Documentos de Académico
Documentos de Profesional
Documentos de Cultura
A THESIS
SUBMITTED TO THE BUILDING AND CONSTRUCTION ENGINEERING
DEPARTMENT OF THE UNIVERSITY OF TECHNOLOGY IN PARTIAL
FULFILLMENT OF THE REQUIREMENTS FOR THE DEGREE OF
MASTER OF SCIENCE IN GEOTECHNICAL ENGINEERING
By
Supervised by
الىجم ()14-93
To
MY FAMILY
MY FRIENDS
Acknowledgment
Many thanks and praise are due first of all and above all, to my Creator,
Almighty ALLAH, the Most Beneficent, the Most Gracious, and the Most
Merciful, Who gave me the ability and the desire to complete this work
despite all the hurdles and constraints in the way of its completion.
Appreciation and thanks are also extended to Dr. Zeena Waleed for
providing me with her own geogrid reinforcement.
Profuse thanks are due to the staff of soil mechanics laboratory in the
University of Technology.
Thank also extend to Mr. Khaldoon Satee Ahmed, Ali Malik and
Ahmed shamil M. Sc. students for helping me during the Master degree
stages.
The total number of the tests carried out is 58 models. Two models
were tested under static load with two relative densities (40% and 80%).
All the other 56 model tests were tested under dynamic load which
represent two series were carried out using two relative densities (40% and
80%) corresponding to loose and dense sand, respectively. All the 56 dry
sand models were subjected to dynamic load with two load amplitudes
corresponding to (0.5 ton and 1 ton) using two frequencies 1 and 2 Hz for
each load amplitude. For each amplitudes and frequency of the load, the
sand models were tested without geogrid and with geogrid of two widths
(1B and 2B) where B is the width of the footing. In addition, three series of
I
geogrid depths from the model surface (0.5B, 1B and 1.5B) were carried
out.
The dynamic load was applied in the tests by hydraulic jack system.
The response of the tunnel to dynamic loading includes measuring the
pressure above the crown of the tunnel by using pressure cell
(manufactured by Geokon company) as well as measuring the amplitude of
displacement by using a vibration meter. The response of footing was
elaborated by measuring the total settlement by using sensors in the
dynamic load apparatus.
It was found the pressure above the crown of tunnel decreased by about
(13-65) % when using geogrid reinforcement and this percentages different
according to the intensity of dynamic load and geogrid states and soil
density. Also, the pressure above the crown of the tunnel increases with
increase of load amplitude and frequency while the pressure decreases
when the relative density increase.
It was found the settlement decreased by about (13-45) % when using
geogrid reinforcement in loose sand and this percentages is different
according to the intensity of dynamic load and geogrid states, while, the
settlement has no effect when using the geogrid in dense sand. Also, the
settlement increased when the load amplitude and frequency increased
while, the settlement decreased when the relative density of the sand
increased.
II
CONTENTS
Item
Subject Page
No.
ABSTRACT I
CONTENTS III
LIST OF FIGURES VII
LIST OF TABLES XIV
LIST OF PLATES XV
LIST OF APPENDICES XVI
NOTATIONS XVII
Chapter One
INTRODUCTION
1.1 General 1
III
Item
Subject Page
No.
2.5.3 O Methods of analysis of machinery foundation 11
2.6 Geosynthetics 15
2.7 Underground Structures 16
2.7.1 Construction 16
2.7.2 Stress on tunnel wall 18
2.9 Summary 33
Chapter Three
EXPERIMENTAL WORK
3.1 Introduction 34
IV
Item
Subject Page
No.
3.4.2 Axial loading system 42
Chapter Four
PRESENTAION AND DISCUSSION OF TEST
RESULTS
4.1 Introduction 57
V
Item
Subject Page
No.
Effect of depth of reinforcement on the vertical
4.4.1 97
pressure
Effect of depth of reinforcement on the surface
4.4.2 99
settlement
Effect of width of reinforcement on the vertical
4.4.3 101
pressure
Effect of width of reinforcement on the surface
4.4.4 102
settlement
Comparison of Dynamic Load pressure transmitted
4.5 to tunnel with the ultimate bearing capacity of the 104
surface footing
Chapter Five
CONCLUSIONS AND RECOMMENDATIONS
5.1 General 107
References 111
VI
LIST OF FIGURES
Figure Title
No.
Page
(2.1) Types of dynamic load ( Aguiar, 2008). 6
(2.2) Common types of machine foundations (Rao, 2011). 10
Schematic representation of the test setup (after Tafreshi ,
(2.3)
and Khalaj, 2007).
21
Variation of the maximum ΔD with the number of
(2.4) reinforcement layer for H/D = (a) 1.5, (b) 2.5, (d) 3. (after 21
Tafreshi , and Khalaj, 2007).
Influence of geogrid on vertical and horizontal strain (after
(2.5)
Ilamparuthi 2008 ).
23
Schematic representation of the test setup (Not to scale)
used in the experiments of Mehrjardi . “A, B location of
(2.6)
soil pressure cells and strain gauges; C location of soil
29
pressure cell” (after Mehrjardi et al. 2012 ).
(2.7) Sketch of test setup adopted by Hegde (2014). 32
Pressure and strain above the pipe.(a) vertical pressure (b)
(2.8)
strain (after Hedge, 2014).
32
(3.1) Flow chart of the testing program . 35
(3.2) Grain size distribution of the used soil. 37
(3.3) Loading steel frame. 43
(3.4) Dynamic load wave. 56
(4.1) Static tests result at different relative densities. 58
Variation of the vertical pressure above the tunnel crown
(4.2) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 61
and with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.3) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 61
and with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.4) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 61
and with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.5) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 62
and with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.6) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 62
and with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.7) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 62
and with geogrid (d= 1.5B and b= 1B).
VII
Figure Title
No.
Page
Variation of the surface settlement with time for a =0.5 ton,
(4.8) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 64
B and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.9) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B 64
and b= 1 B).
Variation of the surface settlement with time for a =0.5
(4.10) ton, w = 1 Hz and Dr. = 40%, without and with geogrid (d= 65
1.5 B and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.11) w = 1 Hz and Dr. = 80%, without and with geogrid (d= 0.5 65
B and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.12) w = 1 Hz and Dr. = 80%, without and with geogrid (d= 1 B 65
and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.13) w = 1 Hz and Dr. = 80%, without and with geogrid (d= 1.5 66
B and b= 1 B).
Variation of the vertical pressure above the tunnel crown
(4.14) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 67
and with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.15) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 68
and with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.16) with time for a =0.5 ton, w =1 Hz and Dr. =40%, without 68
and with geogrid (d= 1.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.17) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 68
and with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.18) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 69
and with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.19) with time for a =0.5 ton, w =1 Hz and Dr. =80%, without 69
and with geogrid (d= 1.5B and b= 2B).
Variation of the surface settlement with time for a =0.5 ton,
(4.20) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 70
B and b= 2 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.21) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B 70
and b= 2 B).
VIII
Figure Title
No.
Page
Variation of the surface settlement with time for a =0.5 ton,
(4.22) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 70
B and b= 2 B).
Variation of the vertical pressure above the tunnel crown
(4.23) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 72
with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.24) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 72
with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.25) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 72
with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.26) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 73
with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.27) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 73
with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.28) with time for a =1 ton, w =1 Hz and Dr. =40%, without and 73
with geogrid (d= 1.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.29) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 74
with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.30) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 74
with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.31) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 74
with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.32) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 75
with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.33) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 75
with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.34) with time for a =1 ton, w =1 Hz and Dr. =80%, without and 75
with geogrid (d= 1.5B and b= 2B).
Variation of the surface settlement with time for a =1 ton,
(4.35) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 76
B and b= 1 B).
IX
Figure Title
No.
Page
Variation of the surface settlement with time for a =1 ton,
(4.36) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B 77
and b= 1 B).
Variation of the surface settlement with time for a =1 ton,
(4.37) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 77
B and b= 1 B).
Variation of the surface settlement with time for a =1 ton,
(4.38) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 77
B and b= 2 B).
Variation of the surface settlement with time for a =1 ton,
(4.39) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B 78
and b= 2 B).
Variation of the surface settlement with time for a =1 ton,
(4.40) w = 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 78
B and b= 2 B).
Variation of the vertical pressure above the tunnel crown
(4.41) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 79
and with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.42) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 80
and with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.43) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 80
and with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.44) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 80
and with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.45) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 81
and with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.46) with time for a =0.5 ton, w =2 Hz and Dr. =40%, without 81
and with geogrid (d= 1.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.47) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 81
with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.48) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 82
with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.49) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 82
with geogrid (d= 1.5B and b= 1B).
X
Figure Title
No.
Page
Variation of the vertical pressure above the tunnel crown
(4.50) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 82
with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.51) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 83
with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.52) with time for a =1 ton, w =2 Hz and Dr. =40%, without and 83
with geogrid (d= 1.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.53) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 83
and with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.54) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 84
and with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.55) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 84
and with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.56) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 84
and with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.57) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 85
and with geogrid (d= 1B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.58) with time for a =0.5 ton, w =2 Hz and Dr. =80%, without 85
and with geogrid (d= 1.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.59) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 85
with geogrid (d= 0.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.60) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 86
with geogrid (d= 1B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.61) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 86
with geogrid (d= 1.5B and b= 1B).
Variation of the vertical pressure above the tunnel crown
(4.62) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 86
with geogrid (d= 0.5B and b= 2B).
Variation of the vertical pressure above the tunnel crown
(4.63) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 87
with geogrid (d= 1B and b= 2B).
XI
Figure Title
Page
No.
Variation of the vertical pressure above the tunnel crown
(4.64) with time for a =1 ton, w =2 Hz and Dr. =80%, without and 87
with geogrid (d= 1.5B and b= 2B).
Variation of the surface settlement with time for a =0.5 ton,
(4.65) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 88
B and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.66) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B 88
and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.67) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 89
B and b= 1 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.68) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 89
B and b= 2 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.69) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B 89
and b= 2 B).
Variation of the surface settlement with time for a =0.5 ton,
(4.70) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 90
B and b= 2 B).
Variation of the surface settlement with time for a =1 ton,
(4.71) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 90
B and b= 1 B).
Variation of the surface settlement with time for a =1 ton,
(4.72) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B 90
and b= 1 B).
Variation of the surface settlement with time for a =1 ton,
(4.73) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 91
B and b= 1 B).
