Documentos de Académico
Documentos de Profesional
Documentos de Cultura
ANNEXURE-IV
ABSTRACT OF PROJECT COST
Sl. No. Particular Amount in Million Nu
I Works
A Preliminary 9.74
B Land 1.65
C Civil Works & HM Works 271.80
i Integration tank 1.04
ii Headrace system 144.41
iii Forebay tank 29.18
iv Penstock system 10.62
v Powerhouse complex 56.80
vi Tail race system 20.12
vi H&M cost 9.63
K Building 14.08
O Miscellaneous 16.00
P Maintenance 1% of Civil works and Building 2.86
Q Special T & P 4.50
R Communication 52.87
X Environment, Ecology & Plantation 8.47
Y Losses on Stock 0.25% of Civil works and Building 0.71
I Sub Total (I-Works) 382.68
II Establishment 8% of I-Works less B-land 30.48
III T&P 1% of I-Works 3.83
IV Receipt and Recoveries 15% of Building & 25% of Special T&P (3.24)
V Indirect charges_Audits and Accounts 0.5% of I-Works 1.91
TOTAL I TO IV 415.67
S Electro-Mechanical 158.90
Grand Total hard cost 574.57
PRELIMINARY COST
Sl. No. Description
1 Topographical survey of the project area
2 Geological & Geotechnical Investigations
3 General Expenses
4 Design and Engineering @3% of civil works
Total amount
ANNEXURE-IV
Amount in Million Nu
0.55
1.13
0.20
7.87
9.74
ANNEXURE-IV
LAND COST
Sl. Rate Amount in Million
Category Unit Total Land-type
No. (Nu.) Nu
Cash Compensation for 1 affected
1 acre 0.057 Kamzhing 2,860.52 0.02
HH
Land Development for 2 HHs (after
2 acre 0.394 Kamzhing 191,800.00 0.08
land to land replacement)
3 Cost involved in greivance redress Lump sum 0.10
4 Cost of RP implementation Lump sum 0.10
5 External evaluator studies Lump sum 0.30
Sub-total 0.59
6 Contingency 10% on sub-total 0.06
Total RP Costs 0.65
7 Community Support Lump sum 1.00
Grand total 1.65
ANNEXURE-IV
COST FOR CIVIL WORKS
Sl. No. Description Amount in Million Nu
1 Integration tank 1.04
2 Headrace pipe system 144.41
3 Forebay tank 29.18
4 Penstock system 10.62
5 Powerhouse complex 56.80
6 Tail race system 20.12
Total amount 262.17
ANNEXURE-IV
ABSTRACT FOR INTEGRATION TANK
3 Concrete
3.1 M15 cum 49.71 5,020.08 0.06
3.2 M25 cum 60.56 6,677.84 0.08
ANNEXURE-IV
ABSTRACT OF COST FOR HEAD RACE PIPE
Unit Rate in Amount in
Sl.No. Item Unit Quantity
Nu Million Nu
Clearing jungle including uprooting of vegetation &
1 trees of girth < 300mm & disposal within 50m of the sqm 13,520.00 9.56 0.13
site
3 Excavation
3.1 In soil cum 22,805.07 184.08 4.20
3.2 In rock cum 9,773.60 418.08 4.09
3.3 Backfilling with selected excavated earth cum 1,165.50 117.52 0.14
4 Concrete
4.1 M25 concrete including shuttering ,etc all complete cum 1,903.77 6,677.84 12.71
5 Steel reinforcement
Providing & fixing reinforcement bar for R.C.C work
5.1 including cutting, bending, binding and placing in mt 157.06 57,508.88 9.03
position complete
7 Protection works
7.1 Gabion/Crate wall cum 243.00 12,001.85 2.92
7.2 RRM Wall in CM 1:6 cum 114.40 3,784.16 0.43
ANNEXURE-IV
ABSTRACT FOR FORBAY
2 Excavation
2.1 In soil cum 3,799.97 184.08 0.70
2.2 In Rock cum 5,699.96 418.08 2.38
3 Concrete
M15 cum 69.59 5,020.08 0.35
M25 cum 1,799.64 6,677.84 12.02
8 Slope stablization
8.1 Shotcrete_50 mm thick sqm 392.40 635.44 0.25
8.2 Shotcrete_50 mm thick with 50mm wire mesh sqm 302.20 1,294.47 0.39
ANNEXURE-IV
ABSTRACT FOR PENSTOCK
Unit Rate in Amount in Million
Sl.No. Item Unit Quantity
Nu Nu
Clearing jungle including uprooting of
1 vegetation & trees of girth < 300mm & sqm 1,700.00 9.56 0.02
disposal within 50m of the site
3 Concrete
3.1 M15 cum 16.35 5,020.08 0.08
3.2 M25 cum 293.30 6,677.84 1.96
ANNEXURE-IV
SEMI-SURFACE POWER HOUSE
Amount in
SI. No. Description of Items Unit Quantity Rate (In Nu.)
Million Nu
1.0 Surface Excavation and Backfill
Surface excavation in all types of
soil /overburden and rock including
disposal at disposal sites and complete
in all respect.
