RESUMEN CRONOGRAMA DE EJECUCION

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE
YANACCA DEL DISTRITO DE TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018

MES1 MES2 MES3


ITEM DESCRIPCION PARCIAL
S/. % S/. % S/. %

A LINEA DE CONDUCCION PRINCIPAL 484,552.64 63,334.43 13.07% 271,249.83 55.98% 149,968.39 30.95%

1 OBRAS PROVISIONALES 3,275.50 39.31 1.20% 26.20 0.80% 3,209.99 98.00%


2 OBRAS PRELIMINARES 76,596.30 8,943.00 11.68% 48,345.30 63.12% 19,308.00 25.21%
3 REDES DE DISTRIBUCION (6,654.67 ML) 114,340.19 11,379.50 9.95% 53,172.94 46.50% 49,787.75 43.54%
4 PASE AEREO CON CABLE L=40.00 M (02 UND) 7,437.45 347.04 4.67% 3,225.26 43.37% 3,865.15 51.97%
5 BOCATOMA Y DESARENADOR (02) 51,819.99 2,216.32 4.28% 35,038.72 67.62% 14,564.95 28.11%
6 CAMARA DE CARGA T-1 (02 UND) 17,461.52 7,240.25 41.46% 8,721.58 49.95% 1,499.70 8.59%
7 CAMARA DE CARGA T-2 (01 UND) 6,395.85 2,722.32 42.56% 2,695.13 42.14% 978.40 15.30%
8 RESERVORIO (02 UND) 96,328.60 20,594.88 21.38% 70,081.61 72.75% 5,652.11 5.87%
9 CERCO PERIMETRICO (02 UND) 17,445.69 1,618.15 9.28% 166.77 0.96% 15,660.77 89.77%
10 CAMARA ROMPE PRESION T-01 (05) 14,271.84 2,882.10 20.19% 9,750.90 68.32% 1,638.85 11.48%
11 VALVULAS DE PURGA (16 UND). 2,076.36 549.90 26.48% 1,106.46 53.29% 420.00 20.23%
12 HIDRANTES (149 UND) 31,544.00 975.80 3.09% 22,284.13 70.64% 8,284.07 26.26%
13 MODULO DE RIEGO POR ASPERSION 19,541.20 0.00 0.00% 6,979.00 35.71% 12,562.20 64.29%
14 OBRAS COMPLEMENTARIAS 8,196.81 0.00 0.00% 4,895.00 59.72% 3,301.81 40.28%
15 MODULO DE CAPACITACION 8,151.84 135.86 1.67% 543.46 6.67% 7,472.52 91.67%
16 TRANSPORTE DE MATERIALES 9,000.00 3,690.00 41.00% 4,050.00 45.00% 1,260.00 14.00%
17 VARIOS 669.50 0.00 0.00% 167.38 25.00% 502.13 75.00%
COSTO DIRECTO 484,552.64 63,334.43 13.07% 271,249.83 55.98% 149,968.39 30.95%
GASTOS GENERALES 72,682.91 9,500.17 13.07% 40,687.48 55.98% 22,495.26 30.95%
COSTO TOTAL DE OBRA 557,235.55 72,834.59 13.07% 311,937.31 55.98% 172,463.65 30.95%
GASTOS DE SUPERVISION 24,000.00 3,136.97 13.07% 13,435.06 55.98% 7,427.97 30.95%
EXPEDIENTE TECNICO 40,000.00 40,000.00 100.00% 0.00 0.00% 0.00 0.00%
MITIGACION AMBIENTAL 9,000.00 0.00 0.00% 4,000.00 44.44% 5,000.00 55.56%
LIQUIDACION DE OBRA 5,000.00 0.00 0.00% 0.00 0.00% 5,000.00 100.00%
PRESUPUESTO TOTAL 635,235.55 115,971.56 18.26% 329,372.37 51.85% 189,891.62 29.89%
CRONOGRAMA FINANCIERO- MENSUALIZADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE YANACCA DEL DISTRITO DE
TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018 Lugar: APURIMAC - COTABAMBAS - TAMBOBAMBA

