METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018
PARTIDA: 02.05.04.02.03 ACERO fy=4200 kg/cm2 VIGA DE CIMENTACION

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

EJE C,D 1-2-3 2 6.4 5/8" 3.00 6.00 6.40 38.40 38.40
2 5/8" 2.00 4.00 6.50 26.00 26.00
2 6.5 1/2" 1.00 2.00 6.50 13.00 13.00

0.18

0.13
0.38

0.38
2 3/8" 30.00 60.00 1.42 85.20 85.20

0.22
EJE 1 C-D 1 4.93 5/8" 3.00 3.00 4.93 14.79 14.79
1 5/8" 2.00 2.00 5.03 10.06 10.06
1 5.03 1/2" 1.00 1.00 5.03 5.03 5.03

0.18

0.13
0.38

0.38

1 3/8" 34.00 34.00 1.38 46.92 46.92

0.18
CANTIDAD LONGITUD LONGITUD POR ml
DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

EJE 2 D-C-B 1 6.79 5/8" 3.00 3.00 6.79 20.37 20.37


METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018
1 5/8" 2.00 2.00 6.89 13.78 13.78
1 6.89 1/2" 1.00 1.00 6.89 6.89 6.89

0.18

0.13

0.38

0.38
1 3/8" 54.00 54.00 1.38 74.52 74.52

0.18

EJE 3 A-C-D 1 8.44 5/8" 3.00 3.00 8.44 25.32 25.32


1 5/8" 2.00 2.00 8.54 17.08 17.08
1 8.54 1/2" 1.00 1.00 8.54 8.54 8.54

0.18

0.13
0.38

0.38
1 3/8" 65.00 65.00 1.38 89.70 89.70

0.18
METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018
CANTIDAD LONGITUD LONGITUD POR ml
DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"
TRAMO A,B,C 1 7.48 5/8" 3.00 3.00 7.48 22.44 22.44
1 5/8" 2.00 2.00 7.58 15.16 15.16
1 7.58 1/2" 1.00 1.00 7.58 7.58 7.58

0.18

0.13

0.38

0.38
1 3/8" 60.00 60.00 1.38 82.80 82.80

0.18
3/8" 1/2" 5/8" 3/4" 1"
PESO EN KILOGRAMOS POR METRO LINEAL 0.56 0.99 1.55 2.24 3.97
LONGITUD TOTAL EN METROS LINEALES 379.14 41.04 203.40 0.00 0.00
TOTAL DE KILOGRAMOS 211.94 40.75 315.68 0.00 0.00
METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018

PARTIDA: 02.05.04.01.03 ACERO fy=4200 kg/cm2 ZAPATAS

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

ZAPATAS 1-D,3-D 2 2.69 5/8" 5.00 10.00 0.90 9.00 9.00


2 2.69 5/8" 5.00 10.00 1.10 11.00 11.00
2-D 1 2.69 5/8" 6.00 6.00 0.90 5.40 5.40
1 2.69 5/8" 5.00 5.00 1.40 7.00 7.00
1-C 1 2.69 5/8" 6.00 6.00 0.90 5.40 5.40
1 2.69 5/8" 5.00 5.00 1.26 6.30 6.30
2-C-B 1 2.69 5/8" 11.00 11.00 1.40 15.40 15.40
1 2.69 5/8" 6.00 6.00 2.66 15.96 15.96
3-C 1 2.69 5/8" 4.00 4.00 1.40 5.60 5.60
1 2.69 5/8" 6.00 6.00 1.00 6.00 6.00
3-A 1 2.69 5/8" 5.00 5.00 0.82 4.10 4.10
1 2.69 5/8" 3.00 3.00 1.10 3.30 3.30

3/8" 1/2" 5/8" 3/4" 1"


PESO EN KILOGRAMOS POR METRO LINEAL 0.56 0.99 1.55 2.24 3.97
LONGITUD TOTAL EN METROS LINEALES 0.00 0.00 94.46 0.00 0.00
TOTAL DE KILOGRAMOS 0.00 0.00 146.60 0.00 0.00
METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018

