properly.
Fig 08
Hanging wires
Fig 09
Trip and fall Placing stones to All Walk carefully. Medium Use magnets instead of
prevent doors from stones.
closing. Use large stones which
Fig 10 are not sharp and easily Remove the stones from
visible. the walking path way.
Wires on the
classroom floor. Remove the unwanted
Fig 11 Lecturers and wires from the floor.
students
Placing buckets on Place the buckets in
the stair case after proper place.
working.
Fig 12 All
Falling Broken chairs in Students Don’t sit on broken Medium Remove or repair the
classrooms. chairs. broken chairs.
Fig 13
Slipping Water on the main Students Walk carefully. Medium Clean the steps.
stair way.
Fig 14 Clean the steps.
16
Damaging the Improper wiring. All Medium Proper wiring.
concrete Fig 16
Falling from height. Large windows All Don’t climb, peep High Fix drills, close the
placed in 3rd and 4th through or try to just windows if not needed.
floors from the windows.
Fig 17
Slip and fall Wet surfaces near All Walk carefully High Clean the floor tiles
washrooms. Don’t run or rush in always keep them dry.
Fig 18 those particular areas.
Damage in concrete water soaked All Medium Use proper plumbing.
slab. through the
concrete.
Fig 19
Cracks on the slab
Fig 20
Electric shocks Uncovered circuit All Medium Close the circuit main
boxes box.
Fig 24
Falling on to people Broken fans Students Avoid using that fan Medium Replace the broken fan.
Fig 25
Head injuries Lack of space gap Students Medium keep a proper gap
between roof and distance
staircase
Fig 26
Diseases due to dirty Impure water in the Students Avoid drinking impure Medium Keep the filters clean,
water filters placed in water and replace them if they
student area and are not functioning
canteen. properly.
Fig 27 Maintain the filters.
Hand injuries, cutting Uncovered steel Lecturers, students. Be careful while using Medium Cover the sharp edges
etc. edges near the white the white board. using rubber
board.
Fig 28
Lack of light/visibility No electricity Mainly students, Medium Buy a generator.
generator lecturers
17
Figure 01 Figure 02 Figure 03 Figure 04
Figure 13 Figure 14
Figure 15 Figure 16
18
Figure 19 Figure 20
Figure 17 Figure 18
Figure 22
Figure 23
Figure 24
Figure 21
Figure 25 Figure 28
4.2. Figure 27
Figure 26
19
Safe to use
Safe to maintain
CDM Revision:
Simplify and clarified.
Maximizing flexibility
Main focus on planning and management not only on paper work.
Strengthened coordination and cooperation requirements between designer and contractor.
Simplified assessment of competence.
According to CDM 2015:
Clients will have a number of new responsibilities.
If more than one contractor is on site, the client will be responsible for appointing a Principal Designer and Principal
Contractor.
Clients will be responsible for ensuring that the Principal Designer and Contractor are compliant with their
responsibilities.
In addition, the new regulations stipulate that it will be the client’s responsibility to notify the HSE of a project by
providing the F10 notification.
The Principal Designer will be a key duty holder.
Most of the duties will be taken by him, which are currently delivered by independent CDMCs and clients will be
responsible for ensuring that these requirements are fulfilled.
There is a full list of the new responsibilities in the draft guidance. Unlike the CDMC, the Principal Designer will work
within the project team itself, rather than as an independent safety specialist.
The new approach to ‘competence’.
Concept of competence is removed, and replaced with a legal obligation for those who appoint duty holders to ensure
they have the skills, knowledge and experience to carry out their duties.
4.3. Evaluate the role of the planning supervisor in civil engineering activities.
Planning supervisor is responsible for the overall administration of the engineering programs.
He also supervise, plan, and direct all section activities including development, administration, and control of program budget.
Preparing departmental recommendations on public policy issues, procedural requirements, plans and regulations.
Managing program implementation activities including monitoring and reporting on performance.
Managing projects like the scope of work, consultant contracts, intra-inter-jurisdictional project coordination, performance
evaluation, and meeting the project time and budget objectives.
Preparing and submissions of grants.
Communicating with community groups and citizens to solicit public involvement and city policies.
Preparing and presenting reports and recommendations to city council, community groups, and state federal agencies.
Supervising and evaluating performance of assigning staff, working as a coach, mentor, facilitator and trainer for workers and
interns.
A planning supervisor must always be punctual and must have a reliable attendance.
He/she should have the knowledge of:
Applicable federal, state and local policies and regulations.
