Está en la página 1de 9

Improving Projects Performance

With Lean Construction: State Of


The Art, Applicability And Impacts

Giorgio Locatelli Mauro Mancini Giulia Gastaldo Federica Mazza


School of Engineering - Dpt. Management, Economics FGP - Maserati Sector Consultant at Mind the Value
University of Lincoln, and Industrial Engineering; giulia.gastaldo@fiat.com federica.d.mazza@gmail.com
Brayford Pool, Lincoln; UK Politecnico di Milano; Milan Italy Italy
glocatelli@lincoln.ac.uk mauro.mancini@polimi.it

DOI 10.5592/otmcj.2013.2.2 Construction projects are not often delivered on time and
Research paper on budget and re-workings are usually required to satisfy
customer’s needs. This papers aims to present an overview of
Lean Construction (LC) and how this construction philosophy
tackles the aforementioned problems. The research is empirical
and based on data from the literature, 7 new Case Studies built
with primary data, 12 Case Studies on CLIP (Construction Lean
Improvement Programme) projects, 4 semi-structured Interviews
with Firms adopting LC and several interviews (face to face and
email) with LC experts. The results show as LC can achieve
astonishing results focusing on reducing waste caused by
unpredictable work-flow, paying attention on how every single
activity affects the next one and avoiding reworking considered
as no valued-added activity. The paper provides three original
Keywords set of results: (1) a fuzzy cognitive map of LC showing how the
Lean Construction, different elements are linked to each other; (2) a pathway for the
State of Art, implementation of LC; (3) a synthesis of the strengths and the
Project Delivery Chain, weaknesses of LC merging literature review with case studies
Time and Budget
analysis. In particular (3) shows the dimensions of projects
adequate for lean construction, the increase of productivity
Management,
and time reduction due to LC implementation and finally the
Fuzzy Cognitive Map
reasons moving firms to adopt LC.