Variation of the surface settlement with time for a =1 ton,
(4.74) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 91
B and b= 2 B).
Variation of the surface settlement with time for a =1 ton,
(4.75) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B 91
and b= 2 B).
Variation of the surface settlement with time for a =1 ton,
(4.76) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 92
B and b= 2 B).
displacement of the tunnel with time for a =0.5 ton, w = 1
(4.77) Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and 97
b= 1 B).
XII
Figure Title
Page
No.
displacement of the tunnel crown with time for a =0.5 ton,
(4.78) w = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 97
B and b= 1 B).
Relationship between the vertical pressure on the tunnel
(4.79)
crown and (d/B) ratio for b = 1B
98
Relationship between the vertical pressure on the tunnel
(4.80)
crown and (d/B) ratio for b = 2B
99
Relationship between the surface settlement and (d/B) ratio
(4.81)
for b= 1B
100
Relationship between the surface settlement and (d/B) ratio
(4.82)
for b= 2B
100
Relationship between the vertical pressure and (b/B) ratio
(4.83)
for d= 0.5B
101
Relationship between the vertical pressure and (b/B) ratio
(4.84)
for d= 1B
102
Relationship between the surface settlement and (b/B) ratio
(4.85)
for d= 0.5B
103
Relationship between the surface settlement and (b/B) ratio
(4.86)
for d= 1B
103
XIII
LIST OF PLATES
Plate
Title Page
No.
(2.1) Geocell. 16
(2.2) Geogrid reinforcement. 16
XV
LIST OF TABLES
Table
Title Page
No.
(3.1) Physical properties of sand used. 36
(4.2) Vertical pressure above the tunnel crown for loose sand 93
(4.3) Vertical pressure above the tunnel crown for dense sand 94
(4.7) The ratio between Qd max and Qs for dense sand 105
XIV
LIST OF APPENDICES
Appendix
Title Page
Item
A Additional Results
Results of Variation of Surface Settlement with Time in
A-1 A-1
Dense Sand
Results of Variation of Amplitude of Vibration with
A-2 A-9
Time for Loose and Dense Sand
XVI
NOTATIONS
Symbol Definition
ASTM American society for testing and materials
b Width of reinforcement
B Width of footing
BE Boundary element method
c Cohesion of soil
Cc Coefficient of curvature
Cu Coefficient of uniformity
D Diameter of the pipe
d Depth of geogrid
Df Depth of the footing
DD Damping ratio
Dr Relative density
FE Finite element method
G Dynamic shear modulus
H Depth of geocell
Hz Hertz (cycle/sec).
k0 Coefficient of lateral earth pressure
ky Wave number
LCD Liquid crystal display
Nc, Nq, Nγ Bearing capacity factors which depend on φ
PLC Programmable Logic Controller.
PPV Peak particle velocity
Pu Measured pressure value
PUR Peak uplift resistance
PVC Poly Vinyl Chloride
q Applied vertical stress
Qd max Maximum pressure transmitted to the tunnel
Qult Ultimate bearing capacity.
SSS Settlement of soil surface
t Time
T Load period
U.V Ultraviolet
USCS Unified soil classification system.
Vs Shear wave velocity
Z Depth of the pipe
XVII
Symbol Definition
γ Unit weight of the soil
ΔD Vertical diameter change
ν Poisson’s ratio
φ Angle of soil internal friction.
Frequency of load
n Natural frequency of the soil-foundation system
r Operating frequency of the machine
Amplitude of load
XVIII
CHAPTER ONE
INTRODUCTION
1.1 General
In process design, the stability of tunnels and other underground
structures under the influence of seismic waves and dynamic load is one of
the important issues that should be studied carefully. Although seismic
waves are not the only cause of earthquakes, however, earthquakes are the
most known source of seismic waves. In addition, the movement of trains
in underground tunnels, the operation of machinery on ground surface and
many other activities as such produce seismic waves that if to be neglected,
may cause different damages such as subsidence. Such damages not only
result in an increase in costs, but also remain to be a source of danger to the
human lives.
In the past, it has always been assumed that earthquakes have no major
effect on tunnels, however the study of tunnel behaviors on seismic loads
and also the damage of these structures, emphasize the necessity of the
stability study under dynamic loading generated by earthquake (Williams,
1997).
Nowadays, the development in industry introduced huge machines
which have a great influence on the performance of the foundations and the
soil underneath and produces another type of vibration load.
Essentially in this, the engineer has to study the problems of shocks and
vibrations on the foundations supporting industrial installations, as well as
the laws governing the propagation of waves from these foundations
through the soil (Rao, 2011).
Problems in dynamic soil-structure interaction (DSSI) are characterized
by a system consisting of a structure, which rests on or embedded in a soil
region of unbounded extent, and is subjected to a specified time-varying
load. Dynamic analysis of (SSI) refers to how soil deformations affect the
1
Chapter One Introduction
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
motions of buildings being subjected to a dynamic loading (Park and Antin,
2003).
Geosynthetics are very durable polymeric products being used in
different civil engineering applications in order to provide strength,
stability, and durability. Use of geosynthetic materials has become more
and more common in the past 40 years for a number of applications and
they have the potential to reduce the cost of maintenance by increasing the
design life. Geosynthetics could be categorized into seven different
products as follows: geotextiles, geogrids, geonets, geomembrances,
geosynthetics clay liners, geofoam, and geocell.
This thesis will address itself to the influence of geogrid reinforced dry
sand in transfer of dynamic loading to underground structure.
2
Chapter One Introduction
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
the extent and nature of the movements and disturbance occurring in
areas above and adjacent to tunnels. These deformations may
significantly affect nearby structures and need to be considered
during design.
The state of stress and the displacements in an influence zone around a
tunnel will be modified by the construction of a tunnel. The size of this
influence zone depends on the type and properties of soil, in situ stresses,
tunnel depth and size, the tunnel support system, and tunneling method.
3
Chapter One Introduction
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Chapter four: Presents analysis and discussion of the test results obtained
from the model tests.
Chapter five: Summarizes the main conclusions from this work and the
recommendations for the future works.
4
CHAPTER TWO
REVIEW OF LITERATURE
2.1 Introduction
The behavior of underground structures is usually complicated in
comparison with super structures; this is mainly due to the soil-structure
interaction, which in many cases can hardly be predicted.
Among the underground structures, lifelines are of great importance and
sensitivity because they are quite spread in the urban areas and serve the
vital needs of the societies. Although different codes and provisions are
suggested for the safe design of lifelines, the designed and constructed
lifelines could not escape damaging when subjected to severe dynamic
loadings particularly strong blasts or earthquakes.
This chapter presents a brief review of important literatures that have
concern with the main objectives of this study. Other literature related to
some topics will implicitly be mentioned when these topics will be
discussed.
The type of the soil affects its response under dynamic loading
conditions. The most significant factors separating different types of soils
are the grain size distribution. Well graded materials are less susceptible to
losing strength under dynamic loading, on the other hand uniform soils are
more susceptible to losing strength under dynamic loading.
Loose, uniform soil is especially subjected to collapse and failure.
Loose soil may densify under vibrating loading and causes permanent
settlement.
The presence of fines in the soil, especially clays inhibits the
dissipation of excess pore water pressure. It also decreases the tendency for
liquefaction, as well as degree of saturation of soil system plays role in this
connection.
When the soil is saturated, a transient dynamic loading will usually
last for a very short duration. The duration is so short that the soil response
is essentially undrained. It is also important to know whether the dynamic
loading is a transient phenomenon, such as a blast loading or earthquake, or
8
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
is a long term phenomenon, like a vibratory loading from rotating
machinery. The distinction is important because a transient dynamic
phenomenon occurs so rapidly that excess pore pressure does not have time
to dissipate. Dissipation of pore water is possible only in the case of very
coarse, clean gravels. In this context, the length of the drainage path is also
important. Even a clean, granular material may retain large excess pore
pressure if the drainage path is so long that the pressures cannot dissipate
during the dynamic loading consequently (MIL-HDBK, 1997).
Dynamic loading may produce a wide range of deformations of soils.
In intermediate range, soil deformations vary from small amplitude near
elastic to plastic following earthquakes; water waves and machine develop
forces in problems that involve dynamic loading of soils. There are two
important parameters; the first is the strain levels induced in the soil, below
the order 10-5. The deformation exhibited by most soils is purely elastic and
recoverable. The phenomena associated with such small strains would be
small amplitude vibration or wave propagation through soils. Over the
intermediate range of strain between 10 -4 and 10-2, the behavior of soils is
elasto-plastic and produces irrecoverable permanent deformations
(Daghigh, 1993). The second dynamic parameter for the soil is the
damping.
Roesset and Jose, (2009) stated that the design of foundations to support
heavy machinery was first recognized in the 1920, giving rise to the field of
soil dynamics.
9
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.5.1 Types of machinery foundations
The foundations supporting machines are classified according to different
bases. However, the most popular types of machine foundations fall within
the following categories and explained in Figure (2.2) (Rao, 2011):
Block foundations resting on soil or piles.
Frame foundations.
Wall foundations.
Spring mounted machines resting on rafts/grade slabs.
2.5.2 Types of machines
Rotary machine.
Reciprocating machines.
Impact type machines.
2- Based on the operating speed:
11
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
supported structure can be readily evaluated (Banerjee and Butterfield,
1987). Some of the methods for the foundation vibration analysis are:
12
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3. Foundation material
The most common material used for machine foundation is the
reinforced concrete. In specific cases, structural steel has also been
used for frame foundations. However, the material properties
required for foundation design and analysis are mass density,
dynamic shear modulus, static elastic modulus, and Poisson's ratio.
Other material parameters may be needed for analysis using specific
analysis model and available computer software.
4. Compatibility in geometry between foundation and machine
The geometry of the foundation as well as machine type plays a
great role in the analysis and design of the machine-foundation
system. For this reason, many parameters and limitations should be
taken into consideration in the analysis and design of such system.
These limitations are listed below (Barkan, 1962, Srinivasulu and
Vaidyanathan, 1977, Arya et al., 1979, Das, 1983 and Bhatia, 2009):
Center of gravity: The combined center of gravity of machine
and foundation and the center of contact area (with the soil)
should lie on the same vertical line as far as possible.
Eccentricity: The eccentricity should not exceed 5 percent of
the least width in any horizontal direction.
Area of the block: The size of a foundation should be larger
than the bedplate of the machine it supports with a minimum
all-round clearance of 150mm.