Current principles and practices related to planning, policy development and implementations of program
related activities.
Traffic engineering principles, practices, standards and methods.
He should be able to:
Interpret and apply policies, regulations and laws to complex problems.
Monitoring the budgets, granting requirements and contracts.
Create innovative programs and projects.
Planning long term solutions to problems in assigned areas.
Coaching, mentoring and facilitating individuals and working teams, and interns etc.
Preparations and presenting clear, concise and comprehensive reports.
Working independently.
Establishing and maintaining effective service oriented team comprised of professionals and volunteers.
Supervising and performing complex and technical engineering duties in coordination and direction of traffic
engineering projects.
Developing and preparing technical drawings.
Preparing engineering plans, specifications and estimates.
20
He must have daily contacts with assigned staff for the purpose of supervision, direction, work coordination and information
gathering.
He must have meetings particularly with officials and general public.
He must be able to explain the city’s policies and practices under any circumstances.
He should ensure designers cooperated and must avoid risk.
Ensuring health and safety plan and health and safety file were prepared.
He must provide or ensure that the client provides relevant pre-construction information.
He has to coordinate the health and safety aspects of project design and initial planning to ensure as much as they can.
Preparing a health and safety plan.
Preparing or compiling the health and safety file.
He must be able to advise the client about health and safety plan.
Advising the clients about the adequacy and competence of designers and contractors.
Ensuring that the project is notified to the health and safety executive.
He must have the ability to communicate with many different individuals, and ability to state the city’s position clearly and
presenting.
Recommendations in a polite and professional manner.
21
5.1 Identify the key problems and issues inherent to construction industry in UK. After identifying the problems associated with the
construction industry, you are required to categorize the issues or problems accordingly:
Economical:
It has a low and unreliable rate of profitability
Margins are very low.
Capital investment is very low, for example: in-house R & D has fallen by 80% since 1981.
Capital cost in a project is very high, but clients need a lesser capital cost.
Economic cycles have affected the industry seriously over past decades and have meant that it has been forced to concentrate more on survival
than on future investments.
Technical:
Lack of investments is heading towards the fall of process of new innovation in process and technology.
There is a reduction of trainees as given proportion of trainees have gone down by half since 1970s, therefore there is a shortage of skilled labors
Very few workmen have the knowledge on the technical and managerial skills.
Lack of multi-skills.
Quality:
Quality means not only zero defects but right first time, delivery on time and to budget.
Quality is also the innovative side while reducing the waste.
Clients indiscriminate and still equate price with cost.
Projects are unpredictable when considering whether it’s up to the standards of expected quality.
Constructions often fail to meet needs of modern business that must be competitive in international market.
It rarely provides the best value for clients and tax payers.
Industry cannot provide the best quality when clients select designers and constructers on the basis of lowest cost and not overall value for
money.
Time:
It’s unpredictable in terms of delivery on time.
Clients are dissatisfied as the project is not finished on the promised time.
Financial/cost
Projects are unpredictable in terms of finishing within the budget.
Investments in constructions are seen as its expensive when compared to both goods and services to other countries.
Dissatisfaction of clients due to the poor performance of the contractor, in maintaining quoted price and to time, resolving defects and delivery in
final product.
Social:
Work place must be with fair wages.
Dissatisfaction of clients of both public and private sectors due to under-achievement.
Lack of loyal, strategic long term shareholders due to the lower exceptions, investors cannot identify brands among companies to which they can
attach future value.
Environmental:
Work place must be a decent place for work.
Committed leadership:
Agenda should be made accordingly to improve and communicate the expected cultural and operational changes
Satisfying the customer needs and bringing out the best of his ideas must be the main objective.
The product should reflect the price that was spent by the customer; there shouldn’t be any circumstance where the customer
If there are any additions that don’t show any value to the customer those additions must be removed as waste.
The team and workers and there process must be integrated to give the value to the customer efficiently.
Concern on quality:
Mostly customers are dissatisfied regarding the quality of the final product.
Design, materials, each and everything should reflect its quality to the customer.
Best products must be used according to the paid amount of the customer.
When selecting materials, best materials must be selected according to the budget, we should always let the client know
what the best is, and if he is trying to go for cheaper products we should stop it.
Same thing happens when selecting the contractor, always the best and experienced contractor must be appointed rather than
Paying a considerably high amount would increase the quality and durability while going for a cheaper product maybe very
23
commitment to people:
This also includes the decent site conditions, and fair wages paid to the workers, and caring about the health and safety of
workers.