g. locatelli · m. mancini · g. gastaldo · f. mazza · improving projects per formance with lean construction: state ... · pp 775 - 783 775
INTRODUCTION to avoid re-working. This reduces the Production system, maximizing value
There is an alarming number of proj- overall risk particularly in case of inter- and minimizing waste (LCI, 2007).
ects failing to be delivered on time or/ related projects, where the delay of LC takes the five principles of Lean
and within budget or/and with a sat- one project impact on another one, e.g. Production (Value, Value Stream, Flow,
isfactory standard that require addi- during a global exposition (Locatelli Pull and Perfection) and applies them
tional work and re-works. (Ashkena and Mancini, 2010) to construction industry to minimize
and Matta, 2003) refer to an astonish- � Supply System waste (Picchi and Granja, 2004). Lean
ing number of projects failing despite LC puts a great effort in involving thinking applied to construction can
the substantial amount of effort in suppliers in project planning and pro- be summarized in: waste elimination;
the installation of new technologies cess with the aim to minimize vari- Improving reliability; Creating continu-
and the adoption of new strategies. ability. As already demonstrated with ous flow in a pull system; Meet the cus-
(Arbulu and Ballard, 2004) identify an system engineering (Locatelli et al. tomer’s need; Involvement of workers
additional significant problem due to 2013) the suppliers’ involvement is at every level; Involvement of supplier
the absence of an effective system in essential to deliver material on time and client in the project process; Built
place to manage the working relation- at a minimum cost and maximum value in quality; Continuous improvement;
ship between construction firm and for the customer. Moreover a lean local Knowledge sharing.
its suppliers. Variability in supply and project delivery chain has clear advan- Table 1 shows the main differences
demand has an adverse effect on proj- tages respect to a more global one between LC and usual construction
ect management increasing cost and (Locatelli and Mancini, 2011). techniques. The main effort of lean
time delivery and decreasing project The aim of this paper is to provide a thinking is in reducing the high variabil-
quality and safety. holistic view on LC (through the defini- ity that affects projects through a more
One of the most interesting meth- tion of a fuzzy cognitive map updated reliable workflow of materials, informa-
odologies proposed to deal with these with recent studies on LC) and answer tion and equipment mainly through the
issues is the Lean Construction (LC). LC to these specific research questions: Last Planner System (Thomas et al.,
aims to identify and minimize wastes 1. Which projects are suitable for LC? 2003). Moreover, LC is not aimed to
(Ballard and Howell, 1994) through four One of the research aims is to define optimize the project activity by activity
main elements: in what kind of projects, in terms of but optimize the overall project consid-
� Built in quality: reduction of rework sector and budget are suitable for LC. ering how every single activity affects
doing the right thing the first time; 2. How can a firm implement LC? the next (Howell, 1999).
� Customer focus: elimination of The research aims to define a stan- The LC includes a set of tools, most
no value-added activities for the dard procedure to implement the of them presented by (Salem et al.,
customer; LC approach and determine how to 2005). The most relevant are (with
� Minimization of waiting: involvement apply lean theoretical principles. related focused reference): Last Planner
of supplier in planning task; 3. Which are strengths and weak- (Neil, 2003), Visualization (Hall, 1986),
� Creation of a continuous flow: avail- nesses of LC and its implementation? (Highways Agency, 2010), Daily Huddle
ability of needed resources and com- The research aims to evaluate the Meeting (Highways Agency, 2010), 5s
ponents, when and where they are strengths and weaknesses of LC. Processes: (Ballard and Howell, 1994),
required, in a pull system. Moreover the research aims to Fail Safe for Quality and Safety “Poka-
By leveraging the LC principles it is define LC impacts and benefits on Yoke” (Bertelsen, 2004), Target Value
possible to deliver better projects. the projects in terms of cost, time Design (Howell et al., 2007). In particu-
This is due to the collaboration of all and quality. lar, “Poka-Yoke (Shingo, 1985) means
parties and the quality control in the ‘mistake-proofing’ or more literally
construction phase through a pull con- The research is based on literature avoiding (yokeru) inadvertent errors
trol system (Juanfang and Xing, 2001). review, case study analysis and inter- (poka). Ideally, poka-yokes ensure that
views with top-experts. proper conditions exist before actu-
This paper shows how LC is able to ally executing a process step, prevent-
cope with the following aspects: Literature review ing defects from occurring in the first
� Cost, Time and Quality LC is a project management philosophy place. Where this is not possible, poka-
LC aims to reduce time and cost based on a set of approaches devel- yokes perform a detective function,
stressing the links between project’s oped in production management and eliminating defects in the process as
activities (Pinch, 2005). Following the adapted for the project management. early as possible. Poka-yoke can be
principle of waste reduction, it aims LC targets the objectives of a Lean used wherever something can go wrong

776 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(2)2013


Traditional Construction Lean Construction

Uses the same activity centered approach used in mass


Defines a clear set of objectives for delivery process
production and project management �
Aims to optimize the project activity by activity and identifies Aims at maximizing performance to the customer at the
customer value in design � project level

Breaks the project into pieces and puts them in a logical


� Designs concurrently product and process
sequence focusing on each activity

Considers control as monitoring each activity against its


� Applies production control throughout the entire project life
schedule and budget projections