MES1 MES2 MES3


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
METR. S/. % METR. S/. % METR. S/. %

01 LINEA DE CONDUCCION PRINCIPAL

01.01 OBRAS PROVISIONALES 3,275.50 39.31 1.20% 26.20 0.80% 3,209.99 98.00%

01.01.01 CAMPAMENTOS EN GENERAL und 50.00 65.51 3,275.50 0.60 39.31 1.20% 0.40 26.20 0.80% 49.00 3,209.99 98.00%

01.01.02 OBRAS PRELIMINARES 76,596.30 8,943.00 11.68% 48,345.30 63.12% 19,308.00 25.21%
01.01.02.01 CARTEL DE IDENTIFICACION DE LA OBRA 3.60x2.40m. und 1.00 800.00 800.00 1.00 800.00 100.00% - 0.00% - - 0.00%
01.01.02.02 TRAZO Y REPLANTEO DE TUBERIAS AGUA (CONTROL TOPOGRAFICO) m 2,150.00 1.03 2,214.50 1,500.00 1,545.00 69.77% 600.00 618.00 27.91% 50.00 51.50 2.33%
01.01.02.03 EXCAVACION A MANO EN TERRENO NORMAL m3 430.00 10.18 4,377.40 250.00 2,545.00 58.14% 180.00 1,832.40 41.86% - - 0.00%
01.01.02.04 EXCAVACION EN ROCA FIJA INCLUYE DESQUINCHE REFINE Y PEINADO m3 24.00 182.10 4,370.40 15.00 2,731.50 62.50% 9.00 1,638.90 37.50% - - 0.00%
01.01.02.05 REFINE Y NIVELACION DE ZANJAS m2 860.00 1.44 1,238.40 400.00 576.00 46.51% 400.00 576.00 46.51% 60.00 86.40 6.98%
01.01.02.06 CAMA DE APOYO PARA TUBERIAS DE 110mm. m 1,872.00 2.13 3,987.36 350.00 745.50 18.70% 1,500.00 3,195.00 80.13% 22.00 46.86 1.18%
01.01.02.07 TUBERIA DE POLIETILENO PEHD DE 110mm C-10 m 2,150.00 26.99 58,028.50 - 0.00% 1,500.00 40,485.00 69.77% 650.00 17,543.50 30.23%
01.01.02.09 INSTALACION DE ACCESORIOS PEHD DE 110mm. glb 5.00 210.42 1,052.10 - 0.00% - 0.00% 5.00 1,052.10 100.00%
01.01.02.10 VALVULA DE AIRE CADA (500 ml) und 4.00 131.91 527.64 - 0.00% - 0.00% 4.00 527.64 100.00%