Excavation in soil / overburden without
1.1 cum 45,478.55 184.08 8.37
blasting
1.2 Compacted Earth Backfilling cum 4,130.71 117.52 0.49
2.0 Concrete
Providing and laying reinforced cement
concrete accessories, shuttering,
scaffolding, curing labour, etc complete in
all respect.
2.1 Grade M25 cum 861.35 6,677.84 5.75
2.2 Grade M-20 cum 98.53 5,867.68 0.58
2.3 Grade M15 cum 29.78 5,020.08 0.15
3.0 Reinforcement
Providing, cutting, bending and laying in
position, binding, tack welding of
reinforcement steel of different diameter
and sizes including cost of all materials,
tools & plants & accessories and labour
etc complete in all respect.
3.1 Reinforcement in M-25 mt 64.60 57,508.88 3.72
3.2 Reinforcement in M-20 mt 13.80 57,508.88 0.79
5.0 Plastering
Plastering of brick wall 20mm thick cement
sand mortar (1:4) including cost of all
5.1 materials, curing, tools & plants & sqm 390.00 183.27 0.07
accessories, scaffolding and labour etc
complete in all respect.
ANNEXURE-IV
SEMI-SURFACE POWER HOUSE
Steel frame glazed windows of size of
6.3 nos 16.00 LS
1.8m (L) x1.2m (H) 0.04
Steel frame glazed ventilators of size of
6.4 nos 16.00 LS
1.8m(L)x 0.45m(H) 0.02
ANNEXURE-IV
SEMI-SURFACE POWER HOUSE
ANNEXURE-IV
ABSTRACT FOR TAIL RACE CHANNEL
SI. No. Description of Items Unit Quantity Rate (In Nu.) Amount in Million Nu
1 Clearing
Clearing jungle including uprooting of vegetation
1.1 & trees of girth < 300mm & disposal within 50m sqm 700.00 9.56 0.007
of the site
3 Concrete work
Concrete work including Shuttering in complete
3.1 M25 cum 406.59 6,677.84 2.72
5 Steel Support
Providing and fixing in position of Permanent
5.1 mt 0.22 118,700.40 0.03
steel support in tunnel portion ISMB 150
6 Reinforcement
Providing, cutting, bending and laying in position,
binding, tack welding of reinforcement steel of
different diameter and sizes including cost of all
materials, tools & plants & accessories and
labour etc complete in all respect.
6.1 Reinforcement in M-25 mt 33.54 57,508.88 1.93
8 Support
8.1 25mm dia Rock bolt (3 m long) rm 378.00 795.76 0.30
Sub-total (A) 18.80
Miscellaneous works like site clearance @ 1% of
9.0 1.0%
Sub-total (A) 0.19
Sub-total (B) 18.98
10 Instrumentation @ 1% of Sub-total (A) 1% 0.19
Contingencies and Work Charge Establishment
11 3%
@ 3% of above item except Lump sum 0.57
Dewatering @ 2% of above item except Lump
12 2%
sum 0.38
Grand total 20.12
ANNEXURE-IV
COST OF BUILDINGS
Amount in Million
Sl. No. Description Unit Quantity Rate (In Nu.)
Nu
1 Temporary Building sqm 1,150.00 11,445.19 13.16
Sub-total 13.16
Add for:
Land development 1% 0.13
Colony road
Fencing,boundry walls & 2% 0.26
security/observation 1% 0.13
booths
Lawns, Gardens and Plantation 1% 0.13
Retaining Walls & terracing 2% 0.26
Grant total 14.08
ANNEXURE-IV
COST OF SPECIAL TOOLS AND PLANTS
Unit rate in
Sl. No. Description No. Amount (Million Nu.)
Million
1 Light vehicle (Bolero) 3.00 1.00 3.00
2 Workshop Equipment LS 1.50 1.50
ANNEXURE-IV
COST FOR COMMUNICATION
Rate in
Sl. No. Item of Work Qty Unit Amount (Million Nu.)
(Million Nu.)
1 External Roads
Improvement/widening of existing road SNH inbetween
1.00 km. 4.00 4.00
Sipsu and Tendruk
2 Internal Roads (within project area)
a New road for Project along HRP aligment till forebay 1.50 km. 16.85 25.28
b New road for Powerhouse & TRC 1.40 km. 16.85 23.59
Grand total Nu. 52.87
ANNEXURE-IV
COST FOR MISCELLANEOUS
Sl. No. Description Unit Amount (Million Nu.)
1 Construction power LS 3.00
3 Water Supply Nu. 5.00
5 Recreation facilities LS 1.00
6 Security arrangement Nu. 2.00
7 Transport Vehicle POL and Maintenance Nu. 5.00
Total amount 16.00
ANNEXURE-IV
ENVIRONMENT,ECOLOGY & PLANTATION
Sl.
EMP Aspects Amount (Million Nu.)
No.
1 Compensatory Afforestation 1.600
2 Air and Noise Management Plan 0.076
3 OHS Management Plan 0.524
4 Awareness Programs 0.250
5 Surface Water Management Plan 0.062
6 Solid Waste Management Plan 0.280
7 Public Health Delivery Plan 2.000
8 Land Restoration and Landscaping 2.320
9 Biodiversity conservation 1.000
10 Monitoring Costs 0.360
Total amount 8.472