PARTIDA: 02.05.04.03.03 ACERO fy=4200 kg/cm2 COLUMNA

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

Columna C10 8 5.6 5/8'' 6.00 48.00 5.60 268.80 268.80

0.32

0.1
0.17

0.17
8 3/8" 36.00 288.00 1.18 339.84 339.84

0.32

3/8" 1/2" 5/8" 3/4" 1"


PESO EN KILOGRAMOS POR METRO LINEAL 0.56 0.99 1.55 2.24 3.97
LONGITUD TOTAL EN METROS LINEALES 339.84 0.00 268.80 0.00 0.00
TOTAL DE KILOGRAMOS 189.97 0.00 417.18 0.00 0.00
METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018

PARTIDA: 02.05.04.04.03 ACERO fy=4200 kg/cm2 VIGA

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

VIGA 101 1 4.9 5/8'' 2.00 2.00 4.90 9.80 9.80


1 1/2" 1.00 1.00 4.90 4.90 4.90
1 5 5/8'' 3.00 3.00 5.00 15.00 15.00
0.17

0.1
0.32

0.32
1 3/8" 12.00 12.00 1.18 14.16 14.16

0.17

VIGA 102 1 6.7 5/8" 2.00 2.00 6.70 13.40 13.40


1 1/2" 1.00 1.00 6.70 6.70 6.70
1 6.8 5/8'' 3.00 3.00 6.80 20.40 20.40
0.17

0.1
0.32

0.32

1 3/8" 50.00 50.00 1.18 59.00 59.00

0.17

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"
METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018
VIGA 103 1 8.4 5/8" 2.00 2.00 8.40 16.80 16.80
1 1/2" 1.00 1.00 8.40 8.40 8.40
1 8.5 5/8" 3.00 3.00 8.50 25.50 25.50
0.17

0.1

0.32

0.32
1 3/8" 56.00 56.00 1.18 66.08 66.08

0.17

VIGA 104 1 6.4 5/8'' 2.00 2.00 6.40 12.80 12.80


1 1/2" 1.00 1.00 6.40 6.40 6.40
1 6.5 5/8'' 3.00 3.00 6.50 19.50 19.50
0.17

0.1
0.32

1 0.32 3/8" 48.00 48.00 1.18 56.64 56.64

0.17

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

VIGA 105 1 12.64 5/8'' 2.00 2.00 12.64 25.28 25.28


1 1/2" 1.00 1.00 12.64 12.64 12.64
1 12.64 5/8'' 3.00 3.00 12.64 37.92 37.92
0.17

0.1
0.32

0.32

1 3/8" 48.00 48.00 1.18 56.64 56.64


METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018

0.17

VIGA 106 1 7.5 5/8" 6.00 6.00 7.50 45.00 45.00


1 1/2" 6.00 6.00 7.50 45.00 45.00
1 7.6 5/8" 6.00 6.00 7.60 45.60 45.60
0.17

0.32 0.1

0.32
1 3/8" 52.00 52.00 1.18 61.36 61.36

0.17
3/8" 1/2" 5/8" 3/4" 1"
PESO EN KILOGRAMOS POR METRO LINEAL 0.56 0.99 1.55 2.24 3.97
LONGITUD TOTAL EN METROS LINEALES 313.88 84.04 287.00 0.00 0.00
TOTAL DE KILOGRAMOS 175.46 83.45 445.42 0.00 0.00

PARTIDA: 02.04.04.05.03ACERO fy=4200 kg/cm2 LOSA

CANTIDAD LONGITUD LONGITUD POR ml


DESCRIPCION ELEMENTO CANTIDAD DISEÑO DE FIERRO
Φ ELEMENTO TOTAL DISEÑO TOTAL 3/8" 1/2" 5/8" 3/4" 1"

VIGUETAS 1-2 2 2.84 1/2" 11.00 22.00 2.84 62.48 62.48

2-3 2 3.03 1/2" 11.00 22.00 3.03 66.66 66.66


METRADO DE ACERO BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE HECHO POR: D.E.L.C
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA - REGIÓN CUSCO
FECHA: 11/2/2018
1-3 2 5.1 1/2" 9.00 18.00 6.11 109.98 109.98