01.01.02.11 REDES DE DISTRIBUCION (6,654.67 ML) 114,340.19 11,379.50 9.95% 53,172.94 46.50% 49,787.75 43.54%

01.01.02.11.01 TRAZO Y REPLANTEO DE TUBERIAS AGUA (CONTROL TOPOGRAFICO) m 7,059.90 1.03 7,271.70 850.00 875.50 12.04% 4,000.00 4,120.00 56.66% 2,209.90 2,276.20 31.30%
01.01.02.11.02 EXCAVACION A MANO EN TERRENO NORMAL m3 1,411.98 10.18 14,373.96 350.00 3,563.00 24.79% 850.00 8,653.00 60.20% 211.98 2,157.96 15.01%
01.01.02.11.03 REFINE Y NIVELACION DE ZANJAS m2 2,823.96 1.44 4,066.50 150.00 216.00 5.31% 1,850.00 2,664.00 65.51% 823.96 1,186.50 29.18%
01.01.02.11.04 CAMA DE APOYO PARA TUBERIAS DE 110MM,63MM,50MM,32MM y 25mm. m 7,059.90 2.69 18,991.13 2,500.00 6,725.00 35.41% 3,000.00 8,070.00 42.49% 1,559.90 4,196.13 22.10%
01.01.02.11.05 TUBERIA DE POLIETILENO PEHD DE 90mm C-10 m 280.00 24.77 6,935.60 - 0.00% 200.00 4,954.00 71.43% 80.00 1,981.60 28.57%
01.01.02.11.06 TUBERIA DE POLIETILENO PEHD DE 63mm C-10 m 1,850.00 14.21 26,288.50 - 0.00% 650.00 9,236.50 35.14% 1,200.00 17,052.00 64.86%
01.01.02.11.07 TUBERIA DE POLIETILENO PEHD DE 50mm C-10 m 1,160.00 9.60 11,136.00 - 0.00% 500.00 4,800.00 43.10% 660.00 6,336.00 56.90%
01.01.02.11.08 TUBERIA DE POLIETILENO PEHD DE 32mm C-10 m 1,900.00 3.99 7,581.00 - 0.00% 850.00 3,391.50 44.74% 1,050.00 4,189.50 55.26%
01.01.02.11.09 TUBERIA DE POLIETILENO PEHD DE 25mm C-10 m 1,960.00 3.17 6,213.20 - 0.00% 1,000.00 3,170.00 51.02% 960.00 3,043.20 48.98%
01.01.02.11.10 INSTALACION DE ACCESORIOS DE RED DISTRIBUCION glb 1.00 4,698.00 4,698.00 - 0.00% 0.25 1,174.50 25.00% 0.75 3,523.50 75.00%
01.01.02.11.11 INSTALACION DE VALVULAS DE AIRE DE DOBLE EFECTO (06 UND) und 6.00 241.22 1,447.32 - 0.00% 2.00 482.44 33.33% 4.00 964.88 66.67%
01.01.02.11.12 RELLENO Y COMPACTADO CON MAT. PROPIO EN CAPAS DE 0.20 m m3 1,411.98 3.78 5,337.28 - 0.00% 650.00 2,457.00 46.03% 761.98 2,880.28 53.97%

01.02 PASE AEREO CON CABLE L=40.00 M (02 UND) 7,437.45 347.04 4.67% 3,225.26 43.37% 3,865.15 51.97%

01.02.01 TRAZO, NIVELES Y REPLANTEO m2 40.00 1.32 52.80 40.00 52.80 100.00% - 0.00% - - 0.00%
01.02.02 EXCAVACION PARA ESTRUCTURAS m3 3.97 32.55 129.22 3.97 129.22 100.00% - 0.00% - - 0.00%
01.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 3.38 48.82 165.01 3.38 165.01 100.00% - - 0.00% - - 0.00%
01.02.04 SOLADO DE CONCRETO e=2" Mezcla 1:12 C:H. m2 0.49 36.66 17.96 - 0.00% 0.49 17.96 100.00% - - 0.00%
01.02.05 CONCRETO f'c=140 kg/cm2 + 70% P.M P/Anclajes. m3 2.88 421.78 1,214.73 - 0.00% 2.88 1,214.73 100.00% - - 0.00%
01.02.06 CONCRETO f´c = 210 kg/cm2. m3 1.90 369.91 702.83 - 0.00% 1.90 702.83 100.00% - - 0.00%
CRONOGRAMA FINANCIERO- MENSUALIZADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE YANACCA DEL DISTRITO DE
TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018 Lugar: APURIMAC - COTABAMBAS - TAMBOBAMBA

