Documentos de Académico
Documentos de Profesional
Documentos de Cultura
1. GENERAL
1.1 This instruction covers the general requirements for shop inspection and testing of
equipment and materials (GOODS) to be supplied by the Contractor. Contractor
shall be responsible for inclusion of inspection requirements herein and
requirements of applicable individual specification as contractual requirements of
Sub vendors.
1.3 GOODS for which no individual specification is issued can be inspected and tested
in accordance with this instruction and Contractor's standards approved by the
Purchaser
1.4 All deviations from this instruction and related inspection specifications shall be
previously proposed to the Purchaser in writing and shall be approved by the
Purchaser before placement of the order.
1.5 The word "specification(s)" used in this instruction and related inspection
specifications often collectively means all technical specifications, drawings, and
other technical documents supplied b^ the Purchaser and also specifications and
technical documents as may be agreed and/or made by the Contractor and the
Purchaser.
2. DEFINITIONS
Words used in this instruction and related inspection specifications shall have the
following meanings, unless the context requires otherwise :
Test Report: Means the individual record or certificate for respective test or
inspection.
QC Dossier: means the compiled document package consisting of prescribed
Purchaser's cover sheet for QC Dossier, Contractor's cover sheet,
table of contents, Test Reports, and other necessary documents.
Purchaser: means Gujarat Narmada Valley Fertilizer Company limited
Purchaser's Inspector: Means inspector(s) dispatched by the Purchaser or
inspector(s) of inspection agencies designated by
the Purchaser.
Owner’s Inspector: Means one or combination of inspector(s) dispatched
by the Owner and inspector(s) of the inspection
agency (agencies) designated by the Owner.
Contractor: Means a supplier or manufacturer of GOODS.
Sub vendor: Means an organization, company or individual under
contract to Contractor for the supply of material,
equipment sub-assemblies or services necessary to
the completion of Contractor’s scope of work.
1
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
4. CLARIFICATION OF CONFLICTS
If there is any conflict between the related specifications, codes and standards, the
Contractor shall immediately consult with the Purchaser in writing for clarification.
Failure of Contractor to seek, in writing, clarification of conflicting requirements prior
to acceptance of the Purchase Order shall constitute obligation of Contractor to
comply with all of the conflicting requirements at no additional cost, even to the
extent that rework and/or retesting may be required.
5.1 Inspection or non-inspection by the Purchaser shall not relieve the Contractor of its
obligation for quality control activities and guarantees for the workmanship or
performance of the GOODS.
5.2 The Contractor shall be responsible for inspection and testing of the GOODS,
including parts and materials supplied by Sub vendors.
5.3 The Contractor shall carry out all inspections and testing specified in the purchase
documents.
5.4 All Contractor's fabrication documents, including, but not limited to, welding,
nondestructive examination, heat treatment, and major repair procedures, specified
in the requisition shall be reviewed and approved by the Purchaser prior to start of
fabrication.
6. PRE-INSPECTION MEETING
2
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
7.1 The Contractor shall notify the Purchaser of readiness for witness inspection in
writing at least 4 calendar weeks prior to the date when the GOODS will be ready
for inspection.
The Contractor shall also inform the Purchaser of the definite witness inspection
date and time at least 10 working days in advance of the date of the witness
inspection.
7.2 Verbal inspection notice is not acceptable. Notice shall be sent to Purchaser by
Facsimile (telefax) OR e-MAIL. The inspection notice shall also include the map or
the necessary information to reach Contractor's shop, if such information was not
given in advance.
7.3 Work shall not proceed beyond "Inspection Hold Points" established by contract
correspondence, Specifications or Pre-Inspection Meeting without written
authorization of Purchaser.
8. WITNESS INSPECTION
Purchaser's and/or Owner's Inspector shall have free entry to those parts or areas
of manufacturing shops of the Contractor or its sub vendors where and when work,
testing or inspection on the GOODS is being performed.
Access shall not be limited to "normal office hours" and escort shall not be required
except when agreed for reasons of safety or proprietary work.
Where escort restriction is agreed, Contractor and/or Sub vendor shall make escort
available during all hours of shop fabrication, testing or inspection.
8.2 Purchaser's and Owner's Inspector reserve the right to monitor, audit, and visit
plants or other inspection locations with or without prior notice to the Contractor or
Sub vendor.