ACERO DE TEMPERATURA
D-C 1 6.11 1/4" 20.00 20.00 6.11 122.20

C-A 1 6.11 1/4" 7.00 7.00 6.11 42.77

1-2-3 1 6.24 1/4" 25.00 25.00 6.24 156.00

1/4" 3/8" 1/2" 5/8" 3/4" 1"


PESO EN KILOGRAMOS POR METRO LINEAL 0.25 0.56 0.99 1.55 2.24 3.97
LONGITUD TOTAL EN METROS LINEALES 320.97 0.00 239.12 0.00 0.00 0.00
TOTAL DE KILOGRAMOS 80.24 0.00 237.45 0.00 0.00 0.00
D.E.L.C

11/2/2018
D.E.L.C

11/2/2018

TOTAL
EN KG.

568.37
D.E.L.C

11/2/2018

TOTAL
EN KG.

146.60
D.E.L.C

11/2/2018

TOTAL
EN KG.

607.15
D.E.L.C

11/2/2018

TOTAL
EN KG.

704.33
D.E.L.C

11/2/2018

TOTAL
EN KG.

317.69
HOJA DE METRADOS - ESTRUCTURAS BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE HECHO POR:


RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA -
REGIÓN CUSCO FECHA:
PARTIDA DESCRIPCION NOMBRE CANTIDAD LONGITUD ANCHO ALTURA SUB-TOTAL
02.05 CUARTO DE MAQUINAS

02.05.01 TRABAJOS PRELIMINARES


02.05.01.01 LIMPIEZA DE TERRENO MANUAL
1.00 6.39 6.11 39.04

02.05.01.02 TRAZO, NIVELES Y REPLANTEO PRELIMINAR


1.00 6.39 6.11 39.04

02.05.02 MOVIMIENTO DE TIERRAS

02.05.02.01 EXCAVACION EN TERRENO NORMAL


ZAPATA 1-D,3-D 2.00 1.20 1.00 1.60 3.84
ZAPATA 2-D 1.00 1.50 1.00 1.60 2.40
ZAPATA 1-C 1.00 1.2 1.36 1.60 2.61
ZAPATA 2-C-B 1.00 1.50 2.76 1.60 6.62
ZAPATA 3-C 1.00 1.10 1.50 1.60 2.64
ZAPATA 3-A 1.00 1.20 0.92 1.60 1.76
EJE 1,2,3 D-C 3.00 4.32 0.25 0.45 1.46
EJE 2 C-B 1.00 1.76 0.25 0.45 0.20
EJE 3 C-A 1.00 3.53 0.25 0.45 0.40
EJE D,C 1-2 2.00 2.84 0.25 0.45 0.64
EJE D,C 2-3 2.00 3.03 0.25 0.45 0.68
EJE C-3 1-2 1.00 3.36 0.25 0.45 0.38
EJE C-3 2-3 1.00 3.49 0.25 0.45 0.39

02.05.02.02 RELLENO CON MATERIAL PROPIO Y APISONADO


ZAPATA 1-D,3-D 2.00 1.20 1.00 0.50 1.20
ZAPATA 2-D 1.00 1.50 1.00 0.50 0.75
ZAPATA 1-C 1.00 1.2 1.36 0.50 0.82
ZAPATA 2-C-B 1.00 1.50 2.76 0.50 2.07
ZAPATA 3-C 1.00 1.10 1.50 0.50 0.83
ZAPATA 3-A 1.00 1.20 0.92 0.50 0.55

02.05.02.03 NIVELACION Y COMPACTADO


1.00 6.39 6.11 39.04

02.05.02.04 ELIMINACION DE MATERIAL EXCEDENTE


EXCAVACIONES MASIVAS 1.00 30.02 1.30 39.03
RELLENOS C/MAT. PROPI 1.00 -6.21 1.90 -11.80

02.05.03 OBRAS DE CONCRETO SIMPLE

02.05.03.01 FALSA ZAPATA

02.05.03.01.0 CONCRETO 1:8+25% PM PARA FALSA ZAPATA


HOJA DE METRADOS - ESTRUCTURAS BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE HECHO POR:


RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA -
REGIÓN CUSCO FECHA:
PARTIDA DESCRIPCION NOMBRE CANTIDAD LONGITUD ANCHO ALTURA SUB-TOTAL
ZAPATA 1-D,3-D 2.00 1.20 1.00 0.30 0.72
ZAPATA 2-D 1.00 1.50 1.00 0.30 0.45
ZAPATA 1-C 1.00 1.2 1.36 0.30 0.49
ZAPATA 2-C-B 1.00 1.50 2.76 0.30 1.24
ZAPATA 3-C 1.00 1.10 1.50 0.30 0.50
ZAPATA 3-A 1.00 1.20 0.92 0.30 0.33

02.05.03.01.0 CONCRETO PARA SOLADO e= 10cm


ZAPATA 1-D,3-D 2.00 1.20 1.00 0.10 0.24
ZAPATA 2-D 1.00 1.50 1.00 0.10 0.15
ZAPATA 1-C 1.00 1.2 1.36 0.10 0.16
ZAPATA 2-C-B 1.00 1.50 2.76 0.10 0.41
ZAPATA 3-C 1.00 1.10 1.50 0.10 0.17
ZAPATA 3-A 1.00 1.20 0.92 0.10 0.11

02.05.03.02 CIMIENTOS Y SOBRECIMIENTOS

02.0503.02.01SOBRE CIMIENTO 1:8 + 25% PM


EJE 1,3 D-C 2.00 4.32 0.15 1.00 1.30
EJE 3 C-A 1.00 3.53 0.15 1.00 0.53
EJE D 1-2 1.00 2.84 0.15 1.00 0.43
EJE D 2-3 1.00 3.03 0.15 1.00 0.45
EJE C-3 1-2 1.00 3.36 0.15 1.00 0.50
EJE C-3 2-3 1.00 3.49 0.15 1.00 0.52

02.0503.02.02ENCOFRADO Y DESENCOFRADO PARA CIMIENTOS Y SOBRECIMIENT


EJE 1,3 D-C 2.00 4.32 0.15 1.00 17.28
EJE 3 C-A 1.00 3.53 0.15 1.00 7.06
EJE D 1-2 1.00 2.84 0.15 1.00 5.68
EJE D 2-3 1.00 3.03 0.15 1.00 6.06
EJE C-3 1-2 1.00 3.36 0.15 1.00 6.72
EJE C-3 2-3 1.00 3.49 0.15 1.00 6.98

02.05.04 OBRAS DE CONCRETO ARMADO


02.05.04.01 ZAPATAS
02.05.04.01.0 CONCRETO PARA ZAPATASf'c=210 kg/cm2
ZAPATA 1-D,3-D 2.00 1.20 1.00 0.50 1.20
ZAPATA 2-D 1.00 1.50 1.00 0.50 0.75
ZAPATA 1-C 1.00 1.2 1.36 0.50 0.82
ZAPATA 2-C-B 1.00 1.50 2.76 0.50 2.07
ZAPATA 3-C 1.00 1.10 1.50 0.50 0.83
ZAPATA 3-A 1.00 1.20 0.92 0.50 0.55

02.05.04.01.0 ACERO fy=4200 kg/cm2 ZAPATAS

02.05.04.02 VIGAS DE CIMENTACIÓN


02.05.04.02.0 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2
EJE 1,2,3 D-C 3.00 4.32 0.25 0.45 1.46
HOJA DE METRADOS - ESTRUCTURAS BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE HECHO POR:


RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA -
REGIÓN CUSCO FECHA:
PARTIDA DESCRIPCION NOMBRE CANTIDAD LONGITUD ANCHO ALTURA SUB-TOTAL
EJE 2 C-B 1.00 1.76 0.25 0.45 0.20
EJE 3 C-A 1.00 3.53 0.25 0.45 0.40
EJE D,C 1-2 2.00 2.84 0.25 0.45 0.64
EJE D,C 2-3 2.00 3.03 0.25 0.45 0.68
EJE C-3 1-2 1.00 3.36 0.25 0.45 0.38
EJE C-3 2-3 1.00 3.49 0.25 0.45 0.39

02.05.04.02.0 ENCOFRADO Y DESENCOFRADO EN VIGAS DE CIMENTACION


EJE 1,2,3 D-C 3.00 4.32 0.45 11.66
HOJA DE METRADOS - ESTRUCTURAS BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE HECHO POR:


RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA -
REGIÓN CUSCO FECHA:
PARTIDA DESCRIPCION NOMBRE CANTIDAD LONGITUD ANCHO ALTURA SUB-TOTAL
EJE 2 C-B 1.00 1.76 0.45 1.58
EJE 3 C-A 1.00 3.53 0.45 3.18
EJE D,C 1-2 2.00 2.84 0.45 5.11
EJE D,C 2-3 2.00 3.03 0.45 5.45
EJE C-3 1-2 1.00 3.36 0.45 3.02
EJE C-3 2-3 1.00 3.49 0.45 3.14

02.05.04.02.0 ACERO fy=4200 kg/cm2 VIGA DE CIMENTACION

02.05.04.03 COLUMNAS
02.05.04.03.0 CONCRETO COLUMNAS f'c = 210 kg/cm2
C-1 8.00 0.40 0.25 3.80 3.04

02.05.04.03.0 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS


C-1 8.00 0.40 0.25 3.80 39.52

02.05.04.03.0 ACERO fy=4200 kg/cm2 COLUMNA

02.05.04.04 VIGAS
02.05.04.04.0 CONCRETO f'c=210 kg/cm2 PARA VIGAS
PRIMER NIVEL 3.87
V101 1.00 4.62 0.25 0.40 0.46
V102 1.00 6.45 0.25 0.40 0.65
V103 1.00 8.16 0.25 0.40 0.82
V104 1.00 6.11 0.25 0.40 0.61
V105 1.00 6.11 0.25 0.40 0.61
V106 1.00 7.21 0.25 0.40 0.72

02.05.04.04.0 ENCOFRADO DE VIGAS

V101 1.00 4.62 0.25 0.20 3.00


V102 1.00 6.45 0.25 0.20 4.19
V103 1.00 8.16 0.25 0.20 5.30
V104 1.00 6.11 0.25 0.20 3.97
V105 1.00 6.11 0.25 0.20 3.97
V106 1.00 7.21 0.25 0.20 4.69

02.05.04.04.0 ACERO fy=4200 kg/cm2 VIGA

02.05.04.05 LOSAS ALIGERADAS


02.04.04.05.0 CONCRETO EN LOSA ALIGERADA f'c=210 kg/cm2
2.84
EJE D,C 1-2 1.00 4.10 2.60 0.05 0.53
VIGUETAS 11.00 2.84 0.10 0.15 0.47
2-3 1.00 4.10 2.80 0.05 0.57
VIGUETAS 11.00 3.03 0.10 0.15 0.50
EJE A,B,C 1-3 1.00 3.31 5.10 0.05 0.42
VIGUETAS 9.00 5.10 0.10 0.15 0.34
HOJA DE METRADOS - ESTRUCTURAS BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE HECHO POR:


RECREACIÓN Y ESPARCIMIENTO EN EL SECTOR DE
PROYECTO:
MACHACANCHA, PROVINCIA Y DISTRITO DE CALCA -
REGIÓN CUSCO FECHA:
PARTIDA DESCRIPCION NOMBRE CANTIDAD LONGITUD ANCHO ALTURA SUB-TOTAL

02.04.04.05.0 ENCOFRADO Y DESENCOFRADO DE LOSAS ALIGERADAS


39.02
EJE D,C 1-2 1.00 4.10 2.60 10.66
2-3 1.00 4.10 2.80 11.48
EJE A,B,C 1-3 1.00 3.31 5.10 16.88

02.04.04.05.0 ACERO fy=4200 kg/cm2 LOSA

02.04.04.05.0 LADRILLO HUECO DE ARCILLA H=15CM PARA TECHO DE ALIGERADO


#veces long. undxlongsubtotal 575.00
EJE D,C VIGUETAS 11.00 2.84 14.20 15.00 165.00
VIGUETAS 11.00 3.03 15.15 16.00 176.00
EJE A,B,C VIGUETAS 9.00 5.10 25.50 26.00 234.00
LOQUE V