MES1 MES2 MES3


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
METR. S/. % METR. S/. % METR. S/. %
01.02.07 ENCOFRADO Y DESENCOFRADO m2 16.28 34.75 565.73 - 0.00% 16.28 565.73 100.00% - - 0.00%
01.02.08 ACERO fy=4,200 kg/cm2 kg 106.16 6.82 724.01 - 0.00% 106.16 724.01 100.00% - - 0.00%
01.02.09 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 11.48 34.26 393.30 - 0.00% - 0.00% 11.48 393.30 100.00%
01.02.10 SUM. E INST. CABLE ACERO TIPO BOA 6X19 C/ ALMA DE ACERO DIAM. 1/2". m 60.00 33.48 2,008.80 - 0.00% - 0.00% 60.00 2,008.80 100.00%
01.02.11 SUM. E INST. ACCESORIOS PASE AEREO P/ CABLE 3/8" glb 1.00 1,380.62 1,380.62 - 0.00% - 0.00% 1.00 1,380.62 100.00%
01.02.12 PINTURA ESMALTE ESMALTE EN ESTRUCTURAS 2 MANOS m2 11.48 7.18 82.43 - 0.00% - 0.00% 11.48 82.43 100.00%

01.03 BOCATOMA Y DESARENADOR (02) 51,819.99 2,216.32 4.28% 35,038.72 67.62% 14,564.95 28.11%

01.03.01 TRAZO, NIVELES Y REPLANTEO m2 162.00 1.32 213.84 162.00 213.84 100.00% - 0.00% - - 0.00%
01.03.02 EXCAVACION EN TERRENO SEMIROCOSO MANUAL m3 61.52 32.55 2,002.48 61.52 2,002.48 100.00% - 0.00% - - 0.00%
01.03.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 21.91 48.82 1,069.65 - 0.00% 7.72 376.89 35.24% 14.19 692.76 64.76%
01.03.04 SOLADO DE CONCRETO e=2" Mezcla 1:12 C:H. m2 16.50 36.66 604.89 - 0.00% 16.50 604.89 100.00% - - 0.00%
01.03.05 CONCRETO f´c = 210 kg/cm2. m3 43.33 369.91 16,028.20 - 0.00% 43.33 16,028.20 100.00% - - 0.00%
01.03.06 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURA CARAVISTA m2 155.92 66.54 10,374.92 - 0.00% 155.92 10,374.92 100.00% - - 0.00%
01.03.07 ACERO fy=4,200 kg/cm2 kg 152.32 6.82 1,038.82 - 0.00% 108.64 740.92 71.32% 43.68 297.90 28.68%
01.03.08 EMBOQUILLADO DE PIEDRA CON CONCRETO f'c=140 kg/cm2 m3 36.71 411.41 15,102.86 - 0.00% 12.70 5,224.91 34.60% 24.01 9,877.95 65.40%
01.03.09 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 51.67 34.26 1,770.21 - 0.00% 49.27 1,687.99 95.36% 2.40 82.22 4.64%
01.03.10 COMPUERTA METALICA TIPO IZAJE 0.30X0.80X1.80m. und 2.00 203.53 407.06 - 0.00% - 0.00% 2.00 407.06 100.00%
01.03.11 COMPUERTA METALICA TIPO IZAJE 0.25X0.60X1.00m. und 2.00 153.53 307.06 - 0.00% - 0.00% 2.00 307.06 100.00%
01.03.12 SUM. E INST. DE REJILLAS METALICAS DE 0.30X6.20m. glb 2.00 1,450.00 2,900.00 - 0.00% - 0.00% 2.00 2,900.00 100.00%