8.3 For inspection items designated for witness of Purchaser's and/or Owner's
inspector, but not designated as inspection hold points, Contractor may, at
Contractor's cost and risk, elect to proceed with fabrication after completion of
Contractor's in-house inspection, provided that the witness inspection is repeated
for witness of the Purchaser's and/or Owner's inspector at time of next inspection
visit.
8.4 The Contractor, when so requested, shall provide one additional copy of the latest
approved drawings for the use of Owner's Inspector prior to the start of inspection.
8.5 The Contractor shall furnish Purchaser's and/or Owner's Inspector with shop test
data, mill certificates, and other materials to verify that each GOODS meets the
requirements of the applicable specifications. Free copy, telex, facsimile (tele
- fax), and telephone service by the Contractor shall be made available to
Purchaser's and/or Owner's Inspector.
8.6 Safety equipment and inspection tools as necessary to safely and expeditiously
demonstrate compliance with applicable specifications, as well as assistance from
3
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
8.7 When requested by the Purchaser, the Contractor shall prepare the required
number of QC Dossier, its part, or other documents for Owner's Inspector by the
requested date.
9.1 Purchaser's Inspector will issue "Inspection Release Note" to the Contractor shortly
after the final inspection and review of QC Dossier prepared by the Contractor.
9.2 The Contractor shall not ship any GOODS without securing the Inspection Release
Note.
9.3 When the Contractor is permitted to ship on condition to perform the additional work
at the work site, the Contractor shall bear all costs and expenses incurred by such
work.
(1) Special provision for storage or proper care
(2) Repair and/or Inspection
10. DOCUMENTATION
Incomplete, inaccurate or illegible documentation shall be the cause for rejection of
GOODS until such time as satisfactory rectification has been effected.
All Contractor's inspection and test procedures, including, but not limited to, welding,
nondestructive examination, heat treatment, definition of major repairs, and major
repair procedures, required for submittal in the requisition shall be reviewed and
approved by the Purchaser prior to start of fabrication or prior to use, whichever is
the earlier.
(1) The Contractor shall submit to the Purchaser 5 white copies for documents such as
Contractor's shop inspection and test procedure and welding procedure
specification as required.
Unless otherwise specified, all these documents shall be prepared in English.
The Contractor will be requested to submit these documents prior to fabrication.
(2) The Purchaser will need a maximum of fifteen (15) working days, excluding mailing
time, from the receipt of the Contractor document to study and accept or give
alternative decisions.
4
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
11 .2 Forms
To prepare the QC Dossier, the Contractor may use its standard forms.
11.3 Compilation
(1) As far as possible, A4 (210mm X 297mm) or 8-1/2 in. x 11 in. size paper shall be
used for the test report sheet. For larger sizes, A3 ( 297 mm X 420 mm) may be
used, folded to A4 size.
When thickness of the QC Dossier is too thick to compile in one package, it can be
divided into two or more packages.
5
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
Apart from Hard Copies, Soft Copies as per following descriptions shall be
submitted by the Contractor:
(1) In principle, measuring units on QC Dossier documents shall be metric unit except
English unit may be applied for pipe, fitting, flange, flange bolts/nuts, and rating.
(2) Units for mill certificates of raw materials may be in accordance with specified
codes and standards applicable to such materials.
6
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
2. Main materials shall be verified to conform to the specified materials by mill test
reports. The mill test reports shall include chemical analysis of each lot or heat of
material and a statement that it has been tested in accordance with and meets the
physical and mechanical requirements of the applicable specification.
3. WITNESS INSPECTION
3.1 Pressure vessels for which ASME official code stamps (U) is required shall be
inspected by the ASME Authorized Inspector in accordance with the requirements
of ASME Code, Section VIII, Division 1.
3.2 In addition, all pressure vessels shall be subject to inspection, at the option of the
Purchaser or representatives of the Purchaser at all reasonable times and places
before, during and/or after fabrication.
3.3 Witness test and inspection agenda shall be in accordance with Table 3
3.4 The Owner has the right of access to the Contractor's or Sub vendor's shop for
inspection matters. If the Contractor received any instruction from the Owner's
Inspector, the Contractor should report to the Purchaser before making any
changes.
4. PRINCIPAL REQUIREMENTS
All inspection and tests shall conform to the requirements of ASME Code, Section
VIII, Division 1.
5.1 Material
1) The following materials for the pressure parts shall be inspected by ultrasonic
examination method in accordance with SA-578 Level B of ASME Code, Section II.
Test results shall be described in mill test reports.