Foundation mass ratio: It is the ratio of the mass of
foundation to that of machine. This ratio is of different values
depending on the machine type. For rotary machine, the mass
ratio of 2.5-4.0 is generally considered appropriate. For
reciprocating machine, the mass ratio is always high and may
reach 8.0.
13
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.5.5 Vibration criteria
Bhatia, (2009)
where:
14
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
as soil type and characteristics. In no case should the permissible amplitude
exceed the limiting amplitude prescribed for the machine by the
manufacturer.
2.6 Geosynthetics
Geosynthetics are very durable polymeric products being used in
different civil engineering applications in order to provide strength,
stability, and durability. Use of geosynthetic materials has become more
and more common in the past 40 years for a number of applications and
they have the potential to reduce the cost of maintenance by increasing the
design life. Geosynthetics could be categorized into eight different products
as follows: geotextiles, geogrids, geonets, geomembranes, geosynthetic
clay liners, geofoam, and geocells. Geocells are three-dimensional
honeycomb shape product made of high-density polyethylene (HDPE).
Examples of geocells are shown in Plate (2.1)
15
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
17
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
advance is usually undertaken by using headings and side drifts to limit the
size of the open excavation face (Potts and Zdravkovic, 2001).
2.7.2 Stresses on tunnel wall
The three principal stresses in a cylindrical tunnel are; the stress
acting in a direction parallel to the axis of the tunnel barrel, is termed the
longitudinal stress, the stress acting in the circumferential direction, is
called the circumferential or tangential stress and the stress acting in the
radial direction and varying through the thickness of the tunnel wall, is
termed the radial stress.
For thin walled tunnel, where the ratio of the mean radius of the tunnel
and the thickness of the tunnel wall is more than 10 the longitudinal stress
and tangential stress are practically uniform throughout the thickness of the
wall and are the only important ones present, the radial stresses are usually
negligibly small (Young, 1989).
19
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
found that the maximum pore water pressure ratio in soil occurs near the
top of the tunnel and it almost has no effect on the tunnel. Using different
depths of input, base boundary will affect the results of dynamic analysis of
the tunnel. The response values with the depth of 280 m of input base
boundary are larger than that with the depth of 50 m of input base
boundary. Using different input motions will also affect the results of
dynamic analysis of the tunnel. Using Tangshan earthquake and Lotung
earthquake record as input motion will get relatively larger response values
of dynamic analysis of the tunnel.
Tafreshi, and Khalaj, (2007) described laboratory tests on small-
diameter high-density polyethylene pipes buried in reinforced sand with
geocell subjected to repeated loads to simulate the vehicle loads. Figure
(2.3) shows the physical model test. The amplitude of applied stress was
5.5 kg/cm2 in all tests. Deformation of the pipe was recorded at eight points
on the circumference of the tested pipes to measure the radial deformations
of the pipe. Also, settlement of the soil surface was measured throughout
the test for up to 1000 cycles of loading. These values increased rapidly
during the initial loading cycles; thereafter the rate of deformation reduced
significantly as the number of cycles increased. The variables examined in
the testing program included relative density of the sand, number of
reinforced layers, and embedment depth of the pipe. The influence of
various reinforced layers at relative densities of 42%, 57%, and 72% in
different embedded depths of 1.5–3 times of pipe diameter were
investigated. The results showed that the percent vertical diameter change
(ΔD) and settlement of soil surface (SSS) can be reduced up to 56% and
65% for ΔD and SSS, respectively, by using geogrid reinforcement, and
increase the safety of embedded pipes. Also, the efficiency of
reinforcement was decreased by increasing the number of reinforcement,
the relative density of soil and the embedded depth of the pipe as shown in
Figure (2.4) . The influence of the first cycle was also found to be one of
20
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
the main behavioral characteristics of buried pipes under repeated loads.
The ratio of deformation of the pipe from the first cycle to the last cycle
changes from 0.5 to 0.9 in different tests. It should be noted that only one
type of pipe, one type of geogrid, and one type of sand are used in
laboratory tests.
Figu
re (2.3): Schematic representation of the test setup adopted by Tafreshi ,
and Khalaj, (2007).
Figure (2.4): Variation of the maximum ΔD (strain of the pipe) with the
number of reinforcement layers for H/D = (a) 1.5, (b) 2.5, (c) 2.5, (d) 3
(after Tafreshi , and Khalaj, 2007).
21
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Tafreshi et al. (2007) studied artificial neural network and regression
model for predicting the vertical deformation of high-density polyethylene
pipes. Small diameter flexible pipes buried in reinforced trenches, which
were subjected to repeated loadings to simulate the heavy vehicle loads
were proposed. The experimental data from tests showed that the vertical
diametric strain (ΔD) of pipe embedded in reinforced sand depends on
relative density of sand, number of reinforced layers and height of
embedment depth of pipe significantly. Therefore, the value of ΔD was
related to the above pointed parameters. A database of 72 experiments from
laboratory tests were utilized to train, validate and test the developed neural
network and regression model. The results showed that the predicted
vertical diametric strain (ΔD) using the trained neural network and
regression model are in good agreement with the experimental results but
the predictions obtained from the neural network are better than regression
model as the maximum percentage of error for training data is less than
1.56% and 27.4%, for neural network and regression model, respectively.
Also the additional set of 24 data was used for validation of the model as
90% of predicted results have less than 7% and 21.5% error for neural
network and regression model, respectively. A parametric study was
conducted using the trained neural network to study the important
parameters on the vertical diametric strain.
Ilamparuthi and Rajkumar (2008) studied the experimental
investigation conducted on flexible PVC pipes buried in loose and dense
conditions of sand bed and subjected to surface pressures. The response of
the pipes was studied with and without geogrid reinforcement. It was
observed that the incorporation of geogrid reinforcement resulted in
significant decrease in the crown deflection of the pipe and offered better
protection to the pipe at shallow burial depths . Figure (2.5) shows the
influence of geogrid on the deflection of the pipe.
22
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
25
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
material damping and the shear modulus of the soil have an important
influence on the propagation of vibrations. The influence of structural
changes to the tunnel as well as geometrical properties such as the size and
shape of the tunnel was investigated. It was observed that a larger tunnel
results in a smaller response above the tunnel as more energy is radiated
downwards. Moreover, it is demonstrated that the tunnel geometry has a
considerable influence on the response closer to the tunnel.
Goltabar and Shekarchi (2010) studied the effects of truck load on the
buried pipeline which were done with numerical and experimental
methods. In numerical method, model is assumed half extreme and length
of them are considered extreme, mathematically. For performing of
numerical method, 3Diamentional models were used in Plaxis-
3Diamentional software. For comparison and checking of results,
experimental model was prepared and with using of electrical strain gages
and computer, results of experimental model were recorded. Results
showed that the experimental and finite element models results are
compatible.
26
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
increases. Due to increases of the axial force, the bending moment and the
shear-force applied on tunnel by seismic loading, the dynamic analysis and
also static analysis for tunnel stability is required.
Yang et al. (2010) studied the numerical simulation of dynamic
response of operating metro tunnel induced by ground explosion with the
general commercial program ANSYS/LS-DYNA and found that the blast
induced waves propagate in the soil in the form of hemispherical waves.
The numerical simulation results of the peak pressure and the peak
acceleration in the soil are compared with the predictions. The discrepancy
between two results is analyzed. The distribution and magnitude of the
stress field of the tunnel lining are influenced by the tunnel depth and TNT
equivalence. According to the von Mises failure criterion, the upper part of
the tunnel lining, ranging from 0° to 22.5° of the cross-section and the
horizontal distance 0 to 7 m away from the explosive center, is the unstable
area. The metro tunnel at the above-mentioned area maybe fail when the
tunnel depth is 7 m and the TNT equivalence reaches 1 000 kg. In other
words, the metro tunnel in soft soil might be safer when the tunnel depth is
more than 7 m and the TNT charge of ground surface explosion is no more
than 500 kg.
Figure (2.6): Schematic representation of the test setup (Not to scale) used
in the experiments of Mehrjardi . “A, B location of soil pressure cells and
strain gauges; C location of soil pressure cell” (after Mehrjardi et al. 2012 )
Bildik, et al. (2012) investigated the buried pipe behavior by the finite
element method using the computer program PLAXIS. The undertaken
analyses have been done with different surcharges and different soil
conditions. Based on the results, it was concluded that the intensity of
surcharge load affect the pipe behavior. The pipe displacements increased
linearly with increase in surcharge load. The results showed that the pipe
displacements decrease with increase of embedment ratio. This behavior
can be explained using stress-displacement behavior. The vertical stress
decreases with increase of embedment ratio. The variation of vertical stress
with embedment ratio from the PLAXIS analyses showed generally similar
behavior with Boussinesq's theory. The pipe behavior is strongly
influenced by the relative density of sand. The pipe displacements decrease
with increase on relative density of sand. The results also showed that the
pipe displacements decrease with increase of rigidity of pipe .
29
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Ozdemir et al. (2012) studied the response of pipelines to vibrations
induced by the operation of a pavement breaker during the rehabilitation of
concrete pavements. An efficient two-and-a-half-dimensional
(2.5Diamentionall) formulation was employed, where the geometry of the
structure and the soil was assumed to be invariant in the longitudinal
direction. The dynamic soil–structure interaction problem is solved by
means of a 2.5Diamentional coupled finite element–boundary element (FE–
BE) method using a subdomain formulation. The numerical model was
verified by means of results available in the literature for a buried pipeline
subjected to incident P- and SV-waves with an arbitrary angle of incidence.
The presented methodology is capable to incorporate any type of incident
wave field induced by earthquakes, construction activities, traffic,
explosions or industrial activities. The risk of damage to a high pressure
steel natural gas pipeline and a concrete sewer pipe due to the operation of
a pavement breaker is assessed by means of the 2.5Diamentional coupled
FE–BE methodology. It was observed that the stresses in the steel pipeline
due to the operation of the pavement breaker are much lower than those
induced by the operating internal pressure. The steel pipeline behaves in
the linear elastic range under the combined effect of the loadings,
indicating that damage to steel pipelines close to the road due to the
operation of a pavement breaker is unlikely. The maximum principal stress
in the concrete pipe, on the other hand, remains only slightly lower than the
specified tensile strength. The decision to use a pavement breaker should
hence be taken with care, as its operation may induce tensile stresses in
concrete sewer pipes which are of the same order of magnitude as the
tensile strength of the concrete.
