Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Factory List:
1. Hams Garments Ltd.
1. INTRODUCTION
The Factory was surveyed for electrical safety by Woosun Energy and Construction Co., Ltd.
(WEC). The purpose of the survey was to identify significant electrical safety issues and to provide
recommendations for remediation based on applicable standards specified by the Accord. The
scope of this initial electrical safety inspection was limited to the review and identification of major
electrical safety issues. The inspection did not include identification of minor deficiencies, which will
be further addressed as part of follow-up inspections.
2. LIMITATIONS
The information in this electrical safety inspection report was obtained during a visit to the facility
and during interviews with local factory management. It has not been possible to provide
independent verification for all the information and data collected, and, therefore, WEC cannot
accept general responsibility for omissions or errors arising from inaccuracies in this report from the
information obtained.
The findings and recommendations in this report are not intended to imply, guarantee, ensure or
warrant compliance with any government regulations. Additionally, the results do not imply in any
way that compliance with the findings or recommendations as stated in this report will eliminate all
hazards, risks or exposures or that hazards, risks or exposures not referred to in this report do not
exist. Compliance with the findings and recommendations stated in this report does not relieve the
factory owner from obligation to comply with specific project requirements, industry standards, or
the provisions of any local government regulations.
3. Accord ID : 09294
4. Inspection Participants : Md. Mahfuzur Rahman, AGM, HR, Admin & Compliance,
Hams Garments Ltd.,
Ph: +88 01929998126, 01916788409,
E-mail: mahfuz@hamsgroupbd.com.
a. General:
There are three buildings and two sheds owned by the Hams Garments Ltd., and only one
building is used for production. As reported in the meeting, the construction of building one
started in 2008 and production commenced in 2010.
The floor wise utilizations of Shed one and two are as follows:
c. Electrical System:
The main supply for Hams Garments Ltd. is from 1,287 kVA gas operated generator. REB
supply is used only for compound and emergency lights. They also have two diesel operated
generators as back up supply (637 kVA and 262 kVA)
An implementation schedule shall be developed by the factory to remediate each of the findings.
The specific timing of improvements, including any requested extensions due to design /
installation constraints, shall be submitted to the Accord for approval.
Recommendation:
The insulating rubber mat in front of panel
must be replaced with proper size and grade
Finding #: E- 2
Category: DISTRIBUTION & LT PANELS
Finding:
Dedicated earth connection for panel frame
not installed.
Recommendation:
Firmly connect the panel frame and door
using a earth bonding.
Finding #: E- 3
Category: TRANSFORMER ROOM
Finding:
The arching horn on the transformer is not
paired.
Recommendation:
The arching horn on the transformer must
be installed in a pair and their gap must
be properly aligned and maintained.
The arching horn is not paired.
Recommendation:
The transformer guard must be firmly
connected to the earth at least at one
point near to the opening
No earth connection to the
transformer guard
Remediation Timeframe: Within 1 Month
Finding #: E- 5
Category: DISTRIBUTION & LT PANELS
Finding:
Cables are not marked with proper phase
colors.
Recommendation:
All the power cables shall be provided with
proper phase color marking.
No phase color marking
Finding #: E- 6
Category: TRANSFORMER ROOM
Finding:
Combustible materials used to cover the
power cables
Recommendation:
Combustible materials must be replaced with
non-combustible ones to cover the cables
for protection.
Recommendation:
The wires shall be fully covered by PVC
case capping with Ts and bends
Finding #: E- 8
Category: ELECTRICAL SHAFT
Finding:
Openings for cables are not sealed with fire
rated sealant.
Recommendation:
The cable shafts running through the floor
and ceiling openings shall be closed
properly to avoid physical damages to the
cables with fire rated sealant. Openings for cables
are not sealed
Remediation Timeframe: 3 Months
Finding #: E- 9
Category: WIRINGS
Finding:
The ceiling junction box is not closed
Recommendation:
The ceiling junction boxes shall be either
connected with appropriate fittings or closed
with cap.
Recommendation:
The cables should be tied/ clamped firmly on
the cable tray in a proper way without causing
damage to the cables and wires
Cables not fixed properly
Finding #: E- 11
Category: DISTRIBUTION & LT PANELS
Finding:
Phase barrier/separators between different
phases with voltage exceeding 400V are
not installed.
Recommendation:
Phase barriers between different phases
must be installed to avoid arc flashing.
Finding #: E- 12
Category: DISTRIBUTION & LT PANELS
Finding:
Cables entering or exiting Distribution panel
are not firmly fixed.
Recommendation:
Cables entering panel must be firmly fixed
through base plates using cable glands.
Recommendation:
Cables and wiring inside panels must be
arranged and firmly fixed to avoid
unintendedly touching other parts.
Finding #: E- 14
Category: TRANSFORMER ROOM
Finding:
Transformer is covered with lint and dust.
Recommendation:
Transformer must be cleaned during routine
maintenance.
Transformer is covered
with lint and dust.
Finding #: E- 15
Category: TRANSFORMER ROOM
Finding:
The dust trap oil container below transformer
breather is not filled with transformer oil.
Recommendation:
Dust trap must be filled with transformer oil
to required level as instructed by the
manufacturer.
Recommendation:
Wirings shall be laid in cable trays or else
and supported throughout its length.
Finding #: E- 17
Category: TRANSFORMER ROOM
Finding:
Oil level in conservator tank of transformer is
low.
Recommendation:
Transformer oil must be filled to the required
level after shutting down the transformer.
Finding #: E- 18
Category: SERVICE LINE
Finding:
HT cable entering electrical room is not
protected.
Recommendation:
All cables passing through permanent wall must
be protected against possible physical damages
and stress at the point of entry/exit and
remaining gaps must be sealed with similar
materials or higher fire rating materials. HT cable entering electrical
room is not protected.
Remediation Timeframe: 3 Months
Recommendation:
Cables must be supported on tray/riser and
protected from possible physical damages.