Table 1. Difference between traditional construction and L

or an error can be made. It is a tech- � Firms Interviews conducted using a 1986). Figure 1 presents one of the main
nique, a tool that can be applied to any semi-structured questionnaire; results of this research: a fuzzy cog-
type of process in manufacturing, ser- � Several interviews (face to face and nitive map on LC. This output comes
vice or construction industry. It copes email) with a LC experts. from the analysis of integrated data of
with several types of errors, including: literature review, construction firms’
Processing error, Setup error, Missing The case studies are based both interviews and case studies. It is the
part, Improper part/item, Operations on primary and secondary data. The result of a progressive approach ended
error and Measurement error, errors authors built the case studies following with its validation between May and
in machine adjustment, test measure- the guidelines from (Yin, 2009). The November 2011 by lean experts and
ment or dimensions of a part coming number of cases analyzed is consistent 3 authors of references cited in this
in from a supplier. with the concept of “Theoretical satura- paper as Ballard, Howell and Koskela.
tion” presented in (Eisenhardt, 1989). Arrows indicate which elements influ-
Methodology Regarding the interviews, the ence which other while the “plus” and
The methodology employed in this authors discussed the salient aspects “minus” signs show the positive and
research is based on the following of LC with a semi-structured question- negative correlation and its intensity.
steps: naire. The authors interviewed pro- The main elements and relationships
1. Initial literature review to define the fessionals working for construction are discussed right after.
state of the art of LC companies and a consultant expert of
2. First set case studies analysis of proj- implementation of LC in construction Stakeholders involvement: LC is
ects adopting LC principles companies. Furthermore, the authors based on the supplier involvement in
3. Interviews with experts to discuss interviewed 4 firms applying LC in their order to achieve on time delivery of
the findings projects. This highlighted the aspects information and materials to project
4. Second literature review focused on considered most critical by the senior sites. LC leads to customer involve-
the critical aspects emerged from the managers. A final interview to a lean ment in order to develop the project in
previous steps expert mentoring firms in developing a better way i.e. it is possible to under-
5. Second group of case studies LC in their projects, provided a summa- stand the real needs and to reveal the
analysis tive view about how construction firms consequences of the wishes (Ballard
6. Interviews with experts might move in the initial phases and and Zabelle, 2000). The lean idea is (1)
7. Definition of the Fuzzy cognitive maps how they might solve initial problems. to provide to the customers exactly what
(see section 4) By integrating firms and expert inter- they need; (2) to accomplish this goal
8. Final validation with experts. views, it has been possible to picture without waste, focusing on customer
an holistic view of LC. value (Ballard, 2007). A key aspect is
In summary the research is based on to involve the stakeholders to learn
the following data: The LC Fuzzy Cognitive Map lessons useful for future projects and
� 7 Case Studies built with primary A Fuzzy Cognitive Map is a graph that avoid repeating the same mistakes
data; shows the degree of causal relation- twice (Locatelli and Mancini, 2012). An
� 12 Case Studies on CLIP (Construction ship among concepts of the map. It important feature of LC is sharing knowl-
Lean Improvement Programme) can be used to compute the “strength edge. LC promotes information sharing
projects; of impact” of these elements (Kosko, at every level (Sacks et al., 2010).

g. locatelli · m. mancini · g. gastaldo · f. mazza · improving projects per formance with lean construction: state ... · pp 775 - 783 777
Quality

- +
+
Training

-- (Sue Housley, 2011)


Sharing Knowledge

(Juanfang and Xing, 2001) --


(Bertelsen, 2004)
Change Resistance Visualization

(Ballard, 2011)
+
--
(Howell, 1999)

+ -
-
(Afshan Barshan, 2011)

Application of +++ More Effort

--
(Howell & Ballard, 1999)
LEAN CONSTRUCTION in Planning
Waste Philosophy

-- --

(Arbulu and Ballard, 2004)

(Thomas, et al. 2003)


(Arbulu and Ballard, 2004)
++

(Afshan Barshan, 2011)


Cost
+
+
+ --
--
Workers
Involvement
+ + Supplier

+
Variability
Involvement

-- + ++ -- (Arbulu and Ballard, 2004)

Profitability Continuous
Improvement
Construction
Duration
--
+ ++ --
Costumer (Ballard and Zabelle, 2000)
(Koskela, 2011) ++ ++
Costumer Value
Involvement

Figure 1. Fuzzy Cognitive Map of LC.