Figure (2.8): Pressures and strains above the pipe. (a) vertical pressure (b)
strain (after Hedge et al., 2014).
32
Chapter Two Review of Literature
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Armaghani et al. (2015) examined the effect of performing geogrid to
increase the uplift resistance of buried pipelines, and the effect of burial
depth, pipe diameter, length of geogrid layers and the number of geogrid
layers on the peak uplift resistance (PUR) of loose sand. Thirty three small-
scale tests were performed in the laboratory. Results of laboratory tests
revealed that the depth of burial and pipe diameter have a direct effect on
the PUR results. The findings showed that the number of geogrid layers
does not have a remarkable influence on PUR values. To verify the
experimental results, 33 experiments were back analyzed using „„PLAXIS
3Diamentional TUNNEL‟‟ program. It was found that experimental and
numerical results are in good agreement.
2.9 Summary
General observations on previous studies by various researchers as
reported in the literature are:
1. There is a huge amount of work available in the literature
concentrated on the behavior of tunnel under dynamic load by
analytical or numerical models.
2. There is few data available on the effect of geogrid in transfer of
dynamic loading to the underground tunnel
3. There are very few data on the effect of variation of dynamic load
amplitude and frequency on the behavior of soil and underground
tunnel.
Hence, the present study is directed to study the influence of geogrid
reinforced earth in transfer of dynamic loading to underground tunnel
focusing on the behavior of surface settlement and pressure on the
tunnel crown. Also the effect of different parameters such as: load
amplitude, frequency, geogrid depth and width and relative density will
be studied.
33
CHAPTER THREE
EXPEREMENTAL WORK
3.1 Introduction
The experimental work consists of performing laboratory model tests to
investigate the behavior of dry sand under the effect of dynamic load. The
effect of geogrid on the settlement and transition of dynamic load to the
underground structure was studied considering different parameters such
as: depth of geogrid, width of geogrid, relative density of sand, amplitude
of dynamic force and load frequency.
The focus of this chapter is to describe the engineering properties of the
sand used in the study and to outline the design and manufacturing of the
testing equipment, model preparation and testing procedures.
34
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
TESTING PROGRAM
Dry Sand
36
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.3.1.1 Soil characterization
Laboratory tests which are carried out on the used soil included the
following:
1- Specific gravity: Specific gravity tests were performed in general
accordance with (ASTM) D 854 – 2005 Standard Test Method for Specific
Gravity of Soils.
2- Grain size distribution: Sieve analysis was performed in general
accordance with (ASTM) D 422 – 2001 Standard Test Method for Particle-
Size Analysis of Soils. Grain size distribution of the used sand is shown in
Figure (3.2).
100
90
80
Percent Passing, %
70
60
50
40
30
20
10
0
10 1 0.1
Grain Size, mm
A PVC pipe was used in all tests to simulate the underground tunnel. The
pipe has a diameter of 110 mm and 700 mm long, it was placed at a depth
equal to 500 mm from the surface. Plate (3.1) shows the PVC pipe used.
40
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
41
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.4.1 Loading steel frame
To support the verticality of piston system used in applying the
central concentrated load, a steel frame was designed and constructed as
shown in Figure (3.3).
The steel frame consists mainly of four columns and four beams.
The cross sectional area of each column and beam are made of steel with
square cross section area of (100 mm×100 mm) and 4 mm thick. The
dimensions of the steel frame (length× width× height) are (1700 mm×
700 mm×1700 mm). To strengthen the steel frame to withstand the
applied load, two beams were added in this work (No. 4 in Figure 3.3).
The steel frame was fixed to the floor base using four base plates of
dimensions (200 mm×200 mm×20 mm). Each base plate was fixed with
the floor using four bolts of 16 mm diameter.
1. Hydraulic jack system: The cross sectional area of the piston is 2025
mm2, the length of the piston is (600 mm) and the maximum limit of load
that can be applied is (8 tones) as shown in Plate (3.5) .
42
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
To study and investigate the real behavior of the tested models during
the application of the dynamic load, it is necessary to find a procedure to
measure and sense the displacement induced by the dynamic load during
the test, which enable the tester to obtain the total accurate information that
consists of a huge data of readings in a very short time. For this reason,
data acquisition system was used.
45
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
vibration and impact, and it saves this process from a huge numerical
operations (Abd Al-Kaream, 2013).
The container was used to prepare the test sample, the internal
dimensions are 1000 mm length, 750 mm width and 700 mm depth. Each
part of the container is made of steel plates 5 mm thick. Plate (3.10) shows
the steel container.
Specification value
Transducer type and output Vibrating wire and 2000-3000Hz
Standard range and accuracy 170 kPa ± 0.1% F.S.
Standard cell dimensions (H×D) 6×100 mm
Transducer dimensions (L× D) 150×25 mm
Temperature range -20ºC to + 80 ºC
The vertical amplitude of tunnel was measured at the surface of the tunnel.
Vibration meter (VT-8204) of one channel was used in the test. This
vibration meter has a working capacity of 0.001 to 2.217 mm, it is capable
50
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
of measuring the displacement, velocity, and acceleration of motion
depending on the function set prior to the test. In addition, all the collected
data can be transferred to the computer easily through built in software.
During the tests, one vibration meter was used to measure the amplitude of
dislacement on the surface of the tunnel. The components of the VT- 8204
vibration meter are shown in Plate (3.13). The vibration meter within the
testing models is shown in Plate (3.14).
51
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.5 Sand Deposit Preparation
The sand deposit was prepared using a steel tamping hummer
manufactured for this purpose. As stated previously in this chapter, two
cases of relative densities are chosen (40% for loose sand and 80% for
dense sand), this means that the weight required to achieve the relative
density is predetermined since the unit weight and the volume of the sand
are predetermined also. The sand is divided into equal weights each weight
represents the quantity of sand required for each layer.
The soil of each layer was compacted to a predetermined depth. A PVC
pipe that simulate a tunnel was installed on a soil bedding of 250 mm. After
that, the pressure cell and vibration meter probe were installed above the
pipe crown and then the soil deposit preparation was completed. Then, the
geogrid was placed in the desired depth and width. After completing the
final layer, the top surface was scraped and leveled by a sharp edge ruler to
get as near as possible a flat surface. The strip footing was then brought in
contact with the top surface of the model. Plate (3.15) presents the steps of
the sand deposit preparation. Table (3.4) summarizes the properties of the
sand used in different states.
Table (3.4): Different states of sand used.
52
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
)(1 )(2
)(3 )(4
Plate (3.15) : Stages of the preparation of the test model.
53
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
)(5 )(6
)(7
54
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3.6 Static Loading Test
The static loading was applied gradually through an axial loading system
manufactured by Rahil, (2007). The system operates at a controlled
displacement of 0.03 mm/sec. Process of the loading is continued till
failure occurs. Plate (3.16) shows the application of static load.
( ) ( )
55
Chapter Three Experimental Work
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
where :
Amplitude of load.
Frequency of load.
t = Time
T = Load period.
The shape of the dynamic wave loading applied is of the form close to the
sinusoidal compressive type as shown in Figure (3.4).
56
CHAPTER FOUR
PRESENTATION AND DISCUSSION OF TEST RESULTS
4.1 Introduction
As a reference, two model tests are performed under static load using
sand of two different relative densities 40% and 80% which are
corresponding to loose and dense sand, respectively. For all model tests,
the failure is defined as the load causing a settlement corresponding to 10%
of the footing width depending on the proposal given by Terzaghi, (1943).
Figure (4.1) represents the relationship between the applied vertical stress
(q) and the settlement of the two model tests. It is clearly shown that the
mode of failure is local shear failure for Dr = 80% and punching shear
failure for Dr = 40%.
57
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
This result agrees well with Terzaghi equation (Terzaghi, 1943).
Qult = c NC+ q Nq+ 0.5 Nγ ……………. (4-1)
where: qu = ultimate bearing capacity,
c = cohesion of soil,
Df = the depth of footing,
q = surcharge (γDf),
Nc, Nq and Nγ Terzaghi bearing capacity factors, and
B = width of foundation and γ unit weight of the soil.
For the soil used in this study, the value of c 0 (cohesionless soil)
and (Df 0) (footing at the surface), so Equation 4.1 becomes:
qult 0.5 γ B Nγ ……………. (4-2)
Table (4.1) summarizes the static bearing capacity.
58
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Table 4.1 : Bearing capacity of strip footing over sandy soil.
Qult. (kPa)
Experimental Theoretical (Eq. 4.2)
Loose sand Dense sand Loose sand Dense sand
15 43 7.2 20.8
59
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
performance of buried pipes, but this percentage decreased to about (7-
13)% when the geogrid is placed at a depth equal to (1B) because the
distribution of load at a depth (1B) gives smaller pressure intensities than at
a depth of (0.5B), whereas no decreasing in pressure was noticed when the
geogrid is placed at depth equal to (1.5B) because the geogrid was placed
at a depth out of the bulb of stresses below the strip footing in comparison
with the results of geogrid and without geogrid. These percentages are
different according to the state of load and geogrid width.
On the other hand, Figures (4.5) to (4.7) present the variation of the
vertical pressure on the crown of a tunnel embedded in dense sand with
time. In general, it can be noticed that when the geogrid is placed at a depth
equal to (0.5B) from the surface, the pressure decreases by about (13-60)%
in comparison with the results without geogrid and this percentage is
greater than in loose sand because the efficiency of pressure redistribution
in dense state is better than in loose state due to rearrangement of soil
particles in loose sand and that does not occur in dense sand, but when the
geogrid is at a depth (1B and 1.5B), there is no decrease in the pressure
compared with the results of pressure without geogrid because the geogrid
was placed at a depth out of the active zone of stresses below the footing.
This percentage is different according to the state of load and geogrid.
When a tunnel is installed in soil, soil columns on both sides of the rigid
pipe are more compressive than the soil columns on top of the rigid pipe
because of the higher stiffness of rigid pipes when compared with soils. As
such, soil columns on both sides tend to settle more than the soils on top of
the rigid pipe and this differential settlement causes a downward shear
force acting along the sides of soil columns on top of the rigid pipe. As
such, the load on the rigid pipes becomes larger than the sole weight of soil
columns on its top. Similarly, if a flexible pipe is adopted instead (as in the
case of the present study), the previous phenomenon shall be reversed .