If the promised time is not enough and the work drags furthermore the client will be dissatisfied, so it’s very important to manage the
time, and use sufficient labors according to the project size to finish it on time up to client expectation.
To solve technical problems, select trained labors, if trained labors are not available train few labors for the needed work purpose.
All the legal documents must be cleared and they should be ready to be used if needed in future.
Assign a health and safety officer if needed, and always keep records on the accidents.
5.2 Based on the hazard assessment carried out at British College of Applied studies, you are required to propose a detailed Health and
Safety Plan for BCAS buildings.
Before starting the plans of solutions for the hazards that were found we must identify :
How we will ensure that the students, lecturers, visitors and others are kept healthy and safe at BCAS.
Whether what we are suggesting is enough or need to do more to prevent that harm.
24
Repair all the improper wirings; assign an experienced mechanic/ electrician for this purpose.
Fix all the wires, tighten them.
Remove all the unnecessary objects from the walk way, instead of stones and stuff we can suggest use of magnets.
Inform the minor staff to always keep the paths free after working.
Remove all the broken chair and tables, replace them with new ones. If they can be reused repair them properly and make them
suitable for use.
Assign and give the minor staff a proper time table or duty list so that everything will be clean, like mopping stairs cleaning
classrooms etc.
Repair or fix the broken roofing’s.
Use drills for the upper floor windows as they are too large there is a risk of falling, or keep the windows locked.
Assign the minor staff to clean the washroom area after each 3 hours at least.
Use proper pipe lines, fix the broken or leaking pipe lines, do a regular checkup in every 3-4 months, assign a trained plumber.
If the tiles are slippery avoid too much of mopping or by the time replace the tiles.
Ask the workers to clean the filters daily.
Cover all the sharp edges with rubber.
Ask the management to buy a generator.
Make a handbook regarding the health and safety issues, keep recordings of the issues and the repairs, and update it time to time.
Conduct risk assessments continuously.
Give detailed information to the staff and students about the health and safety issues and plans and the precautions.
Reference:
Haywardbaker.com. (2016). Hayward Baker - Geotechnical Construction Engineering Solutions for Engineers & Contractors. [online]
Available at: http://www.haywardbaker.com [Accessed 31 Mar. 2016].
Articles, O., Articles, O., Buildings, R., Friction), F., Types, E., Fireproofing, S., Equipment, R., Architects, H., Architects, T.,
Commissioning, G., Exam, H. and Scale, F. (2016). The architect's technical resource - archtoolbox.com. [online] archtoolbox.com.
Available at: http://www.archtoolbox.com [Accessed 31 Mar. 2016].
CivilBlog.Org. (2016). CivilBlog.Org. [online] Available at: http://civilblog.org [Accessed 31 Mar. 2016].
Anon, (2016). [online] Available at: http://snowbutterfkygreen.blogspot.com [Accessed 31 Mar. 2016].
Agency.govermentjobs.com. (2016). govermentjobs.com. [online] Available at: http://agency.govermentjobs.com [Accessed 31 Mar. 2016].
Designingbuildings.co.uk. (2016). Designing Buildings Wiki. [online] Available at: http://www.designingbuildings.co.uk [Accessed 31
Mar. 2016].
Groundwatereng.com. (2016). Groundwater Engineering | Dewatering & Groundwater Control. [online] Available at:
http://www.groundwatereng.com [Accessed 31 Mar. 2016].
Wikipedia. (2016). Main Page. [online] Available at: https://en.m.wikipedia.org [Accessed 31 Mar. 2016].
Northeast Consulting, I. (2016). SmartDitch | Lining Systems | Drainage Systems | Ditch Lining Systems. [online] Smartditch.com.
Available at: http://www.smartditch.com [Accessed 31 Mar. 2016].
25
Anon, (2016). [online] Available at: 1.
https://www.google.lk/url?sa=i&rct=j&q=&esrc=s&source=images&cd=&cad=rja&uact=8&ved=0ahUKEwiEwNLtuNbLAhUUvo4K
HRMVBX0QjRwIBw&url=https%3A%2F%2Fwww.deere.com%2Fen_US%2Fproducts%2Fequipment%2Fbackhoe_loaders%2Fbackhoe
_loaders.page&bvm=bv.117218890,d.c2E&psig=AFQjCNGMzUwsjQ3zWNYM262EwyvJWoAkQw&ust=1458809991966245 [Accessed
31 Mar. 2016].
Asekeen, s., Asekeen, s., Asekeen, s. and Ibtesam, M. (2016). Know the Advantages and Disadvantages of Hydroelectricity. [online] Civil
Engineering Basic. Available at: http://www.civilengineeringbasic.com [Accessed 31 Mar. 2016].
http://www.gwttllc.com/103-services/construction-dewatering/362-sumps-drains-and-open-pumping. (2016). [image].
http://www.lbcivils.co.uk/_resources/images/lb_marine_projects/lb_marine_061.jpg
Civilengineeringbasic.com. (2016). [online] Available at: http://civilengineeringbasic.com/wp-content/uploads/2013/12/ase118-
1728x800_c.jpg [Accessed 31 Mar. 2016].