(Picchi and Granja, 2004)
++
Change Resistance: LC has often to Workers Involvement: Improvements relationships with suppliers intro-
face “change resistance” from most in performance cannot be achieved just duces more reliability in the process
of the stakeholders involved (Howell, through the application of lean prin- also on terms of quality supply (Ruuska
1999). People generally stand out ciples or tools, without a simultane- et al. 2011). The improvements of sup-
against changes of their operational ous strain for a lean culture. Indeed, pliers relationships affect directly
practices and this prevents the applica- it is necessary to involve and moti- on the construction duration. Better
tion of the LC philosophy. vate workers at every level to reach suppliers’relationships decrease the
Training: In order to fight change lean benefits (Höök and Stehn, 2008). lead-time, inventories and the need of
resistance a deep training of the stake- CEDAC is one of the lean tools that quality inspection of material. Thanks
holders involved is necessary. In this strives workers involvement with the to a closer relationships and collabo-
way it is possible to let them under- aim to reach a continuous improvement ration with suppliers, it is possible to
stand the lean principles and increase of the process. It promotes the collec- identify problems, find together solu-
workers motivation. tion of employees’ suggestions for the tions, introduce changes in the project
Visualization: The visualization of the problem setting and problem solving. process and create a system that leads
achieved benefits and the project prog- Supplier Involvement: The inclusion to a continuous improvement.
ress represents a good way to persuade of the suppliers in the planning proc- More Effort in Planning: More effort
workers to embrace lean philosophy and ess fosters the reduction of material in planning, through the Last Planner
overcome resistance. Visualization can lead times and inventories, promotes technique, promotes a smooth work-
be increased, for example, through the the on time delivery of information and flow and decreases the variability in
use of displays placed at construction materials to projects site reducing the the process. A more accurate plan-
site, organizing stand-up meetings and variability linked to the supply system ning allows easier management of the
use of CEDAC (Cause and Effect Diagram (Arbulu and Ballard, 2004). Moreover, project especially during small crises.
with the Addition of Cards). establishing a trust and lasting Moreover a major effort in planning,

778 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(2)2013


focused on coordination and commit- changes in the project processes and Results Answers to Research
ment, allows the reduction of waiting create a system that leads to a continu- Questions
and so the reduction of construction ous improvement. The answers to the research questions
duration. Improving coordination and The application of lean principles or comes from the sources presented in
detailing planning allows the reduc- tools, without a simultaneous strain the methodology section, i.e. literature
tion of waste in terms of waiting for for a lean culture, does not lead to any review, the interviews with the firms
information and materials, space results or benefits (Höök and Stehn, and expert and the analysis of 19 case
used by inventories and unnecessary 2008). In order to reach improvement studies.
transportation. sin performance, LC aims to involve the
Variability: A more reliable process stakeholders through some lean tools, 1. Which projects are suitable to for LC?
in terms of time and quality increases such as Visualization Management Fig. 2 (a) and (b) presents the results
customer satisfaction and therefore and Daily Huddle Meeting (Salem et from the aforementioned 19 case stud-
customer value. al., 2006). LC promotes the supplier ies of LC applications. They analyses
Construction Duration: A reduction involvement in order to achieve on time the dimension of Budget vs. Time
of the construction time decreases, information and materials to project Saving and Budget vs. Productivity
other things being equal, project sites. Moreover LC leads to customer Increases (there are less than 19 points
costs because the necessary human involvement in order to (1) understand because these analyses were not
resources and equipment are used for the real needs, (2) explicit the conse- available for all the case studies). The
less time and because it is less likely quences of the wishes, (3) develop the graphs clearly show as the LC can be
to penalties due to delays in delivery. project in a better way and (4) provide applied to a wide range a projects with
Quality: Improving project quality, exactly what they need. budget spanning from less than 1 mil-
without additional cost, increases cus- lion of $ to multi-billions $. Therefore,
tomer value.
Waste: A reduction of waste leads
decrease the project costs because no
Budget - % Time saving
value added activities are eliminated. 60%
“Reworking” in lean thinking means 50%
waste. The effort spent in eliminat-
40%
ing waste leads also to better qual-
ity. For instance the lean tools, called 30%
poka-yoke devices, alerts for potential 20%
defects avoiding unnecessary rework-
10%
ing (Dos Santos and Powell, 1999).
Cost: It is evident that a reduction 0%
0.001 0.01 0.1 1 10 100
of cost impacts directly on profitabil-
ity. Even considering the initial cost Budget x 100.000.000 $ (log. scale)
of setting up the LC implementation
investment, the overall economic result
is usually positive. Budget - % Productivity Increase
60%
Customers Involvement: Including
customers during project definition 50%
and design phase leads to waste 40%
reduction. It is possible to focus on
30%
the real customers’ needs and to show
immediately the impact of customers’ 20%
wishes. Customers involvement allow 10%
the reduction of reworking and adjust-
0%
ments during the construction. Thanks 0.001 0.01 0.1 1 10 100
to a closer relationship and collabora-
tion with customers in the early stages, Budget x 100.000.000 $ (log. scale)