60
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.2) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω =1 Hz and Dr. =40%, without and with geogrid (d=
0.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.3) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω =1 Hz and Dr. =40%, without and with geogrid (d=
1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.4) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω =1 Hz and Dr. =40%, without and with geogrid (d=
1.5B and b= 1B).
61
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.5) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω =1 Hz and Dr. =80%, without and with geogrid (d=
0.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.6) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω =1 Hz and Dr. =80%, without and with geogrid (d=
1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.7) : Variation of the vertical pressure above the tunnel crown with
time for a =0.5 ton, ω = 1Hz and Dr. =80%, without and with geogrid (d=
1.5B and b= 1B).
62
Chapter Four Presentation and Discussion of Test Results
ـــــ ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2- Effect of depth of reinforcement on the surface settlement:
The surface settlement was measured by sensors in the dynamic load
apparatus as described in Chapter Three. Figures (4.8) to (4.10) show the
variation of the surface settlement with time for model footing on loose
sand. The results show that the vertical settlement can be reduced by about
(20-44)% when using geogrid reinforcement at a depth equals to (0.5 B).
This decrease is attributed to the smaller soil mass above the reinforcing
layer which could have insufficient overburden to generate enough friction
and tension resistance at the soil reinforced interface according to Tafreshi
et al. (2008) who studied the laboratory tests of small diameter pipes buried
in reinforced sand under repeated load. Furthermore, this percentage will
decrease to about (13-37)% when the geogrid is placed at a depth equal to
(1B) because the soil mass increases so the friction and tension resistance
decreases. In addition, when the geogrid is placed at a depth equals to
(1.5B), the results of vertical settlement without geogrid are approximately
close to results of vertical settlement with geogrid. This indicates that the
efficiency of geogrid decreases when the depth increases. The geogrid has
no efficiency at a depth equal to (1.5B) this can be attributed to the stress
zone below the foundation, when the geogrid is placed at a depth of 0.5B or
1B, it is within the stress bulb, so that its presence affects considerably the
values of displacements induced by the dynamic load. These percentages
are different according to the state of load and geogrid. This behavior was
also noticed by Tafreshi and Khalaj (2008) who observed an increase in the
bearing capacity up to approximately 2.7 times by placing the
reinforcement within a homogenous sand at a depth within the range of
u/B= 0.25-0.75 (u is the reinforcement depth and B is the footing width).
On the other hand, Figures (4.11) to (4.13) show the variation of the
surface settlement with time for model footing on dense sand. The results
show that there is no efficiency of using geogrid on the surface settlement
in dense sand and that is compatible with the results of Tafreshi, (2008)
63
Chapter Four Presentation and Discussion of Test Results
ـــــ ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
who found that the reinforcement at lower relative density is more effective
than higher relative density. Further results will be presented in Appendix
(A).
Time, sec.
0 200 400 600 800 1000 1200 1400
0
Surface settlement, mm
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 1 B
90
Figure (4.8) : Variation of the surface settlement with time for a =0.5 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
0
Surface settlement, mm
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 1 B
90
Figure (4.9) : Variation of the surface settlement with time for a =0.5 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 1 B).
64
Chapter Four Presentation and Discussion of Test Results
ـــــ ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 1 B
90
Figure (4.10) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
Without geogrid
70
80 With geogrid, d = 0.5 B, b = 1 B
90
Figure (4.11) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 80%, without and with geogrid (d= 0.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
Without geogrid
70
80 With geogrid, d = 1 B, b = 1 B
90
Figure (4.12) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 80%, without and with geogrid (d= 1 B and b= 1 B).
65
Chapter Four Presentation and Discussion of Test Results
ـــــ ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
Without geogrid
70
80 With geogrid, d = 1.5 B, b = 1 B
90
Figure (4.13) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 80%, without and with geogrid (d= 1.5 B and b= 1 B).
Figures (4.2) to (4.4) in the previous section (4.3.1) and Figures (4.14) to
(4.16) show the variation of vertical pressure on the crown of a tunnel
embedded in loose sand. In general, it can be noticed that when the geogrid
width equals to (1B), the pressure decreases by about (15-46)% compared
with test results without geogrid, but this percentage decreases to (8-33)%
when geogrid width equals to (2B). These results can be discussed as
follows: when the geogrid reinforcement width is 1 B, full interaction will
be mobilized between the geogrid and the soil beneath it, so that the
pressure transferred through the system is small, while geogrid of 2B width
will be subjected to bending and its edges will be raised (this was observed
through the experiments), leading to decrease in the mobilized friction and
interaction with the underlying soil. This behavior was also noticed by
Mehrjardi et al. (2012) who observed that the geocell layer was pulled
down under the plate settlement; however, at a remote distance from the
loading plate periphery, no tension in the geocell was observed.
66
Chapter Four Presentation and Discussion of Test Results
ـــــ ــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figures (4.5) to (4.7) in the previous section (4.3.1) and Figures (4.17) to
(4.19) present the variation of the vertical pressure on the crown of a tunnel
embedded in dense sand. It can be noticed that when the geogrid width
equals to (1B), the pressure decreases by about (13-68)% compared with
the results without geogrid, on the contrary for loose sand, this percent
increases to (25-70)% when the geogrid width equals to (2B).
This is caused by the high density of the sand, full mobilization of
interaction will be developed between the geogrid and the soil which
inhibits bending of the geogrid during loading, so that the geogrid
reinforcement of 2B width will produce a stiff layer which does not allow
propagation of waves and stresses will not be transmitted to the pipe zone.
Tafreshi and Khalaj (2008) found that the value of PDRF (pipe
diameter reduction factor) and SRF (settlement reduction factor) depends
on the width of reinforcement, because adequate width of the reinforcement
should be provided to mobilize the required frictional resistance. Tafreshi
(2008) found that with an increase of the b/D (where b is the width of
reinforcement and D is the diameter of the pipe), the value of PDRF and
SRF decreases, reaching minimum value at b/D approximately 4-5.
120
Without geogrid
100
Pressure, kPa
Figure (4.14) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 2B).
67
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.15) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.16) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.17) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 2B).
68
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.18) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.19) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 2B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement,
0
10
20
30
mm
40
50
60 Without geogrid
70
80 With geogrid, d = 0.5 B, b = 2 B
90
Figure (4.20) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement,
0
10
20
30
mm
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 2 B
90
Figure (4.21) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 2 B
90
Figure (4.22) : Variation of the surface settlement with time for a =0.5 ton,
ω = 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 2 B).
70
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.3.3 Effect of load amplitude
Two different amplitudes of dynamic load (a) were chosen (1 ton and 0.5
ton). Figures (4.2) to (4.4) and Figures (4.14) to (4.16) in the previous
sections in addition to Figures (4.23) to (4.28) show the variation of
vertical pressure on the crown of the tunnel embedded in loose sand with
time. It can be noticed that when the load amplitude decreases from (1) ton
to (0.5) ton, the pressure decreases too by about (57)% .
In dense sand, when the load amplitude is high, dilation may take
place leading to decrease the interaction between the geogrid and the sand,
which results in decreasing the efficiency of the geogrid in spreading the
dynamic waves.
71
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.23) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d =1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.24) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.25) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 1B).
72
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.26) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 2B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.27) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.28) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 2B).
73
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.29) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.30) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.31) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 1B).
74
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 0.5 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.32) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 2B).
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.33) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.34) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 1Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 2B).
75
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2- Effect of load amplitude on the surface settlement
Figures (4.8) to (4.10), Figures (4.20) to (4.22) in the previous sections and
Figures (4.35) to (4.40) present the variation of the surface settlement with
time for model footing on loose sand.. It can be noticed that the vertical
settlement can be reduced by about (25-40)% when using a geogrid under
an applied load amplitude equal to (1 ton). The percent vertical settlement
can be reduced by about (13-35)% when a geogrid layer is used under an
applied load of amplitude equals to (0.5 ton). The results show that the
vertical settlement can be reduced by about (64)% when the load amplitude
decreases from (a = 1 ton to a = 0.5 ton). All of these percentages are
different according to the state of load and geogrid.
These results are compatible with the results of Tafreshi and Khalaj
(2008) who found that the vertical settlement of soil surface can be reduced
up to 65% by using geogrid reinforcement, and increase the safety of
embedded pipes. Also, the efficiency of reinforcement was decreased by
increasing the number of geogrid layers, the relative density of the soil and
the embedded depth of the pipe.
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 1 B
90
Figure (4.35) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
76
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 1 B
90
Figure (4.36) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 1 B
90
Figure (4.37) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 2 B
90
Figure (4.38) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 2 B).
77
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 2 B
90
Figure (4.39) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 2 B
90
Figure (4.40) : Variation of the surface settlement with time for a =1 ton, ω
= 1 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 2 B).
4.3.4 Effect of load frequency
120
Without geogrid
100
With geogrid, d = 0.5 B, b = 1 B
Pressure, kPa
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.41) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 1B).
79
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.42) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.43) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.44) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 2B).
80
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.45) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.46) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 2B).
120
Without geogrid
100 With geogrid, d = 0.5 B, b =1 B
Pressure, kPa
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.47) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 1B).
81
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100 With geogrid, d = 1 B, b = 1 B
Pressure, kPa
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.48) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 1B).
120
100
Pressure, kPa
80
60
40 Without geogrid
20 With geogrid, d = 1.5 B, b = 1 B
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.49) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.50) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 0.5B and b= 2B).
82
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.51) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1B and b= 2B).
120
100
Pressure, kPa
80
60
40 Without geogrid
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.52) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =40%, without and with geogrid
(d= 1.5B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.53) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 1B).
83
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.54) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.55) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.56) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 2B).
84
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.57) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.58) : Variation of the vertical pressure above the tunnel crown
with time for a =0.5 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.59) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 1B).
85
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 1 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.60) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.61) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 1B).
120
Without geogrid
100
Pressure, kPa
Figure (4.62) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 0.5B and b= 2B).
86
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
120
Without geogrid
100
Pressure, kPa
With geogrid, d = 1 B, b = 2 B
80
60
40
20
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.63) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1B and b= 2B).
120
Without geogrid
100
Pressure, kPa
Figure (4.64) : Variation of the vertical pressure above the tunnel crown
with time for a =1 ton, ω = 2Hz and Dr. =80%, without and with geogrid
(d= 1.5B and b= 2B).
87
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
frequency equal to (2 Hz), while the vertical settlement is reduced by about
(27-44)% when the applied frequency equals to (1 Hz).