01.04 CAMARA DE CARGA T-1 (02 UND) 17,461.52 7,240.25 41.46% 8,721.58 49.95% 1,499.70 8.59%

01.04.01 TRAZO, NIVELES Y REPLANTEO m2 23.04 1.32 30.41 23.04 30.41 100.00% - 0.00% - - 0.00%
01.04.02 EXCAVACION A MANO EN TERRENO NORMAL m3 13.82 10.18 140.69 13.82 140.69 100.00% - 0.00% - - 0.00%
01.04.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 70.80 34.59 2,448.97 70.80 2,448.97 100.00% - 0.00% - - 0.00%
01.04.04 CONCRETO f´c = 210 kg/cm2. m3 12.49 369.91 4,620.18 12.49 4,620.18 100.00% - 0.00% - - 0.00%
01.04.05 ACERO fy=4,200 kg/cm2 kg 758.45 6.82 5,172.63 - 0.00% 727.02 4,958.28 95.86% 31.43 214.35 4.14%
01.04.06 CONCRETO SIMPLE f´c = 140 kg/cm2 m3 0.23 447.37 102.90 - 0.00% 0.23 102.90 100.00% - - 0.00%
01.04.07 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 71.34 34.26 2,444.11 - 0.00% 71.34 2,444.11 100.00% - - 0.00%
01.04.08 INSTALACION DE ACCESORIOS VALVULAS DE CONTROL 3" glb 2.00 608.15 1,216.30 - 0.00% 2.00 1,216.30 100.00% - - 0.00%
01.04.09 TAPA METALICA 0.60*0.60*1/8(Camara de carga) und 2.00 203.53 407.06 - 0.00% - 0.00% 2.00 407.06 100.00%
01.04.10 TAPA METALICA 0.35*0.35*1/8(Caja de valvulas) und 4.00 143.53 574.12 - 0.00% - 0.00% 4.00 574.12 100.00%
01.04.11 PINTURA ESMALTE EN ESTRUCTURAS 2 MANOS m2 42.60 7.14 304.16 - 0.00% - 0.00% 42.60 304.16 100.00%

01.05 CAMARA DE CARGA T-2 (01 UND) 6,395.85 2,722.32 42.56% 2,695.13 42.14% 978.40 15.30%

01.05.01 TRAZO, NIVELES Y REPLANTEO m2 6.76 1.32 8.92 6.76 8.92 100.00% - 0.00% - - 0.00%
01.05.02 EXCAVACION EN TERRENO SEMIROCOSO MANUAL m3 7.44 32.55 242.17 7.44 242.17 100.00% - 0.00% - - 0.00%
01.05.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 28.56 34.59 987.89 28.56 987.89 100.00% - 0.00% - - 0.00%
CRONOGRAMA FINANCIERO- MENSUALIZADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE YANACCA DEL DISTRITO DE
TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018 Lugar: APURIMAC - COTABAMBAS - TAMBOBAMBA

MES1 MES2 MES3


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
METR. S/. % METR. S/. % METR. S/. %
01.05.04 CONCRETO f´c = 210 kg/cm2. m3 4.01 369.91 1,483.34 4.01 1,483.34 100.00% - 0.00% - - 0.00%
01.05.05 ACERO fy=4,200 kg/cm2 kg 209.83 6.82 1,431.04 - 0.00% 209.83 1,431.04 100.00% - - 0.00%
01.05.06 CONCRETO SIMPLE f´c = 140 kg/cm2 m3 0.12 447.37 53.68 - 0.00% 0.12 53.68 100.00% - - 0.00%
01.05.07 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 35.33 34.26 1,210.41 - 0.00% 35.33 1,210.41 100.00% - - 0.00%
01.05.08 INSTALACION DE ACCESORIOS VALVULAS DE CONTROL 2" glb 1.00 321.15 321.15 - 0.00% - 0.00% 1.00 321.15 100.00%
01.05.09 TAPA METALICA 0.60*0.60*1/8(Camara de carga) und 1.00 203.53 203.53 - 0.00% - 0.00% 1.00 203.53 100.00%
01.05.10 TAPA METALICA 0.40*0.40*1/8(Caja de valvulas) und 2.00 163.53 327.06 - 0.00% - 0.00% 2.00 327.06 100.00%
01.05.11 PINTURA ESMALTE ESMALTE EN ESTRUCTURAS 2 MANOS m2 17.64 7.18 126.66 - 0.00% - 0.00% 17.64 126.66 100.00%