it is possible to identify some problems


and find together solutions, introduce Figure 2. (a) and (b) show how the LC can be applied to a wide range of projects

g. locatelli · m. mancini · g. gastaldo · f. mazza · improving projects per formance with lean construction: state ... · pp 775 - 783 779
the investment on LC application it is focused on the work-flow and not making little changes on a regular
should always be included in the R&D on time and cost; basis: always improving productiv-
budget of a project. Since one of the � Lean thinking is born as a manufac- ity, safety and effectiveness while
main difficulty in LC implementation turing approach and it might be hard reducing waste. The “Kaizen week”
is the resistance to change, a delay in to prove that it is suitable also in the is a week where the firms, supported
the starting phase of the construction construction industry; by a Kaizen expert, start to intro-
must be considered in order to ade- duce (or strengths) the Kaizen phi-
quately share the LC principles among The case studies and experts’ inter- losophy is its daily work. During this
the stakeholders involved. Regardless views show as the implementation of week changes and improvements
the size the adoption of LC causes a LC often requires an investment of less are made applying lean principles.
time saving of about 20%-30%, and than 100.000€. Considered the typi- This might show and prove the pos-
an increased productivity of the same cal turnaround of construction com- sible and potential benefits of the
order of magnitude. panies is evident as this investment is LC application in a short time;
Figure 3 deeps the analysis show- a tiny portion of the budget available. � Visualization: the project progress
ing the reasons for the adoption of Consequently, the main challenge for and the benefits need to be showed
LC, as reported in the 19 case studies. implementing the LC is not the cost during weekly meetings and on the
Reduction of Waste, development of itself, but the resistance to change from visual displays placed at construc-
better relationships with the customer the workers involved. The measures to tion site.
and more reliability in cost and sched- overcome the resistance are:
ule estimations are the most important � Training: it can include lean semi- An example of possible holistic
benefits. Figure 3 summarises the most nars, guides development, exam- approach is shown in Fig. 5. After the
relevant incentives for adopting LC. ples of real experiences in LC imple- agreement with the top management
“Reduction of waste”, “Better relation- mentation, support of an external about implementing LC the first step
ships” and “Reliability” are the three consultant with experience in the would be to create a multidisciplinary
most important. field of LC. Fig. 4 summarizes time, project team. This would be essential
techniques and tools necessary to since no one have the holistic knowl-
2. How can a firm implement LC? achieve this goal; edge of the workflow required to deliver
The adoption of LC is not always � Kaizen week: the Japanese word an high quality project to the customer.
easy since the main barriers in adopt- Kaizen means “continuous improve- Before starting the project the team
ing the LC are: ment”. Kaizen involves every members need to attend one or more
� It can be undervalued since it might employee. Everyone is encouraged seminars to ensure they were familiar
be seen as a common sense; for this to come up with small improvement with Lean Principles. The seminars are
reason workers’ effort in its applica- suggestions on a regular basis. In also required to overcome any poten-
tion will not be enough; most cases, these are not ideas for tial reticence that team members might
� It seem to be counter-intuitive since major changes. Kaizen is based on have towards the implementation of

10

0
ity ste nt cy rk se e on ty nd
tiv wa me rea im ip
cti ali ity ty tio
n
uc ien wo dt sh Qu bil afe na uc
Pro
d
t i o n
su re
E ffi c
y to
t i n c
bu il
a t ion t isfa e lia n ds a tio re d
du
c
me
a wa Pro
fi
no
f
r re
l sa R ha ian s
Re of er tio tte
er alt ord lay
m B ett u c B e s tom He Co De
ste Re
d Cu
Sy