Time, sec.
0 200 400 600 800 1000 1200 1400
0
Surface settlement, mm
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 1 B
90
Figure (4.65) : Variation of the surface settlement with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
0
Surface settlement, mm
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 1 B
90
Figure (4.66) : Variation of the surface settlement with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 1 B).
88
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 1 B
90
Figure (4.67) : Variation of the surface settlement with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 2 B
90
Figure (4.68) : Variation of the surface settlement with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 2 B
90
Figure (4.69) : Variation of the surface settlement with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 2 B).
89
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 2 B
90
Figure (4.70) : Variation of the surface settlement with time for a =0.5 ton,
= 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 1 B
90
Figure (4.71) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 1 B
90
Figure (4.72) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 1 B).
90
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 1 B
90
Figure (4.73) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 1 B).
Time ,sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 0.5 B, b = 2 B
90
Figure (4.74) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 2 B).
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1 B, b = 2 B
90
Figure (4.75) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 1 B and b= 2 B).
91
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Time, sec.
0 200 400 600 800 1000 1200 1400
Surface settlement, mm
0
10
20
30
40
50
60
70 Without geogrid
80 With geogrid, d = 1.5 B, b = 2 B
90
Figure (4.76) : Variation of the surface settlement with time for a =1 ton, ω
= 2 Hz and Dr. = 40%, without and with geogrid (d= 1.5 B and b= 2 B).
4.3.5 Effect of soil density
1- Effect of relative density on the vertical pressure
Two different soil relative densities were used (40%) and (80%). For
comparison between test results, Figures (4.2) and (4.5) in the previous
sections show the variation of the pressure on the underground tunnel with
time for loose and dense sand, respectively. It can be noticed that when the
relative density increases from (40%) to (80%), the vertical pressure
decreases by about (55)% . This behavior due to the arching phenomena
which occurs as the stress transfer in a tunneling problem from moving
parts of the soil (settle more) to adjacent parts (settle less) that can be
achieved by considering the vertical stress redistribution in the soil mass
above the spring line (Salim, 2006).
Figures (4.8) and (4.11) in the previous section, present the variation of the
surface settlement with time for model footing on loose and dense sand,
respectively. The results show that, the vertical settlement can be reduced
by about (80)% when the relative density of sand increased from (40% to
80%). This is attributed to the loose relative density which is similar to low
stiffness of the backfill and poor soil support during pipe installation while
92
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
the dense relative density corresponds to high stiffness of the backfill and
good soil support, so the high relative densities increase the stiffness of
backfill material and cause reduction in the surface settlement as stated by
Tafreshi and Khalaj (2008).
Table (4.2) Vertical pressure above the tunnel crown for loose sand
A. a = 1 ton, Dr. = 40%.
Average Maximum
Test pressure pressure
(kPa) (kPa)
Without geogrid, ω = 2 Hz. 62.38 79.38
All the tests with amplitude of a = 1 ton in loose sand with geogrid at
(d=1.5 B) showed results similar or near to the results of tests without
geogrid.
93
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
B. a = 0.5 ton, Dr. = 40%.
Average Maximum
Test Pressure pressure
(kPa) (kPa)
Without geogrid, ω = 2 Hz. 28.15 33.42
All the tests with amplitude of a = 0.5 ton in loose sand with geogrid at
(d=1.5 B) showed results similar or near to the results of tests without
geogrid.
Table (4.3) Vertical pressure above the tunnel crown for dense sand
A. a = 1 ton, Dr. = 80%.
Average Maximum
Test pressure pressure
(kPa) (kPa)
Without geogrid, ω = 2 Hz. 26.18 37.22
Tables (4.4) and (4.5) summarize the results of surface settlement above the
tunnel embedded in loose sand under a load amplitude of 1 ton and 2 ton,
respectively
Table (4.4) The maximum settlement measured at the surface of loose sand
layer subjected to dynamic load of amplitude = 1 ton.
Table (4.5) The maximum settlement measured at the surface of loose sand
layer subjected to dynamic load of amplitude = 0.5 ton.
All the tests with amplitude of a = 0.5 ton in loose sand with geogrid at
(d=1.5 B) have a results equal or near to the results of tests without
geogrid.
96
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
2.5
Displacement, mm
2
1.5
1
Without geogrid
0.5 With geogrid, d = 0.5 B, b = 1 B
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.77) : Displacement of the tunnel crown with time for a =0.5 ton,
ω = 1 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
2.5
Displacement, mm
1.5
1
Without geogrid
0
0 200 400 600 800 1000 1200 1400
Time, sec.
Figure (4.78) : Displacement of the tunnel crown with time for a =0.5 ton,
ω = 2 Hz and Dr. = 40%, without and with geogrid (d= 0.5 B and b= 1 B).
97
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
90
80
a= 0.5ton, freq=2 Hz, Dr.=40%
30
20
10
0
0 0.5 1 1.5 2 2.5 3
d/B
98
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
90
70
a= 1 ton, freq= 1Hz, Dr.=40%
50
40
a= 1 ton, freq= 1Hz, Dr.=80%
30
a= 1 ton, freq= 2Hz, Dr.=80%
20
10
0
0 0.5 1 1.5 2 2.5 3
d/B
99
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
70
a= 0.5 ton, freq= 1Hz, Dr.=40%
60
Surface settlement, mm a= 0.5 ton, freq= 2Hz, Dr.=40%
30
20
10
0
0 0.5 1 1.5 2 2.5 3 3.5 4
d/B
Figure (4.81) : Relationship between the surface settlement and (d/B) ratio
for b = 1B.
70
a= 0.5 ton, freq= 1Hz, Dr.=40%
60
a= 0.5 ton, freq= 2Hz, Dr.=40%
Surface settlement, mm
50
a= 1 ton, freq= 2Hz, Dr.=40%
40
a= 1 ton, freq= 2Hz, Dr.=40%
30
20
10
0
0 0.5 1 1.5 2 2.5 3 3.5 4
d/B
Figure (4.82) : Relationship between the surface settlement and (d/B) ratio
for b = 2B.
For dense sand there is no effect of geogrid on the surface settlement.
100
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.4.3 Effect of width of reinforcement on the vertical pressure
Figures (4.83) and (4.84) show the relationship between the vertical
pressure on the tunnel crown and (b/B) ratio. The results show that the
maximum decrement in pressure occurs when the (b/B) ratio is 1 in loose
sand and 2 in dense sand.
90
a= 0.5 ton, freq= 1Hz, Dr.=40%
70
a= 1 ton, freq= 2Hz, Dr.=40%
40
30
20
10
0
0 1 2 3 4
b/B
101
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
90
a= 0.5 ton, freq= 1Hz, Dr.=40%
50
a= 1 ton, freq= 2Hz, Dr.=80%
40
30
20
10
0
0 1 2 3 4
b/B
102
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
70
a= 0.5 ton, freq= 1Hz, Dr.=40%
60
Surface settlement, mm a= 0.5 ton, freq= 2Hz, Dr.=40%
30
20
10
0
0 1 2 3 4
b/B
Figure (4.85) : Relationship between the surface settlement and (b/B) ratio
for d = 0.5B.
70
a= 0.5 ton, freq= 1Hz, Dr.=40%
60
a= 0.5 ton, freq= 2Hz, Dr.=40%
Surface settlement, mm
30
20
10
0
0 1 2 3 4
b/B
Figure (4.86) : Relationship between the surface settlement and (b/B) ratio
for d = 1B.
For dense sand, there is no effect of geogrid on the surface settlement.
103
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
4.5 Comparison of Dynamic Load Pressure Transmitted to
Tunnel with the Ultimate Bearing Capacity of the Surface
Footing.
Tables (4.6) and (4.7) show comparison between the maximum pressure
transmitted to the tunnel (Qd max) and the ultimate bearing capacity of the
surface footing (Qult) for loose and dense sand respectively.
Table (4.6) The ratio between Qd max and Qult for loose sand
A. a = 1 ton, Dr. = 40%.
Test
104
Chapter Four Presentation and Discussion of Test Results
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
B. a = 0.5 ton, Dr. = 40%.
Test
Table (4.7) The ratio between Qd max and Qult for dense sand
A. a = 1 ton, Dr. = 80%.
Test
Test
106
CHAPTER FIVE
CONCLUSIONS AND RECOMENDATIONS
5.1 General
This chapter summarizes the main conclusions drawn through the
analysis of 58 test models performed on reinforced by geogrid and
unreinforced sand, with different relative densities under different dynamic
loads and the recommendations to be made for future work.
5.2 Conclusions
The main conclusions can be listed as follows:
1. When the geogrid is placed at depth equal to (0.5B) from the surface
in loose sand, the pressure on the crown of tunnel will decrease by
about (10-33)%, but when the depth equals to (1B), the pressure will
decrease by about (7-13)%, whereas no decrease in the pressure was
noticed when the geogrid is placed at depth equal to (1.5B) in
comparison between results with geogrid and without geogrid.
While, in dense sand when the geogrid is placed at a depth equals to
(0.5B) from the surface, the pressure decreases by about (13-60)% in
comparison with the results without geogrid, but when the geogrid is
at a depth (1B and 1.5B), there is no decrease in the pressure.
2. The percent vertical settlement in loose sand is reduced by about (20-
44)% when using geogrid reinforcement at a depth equals to (0.5 B).
Also, at depth equal to (1 B), the percent vertical settlement is
reduced by about (13-37)%. In addition, when the geogrid is placed
at a depth equals to (1.5B), the results of vertical settlement without
geogrid are approximately close to results of vertical settlement with
geogrid. This indicates that the efficiency of geogrid decreases when
the depth increases. The geogrid has no efficiency at a depth equal to
(1.5B). On the other hand, there is no efficiency of geogrid on the
surface settlement results in dense sand.
107
Chapter Five Conclusions and Recommendations
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3. When the geogrid width equals to (1B) in loose sand, the pressure on
the crown of tunnel decreases by about (15-46)% compared with test
results without geogrid, but this percentage decreases to (8-33)%
when the geogrid width equals to (2B). On the contrary, in dense
sand, when the geogrid width equals to (1B), the pressure decreases
by about (13-68)% compared with the results without geogrid, but
this percentage increases to (25-70)% when the geogrid width equals
to (2B). The percent vertical settlement in loose sand is reduced by
about (24-44)% when using geogrid reinforcement of width equals to
(2B), while when the width equals to (1B), the results show that the
percent vertical settlement is reduced to about (13-36)%, this
indicates that when the width of geogrid increases, the surface
settlement decreases.