(a) Carbon steel plates of 50 mm (2 inches) thick and over
7
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
2) For heat treated materials, test specimens shall be prepared from actual vessel
material which has been subjected to an equivalent total thermal treatment as the
vessel material in the final fabricated condition.
3) Chemical analysis of weld filler metal shall be certified by the weld filler metal
supplier.
3) If any part of a shell or head seam will be covered by a nozzle reinforcing pad or
other structural overlay, that portion of the seam shall be spot radio graphed before
it is covered.
1) Magnetic particle examination shall be carried out for all welded joints of low-alloy
steel and lifting lugs in accordance with Appendix 6 of ASME Code, Section VIII,
Division 1.
2) For 100% radio graphed vessels, all welded joints between nozzles and vessel shell
and between nozzles and flanges shall be examined by the magnetic particle
method prior to the installation of any reinforcing pads. This examination shall
include:
- The back side of the root area after the root pass has been back gouged or ground
in preparation for the welding required to complete the joint.
- Both sides of the complete weld.
3) Final nozzle welds shall be examined by the magnetic particle method after post
weld heat treatment, unless these welds are inaccessible.
4) When magnetic particle examination is specified, the DC prod method shall be used
prior to final post weld heat treatment, and the AC yoke or coil method after final
post weld heat treatment.
8
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
5.4 All forgings except for flanges as per ANSI shall be UT tested as per ASTM A 388
for the thickness greater than 100 mm and shall be procured in
normalized/annealed condition. Acceptance standards shall be as per AM 203.2 of
ASME Section VIII Div. 2. In case any defect is found, no repair by welding shall be
allowed.
5.5 All forgings including nozzle flanges shall be examined for surface defects by
MP/PT testing after machining as per ASTM A 275.
5.6 Tube sheet and Girth flanges shall of forged quality & ultrasonic tested not have any
segmental weld joint.
5.7 All heat exchanger tubes shall be 100% eddy current tested in addition to hydro
testing
Water temperature for hydrostatic test shall not be lower than 15°C during the test.
Where the ductile-to-brittle transition temperature of steel is known to be, or
suspected to be 4°C or higher, it is the fabricator's responsibility to raise the
temperature of the water to at least 15°C higher than the transition temperature.
Vessels fabricated from solid, clad or lined austenitic stainless steel shall be tested
with potable water containing minimum concentration of chloride and not more than
50 ppm chloride.
2) The test pressure shall be held for one hour or one hour per inch of vessel
thickness, whichever longer.
9
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
3) When austenitic stainless steel materials will be exposed to water during hydro
testing or water washing, the following shall apply:
a) Only treated water or freshwater with less than 50 ppm total chlorides and pH
greater than 7 shall be used.
b) The water shall be drained immediately after testing or washing and the vessel shall
be dried by blowing with dry air or dry nitrogen.
a) Hydrostatic test methods and sequence shall be established before fabrication and
submitted for the approval of the Purchaser.
b) Heat exchangers shall be alternately hydro tested on each side with no water in the
other side being exposed.
c) Girth flange joints taken apart after hydrostatic test shall be reassembled with
unused gaskets and retested for tightness by air at the design pressure.
1) When specified, pressure vessels shall be leak tested at the air pressure specified
on the individual specification and/or drawing.
2) All reinforcing plates shall be tested at air pressure of 1 to 1.4 Kg/cm^ (15 to 20
psig) unless otherwise specified.
3) All tube to tubesheet weld joints of heat exchangers shall be leak tested at the air &
with pressure specified on the drawings.
2) Shells, heads, nozzles, man ways, reinforcing pads, flanges, skirts, tube sheets, flat
cover plates, support lugs, etc., shall be treated as separate components.
3) Results of impact tests shall be incorporated into the vessel records and submitted
to the Purchaser.
The data shall include specimen size, direction in which material being tested
(longitudinal or transverse), test temperature, breaking energy of each specimen,
and average values of breaking energy for a set of three specimens.
1) If post weld heat treatment is required, Brinell hardness tests of the base metal,
weld metal and heat affected zone (HAZ) shall be made for weld seams of pressure
vessels of P-l, P-3, P-4, P-5, P-6, P-7, p-1OA and P-10B materials listed in ASME
Code Section IX. The Brinell hardness shall not exceed the limits set in Table 5.7.