Figure 3 Incentives for adopting LC

780 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(2)2013


Phase Pathway Parties Involved would include the analysis of the effec-
Persuasion of Top Mamagement tiveness of methodologies employed,
Top Management
the efficiency of processes and the
Interdisciplinary Project Team quantities of waste generated. Analysis
Definition
Project Team Members and evaluation would need to inform
Preparation Training/Seminars subsequent work on an on-going basis
Project Team Members to ensure the optimisation of work-
Collaboration with and Workers flows and procedures. This would be
a Lean Consultant
achieved by designing, and then con-
Aims Definition Project Team Members tinually refining a current state process
map. The project team would need to
Work Observation and meet weekly to ensure the implementa-
Workers
Data Collection
tion was effective as possible.
Brainstorming to Define Visual displays need to be placed
Improvement Activities at construction site to allow workers
Implementation
Project Team Members to see how the project is progressing
Weekly Meeting /
and Workers throughout the various stages.
Visual Display
to take Process under Control Research has indicated that the
and show the Benefits majority of firms have firstly chosen
Top Management Project to implement LC in a single pilot proj-
Continuous Results Analysis and Knowledge
Improvement Consolidation
Team Members and ect. Seen the benefits on to the pilot
Workers project they often decide to expand the
approach to the other projects in the
Figure 4. Time, techniques and tools used to persuade portfolio. Another approach has been
and train the three hierarchical levels to firstly use a pilot business unit, and
then apply LC to the other units.
Lean Strategies. Each project requires the consultant, all project aims and
at least an external consultant i.e. an time scales would have been agreed. 3. Which are strength and weaknesses
expert in the field of LC with prior expe- Because of the essential require- of LC and its implementation?
rience of the implementation of LC in ment of colleting several types of data LC strengths and weaknesses are
real-life projects. The role of this con- throughout the life of the project, it summarizes in Table 2.
sultant would be to give guidance to would also be necessary for the consul-
the team during the planning phase tant to promote the need for on-going Conclusions:
and continued help and support during analysis and evaluation and provide how LC can improve project
the implementation phase. During the training in the techniques required. management.
initial meeting between the team and On-going monitoring and evaluation The most common benefits of LC are
a shorter delivery time and a higher
project performance, because:
CEO Workers
1 day: Presentation of the Months: training on the � The Productivity of the workforce
potential results obtained job and presentation of increases (e.g. thanks to Poka-Yoke
thanks to the Lean the results during the devices);
Construction implementation project progress
� There is a better coordination and
communication with suppliers;
� There is a minimization of re-work-
ing following the lean principles
“Do the right thing at the beginning”;
Project Team Members
2 days: Seminars and Lean � There is a minimization of no value-
Construction and presentation of added activities focusing on the real
potential results by construction customer’s needs.
firms with experience in the field of
Lean Construction
To exploit the benefits reached with LC
implementation, it is possible to follow
Figure. 5 Proposed pathway for the implementation of LC a process based on five steps:

g. locatelli · m. mancini · g. gastaldo · f. mazza · improving projects per formance with lean construction: state ... · pp 775 - 783 781
REFERENCES

(Ballard, 2007), (CLIP, 2003), (Dos Santos and Powell, 1999),


Minimization of reworking
(Pinch, 2005),(Salem et al. 2006).

(Arbulu and Ballard, 2004),(Ballard, 2003),(Ballard et al., 1996),


Increased project reliability (Howell G. A., 1999),(Lantelme and Formoso, 1999),(Salem et al., 2005),
(Thomas et al., 2003).

(Arbulu and Ballard), (Ballard, 2003), (Brady et al., 2006), (CLIP, 2003),(Conte,
STRENGTHS

2002),(Dos Santos and Powell, 1999), (Juanfang and Xing, 2011), (Pasternack,
Projects are completed within budget
2008), (Picchi and Granja, 2004), (Pinch, 2005), (Salem and Zimmer, 2005),
(Thomas et al., 2003)

Increased workers motivation and


(CLIP, 2003)
satisfaction

Good organized way of work (CLIP, 2003)

Positive feedback on the basis of trials (CLIP, 2003)

Fewer instances of conflict between all


(CLIP, 2003), (Pasternack, 2008)
parties involved
Promotion of greater degree of creative
(CLIP, 2003)
thinking and innovation

Challenge to widespread the culture (CLIP, 2003), (Howell G. A., 1999)


WEAKNESSES

Need to overcome initial resistance (CLIP, 2003), (Howell G. A., 1999)

