Calculate the cutoff grade iron deposit, taking into account the following:

Iron Price: $ 84 / long. Tonne ($ 82.68 / ton), 100% Fe

Total production cost: $ 25 / long. Tonne ($ 24.61 / ton)

Recovery: 95%

1 ton = 2.240 pounds (1,016 tons)

Calcular la ley de corte de un depósito de hierro, teniendo en cuenta lo siguiente:

Precio del hierro: $ 84 / larga. Tonelada ($ 82,68 / tonelada), 100% de Fe

Costo de producción total: $ 25 / larga. Tonelada ($ 24.61 / tonelada)

Recuperación: 95%

1 tonelada = 2,240 libras (1,016 toneladas)

an undergroun mine is producing zinc ore at $35/ton ($38.59/tonne), which includes all of its
mining and processing cost. if it nets a selling price of $0.60/lb ($1.32/Kg) of zinc in the
concentrate, what is the cutoff grade of the mine (in % zinc) if none of the variables change
and recovery of zinc is 88%

una mina undergroun está produciendo mineral de zinc en $ 35 / tonelada ($ 38.59 /


tonelada), que incluye la totalidad de su costo de extracción y procesamiento. si redes de un
precio de venta de $ 0.60 / lb ($ 1.32 / Kg) de zinc en el concentrado, lo que es la ley de corte
de la mina (en% de zinc) si ninguna de las variables del cambio y la recuperación de zinc es de
88%