4. When the amplitude of the dynamic load decreases from (1) ton to
(0.5) ton, the pressure above the tunnel crown decreases too by about
(57)%.
5. Comparison between the pressure results without geogrid and
pressure results with geogrid in loose sand, showed that when the
load amplitude equals 1 ton, the pressure on the tunnel crown
decreases by about (11-46)% , but this percentage decreases to about
(7-38)% when the applied load equals to 0.5 ton. On the other hand,
the results in dense sand showed that when the load amplitude equals
to 1 ton, the pressure decreased by about (13-27)% compared with
(68-71)% for 0.5 ton amplitude. These percentages are different
according to the states of load and geogrid width and depth.
6. The percent vertical settlement in loose sand is reduced by about
(64)% when the load amplitude decreased from (1) ton to (0.5) ton.
while, the percent vertical settlement is reduced by about (4)% when
the frequency decreased from (2 Hz to 1 Hz).
108
Chapter Five Conclusions and Recommendations
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
7. The percent vertical settlement in loose sand is reduced by about (25-
40)% when using a geogrid under an applied load amplitude equal to
(1 ton). The percent vertical settlement is reduced by about (13-
35)% when a geogrid layer is used under an applied load of
amplitude equals to (0.5 ton). While, the percent vertical settlement
in loose sand is reduced by about (13-36)% when using a geogrid
under an applied frequency equal to (2 Hz), while the percent
vertical settlement is reduced by about (27-44)% when the applied
frequency equals to (1 Hz). All of these percentages are different
according to the state of load and geogrid.
8. The pressure on the crown of the tunnel in loose sand decreases
when the frequency decreases by about (20% for a =0.5 ton and 45%
for a = 1 ton). While, in dense sand the percentage decreases to (9%
for a = 0.5 ton and 18% for a = 1 ton).
9. When the relative density increases from (40%) to (80%), the
vertical pressure on the tunnel crown decreases by about (55)% .
Also, The percent vertical settlement can be reduced by about (80)%
when the relative density of sand increased from (40% to 80%).
10. The dynamic pressure transmitted to the tunnel is affected
considerably by the frequency and amplitude of load and relative
density of the sand. It is worth mentioning that the models showed a
Qd max/Qult ratio greater than 1 also showed failure of the surface
footing by visual inspection and recorded settlement.
5.3 Recommendations
The following recommendations can be suggested for further research:
1. Studying the effect of geogrid in transfer of dynamic load to
underground structure in saturated sand.
2. Studying the effect of geocell (anothor type of geosynthetics) in
transfer of dynamic load to underground structure.
109
Chapter Five Conclusions and Recommendations
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
3. Using vibration meter more accurate and with larger capacity to
measure the displacement velocity and acceleration.
4. Studying the effect of multi-layer geogrid reinforcement in transfer
of the dynamic load to underground structure.
110
References
111
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
ASTM D422-2001. "Standard Test Method for Particle Size-
Analysis of Soils", American Society of Testing and Material.
ASTM D4253-2000. "Standard Test Method for Maximum Index
Density and Unit Weight of Soils Using a Vibratory Table",
American Society of Testing and Materials.
ASTM D4254-2000. "Standard Test Method for Minimum Index
Density and Unit Weight of Soils and Calculation of Relative
Density", American Society of Testing and Materials.
ASTM D854-2005. "Standard Test Method for Specific Gravity of
Soil Solids by Water Pycnometer", American Society of Testing and
Materials.
Azadi, M. R. E. and Soltani, A. A. (2010), "The Effects of Soil-
Foundation-Structure Interaction on the Dynamic Response of
Delijan Cement-Storage Silo under Earthquake Loading", Electronic
Journal of Geotechnical Engineering (EJGE), 15. pp 659-676.
Banerjee, P. K. and Butterfield, R. (1987), "Dynamic Behavior of
Foundations and Buried Structures", Elsevier Applied Science,
London .
Barkan, D., D. (1962), "Dynamics of Bases and Foundations",
McGraw-Hill New York.
Bhatia, K. (2009), "Foundations for Industrial Machines: Handbook
for Practicing Engineers", CRC. press.
Bildik, S., Laman, M. and Sukaeiman, M. T. (2012), "Prametric
Studies of Buried Pipes Using Finite Element Analysis", 3rd
International Conference on New Development in Soil Mechanics
and Geotechnical Engineering, Turkey, pp. 141-147.
Bowles, J. E. (1996), “Foundation Analysis and Design”, 5 th
Edition, McGraw-Hill Book Companiy, Inc., pp. 1175.
112
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Daghigh, Y. (1993), “Numerical Simulation of Dynamic Behavior
of an Earth Dam during Seismic Loading,” Ph.D. Thesis, Delft
University of Technology, Netherlands.
Das, B. M. (1983), "Fundamentals of Soil Dynamics", Elsevier New
York.
Das, B. M. and Ramana, G. (2011), "Principles of Soil Dynamics",
Cl-Engineering.
Fattah, M. Y., Hamood, M. J., Dawood, S. H., (2008), “The Respone
of Tunnels to Earthquake Excitations”, 7th European Conference on
Structural Dynamics (EURODYN 2008), at the Institute of Sound
and Vibration Research University of Southampton.
Fattah, M. Y., Shlash, K. T., Salim, N. M., (2011), “Effect of
Reduced Ko Zone on Time Dependent Analysis of Tunnels”,
Advances in Civil Engineering, Vol. 2011, Article ID 963502, 12
pages, 2011. doi:10.1155/2011/963502, Hindawi Publishing
Corporation.
Fattah, M. Y., Shlash, K. T., Salim, N. M., (2013), “Prediction of
Settlement Trough Induced by Tunneling in Cohesive Ground”, Acta
Geotechnica, DOI 10.1007/s11440-012-0169-4, Springer, Vol. 8, pp.
167–179.
Gaoxiao, H., Quanmei, G., Shunhua, Z. (2011), "Mechanical
Analysis of Soil Arching under Dynamic Load", Geotechnical
Conference, Canada
Goltabar, A. M. and Shekarchi, M. (2010), "Investigation of Traffic
Load on the Buried Pipeline by Using of Real Scale Experimental
and Plaxis-3D Software", Journal of Applied Science, Engineering
and Technology. Vol. 2, pp. 107-113.
113
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Gupta, S., Stanus, Y., Lombeart, G., Degrande, G. (2009), "Influence
of Tunnel and Soil Parameters on Vibrations from Underground
Railways", Journal of Sound and Vibration, Vol. 327, pp. 70-91.
Handy, R. L. (1985), "The Arching in Soil", Journal of Geotechnical
Engineering Division, ASCE, Vol. 111, No. GT3, p.p 302-318.
Hedge, A., Kadabinakatti, S. and Sitharam, T. G. (2014). "Protection
of Buried Pipelines Using Combination of Geocell and Geogrid
Reinforcement : Experimental Study", Ground Improvement and
Geosynthetics. No. 238, pp. 289-298.
Hosseini, N., Oraee, K. and Gholinejad, M. (2010), "Seismic
Analysis of Horseshoe Tunnels under Dynamic Loads due to
Earthquakes", Underground Coal Operator's Conference, Australia,
pp. 140-145,
Ilamparuthi, K. and Rajkumar, R. (2008), "Experimental Study on
the Behavior of Buried Flexible Plastic Pipe", The Electronic Journal
of Geotechnical Engineering. Vol. (13), Bund. C, pp. 1-10.
Koerner, J., Soong, T.-Y. and Koerner, R. M., 1998, “Earth
Retaining Wall Costs in the USA,” GRI Report #10, Geosynthetic
Institute, Folsom, Pennsylvania, 38 pages.
Lee, C.J., Wu, B.R., Chen, H.T. and Chiang, K.H., (2006), "Tunnel
Stability and Arching Effects During Tunneling in Soft Clayey Soil".
Tunneling and Underground Space Technology, Elsevier, Vol. 21,
p.p.119-132.
Luna, R. and Jadi, H. (2000), "Determination of Dynamic Soil
Properties Using Geophysical Methods," Proceedings of the First
International Conference on the Application of Geophysical and
NDT Methodologies to Transportation Facilities and Infrastructure,
St. Louis, MO, December 2000, pp. 1-15.
114
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Mandal, A. and Baidya, D. K. (2003), "Influence of A Rigid
Boundary on the Dynamic Response of A Foundation: An
Experimental Investigation", Electronic Journal of Geotechnical
Engineering (EJGE), Vol. (8).
Mehrjardi, T. Gh., Tafreshi, M. S. N. and Dawson, A. R. (2012),
"Combined Use of Geocell Reinforcement and Rubber-Soil Mixtures
to Improve Performance of Buried Pipes", Geotextile and
Geomembrance. Vol. 34, pp. 116-130.
MIL-HDBK-1007/3 (1997), “Soil Dynamics and Special Design
Aspects”, Department of Defense, United States of America, pp.
144.
Murthy, V. N. (2007)." Principles and Practices of Soil Mechanics
and Foundation Engineering", Marcel Dekker, inc. 270 Madison
Avenue. New York. New York 10016. PP. 45.
New, B.M. and Bowers, K.H. (1994), "Ground Movement Model
Validation at the Heathrow Express Trial Tunnel", Proceedings
Tunnelling ’94, London, pp. 301-329.
Ozdemir, Z., Coulier, P., Lak, M. A., Francois, S., Lombaert, G.,
Degrande, G. (2012), "Numerical Evaluation of the Dynamic
Response of Pipe Lines to Vibrations Induced by the Operation of a
Pavement Breaker", Soil Dynamic and Earthquake Engineering, Vol.
44, pp. 153-167.
Park, S. H. and Antin, N., (2003), "A Space Time Discontinuous
Galerkin Method for Seismic Soil-Structure Interaction Analysis",
16th ASCE Engineering Mechanics Conference, University of
Washington, July 2003
Potts, D.M. and Zdravkovic, L. (2001). "Finite Element Analysis in
Geotechnical Engineering: Application", Thomas Telford, London.
Prakash, S. (1981), "Soil Dynamics", McGraw-Hill New York.
115
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Rahil, F. H. (2007). "Improvement of Soft Clay underneath a
Railway Track Model Using Stone Column Technique", PhD.
Thesis, Building and Construction Engineering Department,
University of Technology, Iraq.