Associated training costs (CLIP, 2003)

Table 2. Strengths and weakness of LC application

1. Definition of indicators that are rel- Mape. The merging of formal academic References
evant for workers and establishing results, real case studies (with primary Arbulu, R. Ballard, G. (2004), “Lean supply
the values of the existing operational and secondary data) and interviews system in construction”, Paper presented
standards. The indicators need to be to international experts brings to the at the 12th annual conference of the
as simple as possible so that every- conclusion that the most important International Group of Lean Construction.

one at construction site can under- investment for a LC strategy imple- Helsinga, Denmark.

stand them. mentation is in the team members’ Ashkena, R. N., Matta, N. F. (2003), “Why good
2. Planning the benefits: all potential training (possibly with the support of projects fail anyway”. Harvard Business

benefits should be considered and external consultants with experience in Review, Vol. 81 No.9, pp. 111-114.

estimated in a realistic way; LC field). Investing in LC might be very Ballard, G. (1999), “Improving workflow
3. Measuring the benefits: during the profitable because with small invest- reliability”, Paper presented at the 7th annual

project the benefits forecast should ments it is possible to strongly increase conference of the international group for lean

be reviewed and updated and evi- the probability to deliver projects on construction. IGLC-7, Berkeley, CA, July.

dence to support benefits should be time avoiding penalties and minimiz- Ballard, G. (2003), “Innovations in lean

captured; ing costs linked to waste. Investment design”. Lean Construction Institute. www.
leanconstruction.org.
4. Realising the benefits: the actual ben- required to introduce LC is generally
efits achieved should be recorded; under €100.000 and the return of the Ballard, G. (2007), “Target value design”.

5. Analysing and reporting the benefits: investment is generally much higher. Lean Construction Institute. www.
leanconstruction.org.
a short and simple benefits report
should be released monthly. Ballard, G., Casten, M., Howell, G. (1996), “Parc:

The main result of the paper is the a case study”, Paper presented at the 4th
annual conference of the international group
formal clustering of LC benefits through
for lean construction. Birmingham, UK.
the definition of a LC Fuzzy Cognitive

782 o rga n i za t i o n , te ch n ol o g y a n d ma na ge m e n t i n co nst r u c t i o n · an international journal · 6(2)2013


Ballard, G., Howell, G. (September 1994), Juanfang, L., Xing, L. (2001), “Application of Pinch, L. (2005), “Lean construction:
“Implementing lean construction: lean construction in quality management eliminating the waste”, Construction
stabilizing work flow”, Paper presented of engineering projects”. IEEE. 2001 Executive, Vol. 11, pp. 34-37.
at the 2nd annual conference on lean International Conference on E -Business Ruuska, I., Ahola, T., Artto, K., Locatelli, G.,
construction, Santiago, Chile. and E -Government (ICEE), Washington, Mancini, M. (2011), “A new governance
Ballard, G., Zabelle, T. (2000), “Readings in lean D.C., USA, April 17-20, 2001. approach for multi-firm projects: Lessons
construction”, www.leanconstruction.org. Kosko, B. (1986), “Fuzzy Cognitive Maps”, from Olkiluoto 3 and Flamanville 3 nuclear

Bertelsen, S. (2004), “Lean Construction: International Journal of Man-Machine power plant projects”, International Journal

where are we and how to proceed?”, Lean Studies, Vol. 24 No.1, pp. 65-75. of Project Management, Vol. 29 No. 6, pp.

Construction Journal, Vol. 1 No. 1, pp. 46-69. Lantelme, E., Formoso, C. T. (1999), 647-660.

Brady, R., Davies, A., Rush, H. (2006), “Improving performance through Sacks, R., Koskela, L., Dave, B.A. , Owen, R.

“Learning to manage mega projects: the measurement: the application of lean (2010) “Interaction of lean and building

case of BAA and Heathrow Terminal 5”, production and organizational learning information modeling in construction”,

Paper presented at the IRNOP VII Project principles”, Paper presented at the 8th Journal of Construction Engineering and

research conference. Xi’an, China, October conference of international group for lean Management, Volume 136, No. 9, pp 968-980.

