INDEX
1 INTRODUCTION ................................................................................................................... 4
2 DOCUMENT SCOPE ............................................................................................................ 5
3 ACRONYMS, DEFINITIONS AND ABBREVATIONS ........................................................... 6
4 REFERENCE DOCUMENTS ................................................................................................ 7
5 ENVIRONMENTAL CONDITION .......................................................................................... 8
6 Utilities ................................................................................................................................... 9
6.1 Electric Power ........................................................................................................................ 9
6.2 Utility Air................................................................................................................................. 9
6.3 Instrument Air ........................................................................................................................ 9
6.4 Nitrogen ............................................................................................................................... 10
6.5 Blanketing Gas .................................................................................................................... 10
7 PROCESS DESCRIPTION ................................................................................................. 11
7.1 Compressed Air Package: 002511104600XX001 ............................................................... 11
7.1.1 Air Compressors 002511104600KC001A/B ........................................................................ 11
7.1.2 Emergency Air Compressors 002511104600KC002A/B ..................................................... 11
7.1.3 Air Compressors Control Panel ........................................................................................... 12
8 SCOPE OF SUPPLY ........................................................................................................... 13
8.1 Detailed Scope of Supply .................................................................................................... 13
8.2 Supplier Documentation ...................................................................................................... 14
8.3 Process Guarantee.............................................................................................................. 15
1 INTRODUCTION
ENI has been awarded the Zubair project for the development of an oil field (ZUBAIR
FIELD) in joint venture with Occidental, Korea Gas and Missan Oil COMPANY (as state
partner), with Eni as operator.
The Zubair Field is located in the southern area of Iraq, 20 km from Basra city. The
structure of the Zubair Field is a relatively gentle anticline oriented NNW - SSE,
approximately 60 km long and 10-15 km wide.
The Zubair project is a “brown field project” in which two main phases can be defined:
o Rehabilitation phase (or RP) in which includes the revamping of existing facilities to
maximise production capacity of the existing treatment plants in order to achieve an oil
production rate of 700 KBOPD at Q3 2013, after rehabilitation of wells, gathering
network and overall facilities, plus installation of new facilities as required. These
activities should be concluded within 36 month starting from the Contractual Effective
Date (CED).
o Enhanced Re-Development (or EP). During this phase the installation of new
permanent production facilities to achieve the plateau rate of 1200 KBOPD of oil
production has been foreseen. The oil will be produced from reservoir with natural
flowing and artificial lift systems requiring also water injection to support reservoir
pressure and maintain it above saturation pressure. This second phase should be
finished within 6 years from the CED.
2 DOCUMENT SCOPE
Scope of present document is to provide process technical requirements for the supply of 1
package for Compressed air system to the Hammar Degassing Station in accordance with
the documents and the process data of Zubair Oil Field Development Project.
4 REFERENCE DOCUMENTS
Reference Title
Hammar DGS – New Facilities – Compressed Air System Utility
1 002511-00-FP-FQ-03134
Flow Diagram
Hammar DGS – New Facilities – Air compressors and Plant Air
2 002511-10-BP-FM-86646
Receiver P&ID
Hammar DGS – New Facilities – Dryers and Instrument Air –
3 002511-10-BP-FM-86647
P&ID
4 002506-00-BG-SG-09005 Site & Climatic Conditions
5 ENVIRONMENTAL CONDITION
All the equipments supplied must be suitable for outside installation, because the location is
an arid zone subject to sandstorms. Their operation shall be guaranteed at the
environmental conditions of doc. Site & Climatic Conditions, Ref. [4].
6 UTILITIES
OPERATING DESIGN
OPERATING DESIGN
6.4 Nitrogen
OPERATING DESIGN
Temperature (°C) 5 60 90
OPERATING DESIGN
Mol
Component(1) mol%
Weight
Water 18.015 0.79
Nitrogen 28.013 0.92
Carbon Dioxide 44.010 1.38
Methane 16.043 68.33
Ethane 28.013 14.63
Propane 44.097 7.42
I-Butane 58.123 3.62
n-Butane 58.123 1.01
I-Pentane 72.150 0.82
n-Pentane 72.150 0.52
n-Exane 86.300 0.37
C7 100.00 0.11
C8 114.00 0.05
C9 128.00 0.02
C 10 plus 165.70 0.01
1
Blanketing Gas Composition is preliminary.
This document is property of Eni S.p.A. Exploration & Production Division.
It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.
Logo and business name of Company Document Owner Document Revision Index Sheet of
Document owner Identification Identification Sheets
Validity
Rev.
00251100BPST86205 2511-ZA-E-86205 Status
11 / 15
CD-FE 01
e & p division
7 PROCESS DESCRIPTION
Wet atmospheric air is compressed by 100% oil free rotating air compressors driven by
electric motor and working in parallel.
Each compressor is equipped with a dust air filter to remove the coarse atmospheric
particles. The compressed air is sent to the Plant Air Receiver in order to remove liquid
droplets as well as to act as hold up buffer for the entire air system.
Compressed Air system will follow a phasing approach to take into account the phasing of
new oil processing trains.
o RP phase: two (2) Air Compressors 002511104600KC001A/B (each one rated for
2300 Nm3/h), fed by Medium Voltage main power circuit, plus two (2) Emergency Air
Compressors 002511104600KC002A/B (each one rated for 1150 Nm3/h), fed by Low
Voltage emergency power circuit.
o EP phase: one (1) Air Compressor 002511104600KC001C rated for 2300 Nm3/h), fed
by Medium Voltage main power circuit. This compressor is outside of Package Scope
of Supply.
Refer to ref. [1], “Hammar Degassing Station: “New Facilities - Compressed Air System
Utility Flow Diagram” and Refer to ref. [5] , “Best Practice – Compressed Air System”.
8 SCOPE OF SUPPLY
1. Specifications
2. Data sheets
3. Procedures
4. Equipment list
5. Electrical equipment list
6. Instrument list
7. Line list
8. Electrical load list
9. Cause & Effect Diagrams
10. Lubricant and utility consumption list
11. Safety valves calibration certificates
12. Pre-commissioning/commissioning spare parts
13. SPIR forms
14. Calculations
15. Miscellaneous
DESIGN DRAWING
1. Assembly/overall layouts
2. PFDs/P&IDs
3. Heat & Material balance
4. Piping, valves and fittings
5. Mechanical
6. Electrical
7. Instrumentation
8. Controls and automation
9. Installation/dismantling drawings
10. Brochures
11. Miscellaneous