01.06 RESERVORIO (02 UND) 96,328.60 20,594.88 21.38% 70,081.61 72.75% 5,652.11 5.87%

01.06.01 TRAZO, NIVELES Y REPLANTEO m2 316.92 1.32 418.33 316.92 418.33 100.00% - 0.00% - - 0.00%
01.06.02 EXCAVACION EN TERRENO SEMIROCOSO MANUAL m3 202.92 32.55 6,605.05 202.92 6,605.05 100.00% - 0.00% - - 0.00%
01.06.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 362.88 34.59 12,552.02 125.00 4,323.75 34.45% 237.88 8,228.27 65.55% - - 0.00%
01.06.04 CONCRETO f´c = 210 kg/cm2. m3 83.78 369.91 30,991.06 25.00 9,247.75 29.84% 54.92 20,315.46 65.55% 3.86 1,427.85 4.61%
01.06.05 ACERO fy=4,200 kg/cm2 kg 4,173.20 6.82 28,461.22 - 0.00% 4,173.20 28,461.22 100.00% - - 0.00%
01.06.06 CONCRETO SIMPLE f´c = 140 kg/cm2 m3 0.67 447.37 299.74 - 0.00% 0.67 299.74 100.00% - - 0.00%
01.06.07 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 372.94 34.26 12,776.92 - 0.00% 372.94 12,776.92 100.00% - - 0.00%
01.06.08 INSTALACION DE ACCESORIOS VALVULAS DE CONTROL 3" glb 2.00 974.25 1,948.50 - 0.00% - 0.00% 2.00 1,948.50 100.00%
01.06.09 ESCALERA DE GATO TUBO 11/2" X 3/4" und 2.00 550.00 1,100.00 - 0.00% - 0.00% 2.00 1,100.00 100.00%
01.06.10 TAPA METALICA 0.60*0.60*1/8(Camara de carga) und 2.00 203.53 407.06 - 0.00% - 0.00% 2.00 407.06 100.00%
01.06.11 TAPA METALICA 0.65*0.65*1/8(Caja de Valvulas) und 2.00 163.78 327.56 - 0.00% - 0.00% 2.00 327.56 100.00%
01.06.12 PINTURA ESMALTE ESMALTE EN ESTRUCTURAS 2 MANOS m2 61.44 7.18 441.14 - 0.00% - 0.00% 61.44 441.14 100.00%

01.06.13 CERCO PERIMETRICO (02 UND) 17,445.69 1,618.15 9.28% 166.77 0.96% 15,660.77 89.77%

01.06.13.01 EXCAVACION PARA ESTRUCTURAS m3 4.60 32.55 149.73 4.60 149.73 100.00% - 0.00% - - 0.00%
01.06.13.02 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30% P.M. m3 3.45 425.63 1,468.42 3.45 1,468.42 100.00% - 0.00% - - 0.00%
01.06.13.03 CONCRETO f'c=175 kg/cm2 m3 0.37 555.89 205.68 - 0.00% 0.30 166.77 81.08% 0.07 38.91 18.92%
01.06.13.04 SUM. E INST. DE MALLA OLIMPICA EN CERCO PERIMETRICO. m 121.00 115.42 13,965.82 - 0.00% - 0.00% 121.00 13,965.82 100.00%
01.06.13.05 PUERTA METALICA P-01 und 2.00 828.02 1,656.04 - 0.00% - 0.00% 2.00 1,656.04 100.00%