11-13, 2006. construction, August 17-19, Brighton, UK. Salem, O., Genaidy, A., Solomon, J., Minkarah,

CLIP (2003), “Construction Lean Improvement LCI. (2007), “What is lean construction”, I. (2006), “Lean construction: from theory

Program: case studies” available athttp:// Lean construction institute available at to implementation”, Journal of management

www.constructingexcellence.org.uk/ http://www.leanconstruction.org in engineering, Vol. 22 No. 4, pp.168–175.

resources/themes/clip/clip.jsp (accessed Locatelli, G., Mancini, M. (2010), “Risk Salem, O., Solomon, J., Genaidy, A., Luegring,
24 jan 2012) management in a mega-project: the M. (2005), “Site implementation and

Conte, A. S. (2002), “Lean construction: from Universal EXPO 2015 case”, International assessment of lean construction

theory to practice”, 10th Conference of the Journal of Project Organisation and techniques”, Lean Construction Journal,

International Group for Lean Construction. Management, Vol. 2 No. 3, pp. 236-253. Vol.2 No.2, pp. 1-21.

Gramado, Brazil, August 6–8, 2002. Locatelli, G., Mancini, M. (2011), “The role Salem, O., Zimmer, E. (2005), “Application

Dos Santos, A., Powell, J. (1999), “Potential of of the reactor size for an investment in of lean manufacturing principles to

poka-yoke deviced to reduce variability in the nuclear sector: An evaluation of not- construction”, Lean Construction Journal,

construction”, Paper presented at the 7th financial parameters”, Progress in Nuclear Vol.2 No.2, 51-54.

conference of the international group for Energy, Vol. 53 No. 2, pp. 212-222. Shingo, S. (1985), Zero quality control: Source
lean construction, Berkeley, California, Locatelli, G., Mancini, M. (2012), “Looking inspection and the poka-yoke system,
USA, 26-28 July 1999. back to see the future: building nuclear Productivity Productivity Press,

Eisenhardt, K. M., (1989), “Building theories power plants in Europe”, Construction Cambridge, UK.

from case study research.” Academy of Management and Economics, Vol. 30 No. 8, Thomas, H. R., Horman, M. J., Minchin, E.
management review, Vol. 14, No. 4, pp. pp. 623-637. J., Chen, D. (2003), “Improving labor
532-550. Locatelli, G., Mancini, M., Romano, E. flow reliability for better productivity as

Hall, R. (1986), “Continuous improvement (2013), “Systems Engineering to improve lean construction principle”, Journal of

through standardization”, Target, Summer the governance in complex project construction engineering and management,

1986, pp. 3-6. environments”, International Journal of Vol. 129 No. 3, pp. 251–261.
Project Management – IN PRESS, DOI: Yin, R. K., (2009), Case study research: Design
Highways Agency, (2010), “Lean improvement
10.1016/j.ijproman.2013.10.007. and methods, Sage, New York.
division. An introduction to lean visual
management”, www.highways.gov.uk Neil, G. (2003), “What is the last planner
System?”, available at http://www.
Höök, M., Stehn, L. (2008), “Lean principles
gregoryneilassociates.com (accessed 2 nov
in industrialized housing production:
2011)
the need for a cultural change”, Lean
Construction Journal, Vol. 2, pp. 20-33. Pasternack, R. (2008), “Building information
modeling and lean construction”, available
Howell, G. A. (1999), “What is lean
at http://www.rebeccapasternack.com/files/
construction” Paper presented at the 7th
pdf/IIEpaper.pdf (accessed 10 october 2011)
annual conference of the international
group for lean construction, Berkeley, Picchi, F. A., Granja, A. D. (2004), “Construction

California, USA, 26-28 July 1999. sites: using lean principles to seek broader
implementations”, Paper presented at 11th
Howell, G., Macomber, H., Barberio, J. (2007),
annual conference of the international group
“Target value design”, The American Instute
for lean construction, Blacksburg, Virginia.
of Architects available at http://info.aia.org/.

g. locatelli · m. mancini · g. gastaldo · f. mazza · improving projects per formance with lean construction: state ... · pp 775 - 783 783

También podría gustarte