11/2/2018
TOTAL UNIDAD

39.04 m2

39.04 m2

30.02 m3

6.21 m3

39.04 m2

27.23 m3

3.73 m3
LOQUE V

11/2/2018
TOTAL UNIDAD

1.24 m3

3.73 m3

38.04 m3

6.83 m3

146.60 kg

4.56 m3
LOQUE V

11/2/2018
TOTAL UNIDAD

33.16 m2
LOQUE V

11/2/2018
TOTAL UNIDAD

568.37 kg

3.34 m3

39.52 m2

607.15 kg

4.25 m3

25.13 m2

704.33 kg

3.13 m3
LOQUE V

11/2/2018
TOTAL UNIDAD

39.02 m2

317.69 kg

805.00 Und.
RESUMEN DE METRADOS - ESTRUCTURAS - BLOQUE V

MEJORAMIENTO Y AMPLIACIÓN DEL SERVICIO DE RECREACIÓN Y


PROYECTO:ESPARCIMIENTO EN EL SECTOR DE MACHACANCHA, PROVINCIA Y DISTRITO
DE CALCA - REGIÓN CUSCO

Item Descripción Und Metrado


02.05 BLOQUE 05
02.05.01 TRABAJOS PRELIMINARES
02.05.01.01 LIMPIEZA DE TERRENO MANUAL m2 39.04
02.05.01.02 TRAZO, NIVEL Y REPLANTEO PRELIMINAR m2 39.04
02.05.02 MOVIMIENTO DE TIERRAS
02.05.02.01 EXCAVACION MASIVA A MAQUINA EN TERRENO NORMAL m3 30.02
02.05.02.02 RELLENO CON MATERIAL PROPIO Y APISONADO m3 6.21
02.05.02.03 NIVELACION Y COMPACTADO m2 39.04
02.05.02.04 ELIMINACION MATERIAL EXCEDENTE m3 27.23
02.05.03 OBRAS DE CONCRETO SIMPLE
02.05.03.01 FALSA ZAPATA
02.05.03.01.01 CONCRETO 1:8+25% PM PARA FALSA ZAPATA m3 3.73
02.05.03.01.02 CONCRETO PARA SOLADO e= 10cm m3 1.24
02.05.03.02 CIMIENTOS Y SOBRECIMIENTOS
02.05.03.02.01 SOBRE CIMIENTO 1:8 + 25% PM m3 3.73
02.05.03.02.02 ENCOFRADO Y DESENCOFRADO PARA CIMIENTOS Y SOBRECIMIENTOS m2 38.04
02.05.04 OBRAS DE CONCRETO ARMADO
02.05.04.01 ZAPATAS
02.05.04.01.01 CONCRETO EN ZAPATAS f'c=210 kg/cm2 m3 6.83
02.05.04.01.03 ACERO fy=4200 kg/cm2 ZAPATAS kg 146.60
02.05.04.02 VIGAS DE CIMENTACION
02.05.04.02.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2 m3 4.56
02.05.04.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2 33.16
02.05.04.02.03 ACERO fy=4200 kg/cm2 VIGA DE CIMENTACION kg 568.37
02.05.04.03 COLUMNAS
02.05.04.03.01 CONCRETO COLUMNAS f'c = 210 kg/cm2 m3 3.34
02.05.04.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2 39.52
02.05.04.03.03 ACERO fy = 4200 kg/cm2 COLUMNA kg 607.15
02.05.04.04 VIGAS
02.05.04.04.01 CONCRETO EN VIGAS f'c = 210 kg/cm2 m3 4.25
02.05.04.04.02 ENCOFRADO DE VIGAS m2 25.13
02.05.04.04.03 ACERO fy=4200 kg/cm2 VIGA kg 704.33
02.05.04.05 LOSAS ALIGERADAS
02.05.04.05.01 CONCRETO EN LOSA ALIGERADA f'c = 210 kg/cm2 m3 3.13
02.05.04.05.02 ENCOFRADO Y DESENCOFRADO EN LOSA ALIGERADA m2 39.02
02.05.04.05.03 ACERO fy=4200 kg/cm2 LOSA kg 317.69
02.05.04.05.04 LADRILLO HUECO DE ARCILLA h=15 cm PARA TECHO ALIGERADO und 805.00