Skylinesteel.com. (2016). Caissons | skylinesteel.com. [online] Available at: http://www.skylinesteel.com/globalnav/products/pipe/caissons
[Accessed 31 Mar. 2016].
Concrete Construction. (1963). Cast-in-Place Concrete Piles. [online] Available at: http://www.concreteconstruction.net/concrete-
articles/cast-in-place-concrete-piles.aspx [Accessed 31 Mar. 2016].
Fast-form formwork hire. (2016). sheet pile capping beam system for hire. [online] Available at:
http://www.fastformsystems.com/index.php/sheet-pile-capping-beam/ [Accessed 31 Mar. 2016].
Civil Engineering. (2016). Setting Out Sewers. [online] Available at: http://www.qs4freshers.com/setting-out-sewers.html [Accessed 31
Mar. 2016].
Macegroup.com. (2016). CDM 2015 - what’s changing and what you need to know | Mace. [online] Available at:
http://www.macegroup.com/media-centre/thinking/cdm-2015-what-s-changing-and-what-you-need-to-know [Accessed 31 Mar. 2016].
Hse.gov.uk. (2016). Construction - Construction Design and Management Regulations 2015. [online] Available at:
http://www.hse.gov.uk/construction/cdm/2015/index.htm [Accessed 31 Mar. 2016].
Wolfe, R., Pritchard, B. and Edmondson, R. (2016). Principles of Constructing Excellence and Rethinking Construction - Constructing
Excellence. [online] Constructing Excellence. Available at: http://constructingexcellence.org.uk/about/principles-of-constructing-
excellence-and-rethinking-construction/ [Accessed 31 Mar. 2016].
Anon, (2016). 1st ed. [ebook] Available at: http://www.hse.gov.uk/aboutus/meetings/iacs/coniac/200706/m220061a3.pdf [Accessed 31
Mar. 2016].
Anon, (2016). [image] Available at: https://www.deere.com/en_US/products/equipment/backhoe_loaders/backhoe_loaders.page [Accessed
31 Mar. 2016].
Anon, (2016). [image] Available at: http://million-base.com/machineries/infrastructure-machinery-7/ [Accessed 31 Mar. 2016].
Wikipedia. (2016). Dump truck. [online] Available at: https://en.wikipedia.org/wiki/Dump_truck [Accessed 31 Mar. 2016].
Newmodellersshop.co.uk. (2016). DG225006 - Corgi Ruston Bucyrus 19 LNER Skimmer - New Modellers Shop. [online] Available at:
http://www.newmodellersshop.co.uk/corgi/dg225006_ruston_bucyrus_19_lner_skimmer.htm [Accessed 31 Mar. 2016].
Anon, (2016). [image] Available at:
http://t0.gstatic.com/images?q=tbn:ANd9GcThFLR2RFSjC3EJyWJUvTQ1dGmMY1E0M1Tlb0Gm6klp55xTg0U8Vw [Accessed 31 Mar.
2016].
Anon, (2016). [image] Available at: http://www.turbosquid.com/3d-models/falsework-building-3d-max/723010 [Accessed 31 Mar. 2016].
TheFreeDictionary.com. (2016). concrete form. [online] Available at: http://encyclopedia2.thefreedictionary.com/concrete+form [Accessed
31 Mar. 2016].
Vishwakarma, A. (2015). FOR COLUMN REINFORCEMENTS, WHY IS HELICAL REINFORCEMENT SOMETIMES DESIGNED
INSTEAD OF NORMAL LINKS?. [online] Civil Engineering Daily. Available at:
https://civilengineeringdaily.wordpress.com/2015/02/17/for-column-reinforcements-why-is-helical-reinforcement-sometimes-designed-
26
instead-of-normal-links/ [Accessed 31 Mar. 2016].
http://www.nra.co.za/content/Chapter_6.pdf
Power to choose HQ. (2004). Home construction Part 2 (Concrete) [online] Available at: http://www.powertochoosehq.com/concrete
27
28