01.07 CAMARA ROMPE PRESION T-01 (05) 14,271.84 2,882.10 20.19% 9,750.90 68.32% 1,638.85 11.48%

01.07.01 TRAZO, NIVELES Y REPLANTEO m2 9.75 1.32 12.87 11.70 15.44 120.00% - 0.00% (1.95) (2.57) -20.00%
01.07.02 EXCAVACION EN TERRENO SEMIROCOSO MANUAL m3 13.35 32.55 434.54 16.02 521.45 120.00% - 0.00% (2.67) (86.91) -20.00%
01.07.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 56.50 34.59 1,954.34 67.80 2,345.20 120.00% - 0.00% (11.30) (390.87) -20.00%
01.07.04 CONCRETO f'c=175 kg/cm2 m3 5.67 555.89 3,151.90 - 0.00% 6.80 3,780.05 119.93% (1.13) (628.16) -19.93%
01.07.05 ACERO fy=4,200 kg/cm2 kg 438.59 6.82 2,991.18 - 0.00% 526.31 3,589.43 120.00% (87.72) (598.25) -20.00%
01.07.06 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 57.93 34.26 1,984.68 - 0.00% 69.51 2,381.41 119.99% (11.58) (396.73) -19.99%
01.07.07 SUM. E INST. DE ACCESORIOS EN CAMARA DE ROMPE PRESION glb 5.00 300.05 1,500.25 - 0.00% - 0.00% 5.00 1,500.25 100.00%
CRONOGRAMA FINANCIERO- MENSUALIZADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE YANACCA DEL DISTRITO DE
TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018 Lugar: APURIMAC - COTABAMBAS - TAMBOBAMBA

MES1 MES2 MES3


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
METR. S/. % METR. S/. % METR. S/. %
01.07.08 TAPA METALICA 0.50*0.50*1/8 (CCRP T-01) und 5.00 223.53 1,117.65 - 0.00% - 0.00% 5.00 1,117.65 100.00%
01.07.09 TAPA METALICA 0.35*0.35*1/8 (C. valvulas) und 5.00 183.53 917.65 - 0.00% - 0.00% 5.00 917.65 100.00%
01.07.10 PINTURA ESMALTE ESMALTE EN ESTRUCTURAS 2 MANOS m2 28.80 7.18 206.78 - 0.00% - 0.00% 28.80 206.78 100.00%

01.07.11 VALVULAS DE PURGA (16 UND). 2,076.36 549.90 26.48% 1,106.46 53.29% 420.00 20.23%

01.07.11.01 TRAZO, NIVELES Y REPLANTEO m2 5.76 1.32 7.60 5.76 7.60 100.00% - 0.00% - - 0.00%
01.07.11.02 EXCAVACION A MANO EN TERRENO NORMAL m3 1.08 10.18 10.99 1.08 10.99 100.00% - 0.00% - - 0.00%
01.07.11.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 15.36 34.59 531.30 15.36 531.30 100.00% - 0.00% - - 0.00%
01.07.11.04 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30% P.M. m3 0.58 425.63 246.87 - 0.00% 0.58 246.87 100.00% - - 0.00%
01.07.11.05 CONCRETO SIMPLE f´c = 140 kg/cm2 m3 0.77 447.37 344.47 - 0.00% 0.77 344.47 100.00% - - 0.00%
01.07.11.06 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 7.68 34.26 263.12 - 0.00% 7.68 263.12 100.00% - - 0.00%
01.07.11.07 INSTALACION DE ACCESORIOS VALVULAS DE PURGA 3/4" glb 16.00 42.00 672.00 - 0.00% 6.00 252.00 37.50% 10.00 420.00 62.50%

01.07.12 HIDRANTES (149 UND) 31,544.00 975.80 3.09% 22,284.13 70.64% 8,284.07 26.26%

01.07.12.01 TRAZO, NIVELES Y REPLANTEO m2 44.70 1.32 59.00 44.70 59.00 100.00% - 0.00% - - 0.00%
01.07.12.02 EXCAVACION A MANO EN TERRENO NORMAL m2 22.35 41.02 916.80 22.35 916.80 100.00% - 0.00% - - 0.00%
01.07.12.03 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS m2 192.21 34.59 6,648.54 - 0.00% 192.21 6,648.54 100.00% - - 0.00%
01.07.12.04 ACERO fy=4,200 kg/cm2 kg 186.25 6.82 1,270.23 - 0.00% 186.25 1,270.23 100.00% - - 0.00%
01.07.12.05 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30% P.M. m3 7.60 425.63 3,234.79 - 0.00% 2.50 1,064.08 32.89% 5.10 2,170.71 67.11%
01.07.12.06 CONCRETO SIMPLE f´c = 140 kg/cm2 m3 7.15 447.37 3,198.70 - 0.00% 3.50 1,565.80 48.95% 3.65 1,632.90 51.05%
01.07.12.07 TARRAJEO CON CEMENTO : ARENA, 1:3 m2 143.04 34.26 4,900.89 - 0.00% 143.04 4,900.89 100.00% - - 0.00%
01.07.12.08 INSTALACION ACCESORIOS DE HIDRANTES ALIM. 3/4". und 149.00 75.94 11,315.06 - 0.00% 90.00 6,834.60 60.40% 59.00 4,480.46 39.60%

