DIAGNOSTICO 9/7/2015 9/9/2015 3 DIAS ENCUESTA 9/10/2015 9/11/2015 2 DIAS MEDICION 9/14/2015 9/14/2015 1 DIA PLANOS 9/14/2015 9/15/2015 2 DIAS PROYECTO 9/7/2015 9/18/2015 10 DIAS IMPLEMENTACION 9/21/2015 10/2/2015 10 DIAS CAPACITACION 9/21/2015 9/25/2015 5 DIAS CONTROL Y SEGUIMIENTO 9/21/2015 11/20/2015 40 DIAS RESPONSABLES CRONOGRAMA FECHA DE INISIO FECHA DE FINALIZACION DURACION DIAGNOSTICO 9/7/2015 9/9/2015 3 DIAS ENCUESTA 9/10/2015 9/11/2015 2 DIAS MEDICION 9/14/2015 9/14/2015 1 DIA PLANOS 9/15/2015 9/15/2015 2 DIAS PROYECTO 9/7/2015 9/18/2015 10 DIAS IMPLEMENTACION 9/21/2015 10/2/2015 10 DIAS CAPACITACION 9/21/2015 9/25/2015 5 DIAS CONTROL Y SEGUIMIENTO 9/21/2015 11/20/2015 40 DIAS MES SEPTIEMBRE RESPONSABLES 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 LINDAMARTIN ARENAS