Presupuesto
Presupuesto 0302001CENTRODE SALUD SANTA ROSA
Subpresupuesto DE CERCOPERIMETRICO
001 REHABILITACION
Cliente GERENCIAREGIONALDE SALUDLAMBAYEQUE Costo al 211't112012
Lugar LAMBAYEQUE.CHICLAYO.SANTAROSA

Descripción Und. Metrado Precio S/. Parcial S/'

01 OBRAS PRELIMINARES 5,747.63

01.0'r D E M U R O SD E L A D R I L L OK K
DEMOLICION m3 24.81 99.68 2,473.06

01.02 S E C O N C R E T O- C I M I E N T O S
D E E S T R U C T U R AD
DEMOLICION Y mó 18.52 132.50 2,453.90
SOBRECIMIENTOS
01.03 L I M P I E Z AD E T E R R E N OM A N U A L m2 58.80 2.86 168.17

01.04 TRMO DE NIVELESY REPLANTEO m2 26.46 24.66 oJz.ou

02 MOVIMIENTODE TIERRAS 4,148.06

02.01 I N T E R I O RA P I S O N A D OM A N U A L
NIVELACION m¿ 30.42 2.17 66.01

02.02 E N T E R R E N ON O R M A L
R E F I N EY N I V E L A C I O N m2 70.56 4.87 343.63

02.03 ACARREODE MATERIALEXCEDENTE m3 50.96 18.68 951.93

02.04 ( C A R G U I OA M A N O )R = 2 5m 3 / d í a m 3
N O NT R A N S P O R T E
ELIMINACIOC 50.96 34.Oó 2,786.49

03 C O N C R E T OS I M P L E 7,575.30

03.01 C O R R I D O SM E Z C L A1 : 1 0C E M E N T O - H O R M I G O3N
CIMIENTOS 0% m3 13.04 189.07 2,465.47
PIEDRA
03.02 Y D E S E N C O F R A DD
ENCOFRADO OE C I M E N T A C I O N m2 70.56 41.62 2,536.71

03.03 c o N C R E T O 1 i 8 + 2 5 %P M P A R AS O B R E C I M I E N T O S m3 2.65 231.23 612.76

03.04 ENCOFRADOY DESENCOFRADONORMALPARA m2 JC.¿O 41.02 1, 4 4 7 . 1 9


OA S T A0 . 3 0m
S O B R E C I M I E N TH
03.05 SOLADOSCONCRETOfc=1 00 ko/cm2h=2" rn2 7.56 14.97 113.17

04 CONCRETOARMADO 12,950.13

04.01 ZAPATAS
04.02 CONCRETOPARA ZAPATASfc=175 kg/cm2 m3 3.78 281.41 1,063.73

04.03 ACERO fy={!ag k9/cm2GRADO60 en ZAPATAS kg 128.50 6.29 808.27

04.04 COLUMNAS
04.05 CONCRETOEN COLUMNASfc=175 kglcm2 m3 4.59 388.92 1,785.14

04.06 ENCOFRADOY DESENCOFRADONORMALEN COLUMNAS m2 51.45 38.94 2,003.40

04.07 ACEROfy={lag kg/cm2GRADO60 en COLUMNAS kg 675.40 o.¿Y 4,248.27

04.08 VIGAS Y DINTELES


04.09 CONCRETOEN VIGASY DINTELESfc=175 kg/cm2 m3 1.76 294.95 5 1 9 .1

04.10 ENCOFRADOY DESENCOFRADONORMALEN VIGAS m2 ¿ó.c¿ 49.87 1,172.94

04.11 ACEROfy=4200kg/cm2GRADO60 en VIGAS Kg 214.50 6.29 1,349.21

05 M U R O SY T A B I Q U E SD E A L B A Ñ I L E R I A 6,090.44

05.01 MURO DE SOGA CARAVISTA LADRILLOKING-KONGCOI'r m2 149.90 40.63 6,090.44


CEMENTO-ARENA
06 REVOOUESENLUCIDOSY MOLDURAS 2,186.87

06.01 TARRAJEODE VIGASY COLUMNASINCLUYEARISTAS rn2 74.97 29.17 2,186.87


't,274.78
07 CONTRAZOCALOS
'
07.01 CONTRAZOCALOCEMENTOSCIN COLOREARH = 60 cm 117.60 10.84 1,274.78

08 PINTURA 3,529.97

08.01 2 MANOS
P I N T U R AV I N I L I C AE N M U R O SE X T E R I O R E S m2 299.90 8.86 2 , 6 5 7. 1 1

08.02 P I N T U R AE N V I G A SY C O L U M N A SV I N I L I C A2 M A N O S m2 74.97 6.78 508.30

08.03 PINTURADE CONTRAZOCALOCON ESMALTEECONOMICO m 11 7 . 6 0 3.10 364.56

09 INSTALACIONESELECTRICAS 23,229.37

09.0'1 S A L I D AD E P A R E DC O N C A B L EA W G T W 4 . 0 M M ( 1 2 )+ D P V CS E L pto 12.00 10 6 . ' 6


1 1.273.92
19 mm (3/4)
09.02 DE 2 X 30 A
LLAVETERMOMAGNETICA u 4.00 32.99 1 3 1. 9 6

09.03 TUBERIAEMPOTRADAPARA SALIDASDE PARED m 59.00 73.01 4,307.59

09.04 TUBERIAVISIBLEPARA SALIDASDE PARED m 114.00 73.01 8,323.14

0s.05 CABLE ELECTRICOTW AWG-MCM# 14 -2.5 mm2 m 356.00 3.77 1,342.12

09.06 PASTORALMETALICOY LAMPARAHG 150 W VAPOR SODIO, 12.00 654.22 7,850.64


ADOSADOA PARED
COSTO DIRECTO 66,732.55

GASTOSGENERALES1O% 6,673.26

UTILIDAD1O%. LAMEAWC¡UE 6,673.26


og sALuo
ESTü¡AÍÉOIO()
tN\,teR8{¡tte
SUBTOTAL 80,079.07

I M P U E S T 9r G V 1 8 % 14,414.23

TOTAL PRESUPUESTO 94,493.30