01.08 MODULO DE RIEGO POR ASPERSION 19,541.20 0.00 0.00% 6,979.00 35.71% 12,562.20 64.29%

01.08.01 MODULO DE RIEGO CON 1 ASPERSOR 3/4" und 70.00 279.16 19,541.20 - 0.00% 25.00 6,979.00 35.71% 45.00 12,562.20 64.29%

01.09 OBRAS COMPLEMENTARIAS 8,196.81 0.00 0.00% 4,895.00 59.72% 3,301.81 40.28%

01.09.01 PRUEBA HIDRAULICA DE TUBERIAS m 9,209.90 0.89 8,196.81 - 0.00% 5,500.00 4,895.00 59.72% 3,709.90 3,301.81 40.28%

01.10 MODULO DE CAPACITACION 8,151.84 135.86 1.67% 543.46 6.67% 7,472.52 91.67%

01.10.01 MODULO DE CAPACITACION DE RIEGO und 6.00 1,358.64 8,151.84 0.10 135.86 1.67% 0.40 543.46 6.67% 5.50 7,472.52 91.67%

01.11 TRANSPORTE DE MATERIALES 9,000.00 3,690.00 41.00% 4,050.00 45.00% 1,260.00 14.00%

01.11.01 FLETE TERRESTRE (MATERIALES) glb 1.00 9,000.00 9,000.00 0.41 3,690.00 41.00% 0.45 4,050.00 45.00% 0.14 1,260.00 14.00%
CRONOGRAMA FINANCIERO- MENSUALIZADO

PROYECTO:
"AMPLIACION Y MEJORAMIENTO DEL SISTEMA DE RIEGO EN EL ANEXO DE CHULLUPATA DE LA COMUNIDAD DE SAN ANDRES DE YANACCA DEL DISTRITO DE
TAMBOBAMBA- COTABAMBAS-APURIMAC"
FECHA: FEBRERO 2018 Lugar: APURIMAC - COTABAMBAS - TAMBOBAMBA

MES1 MES2 MES3


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
METR. S/. % METR. S/. % METR. S/. %
01.12 VARIOS 669.50 0.00 0.00% 167.38 25.00% 502.13 75.00%

01.12.01 LIMPIEZA GENERAL AL FINAL DE LA OBRA glb 1.00 669.50 669.50 - 0.00% 0.25 167.38 25.00% 0.75 502.13 75.00%
COSTO DIRECTO 484,552.64 63,334.43 13.07% 271,249.83 55.98% 149,968.39 30.95%
GASTOS GENERALES 72,682.91 9,500.17 13.07% 40,687.48 55.98% 22,495.26 30.95%
COSTO TOTAL DE OBRA 557,235.55 72,834.59 13.07% 311,937.31 55.98% 172,463.65 30.95%
GASTOS DE SUPERVISION 24,000.00 3,136.97 13.07% 13,435.06 55.98% 7,427.97 30.95%
EXPEDIENTE TECNICO 40,000.00 40,000.00 100.00% 0.00 0.00% 0.00 0.00%
MITIGACION AMBIENTAL 9,000.00 0.00 0.00% 4,000.00 44.44% 5,000.00 55.56%
LIQUIDACION DE OBRA 5,000.00 0.00 0.00% 0.00 0.00% 5,000.00 100.00%
PRESUPUESTO TOTAL 635,235.55 115,971.56 18.26% 329,372.37 51.85% 189,891.62 29.89%