Rao, N. K. (2011), "Foundation Design: Theory and Practice", John
Wiley and Sons (Asia) Pte Ltd.
Richart, F. E. and Whitman, R. (1967), "Comparison of Footing
Vibration Tests with Theory", Journal of Soil Mechanics and
Foundations Division, ASCE, 93, No. 6, pp. 143-167.
Roesset, J. M. and Jose, M. (2009), "Some Applications of Soil
Dynamics", The Seventeenth Buchanan Lecture, Texas A and M
University.
Salim, N. M. (2006), "Time-Dependent Analysis of Tunnels in Clays
Using the Finite Element Analysis Method", Ph.D. Thesis, Building
and Construction Engineering Department, University of
Technology, Iraq.
Sandstrom, G. E. (1963). "The History of Tunneling", Barrie and
Rockliff.
Sauer, G. (1988), "Further Insights into the NATM - When an
Innovation is Something New: from Practice to Theory in
Tunneling", 23rd Sir Julius Wernher Memorial Lecture. Tunneling
’88, London, IMM.
Srinivasulu, P. and Vaidyanathan, C. (1977), "Handbook of Machine
Foundations", Tata McGraw-Hill.
Tafreshi, M. S. N. and Khalaj, O. (2007), "Laboratory Test of Small
Diameter HDPE Pipes Buried in Reinforced Sand under Repeated-
Load", Geotextiles and Geomembrances, Vol. (26), pp. 145-163.
Tafreshi, M. S. N., Mehrjardi, T. Gh. and Tafreshi, M. S. M. (2007),
"Analysis of Buried Plastic Pipes in Reinforced Sand under
116
References
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Repeated-load Using Neural Network and Regression Model",
International Journal of Civil Engineering. No. 2, Vol. 5, pp. 188-
133.
Terzaghi, K. (1943), “Theoretical Soil Mechanics”, Wiley, New
York.
Williams, O, (1997), "Engineering and Design -Tunnels of Shafts in
Rock", U.S. Army Corps of Engineers, Washington, DC 20314-
1000, p. 236
Xiaoyan, H. U., Jian, Z. H. O. U. and Zhanfei, H. U. (2000),
"Seismic Analysis of Tunnel Surrounded by Soft Soil in Shanghai",
12th World Conference on Earthquake Engineering. Auckland,
Newzwland, pp. 1-7.
Yang, Y., Xie, X. and Wang, R. (2010), "Numerical Simulation of
Dynamic Response of Operating Metro Tunnel Induced by Ground
Explosion", Journal of Rock Mechanics and Geotechnical
Engineering. No. 2, Vol. 4, pp. 373-384.
Young, W. C. (1989), "Roark's Formulas for Stress and Strain", 6th
edition, McGraw-Hill.
117
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Appendix (A)
Additional Results
Figure (A.1) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and b=
2 B).
Figure (A.2) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and b=
1 B).
A-1
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.3) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b= 2
B).
Figure (A.4) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b= 1
B).
Figure (A.5) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and b=
2 B).
A-2
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.6) : Variation of the surface settlement with time for a =1 ton, w
= 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and b=
1 B).
Figure (A.7) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and b=
2 B).
Figure (A.8) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and b=
1 B).
A-3
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.9) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b= 2
B).
Figure (A.10) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b= 1
B).
Figure (A.11) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and b=
2 B).
A-4
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.12) : Variation of the surface settlement with time for a =1 ton, w
= 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and b=
1 B).
Figure (A.13) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and
b= 2 B).
Figure (A.14) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and
b= 2 B).
A-5
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.15) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b=
2 B).
Figure (A.16) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b=
1 B).
Figure (A.17) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and
b= 2 B).
A-6
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.18) : Variation of the surface settlement with time for a =0.5 ton,
w = 2 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and
b= 1 B).
Figure (A.19) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and
b= 2 B).
Figure (A.20) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 0.5 B and
b= 1 B).
A-7
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.21) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b=
2 B).
Figure (A.22) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1 B and b=
1 B).
Figure (A.23) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and
b= 2 B).
A-8
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
Figure (A.24) : Variation of the surface settlement with time for a =0.5 ton,
w = 1 Hz and Dr. = 80%, without geogrid and with geogrid (d= 1.5 B and
b= 1 B).
A-9
Appendix(A)
ـــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــــ
A-25
الخالصة
اٌ انًُشآد رحذ األسظٍخ ًْ جضء ال ٌزجضأ يٍ انجٍُخ انزحزٍخ نهًجزًغ انحذٌشٔ ،رغزخذو
نًجًٕػخ ٔاعؼخ يٍ انزطجٍمبد ،ثًب فً رنك يزشٔ االَفبق ٔانغكك انحذٌذٌخ ٔانطشق انغشٌؼخ
ٔيخبصٌ انًٕادَٔ ،مم انًٍبِ ٔانصشف انصحًٔ .اٌ انًُشآد رحذ األسظٍخ انزً رجُى فً انًُبغك
انخبظؼخ نهُشبغ انذٌُبيٍكً ٌجت اٌ رزحًم كال يٍ انحًهٍٍ انغبكٍ ٔانذٌُبيٍكً يؼب .
ٌزؤصش اعزمشاس انحفشٌبد رحذ األسض ثشكهٓبٔ ،حجى انفزحخٔ ،اإلجٓبد انًٕلؼً اظبفخ انى
ظشٔف انزشثخ ٔغٍشْب .ػهى انشغى يٍ أٌ شكم انفزحخ ٌؼزًذ ثصٕسح اعبعٍخ ػهى انغشض
انًغزخذيخ يٍ اجهّ ،اال اٌ انزصًٍى اَيٍ ٔاَشبء فزحخ رحذ األسض ٌزطهت يؼشفخ رٕصٌغ انعغػ
ٔاالصاحخ انزً رحذس داخم ٔحٕل انفزحبد.
رشكض ْزِ انذساعخ ػهى رؤصٍش انًشجكبد فً َمم انحًم انذٌُبيٍكً نًُشؤ رحذ االسض .حٍش
اٌ ْزا انًُشؤ رى رًضٍهّ ثبَجٕة ثالعزٍكً ثذاخم انزشثخٔ .الجم انزحمك يٍ اعزجبثخ انزشثخ ،االعبط
ٔ انُفك رحذ االسض نهحًم انذٌُبيٍكً رى رصٍُغ ًَٕرط يبدئًٌ .كٍ اعزخذاو ْزا انًُٕرط
نًحبكبح رطجٍك انزحًٍم انذٌُبيٍكً.
اٌ اجًبنً ػذد االخزجبساد انزً اجشٌذ ْٕ ًَٕ 58رطًَٕ .رجٍٍ رى فحصٓى رحذ ربصٍش
انحًم انغبكٍ ثبعزخذاو كضبفزٍٍ َغجٍزٍٍ ( .)%84 ٔ %44جًٍغ ال ًَٕ 56رط انًزجٍمخ رى فحصٓب
رحذ ربصٍش انحًبل انذٌُبيٍكً ٔانزً لذيذ ػهى شكم عهغهزٍٍ ثبعزخذاو كضبفزٍٍ َغجٍٍزٍٍ (ٔ ٪44
ٔ )٪84انزً رًضم انزشثخ انعؼٍفخ ٔ انمٌٕخ ػهى انزٕانً .رى إخعبع جًٍغ ًَبرط انشيم ال56
انجبفخ نهحًم انذٌُبيٍكً انى َٕػٍٍ يٍ عؼخ انحًم انًمبثهخ نـ( 4.5غٍ ٔ 1غٍ) ثبعزخذاو رشددٌٍ
ْ 2 ٔ 1شرض نكم عؼخ حًم .رى اخزجبس ًَٕرط انشيم نكم يٍ انغؼخ ٔرشدد انحًم يغ انًشجكبد
ٔثذَٔٓب ثؼشظٍٍ ( )B2 ٔ B1حٍش ْٕ Bػشض االعبط .ثبالظبفخ انى رنك رى رُفٍز صالصخ
يجًٕػبد يٍ اػًبق انًشجكبد يٍ عطح انًُٕرط (.)B1.5 ٔ B1 ، B4.5
رى رغهٍػ انحًم انذٌُبيٍكً فً االخزجبساد ثٕاعطخ َظبو سفغ ٍْذسٔنٍكًٔ .رزعًٍ اعزجبثخ
انُفك نهحًم انذٌُبيٍكً لٍبط انعغػ فٕق لًخ انُفك ثبعزخذاو خهٍخ انعغػ (انًصُؼخ يٍ لجم
ششكخ ٔ )Geokonكزنك لٍبط عؼخ االصاحخ ثبعزخذاو جٓبص لٍبط االْزضاص ٔ.لذ حممذ اعزجبثخ
األعبط ػٍ غشٌك لٍبط انٓجٕغ انكهً ثبعزخذاو أجٓضح االعزشؼبس فً جٓبص انزحًٍم انذٌُبيٍكً.
رجٍٍ اٌ انعغػ فٕق لًخ انُفك اَخفط ثُحٕ ( )65% -13%ػُذ اعزخذاو انزغهٍح
ثبنًشجكبد ٔرزغٍش ْزِ انُغت ٔفمب نشذح انحًم ٔحبنخ انًشجكبد ٔكضبفخ انزشثخ .أٌعب ،فؤٌ انعغػ
فٕق لًخ انُفك ٌضداد ثضٌبدح عؼخ انحًم ٔانزشدد فً حٍٍ ٌمم انعغػ ػُذ صٌبدح انكضبفخ انُغجٍخ.
رجٍٍ اٌ انٓجٕغ ٌمم ثُغجخ حٕانً ( )45%-13%ػُذ اعزخذاو انزغهٍح ثبنًشجكبد فً انشيم
انعؼٍف ْٔزِ انُغت انًئٌٕخ رخزهف ٔفمب نشذح انحًم انذٌُبيٍكً ٔحبنخ انًشجكبد ،فً حٍٍ اٌ
انشجكبد نٍظ نٓب ربصٍش فً انشيبل انمٌٕخ .أٌعب ،فؤٌ انٓجٕغ اصداد ثضٌبدح عؼخ انحًم ٔانزشدد فً
حٍٍ اَخفط ثبصدٌبد انكضبفخ انُغجٍخ نهشيبل.
جمهورية العراق
الجامعة التكنولوجية
الجامعة التكنولوجية
من قبل
بأشراف