10
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
Table 5.7
Material P-Number Maximum Brinell Hardness
P-l 200
P-3, P-4 225
P-5, P-6 235
P-7 225
P-10a, P-10B 225
1) Dimensional tolerance other than specified in ASME Code Section VIII, Division 1
shall be in accordance with the attached drawings in Figure 1. In addition to the
above, the dimensional tolerances specified in TEMA shall be applied to heat
exchangers.
2) Nozzle flange dimensions shall be within the tolerance of the pertinent standards for
flanges.
3) Agitator mounting flanges shall be machined after welding to shell and the flange
face shall be parallel with the indicated plane in any direction + 0.05°.
11
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
qualification record (PQR) shall be submitted to the Purchaser for approval. The
formats shall be Form QW-482 and QW-483 of ASME Code Section IX or
equivalent.
2) PQR on carbon steel and other materials for which hardness limit is specified shall
include hardness measurement across the weld metal, HAZ and base metal to
assure that the WPS is adequate for producing the allowable hardness.
3) The WPS/PQR shall meet the requirements of ASME Code Section IX.
4) Weld maps shall be attached to WPS and PQR. The maps shall show the
traceability of WPS No. to the weld line of each vessel.
5) Weld repair procedures shall be submitted to the Purchaser for approval, before
starting of repair work.
5.16.1 All reinforcing plates shall be tested at the air pressure not less than 3.4 bar g.
Reinforcing plates and other attachments with vent holes on vessels subject to
12
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
post weld heat treatment shall be pneumatically tested before and after post weld
heat treatment.
5.16.2 Sleeve lined nozzles in clad vessels shall be tested at the air pressure not less
than 3.4 bar g.
5.16.3 Strip lined plates shall be tested at the air pressure specified in the data sheets.
5.16.4 If specified in the data sheets, vessels shall be subject to a leakage test at the air
pressure specified in the data sheets after hydrostatic test.
6. DOCUMENT SUBMITTAL
The documents prescribed in the Section A above.
13
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
1 PASS
14
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
15
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
16
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
50000 MTPA PAC PROJECT
SECTION 6 ANNEXURE 4.9
INSPECTION PHILOSOPHY FOR STATIC EQUIPMENT
-Bolts and nuts for shells, shell covers and channel flanges
Note 3) The following inspection shall be conducted as the interim witness inspection for shell and
tube heat exchangers:
- Use of specified gaskets and means of holding them in place
- Ease of bundle insertion
- Bolt makeup and loading
- Assembly of stacked exchangers, if any.
1. GENERAL
Inspection Philosophy for trays shall be read in conjunction with Section A &
Section B of the Inspection Philosophy, Section 6.4.9 of the ITB.
3. WITNESS INSPECTION
3.1 All trays shall be subject to inspection, at the option of the Purchaser, under
witness by the Purchaser or designated representative of the Purchaser at any
reasonable time and place before, during, and after manufacture/fabrication.
3.2 Witness inspection and test agenda shall be in accordance with Table 1,
3.3 The owner has the right of access to the Vendor's or Subvendor's shops for
inspection matters.
If the vendor received any instruction from the Owner's Inspector, the Vendor
should report to the Purchaser before making any changes.
4.1 Material
1) Material shall be verified to conform to the specified materials by mill test reports
or material certificates.
2) Mill test reports or material certificates for such main parts as tray floor, down
comer, weir, seal pan and tray support beam and for other specified parts shall be
submitted.
3) For other parts than specified above, mill test report or material certificates for
corrosion resistant austenitic stainless steel and higher grade material shall be
also submitted.
- 18 -
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
FEED STOCK CONVERSION
(b) Length
Up to 1500 mm, incl. ±2.5mm
Over 1500 mm ±4.5 mm
(c) Width ±1.5 mm
(d) Flatness ±1.5 mm per 1000 mm
at any place
5. DOCUMENT SUBMITTAL
The documents prescribed in the following paragraphs shall be submitted in
accordance with Section A – Inspection Instruction to the Vendors above.
- 19 -
GUJARAT NARMADA VALLEY FERTILIZERS COMPANY LIMITED
FEED STOCK CONVERSION
The procedure shall cover at least the following items and shall meet requirements
of all inquiry and purchase documents, including related vendor's and Purchaser's
correspondence.
1) Inspection and test agenda
2) Specific test methods including test equipment
3) Acceptance criteria
4) Test report and test certificate to be submitted
Note: 1) W: Witness
R: Review of manufacturing test report
Test Category : Purchaser’s Inspection
- 20 -